Cities Index.
Staff Report

Orange City Council
March 12, 2024

Document
Staff Report
Meeting
March 12, 2024
Body
Orange City Council
Original file
128 KB
Text extracted from the city's file for reading and search. Open the original on cityoforange.legistar1.com. That file is the official record.

Agenda Item
City Council
Item #: 3.14. 3/12/2024 File #: 24-0149
TO: Honorable Mayor and Members of the City Council
THRU: Tom Kisela, City Manager
FROM: Christopher Cash, Public Works Director

1. SUBJECT
Approval of payment to Southern California Edison for new electrical service for Well No. 28 located at 225 W. Maple Avenue.

2. SUMMARY
Southern California Edison submitted a payment request in the total amount of $81,005.98 for the design and installation of new electrical service for Well No. 28.

3. RECOMMENDED ACTION
Approve payment to Southern California Edison in the amount of $81,005.98 for the design and installation of electrical service to Well No. 28.

4. FISCAL IMPACT
The expense for this purchase is $81,005.98 and will be funded through:
600.8011.56411.18120 Water Fund (600) Well 28 Construction

5. STRATEGIC PLAN GOALS
Goal 1: Provide for a safe community
b: Provide and maintain infrastructure necessary to ensure the safety of the public.

Goal 4: Provide outstanding public service
b: Provide facilities and services to meet customer expectations.

6. DISCUSSION AND BACKGROUND
Phase 2 of the Well No. 28 project consists of the installation of the well head, Ion Exchange vessels, piping, electrical and chemical buildings, screen walls, and the public pocket park. This project requires a new underground service and electrical meter from Southern California Edison (SCE) to power the well pump, motor, miscellaneous lighting, and other electrical components. While the contractor is tasked with providing all on-site electrical equipment, the City, as the owner, is responsible for requesting electrical service from SCE to the site. SCE has completed the design for the new service and submitted an invoice for both the design and installation in the total amount of $81,005.98. SCE’sinstallation will start upon receiving the requested payment. Staff is requesting the City Council approve the payment to SCE for the new service at Well 28.

City of Orange Printed on 3/7/2024Page 1 of 2
powered by Legistar™
Item #: 3.14. 3/12/2024 File #: 24-0149

7. ATTACHMENTS
· SCE New Meter and Service Plan
· SCE Invoice
City of Orange Printed on 3/7/2024Page 2 of 2
powered by Legistar™

← All documents from this meeting