Agenda Item
City Council
Item #: 3.4. 11/15/2022 File #: 22-0538
TO: Honorable Mayor and Members of the City Council
FROM: Leslie Hardy, Community Services Director
1. SUBJECT
Agreement with RHA Landscape Architects Planners, Inc. for design services for the Capital Improvement Project, Hart Park Pickleball and Fitness Circuit Project.
2. SUMMARY
This project includes the award of design work for preliminary plans (Phase 1) and construction documents (Phase 2) for the installation of pickleball courts and fitness circuit at Hart Park. The proposed pickleball facility and fitness circuit amenities include lighted pickleball courts, area lighting, outdoor fitness equipment, paved access to all amenities, spectator seating, fencing, wind screens, benches, landscaping, and park amenities.
3. RECOMMENDED ACTION
Approve agreement with RHA Landscape Architects Planners, Inc. in the amount of $257,092 for design services for Capital Improvement Project, Hart Park Pickleball and Fitness Circuit Design Project (20315); and authorize the Mayor and City Clerk to execute on behalf of the City.
4. FISCAL IMPACT
The total expenditure for this agreement is $257,092 and will be funded in the Hart Park Pickleball and Fitness Circuit Project (20315) through:
Park Acquisition & Development (511) $200,000
Park Acquisition-Infill (510) 57,092
Total: $257,092
5. STRATEGIC PLAN GOALS
Goal 3: Enhance and promote quality of life in the community a: Renovate, maintain, develop, and/or expand public use places and spaces.
6. DISCUSSION AND BACKGROUND
W.O. Hart Memorial Park (Hart Park) is a 56-acre community park, located within the Old Towne Orange Historic District. Hart Park is home to several historic structures and architectural elements, an orange grove, and beautiful mature shade trees. Hart Park offers acres of passive and open space, as well as active amenities including two lighted softball/baseball fields, a lighted collegiate- level baseball field, soccer/football field, swimming pools and aquatic facility, a bandshell, two lighted tennis courts, horseshoe pits, sand volleyball courts, walking paths, picnic areas, tot-lot playground, two restroom facilities, and an active bike path that runs through the south side of the park.
City of Orange Printed on 11/10/2022Page 1 of 3
powered by Legistar™
Item #: 3.4. 11/15/2022 File #: 22-0538
To fulfill the recreational needs of the surging pickleball community in Orange, as well as provide a space for additional walking paths and exercise equipment, a Capital Improvement Project (CIP) titled Hart Park Pickleball and Fitness Circuit was approved for $2,750,000. Proposed project elements include:
· Multiple lighted pickleball courts, including fencing and windscreens · Shaded outdoor fitness equipment
· Paved access to courts and amenities
· Area and pathway lighting
· Shaded spectator seating
The Request for Proposal for design services (RFP 22-23.03) was advertised on June 16, 2022, and proposals were due on July 21, 2022. Eight proposals were submitted. Staff evaluated the proposals based on the firm’sexperience, overall qualifications, record of success on previous projects, and overall responsiveness to the RFP. Bid amounts were submitted in separate sealed envelopes and reviewed after the rating process was complete. A Proposal Abstract Summary (Attachment 1) is attached for reference. RHA Landscape Architects Planners, Inc. (RHA) received the highest score (96.8 out of 100) and had a total base bid amount of $199,210. Below is a summary of the vendor ratings and bid amounts:
Company/Contractor City
(Location of Company)
Total point Scores
(Out of 100)
Total Bid Amount
RHA Landscape Architects-Planners
(Riverside, CA)
96.8 $199,210
RJM Design Group (San Juan
Capistrano, CA)
92.2 $198,770
David Volz Design (Costa Mesa, CA) 90.5 $207,257
Hirsch & Associates, Inc. (Anaheim,
CA)
82.9 $121,600
IDS Group (Irvine, CA) 82.5 $222,985
Rengel + Co. Architects (Tustin, CA) 78.5 $310,000
Brightview Design Group (Irvine, CA) 76.5 $307,370
Urban Arena, Inc. (Costa Mesa, CA) 74.8 $54,900
Staff conducted interviews with the top two design firms, RHA and RJM Design Group. At the conclusion of interviews, staff determined that RHA was best qualified for the project design. RHA has previous experience designing pickleball courts and exercise stations for other local Southern California municipalities, as well as designing projects within historical parks. The City also has had positive experiences with RHA, as the vendor completed the design for the Yorba Park Renovation and the Handy Park Maintenance Renovation projects. In addition, RHA has secured a pickleball expert who has years of experience coaching and managing pickleball tournaments on their design City of Orange Printed on 11/10/2022Page 2 of 3
powered by Legistar™
Item #: 3.4. 11/15/2022 File #: 22-0538
expert who has years of experience coaching and managing pickleball tournaments on their design team. Lastly, RHA’s reference checks came back with positive feedback The design work will be divided into two phases. Phase 1 will begin the process to design the courts and amenities at a cost of $97,280. Phase 2 is development of biddable construction documents at a cost of $101,930, bringing the cost for Phase 1 and 2 to $199,210. Both phases will take approximately 8 months to complete and will include several opportunities for public input, including discussion at a future Park Planning and Community Events Commission meeting.
Funding Requirements
In the Spring of 2022, Congressman Lou Correa secured $2 million in funding from community projects through the federal Omnibus budget legislation bill. This funding opportunity was made available through the U.S. Department of Housing and Urban Development (HUD)’s Economic Development Initiative Community Project Funding Grants.
Since federal funds will be used, the project is required to demonstrate compliance with the National Environmental Policy Act (NEPA) by preparing and providing environmental documents satisfying federal disclosure obligations. RHA submitted a proposal of $34,510 to complete these documents.
The environmental review will occur during Phase 1 of the project.
Staff is currently working with HUD to complete the necessary steps, including submitting an application, to enter into an agreement with HUD. After the agreement is received, staff will bring it forward for approval at a future Council meeting. Access to the grant funding will be issued after the environmental review is completed and certified.
The additional cost of $34,510 for NEPA documentation services brings the RHA bid total to $233,720. A 10% contingency of $23,372 is also included for a total not-to-exceed amount of $257,092. The total cost budgeted for this project is $2.75 million. Sufficient funds are available within the project budget in the Park Acquisition Fund (510) and the Park Acquisition & Development Fund (511) to cover the cost of design environmental review. Remaining 510 funds assigned to this project will be combined with the $2 million Community Project Grant to fund the construction costs.
7. ATTACHMENTS
· Proposal Abstract Summary
· Draft Agreement with RHA - Hart Park Pickleball and Fitness Circuit Design City of Orange Printed on 11/10/2022Page 3 of 3