FIRST AMENDMENT TO

COOPERATIVE AGREEMENT BETWEEN CITY OF VILLA PARK

AND CITY OF ORANGE FOR FUNDING AND CONSTRUCTION OF

THE EAST CERRO VILLA DRIVE IMPROVEMENT PROJECT

FROM VALLEY DRIVE TO RAMA STREET

This FIRST AMENDMENT to COOPERATIVE AGREEMENT BETWEEN CITY OF

VILLA PARK AND CITY OF ORANGE FOR FUNDING AND CONSTRUCTION OF

THE EAST CERRO VILLA DRIVE IMPROVEMENT PROJECT FROM VALLEY DRIVE TO RAMA STREET (“Cooperative Agreement”) is made so as to be effective as of the ______ day of _____________ 2024, by and between the CITY OF VILLA PARK, a municipal corporation (" VILLA PARK ") and CITY OF ORANGE , a municipal corporation ("ORANGE"), collectively the "Parties."
WHEREAS, the Parties have previously entered into the aforementioned Cooperative Agreement effective April 11, 2023; and
WHEREAS, upon receiving actual bids on July 31, 2024, the lowest responsive and responsible bidder was R.J. Noble Company, at the total bid of $511,702.70; and WHEREAS, as previously agreed upon , with a percentage of cost share of 16% , ORANGE’S cost share is $157,110; and
WHEREAS, VILLA PARK and ORANGE desire to enter into this First Amendment to the Cooperative Agreement pertaining to the addition of a new Paragraph 1 .3.1 and replacing Exhibit “B” with the attached Amended Exhibit “B”.

NOW, THEREFORE, VILLA PARK and ORANGE, in consideration of the mutual covenants and agreements herein contained, agree as follows:

1. Add following Paragraph 1.3.1 below Paragraph 1.3 of the Agreement:

1.3.1. Based on the lowest responsive and responsible bidder’s cost proposal (as shown on attached Amended Exhibit “B”), the total costs to Orange is One Hundred Fifty Seven Thousand and One Hundred Ten Dollars ($ 157,110).

2. Exhibit “B” of Agreement is replaced by attached Amended Exhibit "B”, actual lowest bid cost proposal, by R. J. Noble Company.

3. The Parties hereby agree that this First Amendment shall be incorporated into the Agreement as set forth in full therein. All other provisions of the Agreement not amended by the First Amendment shall remain in full force and effect and are unchanged by this First Amendment.

IN WITNESS WHEREOF, the Parties hereto have caused this Agreement to be executed the day and year first above written.

Date: ____________________

CITY OF VILLA PARK
a municipal corporation

By:___________________________
Vince Rossini, Mayor

Attest:

______________________________
Steve Franks, City Clerk

Approved As to Form:

_________________________________
Todd Litfin, City Attorney

Attachment: Amended Exhibit “B”

CITY OF ORANGE
a municipal corporation

By:___________________________
Daniel R. Slater, Mayor

Attest:

______________________________
Pamela Coleman, City Clerk

Approved As to Form:

Mike Vigliotta, City Attorney

By:____________________________
Melissa M. Crosthwaite
Senior Assistant City Attorney

√

Amended Exhibit "B"
Cost Sharing Amount:

City of Villa Park/City of Orange
(Beneath this Sheet)

CITY OF VILLA PARK

EAST CERRO VILLA DRIVE REHABILITATION PROJECT
ITEM Villa Park Orange
NO. Unit Price Item Cost 84% 16%
1 Mobilization 1 LS $0.00 $0.00 $0.00
2 Traffic & Pedestrian Control,
Construction Phasing, Public
Convenience & Safety
1 LS $90,450.00 $90,450.00 $90,450.00 $75,978.00 $14,472.00 3 Furnish, Install, Maintain and
Remove Portable Changeable
Message Signs (PCMS)*
2 EA $1,250.00 $2,500.00 $2,500.00 $2,100.00 $400.00
4 Project Identification Signs* 2 EA $1,050.00 $2,100.00 $2,100.00 $1,764.00 $336.00 5 Construction Survey & Staking,
Including Monument Recovery and
setting Pre-construction ties per
County of Orange Requirements
1 LS $9,500.00 $9,500.00 $9,500.00 $7,980.00 $1,520.00
6 Post Construction Set New
Centerline Monument & Ties
(Including Missing Monuments)
per City and County of Orange
Requirements, and File Corner
Records
17 EA $787.00 $13,379.00 $13,379.00 $11,238.36 $2,140.64 7 Storm Water Pollution Prevention
Plan & Implementation 1 LS $3,150.00 $3,150.00 $3,150.00 $2,646.00 $504.00 8 Furnish Record Drawings 1 LS $525.00 $525.00 $525.00 $441.00 $84.00 9 Unclassified Excavation 16 CY $64.50 $1,032.00 $1,032.00 $866.88 $165.12 10 Cold Mill Existing Pavement 1.5”
per Typical Sections & Details on
Sheet 2 of Plans
12,630 SY $1.99 $25,133.70 $25,133.70 $21,112.31 $4,021.39 RJ Noble ITEM COST
(Subtotal)DESCRIPTION QUANTITY UNIT
Cerro Villa Bid Line Item - RJ Noble-City of Orange 7-31-2024.xlsx 1 OF 4

CITY OF VILLA PARK

EAST CERRO VILLA DRIVE REHABILITATION PROJECT
Probable Construction CostsITEM Villa Park Orange
NO. Unit Price Item Cost 84% 16%
RJ Noble ITEM COST
(Subtotal)DESCRIPTION QUANTITY UNIT
11 Asphalt Rubber Hot Mix (ARHM-
GG-C PG 64-16) 1,101 TON $139.00 $153,039.00 $153,039.00 $128,552.76 $24,486.24 12 Dense Graded Asphalt Concrete
(DGAC) Base Course Pavement
Type B PG 70-10 (10% Max. RAP)
34 TON $172.00 $5,848.00 $5,848.00 $4,912.32 $935.68
13 Asphalt Concrete (AC) Level
Course Pavement Type C2 PG 70-
10 (10% Max. RAP)
352 TON $183.00 $64,416.00 $64,416.00 $54,109.44 $10,306.56 14 Adjust Water Valve Can and
Cover to Grade per City of Orange
Water Std. Dwg. No. OWD-101
13 EA $1,100.00 $14,300.00 $14,300.00 $6,600.00 $7,700.00 7 valves in Orange
15 Adjust Storm Drain Manhole
Frame and Cover to Grade in AC
Pavement per SPPWC Std. Plan
No. 205-3
5 EA $1,000.00 $5,000.00 $5,000.00 $4,200.00 $800.00
16 Adjust Sewer Manhole Frame and
Cover to Grade in AC Pavement
per SPPWC Std. Plan No. 205-3
7 EA $1,000.00 $7,000.00 $7,000.00 $5,880.00 $1,120.00
Cerro Villa Bid Line Item - RJ Noble-City of Orange 7-31-2024.xlsx 2 OF 4

CITY OF VILLA PARK

EAST CERRO VILLA DRIVE REHABILITATION PROJECT
Probable Construction CostsITEM Villa Park Orange
NO. Unit Price Item Cost 84% 16%
RJ Noble ITEM COST
(Subtotal)DESCRIPTION QUANTITY UNIT
17 Sawcut & Remove Ex. From BCR
to ECR and Construct P.C.C. Curb
Ramp per City of Orange Std. Plan
No. 121, Type 2 with Retaining
Curb (As Needed), with Transition
Sidewalk per Detail C on Sheet 2
& Detectable Warning Devices per
Federal & State ADA Guidelines
4 EA $9,400.00 $37,600.00 $37,600.00 $0.00 $37,600.00
City of
Orange
100%
18 Sawcut & Remove Ex. and
Construct New 4” P.C.C. Sidewalk
per SPPWC Std. Plan No. 112-2
100 SF $19.00 $1,900.00 $1,900.00 $1,596.00 $304.00
19 Sawcut & Remove Ex. and
Construct New P.C.C. Curb &
Gutter per SPPWC Std. Plan No.
120-3 Type A2-8 over 6” CMB
(Modified to Variable Curb Face)
100 LF $105.00 $10,500.00 $10,500.00 $8,820.00 $1,680.00 20 Sawcut & Remove Ex. and
Construct New PCC Curb & Gutter
per SPPWC Std. Plan No. 120-3,
Type A2-8(200) (W=1') Over 6"
C.M.B. (Modified per Plans
Variable curb Face)
100 LF $105.00 $10,500.00 $10,500.00 $8,820.00 $1,680.00 21 Sawcut & Remove Ex. and
Construct Slot Paving per Detail
“A” on Sheet 2 of Plans
400 SF $24.00 $9,600.00 $9,600.00 $8,064.00 $1,536.00
Cerro Villa Bid Line Item - RJ Noble-City of Orange 8-5-2024.xlsx 3 OF 4 JUNE 13, 2024

CITY OF VILLA PARK

EAST CERRO VILLA DRIVE REHABILITATION PROJECT
Probable Construction CostsITEM Villa Park Orange
NO. Unit Price Item Cost 84% 16%
RJ Noble ITEM COST
(Subtotal)DESCRIPTION QUANTITY UNIT
22 Sawcut & Remove Ex. and
Construct P.C.C. Cross Gutter per
SPPWC Std. Plan No. 122-3
500 SF $31.50 $15,750.00 $15,750.00 $13,230.00 $2,520.00 23 Traffic Signing, Thermoplastic
Striping, Curb Painting, Markings
& Raised Pavement Markers
1 LS $14,140.00 $14,140.00 $14,140.00 $11,877.60 $2,262.40 24 Over-excavation* 50 CY $218.00 $10,900.00 $10,900.00 $9,156.00 $1,744.00 25 Crushed Miscellaneous Base(Over-
excavation)* 80 TON $43.00 $3,440.00 $3,440.00 $2,889.60 $550.40 SUB-TOTAL 511,702.70 $511,702.70 $392,834.27 $118,868.43 Contingencies 10% $51,170.27 $39,283.43 $11,886.84
GRAND-TOTAL $562,872.97 $432,117.69 $130,755.28 0.2323
DESIGN $29,020.00 $22,278.66 $6,741.34
CONSTRUCTION MANAGEMENT & INSPECTION 15% $84,430.95 $64,817.66 $19,613.29 TOTAL PROJECT COST $676,323.92 $519,214.01 $157,109.91