Final Acceptance of Bid No. 20-21.07; Fire Station No. 1 and Headquarters; and authorization to file Notice of Completion.
2. SUMMARY
The project consisted of building a new Fire Station 1 and Headquarters facility, including but not limited to clearing and grubbing, site work preparation, grading, landscaping, traffic signal improvements, parking lot, remodel of existing warehouse, paving, sewer, water, storm drain, and all other associated infrastructure needed for a functional and operational Fire Station.
The City of Orange entered into a contract with Robert Clapper Construction Services, Inc. The work was completed to the satisfaction of the Public Works Department.
3. RECOMMENDED ACTION
Accept Fire Station No. 1 and Headquarter (SP-4071) as complete, and authorize staff to file Notice of Completion with the County Recorder.