City of Orange: Summary of Bid Abstracts for:
1 2 3 4 5 6
Bid No. 21-22.13; Project No. SP-4130
Date of Bid Opening: 2/15/2022
NO. DESCRIPTION OF WORK QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT 1 Remove Existing Roof Glazing and Roof
Glazing Framing and Intall Structural
Steel Beams, New Metal Standing Seam
Roofing Over NEW Rigid Insulation and
New Metal Decking and Associated
Curtain Wall System, Interior, Exterior
Improvements, HVAC System
Improvements, and Temporary Office
Facility
1 LS 2,845,525.00$ $2,845,525.00 $2,960,940.00 $2,960,940.00 $3,122,333.00 $3,122,333.00 $3,176,000.00 $3,176,000.00 $3,690,000.00 $3,690,000.00 $4,068,600.00 $4,068,600.00 $4,037,000.00 $4,037,000.00 2 Install New Photovoltaic Panels and
Associated Equipment
1 LS 540,000.00$ $540,000.00 $514,281.00 $514,281.00 $393,947.00 $393,947.00 $350,000.00 $350,000.00 $460,000.00 $460,000.00 $400,000.00 $400,000.00 $746,000.00 $746,000.00 $3,385,525.00 $3,475,221.00 $3,516,280.00 $3,526,000.00 $4,150,000.00 $4,468,600.00 $4,783,000.00 $3,385,525.00 $3,475,221.00 $3,516,280.00 $3,526,000.00 $4,150,000.00 $4,468,600.00 $4,783,000.00 (Rialto, CA)

ENGINEER'S ESTIMATE
Police HQ Lobby Roof and HVAC Rehabilitation
New Dynasty Construction Co.
(Tustin, CA)
Far Electric Inc, dba Far Builders
(Anaheim, CA)
Robert Clapper Const. Serv.,Inc.
dba R.C. Construction Services
Bon Air Inc.
(Los Angeles, CA)
RT Contractor Corp.
(Garden Grove, CA)
S&H Construction, Inc.
(Fremont, CA)
Grand Total
Sub-Total
Building Improvements