City of Orange: Summary of Bid Abstracts for:
1 2 3 4
Bid No. 22-23.16
Date of Bid Opening: 7/13/23
Tel. No. Tel. No. Tel. No. Tel. No.
NO. DESCRIPTION OF WORK QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT 1 Traffic Control & Construction Phasing 1 LS 100,000.00$ $100,000.00 $218,874.00 $218,874.00 $183,850.00 $183,850.00 $192,000.00 $192,000.00 $227,000.00 $227,000.00 2 Remove Existing and Construct Access
Ramp with Truncated Domes per City Std.
121
4 EA 8,000.00$
$32,000.00 $14,000.00 $56,000.00 $9,200.00 $36,800.00 $10,500.00 $42,000.00 $12,000.00 $48,000.00 3 Remove Existing AC Curb and Replace
With 8" Curb and Gutter (Type A) per City
Std. 117
100
LF 100.00$
$10,000.00 $150.00 $15,000.00 $150.00 $15,000.00 $163.00 $16,300.00 $112.00 $11,200.00 4 Remove Existing and Construct Concrete
Sidewalk per City Std. Plan 118 & 120
670
SF 15.00$
$10,050.00 $15.00 $10,050.00 $20.00 $13,400.00 $16.00 $10,720.00 $18.00 $12,060.00 5 Cold Plane 3" Existing Asphalt Concrete
Pavement
26,120 SY 4.00$ $104,480.00 $4.15 $108,398.00 $5.00 $130,600.00 $3.50 $91,420.00 $5.00 $130,600.00 6 Asphalt Concrete/Subgrade Removal (8"
Unclassified Excavation)
290 CY 150.00$ $43,500.00 $132.00 $38,280.00 $135.00 $39,150.00 $195.00 $56,550.00 $132.00 $38,280.00 7 Asphalt Concrete Base Course 590 TON 130.00$ $76,700.00 $120.00 $70,800.00 $180.00 $106,200.00 $123.00 $72,570.00 $145.00 $85,550.00 8 Asphalt Rubberized Hot Mix (ARHM) - 2"
Arterial Surface Course
2,940 TON 120.00$ $352,800.00 $123.00 $361,620.00 $125.00 $367,500.00 $135.00 $396,900.00 $124.00 $364,560.00 9 Adjust/Remove and Replace Water Valve
Box per OWD Std No. 101
12 EA 800.00$ $9,600.00 $1,200.00 $14,400.00 $1,300.00 $15,600.00 $1,075.00 $12,900.00 $2,400.00 $28,800.00 10 Adjust Manhole Frame & Cover to Grade
per City Std. No. 408
15 EA 800.00$ $12,000.00 $1,600.00 $24,000.00 $1,300.00 $19,500.00 $1,000.00 $15,000.00 $2,200.00 $33,000.00 11 Install Traffic Signing & Striping,
Pavement Markings (Legends), and
Raised Pavement Markers (RPM's)
1 LS 50,000.00$
$50,000.00 $27,550.00 $27,550.00 $30,000.00 $30,000.00 $46,000.00 $46,000.00 $29,000.00 $29,000.00 12 Provide & Install Type “E” Detector Loops 40 EA 300.00$ $12,000.00 $380.00 $15,200.00 $400.00 $16,000.00 $375.00 $15,000.00 $400.00 $16,000.00 13 Asphalt Concrete Level Course - 1" Depth 1,470 TON 130.00$ $191,100.00 $115.00 $169,050.00 $120.00 $176,400.00 $140.00 $205,800.00 $143.00 $210,210.00 $1,004,230.00 $1,129,222.00 $1,150,000.00 $1,173,160.00 $1,234,260.00Grand Total
SEWER LINE REPLACEMENT / MAINTENANCE
ENGINEER'S ESTIMATE
SP-4201 - Santiago Canyon Road - Newport to Jamboree
All American Asphalt Hardy & Harper, Inc RJ Noble Excel Paving