City of Orange: Summary of Bid Abstracts for:
1 2 3
Bid No. 22-23.05; Project No. SP-4086
Date of Bid Opening: 9/15/2022
NO. DESCRIPTION OF WORK QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT 1 Unclassified Excavation 200 CY 175.00$ $35,000.00 $350.00 $70,000.00 $360.00 $72,000.00 $320.00 $64,000.00 2 Asphalt Concrete 110 TON 140.00$ $15,400.00 $300.00 $33,000.00 $360.00 $39,600.00 $180.00 $19,800.00 3 Aggregate Base 120 CY 100.00$ $12,000.00 $250.00 $30,000.00 $240.00 $28,800.00 $320.00 $38,400.00 4 Construct 2-inch minimum Asphalt
Rubber Hot Mix (ARHM) Overlay
130 TON 175.00$ $22,750.00 $300.00 $39,000.00 $380.00 $49,400.00 $172.00 $22,360.00 5 Cold Plane Existing AC Pavement 2-inches 740 SY 10.00$ $7,400.00 $25.00 $18,500.00 $17.00 $12,580.00 $33.00 $24,420.00 6 Construct Type A Concrete Curb and
Gutter Per City of Orange Std. 117 (CF=8")
615 LF 100.00$ $61,500.00 $70.00 $43,050.00 $120.00 $73,800.00 $80.00 $49,200.00 7 Construct Sidewalk Per City of Orange
Std. 118, Case 1 (t=4", Finish per
Specifications)
1,700 SF 15.00$ $25,500.00 $15.00 $25,500.00 $20.00 $34,000.00 $18.00 $30,600.00 8 Construct Modified Sidewalk Access
Ramp per City of Orange Std. 121, Type 2
1 EA 7,500.00$ $7,500.00 $10,000.00 $10,000.00 $15,000.00 $15,000.00 $9,000.00 $9,000.00 9 Furnish and Install Filterra Offline Unit
FT0404 with Flume Per Detail on Plans,
Connect to Existing Catch Basin with 6-
inch SDR 35 Pipe and Install Modeified
Gutter per City of Orange Std. 117.
1 LS 65,000.00$ $65,000.00 $45,000.00 $45,000.00 $60,000.00 $60,000.00 $45,000.00 $45,000.00 10 Landscape and Irrigation Modifications,
inclusive of 90-day
Establishment/Maintenance Period
1 LS 25,000.00$ $25,000.00 $1,000.00 $1,000.00 $43,000.00 $43,000.00 $42,000.00 $42,000.00 11 Traffic Signal Modifications 1 LS 200,000.00$ $200,000.00 $90,000.00 $90,000.00 $82,000.00 $82,000.00 $140,000.00 $140,000.00 12 Street Light Installation 1 LS 15,000.00$ $15,000.00 $30,000.00 $30,000.00 $34,000.00 $34,000.00 $41,000.00 $41,000.00 13 Signage and Striping 1 LS 50,000.00$ $50,000.00 $30,000.00 $30,000.00 $34,000.00 $34,000.00 $33,000.00 $33,000.00 14 Traffic Control 1 LS 75,000.00$ $75,000.00 $187,700.00 $187,700.00 $89,000.00 $89,000.00 $300,000.00 $300,000.00 15 Remove Tree 1 EA 9,000.00$ $9,000.00 $3,500.00 $3,500.00 $4,200.00 $4,200.00 $3,800.00 $3,800.00 16 Furnish and Install 4-foot High Wooden
Fence
225 LF 70.00$ $15,750.00 $150.00 $33,750.00 $170.00 $38,250.00 $110.00 $24,750.00 $641,800.00 $690,000.00 $709,630.00 $887,330.00Grand Total
STREET IMPROVEMENTS
ENGINEER'S ESTIMATE
Cannon Street At Serrano Avenue Intersection Improvements Hardy & Harper Gentry General Engineering, Inc. All American Asphalt