FUNDING SOURCE SUMMARY
Fund # Funds Name 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 120 Prop 172 400,000 - - - - 400,000
220 Sewer 3,438,783 3,511,946 3,587,304 3,664,923 3,744,871 17,947,827 263 Traffic Improvemnt -Measure M2 3,148,415 3,245,000 3,130,000 3,345,000 3,180,000 16,048,415 270 Gas Tax Maintenance 275,000 275,000 275,000 275,000 275,000 1,375,000 274 Rmra Road Maint Rehabilitation Account 3,400,000 3,500,000 3,600,000 3,700,000 3,800,000 18,000,000 287 TSIP Citywide 1,724,000 310,000 210,000 290,000 60,000 2,594,000 310 Community Development Block Grant 672,390 - - - - 672,390 500 Capital Projects 3,355,530 4,290,000 9,670,000 2,670,000 2,820,000 22,805,530 510 Park Acquisition (Infill) 2,594,125 175,000 130,000 2,630,000 130,000 5,659,125 512 El Modena Park Facility - Cell Tower Fee 300,000 - - - - 300,000 550 Reimbursable Capital Projects 2,412,746 3,350,000 - 100,000 - 5,862,746 553 CAPITAL BOND PROCEEDS 50,000 - - - - 50,000
560 Fire Facility Fee Districts All Com 6/07 250,000 100,000 90,000 90,000 40,000 570,000 570 Police Facility Fees 50,000 - - - - 50,000
573 Library Facility Fees 201,126 21,000 - - - 222,126
600 Water 5,220,000 5,250,000 5,350,000 5,900,000 5,800,000 27,520,000 790 Computer Replacement 972,000 1,210,000 1,257,000 1,376,000 1,145,000 5,960,000 954 City Trf: Merged 2008 Tax Exempt Bonds 170,000 70,000 70,000 70,000 70,000 450,000 Total 28,634,115 25,307,946 27,369,304 24,110,923 21,064,871 126,487,159 1 Department 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total Community Services 2,894,125 1,025,000 130,000 2,630,000 130,000 6,809,125 Fire 250,000 1,720,000 7,090,000 90,000 40,000 9,190,000 Information Technology 300,000 420,000 450,000 550,000 300,000 2,020,000 Library 201,126 21,000 - - - 222,126
Police 672,000 790,000 807,000 826,000 845,000 3,940,000 Public Works 18,096,864 13,581,946 13,542,304 14,114,923 13,949,871 73,285,908 Public Works - Water 6,220,000 7,750,000 5,350,000 5,900,000 5,800,000 31,020,000 Total 28,634,115 25,307,946 27,369,304 24,110,923 21,064,871 126,487,159
DEPARTMENT SUMMARY
2 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 20476 El Modena Basin Area Improvements Design 230,000 - - 2,500,000 - 2,730,000 20513 New Park in West Orange - 850,000 - - - 850,000
20521 Yorba Dog Park Improvements 114,000 - - - - 114,000 20552 Park Restroom Interior Renovations 210,000 70,000 70,000 70,000 70,000 490,000 20553 Sports Court Resurfacing 60,000 60,000 60,000 60,000 60,000 300,000 20554 Parks Master Plan 270,000 - - - - 270,000
20555 Hart Park Bandshell Roof Renovation 36,000 - - - - 36,000 20557 Rampart Riverwalk (Park) 1,250,000 - - - - 1,250,000 30048 El Modena Park Area Renovation 724,125 - - - - 724,125 30053 Parking Lot Pavement Rehabilitation - 45,000 - - - 45,000 Total 2,894,125 1,025,000 130,000 2,630,000 130,000 6,809,125 Project Summary
COMMUNITY SERVICES
3 20476 El Modena Basin Area Improvements Design
PROJECT DESCRIPTION
Through a 1973 use agreement with Orange County Flood Control District (OCFCD), the City operates the El Modena Basin located north of the intersection of S. Hewes St. and E. Jordan Ave. as a public park. Currently, the El Modena Basin’s amenities include a decomposed granite walking path around the interior open space.
This project would provide area lighting to portions of the walking path and improve the walking path for an enhanced experience and may also include possible ADA access improvements as necessary. The requested funding for Fiscal Year 2025-26 includes the costs to design the project, which includes working with OCFCD for their approval on the project. Preliminary construction costs for new lighting and irrigation are approximately $2.5 million and is being proposed to be funded in Fiscal Year 2028-29.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2020-2021
Estimated Completion Date: June 2030
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20476 El Modena Basin Area Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $230,000 $0 $0 $2,500,000 $0
AMOUNT $230,000 $0 $0 $2,500,000 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
4 20513 New Park in West Orange
PROJECT DESCRIPTION
The New Park in West Orange project was approved as a part of the Community Services FY 24 CIP plan. A
2.4-acre piece of property managed by Orange County Flood Control District (OCFCD) located on W.
Chapman between interstate 5 and the 57 freeway is the identified new park location. In FY 24, the City entered into a long-term 50-year lease with OCFCD to build the park on the property.
Project design and environmental review process began in FY 24. During the park design process, OCFCD notified the City that they would be concurrently working on a levee height correction project in the Santa Ana Riverbed adjacent to the park site. The County’s levee project boundary lines will impact a portion of the new park site, so design plans from the County must be completed prior to the completion of new park plans. As such, the City will continue to work closely with OCFCD to coordinate the timing of design and construction for both projects.
City funding for construction has been identified. In addition, federal Community Projects Funding in the amount of $850,000 was awarded for construction by Congressman Correa in FY 25. City expenses will be offset by the federal funding following execution of an agreement between the City and the federal granting agency.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2030
Funding Source(s): Reimbursable Capital Projects
FINANCIAL SUMMARY
20513 New Park in West Orange
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $0 $850,000 $0 $0 $0
AMOUNT $0 $850,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
5 20521 Yorba Dog Park Improvements
PROJECT DESCRIPTION
The City owns and maintains the Dog Park at Yorba Park. This project will make improvements to the Yorba Dog Park in phases. Phase 1 will replace the decomposed granite (DG) with new hardscape. The dog park at Yorba Park currently uses a system of DG entry paths. Compaction of the DG is difficult to maintain due to foot traffic in and out of the dog park areas, causing the DG to become loose and uneven, which creates tripping hazards. The loose DG also enters the drainage system, causing blockages and reoccurring maintenance issues. At the request of the Orange Dog Park Association (ODPA), staff evaluated options for improving these areas. Installation of hardscape such as concrete pavers in place of the DG and a retaining wall will reduce overall ongoing maintenance costs. In addition, the project includes related ADA access gate, irrigation, and turf repairs.
Phase 2 includes an evaluation and possible installation of several new amenities at the Dog Park, such as shade structures, and lighting, at the request of the ODPA. The potential evaluation of these amenities will include approval from the Orange County Environmental Health Division, the Lead Enforcement Agency, for the methane monitoring system associated with the landfill upon which the Dog Park was built. Based on the results of the evaluation, a design will be completed. This phase of the overall project is pending full funding from ODPA. The appropriation currently associated with the project will fund Phase I of the project only.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: August 2025
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20521 Yorba Dog Park Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $114,000 $0 $0 $0 $0
AMOUNT $114,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
6 20552 Park Restroom Interior Renovations
PROJECT DESCRIPTION
Nineteen of the City’s parks have restroom buildings. Many of these restrooms were last renovated 15 to 20 years ago and are in need of renovation to ensure the restrooms are a safe, durable, and functional space for public use. This project will involve initial evaluation, design, and renovation of facilities that are past their useful life or are in need of an update in subsequent years. A specific scope will be developed for each restroom depending on individual needs. Estimates to rehabilitate each restroom varies, so project budget will vary every fiscal year. Based upon site inspections and evaluations, the first restroom facilities in need of rehabilitation are at Hart Park.
PROJECT DETAILS
Project Type: Ongoing
Estimated Completion Date: Ongoing
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20552 Park Restroom Interior Renovations
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $210,000 $70,000 $70,000 $70,000 $70,000 AMOUNT $210,000 $70,000 $70,000 $70,000 $70,000
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
7 20553 Sports Court Resurfacing
PROJECT DESCRIPTION
The City has 22 parks, of which, several have sports courts. Parks with either tennis/pickleball, basketball, volleyball, and/or handball courts include Steve Ambriz, El Camino Real, Grijalva, Hart, Santiago Hills, and Serrano Parks. Court surfacing is specialized and requires maintenance on a regular schedule in order to maintain a safe playing surface. A typical maintenance schedule includes court resurfacing every five years. The oldest courts were last resurfaced in 2010, 2012, and 2014. With a total of 10 sports courts, the proposed court resurfacing program will resurface two courts annually so that all courts are resurfaced every 5 years. All 10 courts have been assessed by staff and priority for resurfacing has been based upon current conditions.
Estimates to resurface each sports court varies, so project budget will vary every fiscal year. Grijalva Park basketball courts were resurfaced in FY 25. The next courts most in need of resurfacing currently are Hart Park tennis courts.
PROJECT DETAILS
Project Type: Ongoing
Estimated Completion Date: Ongoing
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20553 Sports Court Resurfacing
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $60,000 $60,000 $60,000 $60,000 $60,000 AMOUNT $60,000 $60,000 $60,000 $60,000 $60,000
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
8 20554 Parks Master Plan
PROJECT DESCRIPTION
The current Master Plan for Park Facilities, Recreation, and Community Services is from 1999. This project would initiate and develop a parks and recreation masterplan to determine long-term strategies that will guide how the City’s community parks and recreation facilities are developed, maintained, and optimized. The comprehensive document would cover a range of topics, including Vision, Needs assessment, Priorities, Policies, and a financial plan. The masterplan will consider the City’s existing park system, facilities, and programs and will examine the community’s recreational, programming, environmental, and maintenance needs. Practices for creating the parks and recreation masterplan will include collecting qualitative and quantitative data, engaging the community, creating an action plan, and outlining a plan for funding.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: July 2027
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20554 Parks Master Plan
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $270,000 $0 $0 $0 $0
AMOUNT $270,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
9 20555 Hart Park Bandshell Roof Renovation
PROJECT DESCRIPTION
The Hart Park Bandshell is a historic structure within Hart Park. Wear and tear and damage caused by a fallen tree limb have caused the need to repair the historic roof. This project will be a tile lift and relay which involves removing the existing tile layer and underlayment of the roof and then reinstalling the tiles. New tiles will be installed to replace any broken tiles.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20555 Hart Park Bandshell Roof Renovation
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $36,000 $0 $0 $0 $0
AMOUNT $36,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
10 20557 Rampart Riverwalk (Park)
PROJECT DESCRIPTION
The City is working to secure an operating agreement with OC Public Works for two parcels managed by Orange County Flood Control along the Santa River. The smaller of the two is a narrow parcel, measuring roughly 1 acre, and located next to N. Rampart St., just north of W. Chapman Ave., adjacent to the bike trail, and parallel to the 57 FWY. The parcel has been identified as a location for a new passive park in District 2 that will feature a proposed walking path, dog amenity/park, and water bottle filling station, along with existing mature shade trees. A preliminary conceptual design and cost estimate for design and construction is currently in development.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: 2027
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20557 Rampart Riverwalk Park
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $1,250,000 $0 $0 $0 $0
AMOUNT $1,250,000 $0 $0 $0 $0
Powered by OpenGov
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
11 30048 El Modena Park Area Renovation
PROJECT DESCRIPTION
Several of the amenities at El Modena Park are in need of replacement or repair in order to maintain a safe and functional park environment for patrons. Improvements were planned as a phased project. Phase 1 was completed in FY 23 and included irrigation improvements and installation of a new tot lot shade structure. Phase 2, also completed in FY 23, included installation of rubberized surfacing at the tot lot.
Phase 3 of the project includes design and installation of a new backstop, fencing, poles, and netting around the existing baseball field to address safety concerns related to rogue foul balls. New netting installed along the 3rd baseline will be 70’ high, which will deter foul balls from flying into the street and into neighboring properties. A new 40-foot-tall chain link backstop will include an overhead netting hood. The purpose of the hood is to address foul balls that fly over the current backstop into neighboring houses which cause liability issues due to property damage. This project will also include replacement of failing retaining walls and surface and drainage improvements to the field.
The design process is scheduled for completion in FY 25, with construction anticipated in FY 26. Once the design phase is complete, staff will pursue Major League Baseball (MLB) grant funding to supplement 512 funds. The MLB grant would provide a 50% match, but the City will have to demonstrate full funding of the project to apply. The full funding requirement can be met by utilizing all 512 funds available and supplementing the difference with 510 funds. If the City does not receive the grant funding, the project will be reevaluated.
PROJECT DETAILS
Project Type: One-Time
Estimated Project Completion Date: December 2026
Funding Source(s): El Modena Park Facility - Cell Tower Fee; Park Acquisition (Infill)
FINANCIAL SUMMARY
30048 El Modena Park Area Renovation
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
El Modena Park Facility - Cell Tower Fee $300,000 $0 $0 $0 $0 Park Acquisition (Infill) $424,125 $0 $0 $0 $0
AMOUNT $724,125 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
12 30053 Parking Lot Pavement Rehabilitation
PROJECT DESCRIPTION
The asphalt parking lot pavement in parks are in various stages of degradation and will require protective measures over the next several years. As part of a multi-year parking lot pavement rehabilitation initiative, successful pavement maintenance and rehabilitation treatments have been completed at all City Parks with parking lots within the last eight years with the exception of Steve Ambriz Park. This project is scheduled to resume in FY 27.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Park Acquisition (Infill)
FINANCIAL SUMMARY
30053 Parking Lot Pavement Rehabilitation
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Park Acquisition (Infill) $0 $45,000 $0 $0 $0
AMOUNT $0 $45,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
13 Project Summary
COMMUNITY SERVICES
Carryover Project Balance as of April 1, 2025
20315 Hart Park Pickleball and Fitness Circuit 2,483,873 20321 Grijalva Master Plan Update 100,000
20437 Park Signage Installation 246,923
20477 Area Lighting Replacement at Grijalva 429,315
20506 Ball Field Netting 200,000
20519 Skate Park at Grijalva 1,659,907
20544 Serrano Lodge Pole Fencing 39,000
20547 El Camino Real Exercise Equipment -
30133 Hart Park Field Improvements 128,239
-
Total 5,287,257
14 20315 Hart Park Pickleball and Fitness Circuit
CARRYOVER PROJECT
PROJECT DESCRIPTION
The pickleball facility and fitness circuit has been designed to fulfill the recreational needs of the surging pickleball community, as well as provide a space for other exercise. The new facilities will be located in the southwest portion of the park, adjacent to the existing orange grove to create a unique setting overlooking the park. Facility amenities include ten lighted pickleball courts, shaded outdoor fitness equipment, area and pathway lighting, paved access to courts and amenities, shaded spectator seating, spaces for gathering, fencing, wind screens, benches, drinking fountains, trash receptacles, bike racks, landscaping, and signage. In FY 22, Congressman Lou Correa secured $2 million in federal FY 22 Community Projects Funding for this project. The City committed an additional $750,000 to the project which included design.
In FY 24, the City completed environmental review and design of the project. Construction will begin in mid2025 and is anticipated to be completed by the end of 2025.
PROJECT DESCRIPTION
Project Type: One-Time
Starting Fiscal Year: 2016-2017
Estimated Completion Date: December 2025
Funding Source(s): Park Acquisition (Infill);
Reimbursable Capital Projects
Total Budget: $2,750,000
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
15 20321 Grijalva Park Master Plan Update
CARRYOVER PROJECT
PROJECT DESCRIPTION
The City owns the 42-acre Grijalva Park site which is being developed in phases. In 2003, Phase I was completed on 15 acres and includes an active park with soccer fields, a tot lot, and a small activity room. In 2005, a Grijalva Park Master Plan was developed for the remaining 27 acres which included a sports center/gymnasium, skate park, amphitheater, additional restrooms, picnic facilities, an aquatics center, and additional parking. In 2011, the Sports Center at Grijalva Park was opened, along with adjacent parking. Nine acres remained undeveloped. In 2019, the City Council gave their support for four community partners to fundraise to develop the vacant property. Since then, three groups began to fundraise for amenities including a skatepark, community arts theater, and community/library/senior center. In 2022, the City Council funded the skate park portion of the plan, which is a separate CIP.
This project has carryover funding of $100,000. As the Master Plan has evolved since 2005, the carryover funding would be used to reconceptualize the remaining undeveloped acres to understand what will feasibly fit within the allowable open space. The reconceptualized plan would also include an updated estimate regarding the parking necessary to accommodate all the proposed amenities and suggest what, if any, amendments or technical memoranda need to accompany the existing Mitigated Negative Declaration.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2016-2017
Estimated Completion Date: December 2025
Funding Source(s): Park Acquisition (Infill)
Total Budget: $100,000
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
16 20437 Park Signage Installation
CARRYOVER PROJECT
PROJECT DESCRIPTION
Park signage consists of two major types: monument signs and regulatory signs. Phase one of this project consisted of replacing monument signs at Eisenhower (2), El Modena, El Modena Basin, Hart (2), La Veta, and Killefer Parks in FY 23. Phase two of this project included an evaluation of existing regulatory signage and replacement of missing and/or damaged regulatory signs throughout City parks and bike trails. Fabrication and installation of monument signs, new park rules signs, and bike trail rules signage was completed in FY 24.
Landscape improvements around the new Hart Park monument sign on Glassell Street also occurred in FY
24. Phase three, nearing completion in FY 25, includes the replacement of other missing and/or damaged regulatory signs throughout City parks and will update the entry adjacent to the new Hart Park monument sign located at the Glassell Street entrance.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: Fall 2025
Funding Source(s): Park Aquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
17 20477 Area Lighting Replacement at Grijalva Park
CARRYOVER PROJECT
PROJECT DESCRIPTION
Currently, there are a total of 54 light poles providing area/pathway lighting for Grijalva Park (side A). The lighting was designed with metal poles mounted on concrete foundations at ground level. Deterioration near the base of these poles has resulted in the need to replace several light poles in past years. Despite past measures taken to protect the poles, deterioration progresses due to continued corrosion. Several light poles have now been removed, including two which came down during heavy winds. Nine poles in total have been removed due to safety concerns and all others are being evaluated regularly. The objective of this project is to replace all the area lighting to include new poles and fixtures, designed to resist corrosion. Design was completed in FY 23 and construction is expected to be completed by early FY 26. This project is partially funded through the Per Capita Allocation program funded through Prop 68.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2020-2021
Estimated Completion Date: Fall 2025
Funding Source(s): Park Aquisition (Infill);
Reimbursable Grants
Total Budget: $614,400
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
18 20506 Olive Park Netting Replacement
CARRYOVER PROJECT
PROJECT DESCRIPTION
Olive Park is home to youth baseball programs. Park amenities include several ball fields that are adjacent to homes. The existing netting in some areas is damaged or non-existent, creating safety concerns for fly and foul balls. This project will include the design and construction of new netting. The anticipated cost is $200,000.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2021-2022
Estimated Completion Date: Early 2026
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
19 20519 SKATE PARK AT GRIJALVA
CARRYOVER PROJECT
PROJECT DESCRIPTION
At the City Council meeting of November 15, 2022, the City Council approved the use of $1.75 million in park development fees collected from a housing development in the east side of Orange, known as Orange Heights, to build a skate park at Grijalva Park. In FY 24, the City began the design process which included collecting input from stakeholders and local skaters. Construction is anticipated to begin in FY 26.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: Fall 2026
Funding Source(s): Capital Projects; Grijalva Park Fund
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
20 20544 Serrano Park Lodge Pole Fencing
Installation
CARRYOVER PROJECT
PROJECT DESCRIPTION
Serrano Park has several park amenities, including a large open field adjacent to the right-of-way sidewalk.
The park and the passive field are not fenced in or gated. As the open field is accessible from the street, it often experiences vandalism as a result of unauthorized vehicles intentionally driving onto the grass. This project would install approximately 475 linear feet of new, 3’ high, single rail lodge pole fencing along two sections of the park to prevent unauthorized vehicle access into the park. The poles will be installed at one section off Sierra Vista Drive and another section along the base of the slope that separates the park from the adjacent HOA landscaped area.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: Fall 2025
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
21 20547 El Camino Real Park Exercise Equipment
CARRYOVER PROJECT
PROJECT DESCRIPTION
Currently, the City has two parks with outdoor exercise equipment, Grijalva and Shaffer Parks. The fitness equipment at these locations are popular and highly used by park patrons. This proposed project would include design and installation of a lighted, shaded exercise equipment station at El Camino Real Park. The installation of the exercise equipment will encourage an active and healthy lifestyle for Orange residents and El Camino Real Park patrons. The project is pending grant funding, and a project schedule will be determined based upon grant award.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2027
Funding Source(s): Park Acquisition (Infill)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
22 30133 Hart Park Diamond 1 Field Improvements
CARRYOVER PROJECT
PROJECT DESCRIPTION
Located at Hart Park, Diamond 1 is used as a collegiate level baseball field. Currently, the City partners with Chapman University (Chapman) and Orange Lutheran High School (OLU) to maintain this premier field.
Installation of ball field netting along the first and third base foul lines will protect park users and the adjacent neighborhood from foul balls. Design was completed in FY 25. The City is working with Chapman and OLU to determine cost sharing for the project
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2019-2020
Estimated Completion Date: June 2028
Funding Source(s): Park Acquisition (Infill);
Reimbursable Capital Projects
Total Budget: $250,000
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
CAPITAL IMPROVEMENT PROGRAM
COMMUNITY SERVICES
FISCAL YEAR 2025-2026
23 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 12406 Signal Pre-Emption Installation 50,000 50,000 40,000 40,000 40,000 220,000 20334 Fire Station Repairs 200,000 50,000 50,000 50,000 - 350,000 20505 Fire Station 5 Exercise Room Addition - 720,000 - - - 720,000 20523 Fire Station 2 Remodel - 900,000 7,000,000 - - 7,900,000 Total 250,000 1,720,000 7,090,000 90,000 40,000 9,190,000 Project Summary
FIRE
Funding for some of the below projects includes development impact fees and is dependent on receipt of development revenue. 24 12406 Signal Pre-Emption Installation
PROJECT DESCRIPTION
The Opticom Traffic Pre-emption project involves the purchase and installation of traffic signal pre-emption equipment on the City’s major roadways, intersections, and fire apparatus. This technology enables emergency vehicles to navigate through traffic more efficiently and safely, reducing response times and potentially saving lives during critical situations. Pre-emption equipment installed on fire apparatus triggers the associated equipment within traffic signals to control signal lights for oncoming fire apparatus right-of-way during Code 3 responses. This programming enhances the overall effectiveness of emergency response operations and contributes to public safety.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Fire Facility Fees
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
12406 Signal Pre-Emption Installation
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Fire Facility Fee Districts All Com 6/07 $50,000 $50,000 $40,000 $40,000 $40,000 AMOUNT $50,000 $50,000 $40,000 $40,000 $40,000
CAPITAL IMPROVEMENT PROGRAM
FIRE DEPARTMENT
FISCAL YEAR 2025-2026
25 20334 Fire Station Repairs
PROJECT DESCRIPTION
The Fire Station Maintenance project provides funding to address maintenance issues which go beyond current replacement capacities. This project addresses major station maintenance and repairs, such as painting, carpeting, roof repairs, and any necessary station updates. Regular maintenance is essential to maintaining readiness and operational effectiveness during emergencies, enhancing the safety of both the firefighters and the community they serve.
In FY26, the department is scheduled to replace the flooring at Station 8, update the floors at Station 6, and carry out essential repairs to the building at Station 7, which was formerly occupied by the Orange County Intelligence Assessment Center (OCIAC).
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): FIRE FACILITY FEE DISTRICTS ALL
COM 6/07
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20334 Fire Station Repairs
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Fire Facility Fee Districts All Com 6/07 $200,000 $50,000 $50,000 $50,000 $0 AMOUNT $200,000 $50,000 $50,000 $50,000 $0
CAPITAL IMPROVEMENT PROGRAM
FIRE DEPARTMENT
FISCAL YEAR 2025-2026
26 20505 Fire Station 5 Exercise Room Addition
PROJECT DESCRIPTION
This project establishes funding for the addition of an exercise room at Fire Station 5. Constructed in 1965, Fire Station 5 currently lacks the necessary space to store and utilize exercise equipment, crucial for cultivating a stronger and more physically fit workforce. Presently, the exercise equipment is located on the apparatus bay floor, alongside the frontline apparatus used in daily emergencies, significantly impeding the parking of emergency vehicles within the structure. The addition of an exercise room to the rear of Station 5 will provide flexibility for the future operational needs of the Fire Department by creating more space for personnel and apparatus. The existing fire station will largely remain unchanged, with some minor aesthetic improvements to complement the new room addition.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Capital Projects
FINANCIAL SUMMARY
20505 Fire Station 5 Exercise Room Addition
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $0 $720,000 $0 $0 $0
AMOUNT $0 $720,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
FIRE DEPARTMENT
FISCAL YEAR 2025-2026
27 20523 Fire Station 2 Remodel
PROJECT DESCRIPTION
This project establishes funding for the design and construction of a permanent facility for Fire Station 2, which provides emergency service response to the central portion of the City and neighboring City of Villa Park. The new facility will be designed to accommodate up to three frontline emergency vehicles and eight fire suppression personnel. This project will combine the newly built single-bay apparatus and workout rooms with 9,500 square feet of new construction, which will include the following accommodations: office, living room, kitchen, (8) sleeping dorms, (5) restrooms, training classroom, and two-bay apparatus room.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2028
Funding Source(s): Capital Projects
FINANCIAL SUMMARY
20523 Fire Station 2 Remodel
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $0 $900,000 $7,000,000 $0 $0
AMOUNT $0 $900,000 $7,000,000 $0 $0
CAPITAL IMPROVEMENT PROGRAM
FIRE DEPARTMENT
FISCAL YEAR 2025-2026
28 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 20282 Personal Computer Replacements 200,000 200,000 200,000 200,000 200,000 1,000,000 20510 Storage Area Network Replacement - 120,000 150,000 250,000 - 520,000 30071 Fiber Optic Cable Replacements 100,000 100,000 100,000 100,000 100,000 500,000 -
Total 300,000 420,000 450,000 550,000 300,000 2,020,000 Project Summary
INFORMATION TECHNOLOGY
29 20282 Personal Computer Replacements
PROJECT DESCRIPTION
A recurring annual replacement of the City's aging PC (desktops, laptops, tablets) inventory is recommended.
This initiative is a recommended guideline to replace a fourth of the City's PC inventory to prevent the inventory from becoming excessively aged and prevent impact to staff productivity due to PC failures.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Computer Replacement
FINANCIAL SUMMARY
20282 Personal Computer Replacements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Computer Replacement $200,000 $200,000 $200,000 $200,000 $200,000 AMOUNT $200,000 $200,000 $200,000 $200,000 $200,000
CAPITAL IMPROVEMENT PROGRAM
INFORMATION TECHNOLOGY
FISCAL YEAR 2025-2026
30 20510 Storage Area Network Replacement
PROJECT DESCRIPTION
IT forecasts costs to replace end of life fabric switches in FY27. For FY28, IT forecasts costs to replace backup storage for Civic Center and the Police Department. For FY29, IT forecast costs to replace Civic Center SAN storage.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Computer Replacement
FINANCIAL SUMMARY
20510 Storage Area Network Replacement
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Computer Replacement $0 $120,000 $150,000 $250,000 $0
AMOUNT $0 $120,000 $150,000 $250,000 $0
CAPITAL IMPROVEMENT PROGRAM
INFORMATION TECHNOLOGY
FISCAL YEAR 2025-2026
31 30071 Fiber Optic Cable Replacements
PROJECT DESCRIPTION
Having City locations on our own fiber increases security and bandwidth. IT is proposing a citywide fiber assessment be performed in FY26 to provide recommendations for proactive replacement of aging fiber infrastructure.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Computer Replacement
FINANCIAL SUMMARY
30071 Fiber Optic Cable Replacements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Computer Replacement $100,000 $100,000 $100,000 $100,000 $100,000 AMOUNT $100,000 $100,000 $100,000 $100,000 $100,000
CAPITAL IMPROVEMENT PROGRAM
INFORMATION TECHNOLOGY
FISCAL YEAR 2025-2026
32 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 20461 Main Library Facility Improvements 126,906 21,000 - - - 147,906 20462 Taft Library Facility Improvements 26,345 - - - - 26,345 20463 El Modena Library Facility Improvements 47,875 - - - - 47,875 Total 201,126 21,000 - - - 222,126
Project Summary
LIBRARY
33 20461 Main Library Facility Improvements
PROJECT DESCRIPTION
This project will encompass all facility improvements for Main Library.
The north and south entrance automatic doors need to be replaced for improved accessibility. The dumbwaiter elevator which transports surplus Friends books to the basement needs to be replaced. These projects are expected to be completed by December 2025, and funding for these projects reflects revenue received from the Building Forward Main Grant.
Repairs to the tower roof and removal of the History Center sink are needed to address leaks that are affecting local archives. Cabinetry will be installed in the sink space. In the Tower Reading Room, in-laid carpet will be replaced with carpet tiles and wood floors will be replaced with with luxury vinyl tile flooring.
These flooring types are easier to maintain in high traffic areas. In the Community room, carpet squares and baseboards will be replaced to match library-wide carpet squares/baseboards. Finally, the ceiling wheels in the Steve Ambriz reading room will be repaired or replace to allow the doors to function properly. These projects are expected to be completed by June 2026. Funding for these projects reflects revenue received from library facility development fees.
PROJECT DETAILS
Project Type: Ongoing
Estimated Completion: June 2026
Funding Source(s): Capital Projects; Reimbursable
Capital Projects; Library Facility Fees; Major Building Improvements
FINANCIAL SUMMARY
20461 Main Library Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Library Facility Fees $126,906 $21,000 $0 $0 $0
AMOUNT $126,906 $21,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
LIBRARY
FISCAL YEAR 2025-2026
34 20462 TAFT LIBRARY FACILITY IMPROVEMENTS
PROJECT DESCRIPTION
This project will encompass all facility improvements for Taft Library. The automatic entrance doors need to be replaced for improved accessibility. The windows need replacement and reframing due to aging and vandalism. These projects are expected to be completed by December 2025, and funding for these projects reflects revenue received from the Building Forward Taft Grant. The lighting control panel was upgraded a couple of years ago; however, additional work on the panel is required to complete the project to improve accessibility and efficiency. This project is expected to be completed by June 2026, and the funding reflects revenue received from library facility development fees.
PROJECT DETAILS
Project Type: Ongoing
Estimated Project Completion Date:June 2026
Funding Source(s): Capital Projects; Library Facility
Fees; Major Building Improvements
FINANCIAL SUMMARY
20462 Taft Library Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Library Facility Fees $26,345 $0 $0 $0 $0
AMOUNT $26,345 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
LIBRARY
FISCAL YEAR 2025-2026
35 20463 El Modena Library Facility Improvements
PROJECT DESCRIPTION
This project will encompass all facility improvements for El Modena Library. The automatic entrance doors need to be replaced for improved accessibility. Roofing improvements are needed to mitigate leaks and restore its useful life. These projects are expected to be completed by December 2025, and funding for these projects reflects revenue received from the Building Forward El Modena Grant. The monument sign needs to be replaced because the partner organization OCPT listed is no longer on site. The concrete behind the emergency exit gate needs to be refinished to allow for better emergency access. Installation of a charging station and concrete work behind the building is needed in anticipation of an outreach library vehicle in the future. These projects are expected to be completed by June 2026. The funding reflects revenue received from library facility development fees.
PROJECT DETAILS
Project Type: Ongoing
Estimated Completion Date: June 2026
Funding Source(s): Library Facility Fees
FINANCIAL SUMMARY
20463 El Modena Library Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Library Facility Fees $47,875 $0 $0 $0 $0
AMOUNT $47,875 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
LIBRARY
FISCAL YEAR 2025-2026
36 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 30196 Police Enterprise System 672,000 790,000 807,000 826,000 845,000 3,940,000 Total 672,000 790,000 807,000 826,000 845,000 3,940,000 Project Summary
POLICE
37 30196 Police Enterprise System
PROJECT DESCRIPTION
The Police Enterprise System project provides a flexible platform to help the Police Department reach its vision of adopting a network solution that allows all systems to connect and integrate with one another to meet the objectives of the department. The system consolidates and manages police hardware and software including existing Tasers, body worn, fleet, and interview cameras, Standards for reporting, Axon Air for drone management along with the evidence.com portal, which is cloud based for data storage and sharing. The Records and Dispatch component is not able to integrate into one single solution and must be maintained as a stand-alone system for basic operations. The project is led by the Police Department and primarily funded through the Computer Replacement fund.
PROJECT DETAILS
Project Type: Ongoing
Estimated Completion Date: June 2032
Funding Source(s): Computer Replacement
FINANCIAL SUMMARY
30196 Police Enterprise System
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Computer Replacement $672,000 $790,000 $807,000 $826,000 $845,000 AMOUNT $672,000 $790,000 $807,000 $826,000 $845,000
CAPITAL IMPROVEMENT PROGRAM
POLICE DEPARTMENT
FISCAL YEAR 2025-2026
38 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 11328 ADA Improvements 100,000 - - - - 100,000
12982 Corporate Yard Renovations 100,000 - - - - 100,000 13115 Pavement Management Program Survey 60,000 110,000 60,000 110,000 60,000 400,000 13120 Pavement Management Program 8,250,000 8,650,000 8,750,000 8,950,000 9,050,000 43,650,000 15508 Sewer Line Maintenance & Replacement 2,438,783 2,511,946 2,587,304 2,664,923 2,744,871 12,947,827 15509 Sewer Cleaning & Video 500,000 500,000 500,000 500,000 500,000 2,500,000 16065 Quiet Zone Maintenance 50,000 50,000 50,000 50,000 50,000 250,000 16302 Minor Traffic Control Devices 250,000 250,000 250,000 250,000 250,000 1,250,000 16304 Biennial Traffic Signal Coordination - 95,000 - 95,000 - 190,000 16305 Traffic Signal Controller Changeout 125,000 125,000 125,000 125,000 125,000 625,000 19826 Police Headquarter Exterior Wall Sealing 20,000 20,000 20,000 20,000 20,000 100,000 20329 Chapman & Batavia Left Turn Signal Modification 30,654 - - - - 30,654 20353 Chapman & Grand Left Turn Signal Modification 75,000 - - - - 75,000 20354 Chapman & Cambridge Left Turn Signal Modification 75,000 - - - - 75,000 20374 Streetlight Pole Replacement Program 500,000 500,000 500,000 500,000 500,000 2,500,000 20378 Katella & Batavia Signal Network Extension - - 150,000 - - 150,000 20379 Batavia & Taft Signal Network Extension - 170,000 - - - 170,000 20380 Glassell St Signal Network Extension - 100,000 - - - 100,000 20382 Katella Ave Signal Network Extension 1,300,000 - - - - 1,300,000 20397 Parker Street Restriping - - - 100,000 - 100,000
20425 Tustin St Signal Synchronization 906,387 - - - - 906,387 20430 Storm Drain Improvements 500,000 500,000 500,000 500,000 500,000 2,500,000 20443 Orange Community Shuttle Feasibility Study 8,550 - - - - 8,550 20483 Police Facility Improvements 100,000 - - - - 100,000 20502 Fire Station Apparatus Bay Door Replacement 400,000 - - - - 400,000 20518 Pedestrian Beacon Upgrades 277,300 - - - - 277,300 20525 Santiago Canyon Road Signal Network Extension - - - 250,000 - 250,000 20539 Citywide Bicycle Lane Enhancements - - - - 150,000 150,000 20556 Orange Olive Metrolink Fence Construction 657,800 - - - - 657,800 30150 Local Roadway Safety Plan - - 50,000 - - 50,000
30240 Kraemer Blvd/Glassell St/Grand Ave RTSSP 330,000 - - - - 330,000 30241 Ball Rd/Taft Ave RTSSP 120,000 - - - - 120,000
30247 Citywide Active Transportation Plan 350,000 - - - - 350,000 30264 CDBG Street Improvements Fiscal Year 2025-26 572,390 - - - - 572,390 -
Total 18,096,864 13,581,946 13,542,304 14,114,923 13,949,871 73,285,908 Project Summary
PUBLIC WORKS
39 11328 ADA Improvements
PROJECT DESCRIPTION
This project will modify curbs and ramps at various locations throughout the City to comply with the Americans with Disabilities Act (ADA) regulations. This has been an ongoing project, partially funded with Community Development Block Grants (CDBG).
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Community Development Block
Grant (CDBG)
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
11328 ADA Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Community Development Block Grant $100,000 $0 $0 $0 $0
AMOUNT $100,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
40 12982 Corp Yard Renovations
PROJECT DESCRIPTION
Renovation of the Corporation Yard has completed the final design. This project will focus on improving space allocation, enhancing paths of travel and safety, maximizing equipment and vehicle storage, and redistributing departments’ storage areas of Police, Community Services, and Public Works. Upgrades will also include necessary improvements to comply with NPDES/environmental requirements. The first construction phase includes undergrounding utilities, completing the perimeter wall, lightings, landscaping, pavement reconstruction, and building the material storage for environmental compliance. Construction of the first phase is expected to begin in the Spring of 2024. The second phase of the project includes the replacement of modified wooden sheds / storage containers to prefabricated metal storage buildings along with building a permanent transfer station for environmental compliance. City staff is evaluating options for funding for the second phase.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2028
Funding Source(s): Capital Bond Proceeds (553) and
Capital Projects (500)
FINANCIAL SUMMARY
12982 Corp Yard Renovations
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Police Facility Fees $50,000 $0 $0 $0 $0
CAPITAL BOND PROCEEDS $50,000 $0 $0 $0 $0
AMOUNT $100,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS DEPARTMENT
FISCAL YEAR 2025-2026
41 13115 Pavement Management Program Survey
PROJECT DESCRIPTION
Windshield field surveys of the City's pavement are conducted every two years for arterial streets and every six years for local streets to determine the pavement condition indexes for each segment. These surveys are conducted as a requirement for numerous grant programs, OCTA bi-annual reports, and overall pavement management programs. This project also includes traffic data collection including traffic counts, parking surveys, and speed surveys to be done bi-annually.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Traffic Improvement - Measure M2,
TSIP
FINANCIAL SUMMARY
13115 Pavement Management Program Survey
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $60,000 $40,000 $60,000 $40,000 $60,000
Traffic Improvemnt -Measure M2 $0 $70,000 $0 $70,000 $0 AMOUNT $60,000 $110,000 $60,000 $110,000 $60,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
42 13120 Pavement Management Program
PROJECT DESCRIPTION
The City's Pavement Management Program identifies the condition of 320 miles of streets and identifies the maintenance needs of this roadway system. This program requires $6 million annually for slurry sealing, asphalt overlays, and reconstructions to maintain the City's Pavement Condition Index rating. This fiscal year's CIP lists other road maintenance projects and CDBG projects. This project outlines the remaining funding needs from Gas Tax, Measure M2, and Capital Projects. Approximately $8.2 million of new funding will be allocated to the various roadway management projects for this fiscal year.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Traffic Improvement - M2, Gas Tax
Maintenance, RMRA Road Maintenance Rehabilitation,
Capital Projects, Reimbursable Capital Projects
FINANCIAL SUMMARY
13120 Pavement Management Program
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 Rmra Road Maint Rehabilitation Account $3,400,000 $3,500,000 $3,600,000 $3,700,000 $3,800,000 Traffic Improvemnt -Measure M2 $2,700,000 $3,000,000 $3,000,000 $3,100,000 $3,100,000 Gas Tax Maintenance $150,000 $150,000 $150,000 $150,000 $150,000 AMOUNT $8,250,000 $8,650,000 $8,750,000 $8,950,000 $9,050,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2024-2025
43 15508 Sewer Line Maintenance & Replacement
PROJECT DESCRIPTION
This project annually fixes hot spots due to root intrusion, offset joints, and damaged sewer mains. It also replaces both hydraulically and structurally deficient sewer mains. As part of the 2023 Sanitation Fee study, a new capital improvement component has been established to address the replacement and upgrade needs of the City’s sewer system. This fiscal year, $2.4 million is available to fund necessary sewer facility improvements at various locations citywide.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Sewer Construction
FINANCIAL SUMMARY
15508 Sewer Line Maintenance
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Sewer $2,438,783 $2,511,946 $2,587,304 $2,664,923 $2,744,871 AMOUNT $2,438,783 $2,511,946 $2,587,304 $2,664,923 $2,744,871
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2024-2025
44 15509 Sewer Cleaning & Video
PROJECT DESCRIPTION
The State's Waste Discharge Elimination (WDR) requires the City to complete a condition assessment of its entire 300+ mile sewer line system and develop a rehabilitation and replacement plan. Additional contract services are needed to comply with WDR requirements.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Sewer
FINANCIAL SUMMARY
15509 Sewer Cleaning & Video
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Sewer $500,000 $500,000 $500,000 $500,000 $500,000
AMOUNT $500,000 $500,000 $500,000 $500,000 $500,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
45 16065 Quiet Zone Maintenance
PROJECT DESCRIPTION
This project provides for the annual Quiet Zone and Safe Railroad Crossing maintenance agreement with Southern California Regional Rail Authority and any related maintenance or improvements necessary for compliance.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): CITY TRF: MERGED 2008 TAX
EXEMPT BONDS
FINANCIAL SUMMARY
16065 Quiet Zone Maintenance
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
City Trf: Merged 2008 Tax Exempt Bonds $50,000 $50,000 $50,000 $50,000 $50,000 AMOUNT $50,000 $50,000 $50,000 $50,000 $50,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
46 16302 Minor Traffic Control Devices
PROJECT DESCRIPTION
This project provides for the annual Quiet Zone and Safe Railroad Crossing maintenance agreement with Southern California Regional Rail Authority and any related maintenance or improvements necessary for compliance.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Traffic Improvement - Measure M2,
TSIP, Capital Projects
FINANCIAL SUMMARY
16302 Minor Traffic Control Devices
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $200,000 $200,000 $200,000 $200,000 $200,000 Traffic Improvemnt -Measure M2 $50,000 $50,000 $50,000 $50,000 $50,000 AMOUNT $250,000 $250,000 $250,000 $250,000 $250,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
47 16304 Biennial Traffic Signal Coordination
PROJECT DESCRIPTION
This project is for the on-going implementation of studies and improvements for traffic signals along the City's major arterials within its boundaries. The studies include traffic counts, analysis of traffic flows, provide signal timing, and synchronization. The project will provide for the traffic signal infrastructure improvements necessary to achieve optimum signal timing and synchronization. The coordinated signal timing will be implemented through the City's Traffic Management Center. Changes in traffic flow require updating at twoyear intervals. The traffic signal coordination will reduce travel times, save on gas, and reduce vehicle emissions.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Traffic Improvement - Measure M2
FINANCIAL SUMMARY
16304 Biennial Traffic Signal Coordination
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Traffic Improvemnt -Measure M2 $0 $95,000 $0 $95,000 $0 AMOUNT $0 $95,000 $0 $95,000 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
48 16305 Traffic Signal Controller Changeout
PROJECT DESCRIPTION
The City maintains 158 traffic signals. Nearly two-thirds of the controllers have recently been updated or replaced to allow for better coordination with the City's Transportation Management Center (TMC). The project is an ongoing process of updating or replacing controllers, signal cabinets and communication equipment, CCTV cameras, traffic signal battery backups, future signal controller needs, and upgrading TMC equipment and software.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Gas Tax Maintenance
FINANCIAL SUMMARY
16305 Traffic Signal Controller Changeout
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Gas Tax Maintenance $125,000 $125,000 $125,000 $125,000 $125,000 AMOUNT $125,000 $125,000 $125,000 $125,000 $125,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
49 19826 Police Headquarter Exterior Wall Sealing
PROJECT DESCRIPTION
The ceramic tile exterior of the Police Headquarters requires cleaning and sealing every five years to prevent internal damage from rainwater. This project accumulates funding which is critical for the maintenance of the Police Headquarters and will also fund other water leak repair costs.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): City Trf: Merged 2008 Tax
Exempt Bonds
FINANCIAL SUMMARY
19826 Police Headquarters Exterior Wall Sealing
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
City Trf: Merged 2008 Tax Exempt Bonds $20,000 $20,000 $20,000 $20,000 $20,000 AMOUNT $20,000 $20,000 $20,000 $20,000 $20,000
Powered by OpenGov
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
50 20329 Chapman & Batavia Left Turn Signal
Modification
PROJECT DESCRIPTION
The project will provide for a protected left-turn phase for the northbound and southbound approaches on Batavia Street at Chapman Avenue to improve operational efficiency and enhance safety. The addition of a protected left turn is an effective countermeasure that can reduce the possibility of crashes. The scope of work includes installation of signal poles and gear, controller and cabinet, CCTV camera, new conduits, wiring, battery back-up system, loop detectors, ADA ramps, and restoration of existing improvements.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2016-2017
Estimated Completion Date: June 2026
Funding Source(s): Traffic Improvement - Measure M2;
Reimbursable Capital Projects
FINANCIAL SUMMARY
20329 Chapman & Batavia Left Turn Signal Modification
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $654 $0 $0 $0 $0
Traffic Improvemnt -Measure M2 $30,000 $0 $0 $0 $0
AMOUNT $30,654 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
51 20353 Chapman & Grand Left Turn Signal
Modification
PROJECT DESCRIPTION
The project provides for a protected left-turn phase for the eastbound and westbound approaches on Chapman Avenue at Grand Street. The proposed signal modification will enhance the capacity and improve the traffic signal operation at the intersection. The project features decorative signal poles consistent with the Old Towne District theme. The scope of work includes installation of signal poles and gear, controller and cabinet, wiring, CCTV camera, electrical service; upgrading emergency vehicle preemption; and restoration of existing improvements.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): City-Wide TSIP
FINANCIAL SUMMARY
20353 Chapman & Grand Left Turn Signal
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $75,000 $0 $0 $0 $0
AMOUNT $75,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
52 20354 Chapman & Cambridge Left Turn Signal
Modification
PROJECT DESCRIPTION
The project provides for a protected left-turn phase for the eastbound, westbound, northbound, and southbound approaches at Chapman Avenue and Cambridge Street. The proposed signal modification will enhance the capacity and improve the traffic signal operation at the intersection. The scope of work includes installation of signal poles and gear, controller and cabinet, wiring, CCTV camera, and electrical service and restoration of existing improvements.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): City-Wide TSIP
FINANCIAL SUMMARY
20354 Chapman & Cambridge Left Turn Signal
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $75,000 $0 $0 $0 $0
AMOUNT $75,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
53 20374 Streetlight Pole Replacement Program
PROJECT DESCRIPTION
As a cost-saving measure, the City acquired an additional 4,359 streetlight poles from Southern California Edison (SCE) in Fiscal Year 2018. Over half the poles are steel poles. An annual pole replacement program is necessary to maintain the acquired streetlight infrastructure. This program will biannually replace 40 steel streetlight poles with City standard LED-retrofitted concrete poles and underground overhead wires. Additionally, this project provides for miscellaneous lighting, undergrounding, wiring, and pole knock downs.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Traffic Improvement - Measure M2;
Capital Projects
FINANCIAL SUMMARY
20374 Streetlight Pole Replacement
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $470,000 $470,000 $470,000 $470,000 $470,000 Traffic Improvemnt -Measure M2 $30,000 $30,000 $30,000 $30,000 $30,000 AMOUNT $500,000 $500,000 $500,000 $500,000 $500,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
54 20378 Katella & Batavia Signal Network Extension
PROJECT DESCRIPTION
The project will extend the existing City's Traffic Signal Network along Katella Avenue from Main Street to Struck Avenue and along Batavia Street from Katella Avenue to Palm Avenue. The installation of fiber optic lines will enable the City's Traffic Management Center to communicate with the traffic signals along critical arterials to improve traffic signal operations, and traffic flow. This will also allow immediate incident monitoring and response to reduce traffic congestion.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: July 2026
Funding Source(s): City-Wide TSIP
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20378 Katella & Batavia Signal Network Extension
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $0 $0 $150,000 $0 $0
AMOUNT $0 $0 $150,000 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
55 20379 Batavia & Taft Signal Network Extension
PROJECT DESCRIPTION
The project will extend the existing City's Traffic Signal Network along Taft Avenue from Shaffer Street to Main Street and along Batavia Street from Taft Avenue to Fletcher Avenue. The installation of fiber optic lines will enable the City's Traffic Management Center to communicate with the traffic signals along critical arterials to improve traffic signal operations, and traffic flow. This will also allow immediate incident monitoring and response to reduce traffic congestion.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: July 2026
Funding Source(s): City-Wide TSIP
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20379 Batavia and Taft Signal Network Extension
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $0 $170,000 $0 $0 $0
AMOUNT $0 $170,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
56 20380 Glassell St Signal Network Extension
PROJECT DESCRIPTION
The project will extend the existing City's Traffic Signal Network along Taft Avenue from Shaffer Street to Glassell Street and along Glassell Street from Taft Avenue to Lincoln Avenue. This will connect to the existing fiber lines on Glassell Street from Lincoln Avenue to Riverdale Avenue. The installation of fiber optic lines will enable the City's Traffic Management Center to communicate with the traffic signals along critical arterials to improve traffic signal operations and traffic flow. This will also allow immediate incident monitoring and response to reduce traffic congestion. Current funding is for design of the project while construction funding is requested.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: July 2027
Funding Source(s): City-Wide TSIP
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20380 Glassell St Signal Network Extension
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $0 $100,000 $0 $0 $0
AMOUNT $0 $100,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
57 20382 Katella Ave Signal Network Extension
PROJECT DESCRIPTION
The project will extend the existing City's Traffic Signal Network along Katella Avenue from Tustin Street to Santiago Boulevard and on Santiago Boulevard from Katella Avenue to Meats Avenue. The installation of fiber optic lines will enable the City's Traffic Management Center to communicate with the traffic signals along critical arterials to improve traffic signal operations and traffic flow. This will also allow immediate incident monitoring and response to reduce traffic congestion. Construction of improvements include upgrades to the controller cabinet and communication appurtenances.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2028
Funding Source(s): TSIP Citywide
FINANCIAL SUMMARY
20382 Katella Ave Signal Network Extension
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $1,300,000 $0 $0 $0 $0
AMOUNT $1,300,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
58 20397 Parker Street Restriping
PROJECT DESCRIPTION
This project will provide for the ultimate roadway configuration as the City builds out and adjacent parcels potentially redevelop. By reorganizing the existing paved roadway, this will provide features necessary to best serve various road users.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: July 2029
Funding Source(s): Reimbursable Capital Projects
FINANCIAL SUMMARY
20397 Parker Street Restriping
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $0 $0 $0 $100,000 $0
AMOUNT $0 $0 $0 $100,000 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
59 20425 Tustin St Signal Synchronization
PROJECT DESCRIPTION
The Tustin Street Traffic Signal Synchronization project a multi-jurisdictional project between First Street in Tustin and Wabash Avenue in Yorba Linda. The corridor is over eleven miles and includes 55 signals across seven jurisdictions. 25 of the signals are within the City of Orange. The benefits of signal synchronization include a reduction in travel time, improvement in travel speed, greenhouse gas reduction, less fuel consumption, and an overall better travel experience. This project will be led by City of Orange and primarily funded through OCTA's M2.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2027
Funding Source(s): City-Wide TSIP; Reimbursable
Capital Projects
FINANCIAL SUMMARY
20425 Tustin St Signal Synchronization
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $854,387 $0 $0 $0 $0
TSIP Citywide $52,000 $0 $0 $0 $0
AMOUNT $906,387 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
60 20430 Storm Drain Improvements
PROJECT DESCRIPTION
This project replaces existing deficient drainage systems and constructs new storm drain lines as needed per the Master Plan of Drainage to alleviate localized flooding.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Sewer
FINANCIAL SUMMARY
20430 Storm Drain Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Sewer $500,000 $500,000 $500,000 $500,000 $500,000
AMOUNT $500,000 $500,000 $500,000 $500,000 $500,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
61 20443 Orange Community Shuttle Feasibility Study
PROJECT DESCRIPTION
This project will explore opportunities and benefits for a new community shuttle service. The service could provide an alternative to driving while connecting key destinations such as the Outlets of Orange, medical corridor, Old Towne, and Chapman University.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Traffic Improvement - Measure M2;
Reimbursable Capital Projects
FINANCIAL SUMMARY
20443 Orange Community Shuttle Feasibility Study
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $135 $0 $0 $0 $0
Traffic Improvemnt -Measure M2 $8,415 $0 $0 $0 $0
AMOUNT $8,550 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
62 20483 Police Facility Improvements
PROJECT DESCRIPTION
This project will encompass new furniture and miscellaneous facility improvements for police facilities including paint, carpet, lighting, window tint, and network cabling. This project will replace existing furniture with a new office design, refresh interior paint throughout the department and replace existing carpet and baseboards that have far exceeded its life expectancy. Additionally, the scope of work includes replacing existing lighting with energy efficient lighting to properly illuminate current workstations and offices. One division will be revitalized each year over a span of three years.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): AB3229-COPS/STATE-(SUPPL
LAW ENF SERVS; Police Facility Fees; CITY TRF:
MERGED 2008 TAX EXEMPT BONDS
FINANCIAL SUMMARY
20483 Police Facility Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
City Trf: Merged 2008 Tax Exempt Bonds $100,000 $0 $0 $0 $0 AMOUNT $100,000 $0 $0 $0 $0
Powered by OpenGov
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
63 20502 Fire Station Apparatus Bay Door
Replacement
PROJECT DESCRIPTION
The Fire Station Apparatus Bay Door Replacement program assesses, maintains, and replaces the apparatus bay doors that provide critical access for emergency response vehicles at all 8 fire stations throughout the city. The systematic replacement program ensures all apparatus doors remain in optimal condition, minimizing the risk of malfunctions or delays during emergency response operations. It helps to mitigate the potential for unexpected door failures, reduces downtime for maintenance, and ultimately supports the continuous readiness of the fire station to respond to emergencies effectively. This is the final phase of the project, set to be completed in FY26, involving the replacement of apparatus doors at Stations 7 and 8.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Prop 172
FINANCIAL SUMMARY
20502 Fire Station Apparatus Bay Door Replacement
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Prop 172 $400,000 $0 $0 $0 $0
AMOUNT $400,000 $0 $0 $0 $0
Powered by OpenGov
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
64 20518 Pedestrian Beacon Upgrades
PROJECT DESCRIPTION
This project will upgrade and modernize existing flashing beacon systems at several pedestrian crossings throughout the City. Existing beacons that either flash perpetually or must be manually activated/de-activated will be replaced with push buttons that will activate the beacons on demand. In addition, circular beacons will be upgraded to newer rapid rectangular flashing beacons, which are expected to enhance visibility to motorists. The project will also involve minor modifications to/refurbishment of ancillary equipment, roadway features, and traffic control devices, including, but not limited to, poles, pavement markings, signs, and curb ramps.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Capital Projects; Reimbursable
Capital Projects
FINANCIAL SUMMARY
20518 Pedestrian Beacon Upgrades
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $27,730 $0 $0 $0 $0
Reimbursable Capital Projects $249,570 $0 $0 $0 $0
AMOUNT $277,300 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
65 20525 Santiago Canyon Road Signal Network
Extension
PROJECT DESCRIPTION
The project will extend the existing City's Traffic Signal Network along Santiago Canyon Road from Cannon Street to Chapman Avenue. The installation of fiber optic lines will enable the City's Traffic Management Center to communicate with the traffic signals along critical arterials to improve traffic signal operations, and traffic flow. This will also allow immediate incident monitoring and response to reduce traffic congestion.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: December 2029
Funding Source(s): City-Wide TSIP
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
20525 Santiago Canyon Road Signal Network Extension
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $0 $0 $0 $250,000 $0
AMOUNT $0 $0 $0 $250,000 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
66 20539 Citywide Bicycle Lane Enhancements
PROJECT DESCRIPTION
This project will implement green-colored pavement to enhance the conspicuity of existing City bike lanes.
Colored pavement within a bicycle lane increases the visibility of the facility, identifies potential areas of conflict, and reinforces priority to bicyclists in conflict areas.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2030
Funding Source(s): Capital Projects
FINANCIAL SUMMARY
20539 Citywide Bicycle Lane Enhancements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Capital Projects $0 $0 $0 $0 $150,000
AMOUNT $0 $0 $0 $0 $150,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
67 20556 ORANGE OLIVE METROLINK FENCE
CONSTRUCTION
This project scope of work includes the continuation of an existing fence on Orange Olive Road. The existing fence is part of property owned and maintained by Metrolink. The fence extension will also be part of Metrolink property but is assumed that the City would be responsible for any on-going maintenance of this fence. The existing fence is set back approximately five feet from the street and the proposed fencing would follow the same path and setback distance.
There are 2 possible phases of this project. Phase one would install 6’ fencing and two access gates on Orange Olive from Fellows Drive to Meats Avenue. The cost for phase one is estimated to be $336,050. Phase two of the project would install 6’ fencing and two access gates on Orange Olive from Meats Avenue to Taft Avenue. The cost for phase two is estimated to be $321,750. The total cost for this project is estimated to be $657,800.
PROJECT DETAILS
Project Type: One-Time
Estimated Project Completion Date: June 2026
Funding Source(s): Capital Projects
FINANCIAL SUMMARY
20556 ORANGE OLIVE METROLINK FENCE CONSTRUCTION
Funds Description 2024 Budget 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Home $64,835 $0 $0 $0 $0 $0
AMOUNT $64,835 $0 $0 $0 $0 $0
Powered by OpenGov
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
68 30150 Local Roadway Safety Plan
PROJECT DESCRIPTION
This project develops a Local Road Safety Plan (LRSP) that will define goals, objectives, and strategies to reduce accidents on local roads. The LRSP will also provide a framework to identify, analyze, and prioritize roadway safety improvements and offers a proactive approach to addressing safety needs while demonstrating agency responsiveness to safety challenges. The scope of work includes the following key tasks: state of the system review, accident history assessment, countermeasure development, implementation program, and development of the LRSP document. This project also includes an update which is required by CalTrans every five years.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Traffic Improvement - Measure M2
FINANCIAL SUMMARY
30150 Local Roadway Safety Plan
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Traffic Improvemnt -Measure M2 $0 $0 $50,000 $0 $0
AMOUNT $0 $0 $50,000 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2024-2025
69 30240 Kraemer Blvd/Glassell St/Grand Ave RTSSP
PROJECT DESCRIPTION
The Kraemer Boulevard/Glassell Street/Grand Avenue Regional Traffic Signal Synchronization Program Project (KGG RTSSP) is a multi-jurisdictional project between Lambert Road and Kraemer Boulevard in the City of Brea to Dyer Road and Grand Avenue in the City of Santa Ana. The KGG RTSSP covers 62 signals along the 15.1 mile long corridor within the cities of Brea, Placentia, Anaheim, Orange and Santa Ana. Of those signals, 18 are within the City of Orange. The project is part of OCTA's Measure M2 Project P - Regional Traffic Signal Synchronization Program. The benefits of signal synchronization include a reduction in travel time, improvement in travel speed, greenhouse gas reduction, less fuel consumption, and an overall better travel experience. This project will be led by City of Santa Ana and primarily funded through OCTA's M2. All agencies are required to provide a minimum of 20% matching cash funds. Primary implementation, including construction, is scheduled to be completed in June 2027. A two-year maintenance and operation phase will be initiated after completion of primary implementation.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2027
Funding Source(s): Traffic Improvement - Measure M2
FINANCIAL SUMMARY
30240 KGG RTSSP 2024
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Traffic Improvemnt -Measure M2 $330,000 $0 $0 $0 $0
AMOUNT $330,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
70 30241 Ball Rd/Taft Ave RTSSP
PROJECT DESCRIPTION
The Ball Road/Taft Avenue Regional Traffic Signal Synchronization Program Project (Ball-Taft RTSSP) is a multijurisdictional project between Knott Avenue and Ball Road in the City of Anaheim to Tustin Street and Taft Avenue in the City of Orange. The Ball-Taft RTSSP covers 37 signals along the 10.5 mile long corridor within the cities of Anaheim and Orange. Of those signals, 6 are within the City of Orange. The project is part of OCTA's Measure M2 Project P - Regional Traffic Signal Synchronization Program. The benefits of signal synchronization include a reduction in travel time, improvement in travel speed, greenhouse gas reduction, less fuel consumption, and an overall better travel experience. This project will be led by City of Anaheim and primarily funded through OCTA's M2. All agencies are required to provide a minimum of 20% matching cash funds. Primary implementation, including construction, is scheduled to be completed in June 2027. A two-year maintenance and operation phase will be initiated after completion of primary implementation.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2027
Funding Source(s): City-Wide TSIP
FINANCIAL SUMMARY
30241 Ball-Taft RTSSP 2024
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
TSIP Citywide $120,000 $0 $0 $0 $0
AMOUNT $120,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
71 30247 Citywide Active Transportation Plan
PROJECT DESCRIPTION
This project will develop an Active Transportation Plan by analyzing socioeconomic and crash data to provide recommendations to improve walking and biking conditions at high need areas throughout the City. Using technical data and robust public engagement with disadvantaged community members and the community at large, the plan will incorporate both infrastructure and non-infrastructure recommendations addressing equity, engagement, evaluation, encouragement, and education efforts. As part of this effort, the Citywide Active Transportation Plan will also update the City’s Bikeway Master Plan.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: August 2027
Funding Source(s): City-Wide TSIP; Reimbursable
Capital Projects
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
30247 Citywide Active Transportation Plan
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $308,000 $0 $0 $0 $0
TSIP Citywide $42,000 $0 $0 $0 $0
AMOUNT $350,000 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
72 30264 CDBG Street Improvements Fiscal Year
2025-26
PROJECT DESCRIPTION
This project will rehabilitate Wheeler Street, Killingworths Avenue, and Highland Street which includes but is not limited to, cold planning (milling) the existing asphalt, asphalt concrete overlay installation, reconstruction of sidewalks, curb and gutters, cross gutters, spandrels, sidewalk access ramps, and corresponding adjustment of manholes and water valves to grade.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Community Development Block
Grant
*Project funding includes development impact fees.
Funding is dependent on receipt of development
revenue.
FINANCIAL SUMMARY
30264 CDBG Street Improvements FY 26
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Community Development Block Grant $572,390 $0 $0 $0 $0
AMOUNT $572,390 $0 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
73 Project Summary
PUBLIC WORKS
Carryover Project Balance as of April 1, 2025
13816 Structural Evaluation of City Bridges 2,698,261
14997 Municipal Parking Lot Maintenance 5,215
19809 City Facility Improvements 1,210,131
20325 Santiago Bike Trail Phase IV 601,824
20383 Cannon & Serrano Intersection Modification 50,860 20500 Sycamore and Palmyra Neighborhoods Street Rehabilitation 3,176 20522 Old Towne Parking Management System 101,760
30059 OC & PT Various Improvements 43,706
30163 Chapman Ave BioClean Installation 64,338
30166 Cambridge St Infrastructure Improvement 678,000
30168 Walnut Ave Infrastructure Improvement 3,978,469
30174 Cannon Street Widening 244,806
30243 Pixley & Walnut St. Rehab 608,547
30244 Riverdale Ave Complete St Improvements 2,999,850
30259 Walnut Avenue & Orange Street New Traffic Signal 800,000 -
Total 14,088,942
74 13816 Structural Evaluation of City Bridges
CARRYOVER PROJECT
PROJECT DESCRIPTION
Currently, there are eight roadway bridges located throughout the City that require maintenance. Caltrans has inspected those bridges and has made recommendations for maintenance and repair. A maintenance and retrofit plan are ready for implementation. The City is waiting for Caltrans to program construction funding due to existing funding being no longer available. The project is expected to receive funding for construction phase in FY 26.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: December 2026
Funding Source(s): Gas Tax Maintenance,
Reimbursable Capital Projects
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
75 14997 Municipal Parking Lot Maintenance
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project rehabilitates municipal parking lots every seven years and any maintenance issues annually. Work consists of slurry sealing, crack filling, removing and replacing defective asphalt concrete paving, striping, asphalt concrete overlays, miscellaneous delineation, and wheel stops. This project also includes the maintenance and renovation of trash enclosures.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Capital Projects, Parking In Lieu
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
76 19809 City Facility Improvements
CARRYOVER PROJECT
PROJECT DESCRIPTION
The Citywide Facilities Conditions Assessment (FCA) report identifies high priority facilities projects, and will continually be used as a tool in planning the City’s future facility improvements. Work Items include improvements at the Civic Center and other City facilities. Projects prioritized for Fiscal Year 2024-2025 are as follows:
1. Roof replacement at Fire Station 4, Fire Station 6, and Corp Yard Building 1
2. Plumbing repairs and upgrades at the Civic Center
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Sanitation and Sewer; Reimbursable Capital Projects; Major Building Improvements; Capital Projects; City Trf: Merged 2008 Tax Exempt Bonds
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
77 20325 Santiago Bike Trail Phase IV
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project is the final phase of the Santiago Creek Bike Trail alignment in the Master Bikeway Plan.
Construction of the multi-purpose trail will connect the existing bike trail west of Cannon Street and parallel the existing equestrian trail on the northern bank and terminate at the Santiago Oaks Regional Park. The project will construct an asphalt concrete bike trail and rehabilitate the existing equestrian trail with decomposed granite along with needed amenities such as rest areas and trash receptacles. The trail will allow for pedestrian and bicycle traffic along an eight-mile stretch of trails. The City received funding sources from OCTA's BCIP Grant for this project's preliminary engineering and environmental costs. Estimated construction costs are $10 million. The City is also pursuing additional grants for the construction phase.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: December 2025
Funding Source(s): Capital Projects
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
78 20383 Cannon & Serrano Intersection Modification
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will add a second dedicated right-turn lane on northbound Cannon Street to eastbound Serrano Avenue, in order to accommodate the increase in right-turn movements. The project will also widen the northerly curb face on Serrano Avenue in order to mitigate the bottlenecking effect of the existing two left-turn lanes for Southbound Serrano Avenue. Public Works is working on the construction phase of the project and anticipates completion by June 2025
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Traffic Improvement - Measure M2;
City-Wide TSIP; Reimbursable Capital Projects
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
79 20500 SYCAMORE & PALMYRA NEIGHBORHOODS
STREET REHABILITATION
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will rehabilitate Sycamore Avenue, Holly Street, Ash Street, Palmyra Avenue, Flower Street, and Lilac Lane in the Sycamore and Palmyra Neighborhoods, which includes but not is limited to cold planing (miling) the existing asphalt, asphalt concrete overlay installation, slurry seal, reconstruction of sidewalks, curb and gutters, driveways, cross gutters, and corresponding adjustment of manholes and water valves to grade on residential streets.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2022-2023
Estimated Completion Date: December 2025
Funding Source(s): Community Development Block
Grant; Capital Projects
Total Budget: $629,530
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
80 20522 Evaluation of Smart Parking Devices for Old
Towne
CARRYOVER PROJECT
PROJECT DESCRIPTION
Identified as a game-changing tool for parking management, “smart” parking technologies can increase the efficiency of existing parking infrastructure by providing real time, app-based information that’s easily accessible to visitors. In addition, smart parking equipment can be designed for compatibility with future mobility initiatives, and serve as the foundation for other types of parking management programs currently being reviewed. The purpose of this evaluation is to explore and identify feasible options for smart parking systems and products, including those that are cost-effective, reliable, have the potential for phased deployment best fitting the City’s needs, and can be aesthetically customized to blend in with Old Towne Orange.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2027
Funding Source(s): Old Towne Parking Facility; Parking
in Lieu
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
81 30059 OCPT Facility Improvements
CARRYOVER PROJECT
PROJECT DESCRIPTION
The 501(c)(3) non-profit, Orange Children and Parents Together (OCPT) has an agreement with the City to utilize facility space at the El Modena Branch Library. As part of their agreement, the City utilizes OCPT funding to make various improvements at the facility to comply with State inspections and an aging facility.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): OC HEADSTART (OCPT) BUILDING
MAINT
Total Budget: $95,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
82 30163 Chapman Avenue BioClean Installation
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will install a BioClean Separating Baffle Box or equal on Chapman Avenue approximately 150 feet west of Eckhoff Street. The existing storm drain system is a 66" storm drain line that ultimately discharges into Bitterbush Channel located 2,000 feet downstream of the proposed location. The project will also install 13 connector pipe screens on Main Street, Brian Street, Chapman Avenue, and Katella Avenue to capture litter from commercial and residential sites draining into the Santa Ana River.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2020-2021
Estimated Completion Date: July 2025
Funding Source(s): Sewer; Reimbursable Capital
Projects
Total Budget: $386,004
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
83 30166 Cambridge St Infrastructure Improvement
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will upsize the existing 18” RCP storm drain line from Palm Avenue to Walnut Avenue per the Master Plan of Drainage to alleviate localized flooding on Cambridge Street during 25-year or higher storm events. Other improvements include replacement of deficient sewer and water mains. In addition, Cambridge Street roadway pavement will be rehabilitated, and the existing concrete curb will be replaced with new concrete curb and gutter. The project also includes replacing damaged sidewalk, reconstructing existing ADA ramps to conform to federal guidelines, adjusting utility covers to grade, and restriping the roadway. Staff is seeking federal funding through Hazard Mitigation grant for construction phase.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2020-2021
Estimated Completion Date: September 2026
Funding Source(s):
Total Budget: $2,103,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
84 30168 East Walnut Ave Infrastructure Improvement
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will construct a new 48” RCP storm drain line on Walnut Avenue from Cambridge Street to California Street per the Master Plan of Drainage to alleviate the localized flooding issue on Walnut Avenue during a 25-year or higher storm events. Other improvements include replacement of deficient sewer and water mains. In addition, Walnut Avenue from Cambridge Street to Tustin Street roadway pavement will be rehabilitated, and the existing concrete curb will be replaced with new concrete curb and gutter. The project also includes replacing damaged sidewalk, reconstructing existing ADA ramps to conform to federal guidelines, adjusting utility covers to grade, and restriping the roadway.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2020-2021
Estimated Completion Date: December 2025
Funding Source(s): Water
Total Budget: $2,749,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
85 30174 Cannon Street Bridge Widening
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project widens portions of Cannon Street from Santiago Canyon Road to Serrano Avenue to add a third northbound thru lane. The scope of work includes widening the bridge as well as the roadway north of the bridge in order to maintain the continuity of the thru lane until Serrano Avenue where it would get dropped into a dedicated right-turn lane to eastbound Serrano Avenue. The existing painted median will be replaced with a raised median. All improvements fall within the City of Orange public right-of-way except for a portion between Taft Avenue and Serrano Avenue which falls in City of Villa Park public right-of-way. Current funding is for the preliminary engineering and environmental phase of the project.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2020-2021
Estimated Completion Date: August 2025
Funding Source(s): City-Wide TSIP
Total Budget: $206,250
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2024-2025
86 30243 Pixley Neighborhood and Walnut Street
Rehabilitation
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will rehabilitate Parker Street, Pixley Street, Foley Place, Clark Street, Marietta Avenue, Washington Avenue, and Walnut Avenue, which includes but is not limited to, asphalt concrete grinding and overlay, and adjustment of manholes and water valves to grade.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2025
Funding Source(s): Community Development Block
Grant
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
87 30244 Riverdale Avenue Complete Street
Improvements
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project’s scope of work includes the reconfiguration of Riverdale Avenue from Glassell Street to Orange City limits that allows for the installation of bike and pedestrian facilities, traffic calming strategies and curb space management. Bike and pedestrian facilities include the installation of buffered Class II bike lanes in both directions, installation of painted medians and turn lanes, installation of traffic signs including bike lane, wayfinding and SART access signage, installation of street trees, safety enhancements including street light installation, ADA improvements that include compliant curb access ramps at all intersections and a full build-out of roadway pavement, curb, gutter and sidewalk gap closure for the westbound segment between Orange Olive and Orange City Limits. Traffic calming improvements include consistent and narrowed traffic lanes from 15 feet to 11 feet and lane reductions from two lanes in each direction to one lane in each direction.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2026
Funding Source(s): Traffic Improvement - Measure M2;
Reimbursable Capital Projects
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
88 30259 Walnut Avenue & Orange Street New Traffic
Signal
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project will provide for a new traffic signal at the intersection of Walnut Avenue and Orange Street. The traffic signal will improve the overal flow and safety of the intersection, including managing the flow of vehicles entering and exiting Chapman University's Anderson Parking Structure. The project will include new traffic signal poles, controller and cabinet, video detection, safety lighting, enhanced traffic signs and pavement markings.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: December 2026
Funding Source(s): Reimbursable Capital Projects
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS
FISCAL YEAR 2025-2026
89 Project 2025-2026 2026-2027 2027-2028 2028-2029 2029-2030 5 Year Total 18101 Water Utility Security Improvements 25,000 25,000 25,000 25,000 25,000 125,000 18102 Meter Replacement Program 400,000 550,000 550,000 600,000 600,000 2,700,000 18214 Well Rehabilitation 150,000 150,000 200,000 250,000 250,000 1,000,000 18225 Lower Serrano Pump Station - - 500,000 1,000,000 - 1,500,000 18301 Exterior Cathodic Protection Systems 50,000 50,000 50,000 50,000 50,000 250,000 18302 Reservoir Recoating 300,000 1,400,000 - - - 1,700,000 18315 Reservoir 3A Construction - - 400,000 1,800,000 - 2,200,000 18324 Resevoir 2A Site Remediation 100,000 - 750,000 - - 850,000 18400 Pipeline Renewal Projects 2,000,000 2,000,000 2,100,000 2,100,000 2,100,000 10,300,000 18912 Water Plant Telemetry 75,000 75,000 75,000 75,000 75,000 375,000 18925 Emergency Generator 320,000 - 400,000 - - 720,000 20312 Well 29 Construction 2,800,000 3,500,000 - - - 6,300,000 20429 South Yard Storage Replacement - - 300,000 - - 300,000 20496 Reservoir 4A Construction - - - - 1,500,000 1,500,000 20497 Reservoir 5 Pump Station Replacement - - - - 1,200,000 1,200,000 -
Total 6,220,000 7,750,000 5,350,000 5,900,000 5,800,000 31,020,000 Project Summary
PUBLIC WORKS - WATER
90 18101 Water Utility Security Improvements
PROJECT DESCRIPTION
This project provides funding to replace and construct Water Utility Security improvements at various water facilities as identified in the Water System Vulnerability Assessment. The improvement areas include block walls, fencing, surveillance cameras, and other improvements.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18101 Water Utility Security Improvements
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $25,000 $25,000 $25,000 $25,000 $25,000
AMOUNT $25,000 $25,000 $25,000 $25,000 $25,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
91 18102 Meter Replacement Program
PROJECT DESCRIPTION
This project provides for the repair or replacement of water meters in the water system to reduce water loss and accurately bill for water usage. As part of the on-going 15-year small meter replacement program, an average of 1,800 small meters are replaced per year. Additionally, this project allows for the automated method of gathering meter reads, consumption data, and other system information that will benefit water operations and customers.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18102 Meter Replacement Program
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $400,000 $550,000 $550,000 $600,000 $600,000
AMOUNT $400,000 $550,000 $550,000 $600,000 $600,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
92 18214 Well Rehabilitation
PROJECT DESCRIPTION
This project provides for on-going inspection, repair, and refurbishment of 12 existing water wells.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18214 Well Rehabilitation
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $150,000 $150,000 $200,000 $250,000 $250,000
AMOUNT $150,000 $150,000 $200,000 $250,000 $250,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
93 18225 Lower Serrano Pump Station
PROJECT DESCRIPTION
This project includes the design and construction to complete the 100-horsepower pressure pump station in northeast Orange. This pump station will move water from Zone 3 to Zone 4.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: July 2029
Funding Source(s): Water
FINANCIAL SUMMARY
18225 Lower Serrano Pump Station
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $0 $0 $500,000 $1,000,000 $0
AMOUNT $0 $0 $500,000 $1,000,000 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
94 18301 Exterior Cathodic Protection Systems
PROJECT DESCRIPTION
This project provides for ongoing inspection, repair, and replacement of interior and exterior cathodic protection systems for steel water tanks in the water system. Each of the steel tanks rely on a functioning cathodic protection system for corrosion protection.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18301 Exterior Cathodic Protection Systems
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $50,000 $50,000 $50,000 $50,000 $50,000
AMOUNT $50,000 $50,000 $50,000 $50,000 $50,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
95 18302 Reservoir Recoating
PROJECT DESCRIPTION
This project is part of a long-term reservoir maintenance program that provides for the repair and replacement of exterior/interior protective coatings for all fifteen steel reservoirs in the water system.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18302 Reservoir Recoating
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $300,000 $1,400,000 $0 $0 $0
AMOUNT $300,000 $1,400,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
96 18315 Reservoir 3A Construction
PROJECT DESCRIPTION
This project provides for the design and construction of a one million gallon steel water tank at a site directly adjacent to the existing Reservoir 3. This tank will provide additional storage for existing residential needs and fire protection for Zone 3 in northeast Orange.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2029
Funding Source(s): Water
FINANCIAL SUMMARY
18315 Reservoir 3A Construction
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $0 $0 $400,000 $1,800,000 $0
AMOUNT $0 $0 $400,000 $1,800,000 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
97 18324 Resevoir 2A Site Remediation
PROJECT DESCRIPTION
This project provides for design, specifications, cost estimates, and construction of site stabilization for the Reservoir 2A site in the Vista Royale Tract, located in northwest Orange. This existing facility is being monitored for peripheral movement. The proposed remediation includes the installation of soldier piles and grade beams to minimize future differential movement on site.
PROJECT DETAILS
Project Type: One-Time
Completion Date: June 2029
Funding Source(s): Water
FINANCIAL SUMMARY
18324 Reservoir 2A Site Remediation
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $100,000 $0 $750,000 $0 $0
AMOUNT $100,000 $0 $750,000 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
98 18400 Pipeline Renewal Projects
PROJECT DESCRIPTION
This project provides for the design and construction of water mainline replacements for the City's water system.
Approximately 1.5 miles of pipeline are targeted to be replaced annually due to increasing age, substandard sizing, corrosion, or high maintenance.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18400 Pipeline Renewal Projects
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $2,000,000 $2,000,000 $2,100,000 $2,100,000 $2,100,000 AMOUNT $2,000,000 $2,000,000 $2,100,000 $2,100,000 $2,100,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
99 18912 Water Plant Telemetry
PROJECT DESCRIPTION
This project provides for the maintenance of the Supervisory Control and Data Acquisition (SCADA) system. This computer-driven telemetry system allows for remote monitoring and automatic control of all water sources of supply, pumping, storage, and flow control facilities.
PROJECT DETAILS
Project Type: Ongoing
Funding Source(s): Water
FINANCIAL SUMMARY
18912 Water Plant Telemetry
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $75,000 $75,000 $75,000 $75,000 $75,000
AMOUNT $75,000 $75,000 $75,000 $75,000 $75,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
100
18925 Emergency Generator
PROJECT DESCRIPTION
This project provides for the acquisition of one fixed 480-volt three-phase emergency generator to be used to supply emergency electricity to water pumping facilities during power outages. Locations of the remaining generators are scheduled for Reservoir 8 in FY 28.
PROJECT DETAILS
Project Type: One-Time
Completion Date: June 2028
Funding Source(s): Water
FINANCIAL SUMMARY
18925 Emergency Generator
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $320,000 $0 $400,000 $0 $0
AMOUNT $320,000 $0 $400,000 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
101
20312 Well 29 Construction
PROJECT DESCRIPTION
Well 29 is a proposed new 3,000 gallons-per-minute groundwater production facility to replace Well 8 located at Katella Avenue and Struck Avenue. This project includes design, well drilling, pump installation, electrical, storm drain, piping connection, treatment, and an emergency power generator. The Orange County Water District is funding a treatment program to assist with construction costs.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: November 2027
Funding Source(s): Water
FINANCIAL SUMMARY
20312 Well 29 Construction
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Reimbursable Capital Projects $1,000,000 $2,500,000 $0 $0 $0 Water $1,800,000 $1,000,000 $0 $0 $0
AMOUNT $2,800,000 $3,500,000 $0 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
102
20429 South Water Yard Storage Replacement
PROJECT DESCRIPTION
This project provides for the design and construction of the warehouse replacement. The existing 5,000 square feet warehouse will be renovated and used in conjunction with the proposed Fire Department Headquarter. The replacement warehouse will be constructed at the water division's south yard for parts and equipment storage.
This project also provides for the cover structure over the water division's materials storage area in compliance with the National Pollutants Discharge Elimination System (NPDES) requirements. The structure prevents run-off from washing out construction material such as sands, asphalt, base, and soil into the storm drain system. It also helps reduce noise and assists with dust control. This project will also pursue sustainable energy and efficiency measures such as integrated solar panels.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: June 2028
Funding Source(s): Water
FINANCIAL SUMMARY
20429 South Yard Storage Replacement
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $0 $0 $300,000 $0 $0
AMOUNT $0 $0 $300,000 $0 $0
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
103
20496 Reservoir 4A Construction
PROJECT DESCRIPTION
This project provides for the design and construction of a three million gallon steel water tank at a site near the intersection of Cannon Street and Creekside Avenue. This tank will provide additional storage for existing residential needs and fire protection for Zone 1 in southeast Orange.
PROJECT DETAILS
Project Type: Ongoing
Estimated Completion Date: June 2031
Funding Source(s): Water
FINANCIAL SUMMARY
20496 Reservoir 4A Construction
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $0 $0 $0 $0 $1,500,000
AMOUNT $0 $0 $0 $0 $1,500,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
104
20497 Reservoir 5 Pump Station Replacement
PROJECT DESCRIPTION
This project provides for the design and construction of a replacement pump station at Reservoir 5 in southeast Orange.
PROJECT DETAILS
Project Type: One-Time
Starting Fiscal Year: 2021-2022
Estimated Completion Date: June 2030
Funding Source(s): Water
FINANCIAL SUMMARY
20497 Reservoir 5 Pump Station Replacement
Funds Description 2026 Proposed 2027 Proposed 2028 Proposed 2029 Proposed 2030 Proposed Amount
Water $0 $0 $0 $0 $1,200,000
AMOUNT $0 $0 $0 $0 $1,200,000
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026
105
Project Summary
PUBLIC WORKS - WATER
Carryover Project Balance as of April 1, 2025
20538 Reservoir 7 Hydropneumatics Tank Replacement 1,400,000 -
Total 1,400,000
106
20538 Reservoir 7 Hydropneumatics Tank
Replacement
CARRYOVER PROJECT
PROJECT DESCRIPTION
This project provides for the design and construction of the replacement hydropneumatics tank and pump station at Reservoir 7 in southeast Orange.
PROJECT DETAILS
Project Type: One-Time
Estimated Completion Date: January 2026
Funding Source(s): Water
Powered by OpenGov
CAPITAL IMPROVEMENT PROGRAM
PUBLIC WORKS - WATER
FISCAL YEAR 2025-2026