TO: Honorable Mayor and Members of the City Council
THRU: Thomas R. Hatch, Interim City Manager
FROM: Christopher Cash, Director of Public Works

1. SUBJECT
Approval of specifications for Fire Hydrant Painting Services Project, and authorization to advertise for bids.

2. SUMMARY
Specifications have been completed for Fire Hydrant Painting Services Project. The project is ready to be advertised for bids. The initial one-year cost estimate is $55,000.

3. RECOMMENDED ACTION
Approve the specifications and authorize advertising for bids for the Fire Hydrant Painting Services project; Bid No. 21-22.29.

4. FISCAL IMPACT
The total expenditure for this project is $55,000 and will be funded through Water Fund (600).

5. STRATEGIC PLAN GOALS
Goal 1: Provide for a safe community
b: Provide and maintain infrastructure necessary to ensure the safety of the public.

Goal 4: Provide outstanding public service
b: Provide facilities and services to meet customer expectations.

6. DISCUSSION AND BACKGROUND
Fire hydrants are important assets that help to ensure that the City’s water distribution system functions efficiently and properly. Besides annually flushing, painting of these fire hydrants proves to be critical with extending the service life. With over 4,400 fire hydrants within the City service area, the Water Division has been retaining contractors to paint approximately 1,100 fire hydrants per fiscal year to complete the four-year cycle of fire hydrant painting in the City. The scope of work includes traffic control, removal of grease, oil, loose paint, dirt, foreign materials, and painting with all necessary labor, equipment, and materials.

The term of the contract is for one year with an option to renew the contract annually for a total of three more years if the City is satisfied with the level of service from the contractor. The cost estimate for a one year service is $55,000. Each subsequent year is subject to a formula-based consumer price index (CPI) with an adjustment cap of no greater than 2%. Approval of the City of Orange Printed on 3/3/2022Page 1 of 2
powered by Legistar™
Item #: 3.18. 3/8/2022 File #: 22-0088
extensions will be based on performance and will be executed by the City Manager.

7. ATTACHMENTS
· City of Orange Service Area Map
City of Orange Printed on 3/3/2022Page 2 of 2