Work Order Signature Document

EXHIBIT A
469

3.00 Detailed Scope of Work
Fredi ContrerasMatt McMillonTo: From:

MDJ Management Oxnard Housing
Authority
531 Main St #611 300 N. Marquita Street
El Segundo, CA 90245 Oxnard, CA 93030
310-490-1521 805-890-8319
Work Order Number:

January 09, 2024Date Printed:
124232.00
OHA - 1040 Unit RemodelWork Order Title:

Brief Scope:

Revised FinalPreliminary X
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the items set forth below shall be considered part of this scope of work.

See attached.

Subject to the terms and conditions of ezIQC Contract CA-R7-GB-101723-MDJ.

MDJ Management Date
DateOxnard Housing Authority

Page 1 of 1 ends

1/9/2024
Scope of Work
470
MDJ Management, LLC
License # 1044711
DIR # 1000061313
531 Main St. #611 El Segundo CA 90245
310-490-1521
Job Name: 1040 Colonia Conversion
Location: 1040 E. Colonia Rd. Oxnard, CA 93030
Customer: Oxnard Housing Authority
Submission Date: 1/4/24
Detailed Scope of Work
Demolition
● Demolition of existing apartment per plans
Installation/Buildout
● Saw cutting of slab and demolition of concrete for new plumbing ● Excavation for new plumbing and new concrete footings for addition ● All framing throughout including new walls and soffits ● New rough and finish plumbing throughout
● New electrical rough including new panel per plan
● Concrete work:
○ Excavate under slab for rough plumbing and electrical needs ○ Pour new footings per structural plans
○ Pour back all open trenches inside the unit
○ Outside sidewalk as required
● New windows and doors throughout
● New Insulation
● HVAC per plans
○ Exhaust fan ducting
○ Remove existing wall heater and installation of new wall heaters per plans ● Drywall throughout
○ Patch were needed due to demolition and rough MEP requirements ○ New drywall per plans
○ Double stacked first floor ceiling with resilient channels per plans ● Lath, stucco, and color coat to match existing for stucco patching ● Interior paint
● New Flooring and MDF base
○ New underlayment and self leveling
● New kitchens, countertops, fixtures, sinks and appliances 1 of 3
471
● New bathroom fixtures per plan
● Site work:
○ New sidewalks
○ Handicap ramp with truncated domes
○ Handicap striping
○ New signage at Handicap stall
Installation/Buildout added by Client NOT included on plans ● Remove and replace all outlets and switches throughout, even on all existing walls ● Install MDF baseboards
○ Instead of called out vinyl base
● Remove and replace all interior doors. Complete list of doors from plans as well as clients request
● Clean up existing back yard, the weeds are 5 feet high ○ Includes weed weed whacking and removal of all dead weeds ● All new LED lighting throughout
Notes:
● All work to be performed per plans provided to MDJ
● Any additional add on items will be at the request of Customer. Any adjustment shall be an additional cost.
● Price includes all labor (Normal Working Hours - Davis Bacon Wages), materials, equipment to complete this scope of work.
● Construction Exclusions:
○ New Washer and Dryer not included in contract
○ New stove, range, dishwasher, and fridge not included in contract CLARIFICATIONS AND EXCLUSIONS:
● Warranty
○ One year warranty against workmanship
○ Manufacturer's warranty varies
● We exclude plans, permits, permit fees, related fees, testing, inspection, survey, and engineering unless specified above
● We exclude utilities and hazardous or contaminated material. ● Construction water, power, and sanitary facilities available on site for MDJ’s use at no cost.
● We exclude premium time.
● We exclude anything not specifically mentioned above. ● MDJ reserves the right to review, change, and/or delete any provisions of any prime contract or subcontract, which results from this quotation. ● All terms to be net 30 days in full upon receipt of invoice. Interest will be charged at the rate of 2% monthly on the unpaid balance.

BID PRICE: See Price Proposal
All work to be completed in a substantial and workmanlike manner according to standard practices for the sum of See Price Proposal. Any additional add on items will be at the request of Customer. Any adjustment shall be an additional cost.

Bid price is good for thirty (30) days only.
2 of 3
472
Anycontroversyor claimbasedon, arisingout of, or relatingtothisagreement, or breachthereof, includinganyclaimbasedontheworkperformedpursuant tothisagreement, shall besubmittedtotheAmericanArbitrationAssociationfor bindingarbitrationinaccordancewithitsrules. If anyarbitration, legal actionisbrought toenforcethisagreement, or arisingout of orrelatingtotheagreement, theprevailingpartyshall beentitledtorecover fromthenon-prevailingpartyreasonableattorneyfeesandcostsincurred, inadditiontoanyandall otherrelief towhichthat partymaybeentitled.

Submittedby:

MatthewMcMillonPresident [email protected] 3of 3
473

4.00 Contractor's Price Proposal - Summary
Owner PO #:

OHA
- 1040 Unit Remodel
124232.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
$50,228.90Section - 01
$2,817.60Section - 02
$24,059.94Section - 03
$46,235.58Section - 06
$26,398.68Section - 07
$36,198.70Section - 08
$132,987.65Section - 09
$3,696.32Section - 10
$717.65Section - 11
$12,661.27Section - 12
$130,110.56Section - 22
$44,057.26Section - 23
$72,198.22Section - 26
$20,358.64Section - 31
$1,778.03Section - 32
Proposal Total
Thisl total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 1 of 1 ends

1/9/2024
Contractor's Price Proposal - Summary
474

5.00 Contractor's Price Proposal - Detail
OHA
- 1040 Unit Remodel
124232.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
(Excludes)Equip. MaterialLabor
Line TotalDescriptionUOMMod.ItemSect.

Section - 01
01 22 16 00 0002 Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible costs as directed by Owner. Insert the appropriate quantity to adjust the base cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees, list each one separately and add a comment in the "note" block to identify the Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended warranty, expedited shipping costs, etc.). A copy of each receipt , invoice, or
proof of payment shall be submitted with the Price Proposal. 1 $13,011.90EA
Installation =x x 13,01 1.90
FactorUnit PriceQuantity Total

1.00 1.1000 11,829.00
Bond = $591,493 x 2%
01 22 20 00 0006 CarpenterFor tasks not included in the Construction Task Catalog® and as directed by owner only.
2 $7,623.17
HR
Installation =x x 7,623.17
FactorUnit PriceQuantity Total

99.26 1.2000 64.00
2 guys for 4
days for reconfiguring framing around doors and windows to meet new sizing and ADA requirements.
01 22 20 00 0010 ElectricianFor tasks not included in the Construction Task Catalog® and as directed by owner only.
3 $866.21
HR
Installation =x x 866.21
FactorUnit PriceQuantity Total

90.23 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 22 20 00 0037 PlumberFor tasks not included in the Construction Task Catalog® and as
directed by owner only.
4 $1,027.78HR
Installation =x x 1,027.78
FactorUnit PriceQuantity Total
107.06 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 66 19 00 0060 Handling Material For Over 125' Per 48" x 40" x 48" Container Per 125' Segment
5 $10,586.88
EA
Installation =x x 10,586.88
FactorUnit PriceQuantity Total

9.19 1.2000 960.00
4 guys, averaging 4 trips a day for 3 months for demolition hauling and delivery of purchased materials. 01 74 19 00 0016 40
CY Dumpster (5 Ton) "Construction Debris"Includes delivery of dumpster, rental cost, pick-up cost, hauling, and disposal fee. Non-hazardous material. 6 $12,743.71EA
Installation =x x 12,743.71
FactorUnit PriceQuantity Total
884.98 1.2000 12.00
10 dumpsters for demolition debris: cabinets, drywall from entire house, shower, toilet, stucco, insulation, ... 2 dumpsters for construction debris: drywall cuts, lumber cuts, basic trash 01 74 19 00 0019 15
CY Low-Boy Dumpster Mixed RecyclableFor mixed dirt, rock, concrete brick or asphalt with no trash or organics. Includes service to deliver and pick-up dumpster, hauling, rental and disposal fee.
7 $4,369.25
EA
Installation =x x 4,369.25
FactorUnit PriceQuantity Total
910.26 1.2000 4.00
for removal of excavated soil for footings, slab, trenching $50,228.90Subtotal for Section - 01
Section - 02

Page 1 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
475
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 02
02 41 19 13 0063 Rod Reinforced Concrete Slab Up To 4" Depth, Saw Cut8 $2,817.60LF Installation =x x 2,817.60
FactorUnit PriceQuantity Total

5.87 1.2000 400.00
sawcut existing slab to trench for new electrical and plumbing runs as needed per plans $2,817.60Subtotal for Section - 02
Section - 03
03 21 11 00 0251 Dowels Or Hairpin, 1/2" x 30" Length, Drilled And Epoxy In Concrete, 6" Embedment
9 $6,655.50EA
Installation =x x 6,655.50
FactorUnit PriceQuantity Total

24.65 1.2000 225.00
200 LF of trenching. Epoxy and Dowel every 2'. One on each side. For reinforcement and tying into existing slab adjacent. 25 dowels to attach from porch sidewalk to existing . 03 21 13 00 0093 #6, Grade 50, Slab On Grade, Galvanized Steel Reinforcement Bar10 $2,496.00LF Installation =x x 2,496.00
FactorUnit PriceQuantity Total

2.60 1.2000 800.00
200 LF of trenching and 600 LF for slab, porch, and footings. Installation of rebar every 2'. 03 30 53 00 0009 Hand Mix And Place ConcreteFor use where conventional equipment access is limited or when directed by the owner.

Includes local aggregate, sand, bagged cement (Type I) and water. 11 $4,370.40CF
Installation =x x 4,370.40
FactorUnit PriceQuantity Total

18.21 1.2000 200.00
patch back trenching in existing slab
03 30 53 00 0009 0038 For High Early Strength, Type 3 ASTM C150, Add12 $156.00 Installation =x x 156.00
FactorUnit PriceQuantity Total

0.65 1.2000 200.00
03 30 53 00 0009 0039 For Lightweight Aggregate, ASTM C330, Add13 $544.80 Installation =x x 544.80
FactorUnit PriceQuantity Total

2.27 1.2000 200.00
03 54 16 00 0005 1/2" Thick Self Leveling Cementitious Underlayment For FloorsIncluding Surface Preparation
14 $9,837.24SF
Installation =x x 9,837.24
FactorUnit PriceQuantity Total

4.78 1.2000 1,715.00
self leveling of floors for prior to installation of new vinyl plank flooring $24,059.94Subtotal for Section - 03
Section - 06
06 11 16 00 0061 2" x 4" Wood Wall Framing At 16" On Center15 $2,321.57SF Installation =x x 1,434.24
FactorUnit PriceQuantity Total

1.66 1.2000 720.00
Demolition x x = 887.33 0.79 1.2000 936.00
for new walls. Couple walls require double stacked
06 16 33 00 0020 3/4" CD Grade Plywood Floor DeckingApplied to floor or joists.16 $6,338.64SF Installation =x x 5,083.26
FactorUnit PriceQuantity Total

2.47 1.2000 1,715.00
Demolition x x = 1,255.38 0.61 1.2000 1,715.00
for new floor decking per plans
06 16 33 00 0020 0038 For Exterior Glue, Add17 $185.22 Installation =x x 185.22
FactorUnit PriceQuantity Total

0.09 1.2000 1,715.00

Page 2 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
476
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 06
06 16 33 00 0033 5/8" Thick CDX Plywood Underlayment Grade18 $255.48SF Installation =x x 221.40
FactorUnit PriceQuantity Total

2.46 1.2000 75.00
Demolition x x = 34.08 0.71 1.2000 40.00
for countetop
06 41 13 00 0116 12" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
19 $1,245.28EA
Installation =x x 1,245.28
FactorUnit PriceQuantity Total
345.91 1.2000 3.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0116 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
20 $420.37
Installation =x x 420.37
FactorUnit PriceQuantity Total
116.77 1.2000 3.00
06 41 13 00 0116 0130 For All Plywood Box Construction, Add21 $438.19 Installation =x x 438.19
FactorUnit PriceQuantity Total
121.72 1.2000 3.00
06 41 13 00 0117 15" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
22 $882.84EA
Installation =x x 882.84
FactorUnit PriceQuantity Total
367.85 1.2000 2.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0117 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
23 $280.25
Installation =x x 280.25
FactorUnit PriceQuantity Total
116.77 1.2000 2.00
06 41 13 00 0117 0130 For All Plywood Box Construction, Add24 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0118 18" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
25 $1,846.66EA
Installation =x x 1,846.66
FactorUnit PriceQuantity Total
384.72 1.2000 4.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0118 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
26 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
116.77 1.2000 4.00
06 41 13 00 0118 0130 For All Plywood Box Construction, Add27 $584.26 Installation =x x 584.26
FactorUnit PriceQuantity Total
121.72 1.2000 4.00
06 41 13 00 0119 21" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
28 $486.41EA
Installation =x x 486.41
FactorUnit PriceQuantity Total
405.34 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0119 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
29 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00

Page 3 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
477
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 06
06 41 13 00 0119 0130 For All Plywood Box Construction, Add30 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0121 27" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
31 $579.37EA
Installation =x x 579.37
FactorUnit PriceQuantity Total
482.81 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0121 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
32 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00
06 41 13 00 0121 0130 For All Plywood Box Construction, Add33 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0124 36" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
34 $1,433.42EA
Installation =x x 1,361.04
FactorUnit PriceQuantity Total
567.10 1.2000 2.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 12" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
35 $541.33EA
Installation =x x 517.21
FactorUnit PriceQuantity Total
431.01 1.2000 1.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
36 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
467.08 1.2000 1.00
06 41 13 00 0139 0130 For All Plywood Box Construction, Add37 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0140 15" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
38 $559.45EA
Installation =x x 529.30
FactorUnit PriceQuantity Total
441.08 1.2000 1.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0140 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
39 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0140 0130 For All Plywood Box Construction, Add40 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0142 21" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
41 $1,264.40EA
Installation =x x 1,222.18
FactorUnit PriceQuantity Total
509.24 1.2000 2.00
Demolition x x = 42.23 35.19 1.2000 1.00
removal of existing cabinets, installation of new per plans

Page 4 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
478
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 06
06 41 13 00 0142 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
42 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0142 0130 For All Plywood Box Construction, Add43 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0170 30" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
44 $493.43EA
Installation =x x 433.12
FactorUnit PriceQuantity Total
360.93 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0170 0131 For All Plywood Box Construction, Add45 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0171 33" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
46 $516.13EA
Installation =x x 449.78
FactorUnit PriceQuantity Total
374.82 1.2000 1.00
Demolition x x = 66.35 55.29 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0171 0131 For All Plywood Box Construction, Add47 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0172 36" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
48 $531.48EA
Installation =x x 459.10
FactorUnit PriceQuantity Total
382.58 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0172 0131 For All Plywood Box Construction, Add49 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0174 12" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
50 $2,167.92EA
Installation =x x 2,143.80
FactorUnit PriceQuantity Total
297.75 1.2000 6.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0174 0131 For All Plywood Box Construction, Add51 $470.23 Installation =x x 470.23
FactorUnit PriceQuantity Total

65.31 1.2000 6.00
06 41 13 00 0175 15" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
52 $809.03EA
Installation =x x 778.87
FactorUnit PriceQuantity Total
324.53 1.2000 2.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0175 0131 For All Plywood Box Construction, Add53 $156.74 Installation =x x 156.74
FactorUnit PriceQuantity Total

65.31 1.2000 2.00

Page 5 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
479
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 06
06 41 13 00 0176 18" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
54 $1,282.30EA
Installation =x x 1,246.10
FactorUnit PriceQuantity Total
346.14 1.2000 3.00
Demolition x x = 36.19 30.16 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0176 0131 For All Plywood Box Construction, Add55 $235.12 Installation =x x 235.12
FactorUnit PriceQuantity Total

65.31 1.2000 3.00
06 41 13 00 0178 24" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
56 $525.71EA
Installation =x x 477.46
FactorUnit PriceQuantity Total
397.88 1.2000 1.00
Demolition x x = 48.25 40.21 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0178 0131 For All Plywood Box Construction, Add57 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0179 27" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
58 $578.09EA
Installation =x x 523.78
FactorUnit PriceQuantity Total
436.48 1.2000 1.00
Demolition x x = 54.31 45.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0179 0131 For All Plywood Box Construction, Add59 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0180 30" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
60 $597.17EA
Installation =x x 536.86
FactorUnit PriceQuantity Total
447.38 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0180 0131 For All Plywood Box Construction, Add61 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0182 36" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
62 $674.99EA
Installation =x x 602.60
FactorUnit PriceQuantity Total
502.17 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0182 0131 For All Plywood Box Construction, Add63 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 93 00 0007 7" To 8-1/2", Flat Cabinet Pull Handle64 $3,370.32EA Installation =x x 3,042.00
FactorUnit PriceQuantity Total

39.00 1.2000 65.00
Demolition x x = 328.32 8.55 1.2000 32.00
removal of existing cabinets, installation of new per plans

Page 6 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
480
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 06
06 46 19 00 0005 4-1/2" High White Pine Base Molding, All Dimensions Are Nominal65 $8,657.40LF Installation =x x 7,389.00
FactorUnit PriceQuantity Total

8.21 1.2000 750.00
Demolition x x = 1,268.40 1.51 1.2000 700.00
new base boards throughout
$46,235.58Subtotal for Section - 06
Section - 07
07 21 16 00 0006 5-1/2" Thick, Kraft Faced, R-21 Fiberglass Flexible Insulation66 $17,600.88SF Installation =x x 14,766.84
FactorUnit PriceQuantity Total

1.98 1.2000 6,215.00
Demolition x x = 2,834.04 0.38 1.2000 6,215.00
removal of existing insulation and installation of new 4500 sqft of walls 1715 sqft of ceilings 07 26 13 00 0004 Two Ply 60 Minute Asphalt Saturated Kraft Building Paper, Grade D (Fortifiber Two Ply Super Jumbo Tex 60 Minute)
67 $1,835.40CSF
Installation =x x 1,835.40
FactorUnit PriceQuantity Total

43.70 1.2000 35.00
for stucco patchback
07 62 13 00 0033 22 Gauge, 0.034" Thick, Galvanized Steel Flashing68 $4,485.60SF Installation =x x 4,485.60
FactorUnit PriceQuantity Total

12.46 1.2000 300.00
flashing per plans for new windows
07 62 13 00 0033 0080 For Wrap Around Window Panning, Add69 $2,476.80 Installation =x x 2,476.80
FactorUnit PriceQuantity Total

6.88 1.2000 300.00
$26,398.68Subtotal for Section - 07
Section - 08
08 12 13 13 0008 3' x 6'-8" Through 7'-2" High, 4-3/4" Deep, 16 Gauge, Knock Down Hollow Metal Door Frame
70 $7,015.14EA
Installation =x x 6,170.69
FactorUnit PriceQuantity Total
571.36 1.2000 9.00
Demolition x x = 844.45 100.53 1.2000 7.00
6 frames for interior doors and 3 for exterior doors
08 13 13 13 0039 3' x 6'-8" x 1-3/4", 18 Gauge, Level 2 Heavy Duty, Honeycomb Core, Hollow Metal Door
71 $2,890.61EA
Installation =x x 2,818.22
FactorUnit PriceQuantity Total
782.84 1.2000 3.00
Demolition x x = 72.38 60.32 1.2000 1.00
for new front doors and one rear door per plans
08 13 13 13 0039 0098 For Embossed Panel Door, Add72 $572.15 Installation =x x 572.15
FactorUnit PriceQuantity Total
158.93 1.2000 3.00
08 13 13 13 0039 0099 For Baked Enamel Finish, Add73 $780.34 Installation =x x 780.34
FactorUnit PriceQuantity Total
216.76 1.2000 3.00
08 13 13 13 0039 0104 For 3 Hour Fire Rated Door, Add74 $473.40EA Installation =x x 473.40
FactorUnit PriceQuantity Total
131.50 1.2000 3.00

Page 7 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
481
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 08
08 14 16 00 0134 3'-0" x 6'-8" x 1-3/4" Thick, 5 Ply, Hollow Core (HC), Birch Faced Wood Door75 $2,524.34EA Installation =x x 2,017.66
FactorUnit PriceQuantity Total
280.23 1.2000 6.00
Demolition x x = 506.69 60.32 1.2000 7.00
5 bedroom/bathroom doors and 1 closet door
08 14 73 00 0074 5' Wide, Two 2'-6" x 6'-8" x 1-3/8" Thick, Flush, Hollow Core (HC), Birch Faced Wood Bi-Pass Doors
76 $1,872.97EA
Installation =x x 1,667.99
FactorUnit PriceQuantity Total
463.33 1.2000 3.00
Demolition x x = 204.98 85.41 1.2000 2.00
removal of 2 existing closet sliding doors, installation of 3 new closet sliding doors 08 53 13 00 0121 >60" To 73" UI, Single Hung Premium Vinyl Window (Pella 350)77 $1,415.59EA Installation =x x 1,288.92
FactorUnit PriceQuantity Total
537.05 1.2000 2.00
Demolition x x = 126.67 52.78 1.2000 2.00
replacement of all existing windows
08 53 13 00 0124 >93" To 101" UI, Single Hung Premium Vinyl Window (Pella 350)78 $993.74EA Installation =x x 912.31
FactorUnit PriceQuantity Total
760.26 1.2000 1.00
Demolition x x = 81.43 67.86 1.2000 1.00
replacement of all existing windows
08 53 13 00 0547 >93" To 101" UI, Horizontal Sliding Premium Vinyl Window (Pella 350)79 $4,338.30EA Installation =x x 3,931.14
FactorUnit PriceQuantity Total
655.19 1.2000 5.00
Demolition x x = 407.16 67.86 1.2000 5.00
replacement of all existing windows
08 71 11 00 0004 3-1/2" x 3-1/2" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
80 $550.33PR
Installation =x x 491.28
FactorUnit PriceQuantity Total

81.88 1.2000 5.00
Demolition x x = 59.05 7.03 1.2000 7.00
removal of existing and installation of new
08 71 11 00 0005 4" x 4" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
81 $485.62PR
Installation =x x 485.62
FactorUnit PriceQuantity Total

89.93 1.2000 4.50
for new front doors and one rear door per plans
08 71 11 00 0513 3" Projection, Residential Spring Type, Bright Brass Finish, Steel Wall Stop (Ives 63)
82 $252.10EA
Installation =x x 173.63
FactorUnit PriceQuantity Total

11.13 1.2000 13.00
Demolition x x = 78.47 5.03 1.2000 13.00
per plans
08 71 11 00 0655 190 Degree Angle Of View, Bright Brass Finish, Brass One-Way Wide Angle Door Viewer (Ives U698)
83 $138.60EA
Installation =x x 138.60
FactorUnit PriceQuantity Total

57.75 1.2000 2.00
for new front door per plans
08 71 11 00 2289 Passage/Closet F01 Mortise LatchsetBoth sides always unlocked.84 $1,019.63EA Installation =x x 959.32
FactorUnit PriceQuantity Total
799.43 1.2000 1.00
Demolition x x = 60.31 25.13 1.2000 2.00
removal of existing and installation of new

Page 8 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
482
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 08
08 71 11 00 2290 Bath/Bedroom Privacy F02/F19 Mortise LocksetLocked with thumb knob inside.
85 $5,939.35EA
Installation =x x 5,728.26
FactorUnit PriceQuantity Total
954.71 1.2000 5.00
Demolition x x = 211.09 25.13 1.2000 7.00
removal of existing and installation of new
08 71 11 00 2294 Entrance F08 Mortise LocksetLocked with key outside and thumb knob inside.86 $4,028.14EA Installation =x x 3,997.98
FactorUnit PriceQuantity Total
1,110.55 1.2000 3.00
Demolition x x = 30.16 25.13 1.2000 1.00
for new front doors and one rear door per plans
08 72 33 00 0155 3/8" x 3/16", Silicon Compression Bulb, Adhesive Backed Perimeter Gasketing Weather-Strip (Pemko PK33)
87 $445.68LF
Installation =x x 264.96
FactorUnit PriceQuantity Total

3.68 1.2000 60.00
Demolition x x = 180.72 2.51 1.2000 60.00
for new front doors and one rear door per plans
08 72 43 00 0011 6" Width, 1/4" Height, Aluminum Saddle Threshold (Pemko 272A)88 $442.69LF Installation =x x 442.69
FactorUnit PriceQuantity Total

40.99 1.2000 9.00
for new front doors and one rear door per plans
08 72 43 00 0011 0458 For Color Anodized Finish, Add89 $19.98 Installation =x x 19.98
FactorUnit PriceQuantity Total

5.55 1.2000 3.00
$36,198.70Subtotal for Section - 08
Section - 09
09 05 71 00 0002 5 Mil Tile And Stone Acoustical Underlayment (EasyMat)90 $8,787.66SF Installation =x x 8,787.66
FactorUnit PriceQuantity Total

4.27 1.2000 1,715.00
acoustical mat underlayment per plans
09 05 71 00 0005 2 MM Thick Resilient Plank Floor Acoustical Underlayment (Floormuffler)91 $2,881.20SF Installation =x x 2,881.20
FactorUnit PriceQuantity Total

1.40 1.2000 1,715.00
closest LI to gypsum sanded floor underlayment per plans 09 22 13 23 0008 25 Gauge, 16" On Center, Installed On Walls, Double-Leg Resilient Channel, RC2 Furring Channel
92 $4,062.18SF
Installation =x x 4,062.18
FactorUnit PriceQuantity Total

3.95 1.2000 857.00
Resilient channel per plans
09 22 13 23 0010 25 Gauge, 16" On Center, Installed On Ceilings, Double-Leg Resilient Channel, RC2 Furring Channel
93 $9,549.12SF
Installation =x x 9,549.12
FactorUnit PriceQuantity Total

4.64 1.2000 1,715.00
Resilient channel per plans
09 22 36 23 0005 3.4 LB/SY, Installed On Studs Or Furred Walls, Flat Diamond, Expanded Metal Lath
94 $1,461.60SF
Installation =x x 1,201.20
FactorUnit PriceQuantity Total

2.86 1.2000 350.00
Demolition x x = 260.40 0.62 1.2000 350.00
For stucco patch back

Page 9 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
483
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 09
09 22 36 23 0005 0020 For >100 To 500, Add95 $147.00 Installation =x x 147.00
FactorUnit PriceQuantity Total

0.35 1.2000 350.00
09 24 23 00 0002 Scratch/Brown/Finish, Three Coat Troweled StuccoExcludes lath and felt.

Interior or exterior, one side.
96 $4,956.00SF
Installation =x x 3,754.80
FactorUnit PriceQuantity Total

8.94 1.2000 350.00
Demolition x x = 1,201.20 2.86 1.2000 350.00
For Stucco patch back
09 24 23 00 0002 0024 For Walls >10' High, Add97 $112.32 Installation =x x 112.32
FactorUnit PriceQuantity Total

0.78 1.2000 120.00
09 24 23 00 0002 0031 For Color Added To Finish Coat, Add98 $21.60SF Installation =x x 21.60
FactorUnit PriceQuantity Total

0.15 1.2000 120.00
09 24 23 00 0002 0037 For >100 To 500, Add99 $282.24 Installation =x x 282.24
FactorUnit PriceQuantity Total

1.96 1.2000 120.00
09 29 10 00 0006 5/8" Gypsum Board100 $18,768.96SF Installation =x x 13,912.08
FactorUnit PriceQuantity Total

1.69 1.2000 6,860.00
Demolition x x = 4,856.88 0.59 1.2000 6,860.00
for walls and ceilings per plans. First floor ceiling requires 2 layers per plans 09 29 10 00 0038 Up To 10' High, Walls, Tape, Spackle And Finish Gypsum Board101 $5,597.76SF Installation =x x 5,597.76
FactorUnit PriceQuantity Total

0.68 1.2000 6,860.00
for walls
09 29 10 00 0038 0048 For ASTM C840 Level 5 High Quality Finish, Add102 $4,116.00 Installation =x x 4,116.00
FactorUnit PriceQuantity Total

0.50 1.2000 6,860.00
09 29 10 00 0041 Up To 10' High, Ceilings, Tape, Spackle And Finish Gypsum Board103 $1,811.04SF Installation =x x 1,811.04
FactorUnit PriceQuantity Total

0.88 1.2000 1,715.00
for ceilings
09 29 10 00 0041 0048 For ASTM C840 Level 5 High Quality Finish, Add104 $1,337.70 Installation =x x 1,337.70
FactorUnit PriceQuantity Total

0.65 1.2000 1,715.00
09 29 10 00 0044 Up To 10' High, Vertical Corners, Tape, Spackle And Finish Gypsum Board105 $2,502.05LF Installation =x x 2,502.05
FactorUnit PriceQuantity Total

1.34 1.2000 1,556.00
vertical corners @ 8' throughout both floors and windows 09 29 10 00 0044 0048 For ASTM C840 Level 5 High Quality Finish, Add106 $1,829.86 Installation =x x 1,829.86
FactorUnit PriceQuantity Total

0.98 1.2000 1,556.00
09 29 10 00 0047 Up To 10' High, Horizontal Corners, Tape, Spackle And Finish Gypsum Board107 $2,232.00LF Installation =x x 2,232.00
FactorUnit PriceQuantity Total

1.55 1.2000 1,200.00
walls and windows

Page 10 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
484
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 09
09 29 10 00 0047 0048 For ASTM C840 Level 5 High Quality Finish, Add108 $1,641.60 Installation =x x 1,641.60
FactorUnit PriceQuantity Total

1.14 1.2000 1,200.00
09 29 10 00 0051 Corner Bead, Galvanized Steel For Gypsum Board109 $10,262.74LF Installation =x x 10,262.74
FactorUnit PriceQuantity Total

3.63 1.2000 2,356.00
for walls and windows
09 65 23 00 0004 0.16" Overall Thickness, 0.020" Wear Layer, Vinyl Plank Flooring (Armstrong® Luxe Plank™)
110 $23,687.58SF
Installation =x x 23,687.58
FactorUnit PriceQuantity Total

11.51 1.2000 1,715.00
new flooring throughout per plans
09 91 13 00 0095 1 Coat Primer, Brush/Roller Work, Paint Exterior Stucco Walls111 $1,444.80SF Installation =x x 1,444.80
FactorUnit PriceQuantity Total

0.86 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 13 00 0097 2 Coats Paint, Brush/Roller Work, Paint Exterior Stucco Walls112 $3,057.60SF Installation =x x 3,057.60
FactorUnit PriceQuantity Total

1.82 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 23 00 0067 1 Coat Primer, Brush/Roller Work, Paint Interior Plaster/Drywall Walls113 $5,270.40SF Installation =x x 5,270.40
FactorUnit PriceQuantity Total

0.61 1.2000 7,200.00
for walls
09 91 23 00 0069 2 Coats Paint, Brush/Roller Work, Paint Interior Plaster/Drywall Walls114 $10,540.80SF Installation =x x 10,540.80
FactorUnit PriceQuantity Total

1.22 1.2000 7,200.00
for walls
09 91 23 00 0161 1 Coat Primer, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling115 $1,461.18SF Installation =x x 1,461.18
FactorUnit PriceQuantity Total

0.71 1.2000 1,715.00
for ceilings
09 91 23 00 0163 2 Coats Paint, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling116 $2,675.40SF Installation =x x 2,675.40
FactorUnit PriceQuantity Total

1.30 1.2000 1,715.00
for ceilings
09 91 23 00 0252 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Door Frame And Trim117 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

0.93 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0254 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Door Frame And Trime118 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

2.02 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0275 1 Coat Primer, Brush/Roller Work, Both Faces, Paint Interior Wood Door119 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total

76.57 1.2000 0.00
8 doors on first floor
7 doors on second floor

Page 11 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
485
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 09
09 91 23 00 0277 2 Coats Paint, Brush/Roller Work, Both Faces, Paint Interior Wood Door120 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total
138.02 1.2000 0.00
8 doors on first floor
7 doors on second floor
09 91 23 00 0307 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
121 $192.00LF
Installation =x x 192.00
FactorUnit PriceQuantity Total

1.25 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0309 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
122 $416.26LF
Installation =x x 416.26
FactorUnit PriceQuantity Total

2.71 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0350 1 Coat Primer, Brush Work, Paint Interior Wood Trim To 6" Wide123 $576.00LF Installation =x x 576.00
FactorUnit PriceQuantity Total

0.64 1.2000 750.00
750 LF of baseboards
09 91 23 00 0352 2 Coats Paint, Brush Work, Paint Interior Wood Trim To 6" Wide124 $1,305.00LF Installation =x x 1,305.00
FactorUnit PriceQuantity Total

1.45 1.2000 750.00
750 LF of baseboards
$132,987.65Subtotal for Section - 09
Section - 10
10 14 53 11 0078 18" x 24" Reflective Polyethylene Traffic Sign125 $165.61EA Installation =x x 165.61
FactorUnit PriceQuantity Total
138.01 1.2000 1.00
ADA parking sign
10 14 53 11 0198 Single Bracket And Post Cap For Street Sign126 $29.02EA Installation =x x 29.02
FactorUnit PriceQuantity Total

24.18 1.2000 1.00
ADA parking sign
10 14 53 11 0213 8' Galvanized Steel U-Channel Sign Post127 $165.00EA Installation =x x 165.00
FactorUnit PriceQuantity Total
137.50 1.2000 1.00
ADA parking sign
10 14 53 11 0278 2-3/8" Diameter, Galvanized, Flat Traffic Sign Post Cap (EC-2)128 $26.24EA Installation =x x 26.24
FactorUnit PriceQuantity Total

21.87 1.2000 1.00
ADA parking sign
10 28 13 13 0045 Single Roll, Surface Mounted, Stainless Steel, Satin Finish, Toilet Tissue Dispenser (Bobrick B-6857)
129 $308.30EA
Installation =x x 254.04
FactorUnit PriceQuantity Total
105.85 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans

Page 12 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
486
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 10
10 28 13 13 0170 36" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x36)130 $401.44EA Installation =x x 401.44
FactorUnit PriceQuantity Total
111.51 1.2000 3.00
per plans
10 28 13 13 0170 0148 For Peened Grip, Add131 $24.73 Installation =x x 24.73
FactorUnit PriceQuantity Total

6.87 1.2000 3.00
10 28 13 13 0171 42" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x42)132 $136.87EA Installation =x x 136.87
FactorUnit PriceQuantity Total
114.06 1.2000 1.00
per plans
10 28 13 13 0171 0148 For Peened Grip, Add133 $8.52 Installation =x x 8.52
FactorUnit PriceQuantity Total

7.10 1.2000 1.00
10 28 13 13 0217 Telescoping 60" To 72" Length, 20-Gauge, 1" Diameter, Stainless Steel Curved Shower Rod With Concealed Mounting (Kohler Expanse K-9349) 134 $389.23EA
Installation =x x 334.97
FactorUnit PriceQuantity Total
139.57 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0322 24" Length, 3/4" Diameter, Stainless Steel Towel Bar (Bobrick B-674)135 $333.74EA Installation =x x 279.48
FactorUnit PriceQuantity Total
116.45 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0390 20" x 26", Surface Mounted, Aluminum Medicine Cabinet (Kohler K-CB)136 $1,707.62EA Installation =x x 1,587.05
FactorUnit PriceQuantity Total
661.27 1.2000 2.00
Demolition x x = 120.58 50.24 1.2000 2.00
per plans
$3,696.32Subtotal for Section - 10
Section - 11
11 30 13 13 0015 30" Venting Range Hood (Broan 40000)137 $717.65EA Installation =x x 637.08
FactorUnit PriceQuantity Total
265.45 1.2000 2.00
Demolition x x = 80.57 67.14 1.2000 1.00
removal of existing and installation of 2 new
$717.65Subtotal for Section - 11
Section - 12
12 36 61 19 0005 1-1/4" Thick, Quartz Agglomerate Countertop With Backsplash138 $12,198.00SF Installation =x x 11,117.34
FactorUnit PriceQuantity Total
142.53 1.2000 65.00
Demolition x x = 1,080.66 25.73 1.2000 35.00
kitchen countertops

Page 13 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
487
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 12
12 36 61 19 0006 Quartz Agglomerate Countertop End Splash For Quartz Agglomerate Countertops
139 $101.54LF
Installation =x x 91.30
FactorUnit PriceQuantity Total

19.02 1.2000 4.00
Demolition x x = 10.25 4.27 1.2000 2.00
for end where fridges meet
12 36 61 19 0007 Cutout For Sink And/Or Faucet In Quartz Agglomerate Countertop140 $361.73EA Installation =x x 361.73
FactorUnit PriceQuantity Total
150.72 1.2000 2.00
2 kitchen sinks
$12,661.27Subtotal for Section - 12
Section - 22
22 01 40 81 0004 Removal And Replacement Of Chrome Supply Lines To Sink/Lavatory, Pair141 $335.04EA Installation =x x 335.04
FactorUnit PriceQuantity Total

27.92 1.2000 10.00
replace supply lines in kitchens and bathrooms
22 01 40 81 0006 Removal And Replacement Of Double Bowl Sink/Lavatory Drain Line142 $289.97EA Installation =x x 289.97
FactorUnit PriceQuantity Total

60.41 1.2000 4.00
new drain lines
22 11 16 00 0003 3/4" Schedule 40 Threaded Galvanized Steel Pipe With 150 LB Malleable Iron Fitting AssemblyIncludes all hangers and all galvanized malleable iron fittings (couplings, elbows, tees and reducer fittings). All hangers are complete assemblies. Not for use where detail is available.
143 $13,959.60LF
Installation =x x 12,930.00
FactorUnit PriceQuantity Total

21.55 1.2000 500.00
Demolition x x = 1,029.60 4.29 1.2000 200.00
gas line piping
22 11 16 00 0003 0304 For Work In Restricted Working Space, Add144 $1,010.40 Installation =x x 1,010.40
FactorUnit PriceQuantity Total

4.21 1.2000 200.00
22 11 16 00 0901 3/4" Inside Diameter Copper Pipe/Tubing Type L AssemblyIncludes all hangers and couplings, elbow, tee, reducer fittings. All hangers are complete assemblies. Not for use where detail is available.
145 $32,443.80LF
Installation =x x 29,628.60
FactorUnit PriceQuantity Total

25.99 1.2000 950.00
Demolition x x = 2,815.20 3.91 1.2000 600.00
water line copper piping
22 11 16 00 0901 0315 For Work In Restricted Working Space, Add146 $1,384.80 Installation =x x 1,384.80
FactorUnit PriceQuantity Total

5.77 1.2000 200.00
22 12 23 13 0002 80 Gallon ASME Rated Tank, 150PSI, Jacketed, Insulated, Glass Lined Water Heater Storage Tank (TJ-80A)
147 $479.41EA
Installation =x x 0.00
FactorUnit PriceQuantity Total
2,554.73 1.2000 0.00
Demolition x x = 479.41 399.51 1.2000 1.00
removal of existing water heater

Page 14 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
488
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 22
22 13 16 00 0518 4" Aboveground Schedule 40 Polyvinyl Chloride (PVC) DWV Pipe AssemblyIncludes all fittings, couplings and hangers. Fittings are assumed every 10'. Not for use where detail is available.
148 $48,884.70LF
Installation =x x 46,314.00
FactorUnit PriceQuantity Total

51.46 1.2000 750.00
Demolition x x = 2,570.70 7.79 1.2000 275.00
new Sewer and vent piping
22 13 16 00 0518 0304 For Work In Restricted Working Space, Add149 $2,175.00 Installation =x x 2,175.00
FactorUnit PriceQuantity Total

7.25 1.2000 250.00
22 34 13 00 0011 7.4 GPM, Outdoor Mount, Instantaneous, Tankless, Gas Domestic Water Heater (Rheem RTG-74XN)
150 $10,037.42EA
Installation =x x 10,037.42
FactorUnit PriceQuantity Total
4,182.26 1.2000 2.00
installation of 2 new water heaters
22 41 16 16 0003 33" x 21" x 6-1/2" Stainless Steel Kitchen Sink, Double Bowl, 20 Gauge (Elkay D233213)
151 $1,768.56EA
Installation =x x 1,640.30
FactorUnit PriceQuantity Total
683.46 1.2000 2.00
Demolition x x = 128.26 106.88 1.2000 1.00
removal of existing and installation of new.
22 41 39 00 0006 Chrome Two Handle Kitchen Faucet With Spray, Three Hole Installation, 8" Center (Delta 2402LF-LHP+H215)
152 $565.87EA
Installation =x x 505.94
FactorUnit PriceQuantity Total
210.81 1.2000 2.00
Demolition x x = 59.93 49.94 1.2000 1.00
removal of existing and installation of new.
22 42 13 13 0026 2 Piece Tank Type, Pressure Assisted, Siphon Jet, Floor Mounted, Back Outlet, Handicap Accessible, Elongated Vitreous China Water Closet (American Standard Yorkville™ ADA)
153 $2,811.37EA
Installation =x x 2,686.73
FactorUnit PriceQuantity Total
1,119.47 1.2000 2.00
Demolition x x = 124.64 103.87 1.2000 1.00
remove existing and install new ADA toilet
22 42 16 13 0009 27" x 20" Wheelchair Accessible, Vitreous China Wall Hung Lavatory (American Standard Wheel Chair Users)
154 $1,701.89EA
Installation =x x 1,621.58
FactorUnit PriceQuantity Total
675.66 1.2000 2.00
Demolition x x = 80.30 66.92 1.2000 1.00
remove existing and install new ADA sink, faucet, and drain cover. 22 42 19 00 0027 3 Piece Tub/Shower Surrounds, 32" x 72" Side Walls, 48" x 72" Back, (Swanstone SK-324872)
155 $8,454.49EA
Installation =x x 8,071.78
FactorUnit PriceQuantity Total
3,363.24 1.2000 2.00
Demolition x x = 382.72 318.93 1.2000 1.00
new tub/shower for bathrooms
22 42 39 00 0042 Single Supply EcoPower® Faucet, Polished Chrome Finish (Toto TEL3LS10#CP)
156 $1,885.78EA
Installation =x x 1,885.78
FactorUnit PriceQuantity Total
785.74 1.2000 2.00
ADA sink, faucet, and drain cover.

Page 15 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
489
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 22
22 42 39 00 0064 Three Lever Handle, Chrome Shower And Tub Filler (American Standard Colony Soft 3375.502)
157 $741.02EA
Installation =x x 636.98
FactorUnit PriceQuantity Total
265.41 1.2000 2.00
Demolition x x = 104.04 43.35 1.2000 2.00
per plans
22 42 39 00 0064 0147 For Faucet With Metal Cross Handles, Add158 $109.80EA Installation =x x 109.80
FactorUnit PriceQuantity Total

45.75 1.2000 2.00
22 42 39 00 0211 Lavatory Protective Enclosure (IPS Truebro Lav Shield)159 $390.86EA Installation =x x 390.86
FactorUnit PriceQuantity Total
162.86 1.2000 2.00
drain cover for ADA kitchen and bathroom sink
22 42 39 00 0218 1/2" NPT x 3/8" Compression Chrome, Quarter Turn Dual Angle Stop (SharkBite 25558)
160 $680.78EA
Installation =x x 580.08
FactorUnit PriceQuantity Total

48.34 1.2000 10.00
Demolition x x = 100.70 10.49 1.2000 8.00
new angle stops installed in bathrooms and kitchens
$130,110.56Subtotal for Section - 22
Section - 23
23 09 23 53 0284 Scheduling Program, HVAC (AHU, RTU, AC Units, Etcetera) Programming Measures
161 $8,755.06EA
Installation =x x 8,755.06
FactorUnit PriceQuantity Total
3,647.94 1.2000 2.00
required setup, balancing, and charging for new system
23 31 13 16 0063 4" Diameter, 26 Gauge, Seal Class C, Galvanized Sheet Metal Round And Flat-Oval Connector
162 $3,117.60EA
Installation =x x 3,117.60
FactorUnit PriceQuantity Total

17.32 1.2000 150.00
exhaust ducting per plans
23 33 13 13 0006 12" Diameter Radial Opposed Blade Damper Round, Steel Construction, Manual Operated
163 $696.79EA
Installation =x x 682.22
FactorUnit PriceQuantity Total
142.13 1.2000 4.00
Demolition x x = 14.57 12.14 1.2000 1.00
HVAC per plans
23 33 46 00 0008 12" Diameter Flexible Duct, R8.0 Insulated With Polyester Inner Liner Over Fiberglass Insulation And Metallized Outer Jacket
164 $12,610.20LF
Installation =x x 11,491.20
FactorUnit PriceQuantity Total

21.28 1.2000 450.00
Demolition x x = 1,119.00 3.73 1.2000 250.00
HVAC per plans - exhaust ducting
23 33 46 00 0020 12" Diameter Flexible Duct Collar, Spin In Type, Sheet Metal, With Damper165 $739.63EA Installation =x x 706.03
FactorUnit PriceQuantity Total

98.06 1.2000 6.00
Demolition x x = 33.60 14.00 1.2000 2.00
HVAC per plans

Page 16 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
490
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 23
23 34 16 00 0272 109 CFM, Ceiling/Wall Mounted, Metal Intake Grille, Heavy Duty/Continuous Operation Exhaust Fan (Broan® LoSone® Ventilator L100MG) 166 $2,212.13EA
Installation =x x 2,168.35
FactorUnit PriceQuantity Total
451.74 1.2000 4.00
Demolition x x = 43.78 36.48 1.2000 1.00
Laundry room and bathroom exhaust fan per plans
23 54 16 13 0007 120 MBH, 2,000 CFM Up/Horizontal Flow Multi-Speed, Two Stage 96% AFUE Gas FurnaceBlower cooling capacity up to 5 tons.
167 $15,925.85EA
Installation =x x 15,770.64
FactorUnit PriceQuantity Total
2,628.44 1.2000 5.00
Demolition x x = 155.21 129.34 1.2000 1.00
per plans. wall mounted furnaces
$44,057.26Subtotal for Section - 23
Section - 26
26 01 20 91 0002 Lock Out/Tag Out Local DisconnectExcludes tag or padlock See CSI section 26 01 20 91-0004 for padlock, 26 01 20 91-0005 for tag(s). 168 $590.94EA
Installation =x x 590.94
FactorUnit PriceQuantity Total

32.83 1.2000 15.00
LOTO of existing circuits
26 05 19 16 0402 #12 AWG, 3 Conductors, 600 Volt, Type NM, Copper, Non-Metallic Sheathed Cable
169 $24,763.20MLF
Installation =x x 24,763.20
FactorUnit PriceQuantity Total
4,127.20 1.2000 5.00
for new electrical runs per plans
26 05 19 16 0402 0377 For Installation In Wood Stud Wall (Includes Drilling), Add170 $1,795.14 Installation =x x 1,795.14
FactorUnit PriceQuantity Total
299.19 1.2000 5.00
26 09 23 00 0144 Wall Switch Replacement Occupancy Sensor, Single GangIncludes integral occupancy sensor and relay.
171 $1,483.80EA
Installation =x x 1,483.80
FactorUnit PriceQuantity Total
123.65 1.2000 10.00
per plans
26 09 23 00 0270 Passive Infrared, Wall Switch Mounted, Wired Occupancy Sensor (Encelium PW-100-24)Excludes GB II cable.
172 $725.28EA
Installation =x x 725.28
FactorUnit PriceQuantity Total
302.20 1.2000 2.00
for bathrooms
26 24 13 00 0213 800 Amperes, 480 Volt, 4 Wire, Switchboard Incoming No Switch Circuit173 $6,313.51EA Installation =x x 5,324.36
FactorUnit PriceQuantity Total
4,436.97 1.2000 1.00
Demolition x x = 989.15 824.29 1.2000 1.00
for new main panel to new units subpanels
26 24 16 00 0470 200 Ampere Rating, Main Breaker, Indoor, 42 Circuit, 4 Wire, 120/208 Volt, Assembled Panelboard With 20 Ampere, 1 Pole Plug-In Breakers 174 $8,743.93EA
Installation =x x 7,651.92
FactorUnit PriceQuantity Total
3,188.30 1.2000 2.00
Demolition x x = 1,092.01 910.01 1.2000 1.00
1 new sub panel for each unit

Page 17 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
491
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 26
26 27 13 00 0125 Single Phase M-90 Meter, Socket, NEMA 3R Enclosure175 $8,033.33EA Installation =x x 7,705.73
FactorUnit PriceQuantity Total
1,070.24 1.2000 6.00
Demolition x x = 327.60 54.60 1.2000 5.00
installation of new meters for building
26 27 26 00 0009 20 Amperes, 1 Gang, GFI, Duplex Receptacle Assembly176 $5,103.00EA Installation =x x 4,273.08
FactorUnit PriceQuantity Total
101.74 1.2000 35.00
Demolition x x = 829.92 34.58 1.2000 20.00
All new GFI outlets throughout per clients request
26 27 26 00 0125 20 Amperes, 125 Volt Single Specification Grade Tamper Resistant ReceptaclePass & Seymour TR5351.
177 $2,554.46EA
Installation =x x 2,073.98
FactorUnit PriceQuantity Total

39.28 1.2000 44.00
Demolition x x = 480.48 9.10 1.2000 44.00
all new outlets throughout per clients request
26 27 26 00 0138 1 Gang, 20 Amperes, 120/277 Volt, SPST, Switch Assembly178 $3,774.00EA Installation =x x 2,736.60
FactorUnit PriceQuantity Total

91.22 1.2000 25.00
Demolition x x = 1,037.40 34.58 1.2000 25.00
25 switches total in both units
26 51 19 00 0269 2' x 2', 4,000 Lumens, Surface Mount, Volumetric LED Fixture (Lithonia 2RTX2)179 $7,035.98EA Installation =x x 6,106.46
FactorUnit PriceQuantity Total
212.03 1.2000 24.00
Demolition x x = 929.52 38.73 1.2000 20.00
new LED lights throughout
26 51 19 00 0477 2-1/2" Diameter x 15-1/2" High, Polished Nickel, LED Wall Sconce (Hudson Valley Lighting SHAW 1200-PN)
180 $1,281.65EA
Installation =x x 1,194.29
FactorUnit PriceQuantity Total
497.62 1.2000 2.00
Demolition x x = 87.36 36.40 1.2000 2.00
2 new wall sconces per plans in bathrooms
$72,198.22Subtotal for Section - 26
Section - 31
31 05 16 00 0002 #2 Stone Aggregate Fill (1-1/2" To 2-1/2" Clean)181 $1,650.60CY Installation =x x 1,650.60
FactorUnit PriceQuantity Total

55.02 1.2000 25.00
4" deep, 200 LF, 2' wide base for backfill for trenching. 20 CY for footings, and slabs 31 05 16 00 0002 0053 For Up To 8, Add182 $66.00
Installation =x x 66.00
FactorUnit PriceQuantity Total

11.00 1.2000 5.00
31 11 00 00 0010 Clearing By Machine - Light Brush Without Grub183 $202.36ACR Installation =x x 202.36
FactorUnit PriceQuantity Total
337.26 1.2000 0.50
clear out weeds in back yard
31 11 00 00 0019 Hand Loading Of Cleared And Grubbed Material184 $976.32CY Installation =x x 976.32
FactorUnit PriceQuantity Total

40.68 1.2000 20.00
clear out weeds in back yard

Page 18 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
492
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 31
31 23 16 13 0007 Excavation For Trenching By Hand In SoilIncludes stockpiling excess materials and trimming sides and bottom of trench.
185 $4,027.50CY
Installation =x x 4,027.50
FactorUnit PriceQuantity Total
134.25 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0011 Backfilling or Placing Subbase for Trenches with Imported or Stockpiled Materials by Hand
186 $1,118.70CY
Installation =x x 1,118.70
FactorUnit PriceQuantity Total

37.29 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0014 Compaction of Fill or Subbase for Trenches by Hand187 $1,262.10CY Installation =x x 1,262.10
FactorUnit PriceQuantity Total

42.07 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 36 0009 Excavation For Building Foundations And Other Structures By Hand in Soil188 $7,249.50CY Installation =x x 7,249.50
FactorUnit PriceQuantity Total
134.25 1.2000 45.00
for footings
31 23 16 36 0019 Backfilling Around Building Foundations And Other Structures By Hand189 $1,534.32CY Installation =x x 1,534.32
FactorUnit PriceQuantity Total

63.93 1.2000 20.00
for footings
31 23 16 36 0022 Compaction Of Fill Or Subbase For Building Foundations and Other Structures by Hand
190 $2,271.24CY
Installation =x x 2,271.24
FactorUnit PriceQuantity Total

42.06 1.2000 45.00
for footings
$20,358.64Subtotal for Section - 31
Section - 32
32 16 13 13 0016 6" x 12" Cast In Place Concrete Gutter With 6" Curb And Face - Straight191 $225.96LF Installation =x x 154.98
FactorUnit PriceQuantity Total

25.83 1.2000 5.00
Demolition x x = 70.98 11.83 1.2000 5.00
for parking lot ADA modifications
32 16 13 13 0016 0077 For Up To 20, Add192 $105.42MOD Installation =x x 105.42
FactorUnit PriceQuantity Total

17.57 1.2000 5.00
32 16 23 00 0002 4" Cast In Place Concrete Sidewalk193 $212.16SF Installation =x x 212.16
FactorUnit PriceQuantity Total

8.84 1.2000 20.00
for parking lot ADA modifications
32 16 23 00 0002 0094 For Up To 100, Add194 $92.16 Installation =x x 92.16
FactorUnit PriceQuantity Total

3.84 1.2000 20.00
32 16 23 00 0008 Finish Concrete Handicap Drop Section In SidewalkExcludes patterned (tactile) finish.
195 $167.12EA
Installation =x x 167.12
FactorUnit PriceQuantity Total
139.27 1.2000 1.00
for parking lot ADA modifications

Page 19 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
493
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124232.00
OHA - 1040 Unit Remodel
Section - 32
32 17 23 13 0074 Solid Area, Painted Pavement Marking For Parking AreasUse task for lines >12" wide, stop bars, transverse lines, diagonal lines, crossing lanes, etc. 196 $102.48SF
Installation =x x 102.48
FactorUnit PriceQuantity Total

4.27 1.2000 20.00
for parking lot ADA modifications
32 17 23 13 0088 Handicap Symbol For Van Parking Stalls, Painted Pavement Marking For Parking AreasApproximate overall dimensions: 4-1/3' width x 5' height. White or blue symbol. Excludes striping.
197 $52.66EA
Installation =x x 52.66
FactorUnit PriceQuantity Total

43.88 1.2000 1.00
for parking lot ADA modifications
32 17 26 00 0003 Embedded, VPC Truncated Dome Detectable Warning SurfaceAlso raised strips or directional bars. All colors.
198 $650.04SF
Installation =x x 650.04
FactorUnit PriceQuantity Total

54.17 1.2000 10.00
new truncated domes per
32 31 13 13 0010 12" Diameter Hole, Auger By Machine Fence Post Hole In Soil199 $80.75VLF Installation =x x 80.75
FactorUnit PriceQuantity Total

22.43 1.2000 3.00
ADA parking sign
32 31 13 13 0027 12" Diameter, Concrete Fill For Post Hole200 $89.28VLF Installation =x x 89.28
FactorUnit PriceQuantity Total

24.80 1.2000 3.00
ADA parking sign
$1,778.03Subtotal for Section - 32
Proposal Total
This total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 20 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
494
Subcontractor Listing
124232.00
OHA - 1040 Unit Remodel
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
%DutiesName of Contractor Amount
Refined Construction 86.02$520,000.00

6.00

Page 1 of 1 ends

1/9/2024
Subcontractor Listing
495
Work Order Signature Document
EZIQC Contract No.: CA-R7-GB-101723-MDJ
New Work Order
124238.00
Modify an Existing W
ork Order
Work Order Title:

Work Order Number.: Work Order Date:

X
01/09/2024
Contractor Name:

Contact:

Phone:

Contact:

Phone:

Matt McMillon
310-490-1521
Owner Name:

OHA - 1070 Unit Remodel
Oxnard Housing Authority
Fredi Contreras
805-890-8319
MDJ Management
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of Sourcewell EZIQC Contract No CA-R7-GB-101723-MDJ.

Brief Work Order Description
:

Will not apply:Liquidated Damages Will apply:

Estimated Completion Date:

Estimated Start Date: Time of Performance
X
Work Order Firm Fixed Price: $604,505.00
Owner Purchase Order Number:

Approvals
Date DateMDJ ManagementOxnard Housing Authority

2.00

Page 1 of 1 ends

1/9/2024
Work Order Signature Document

EXHIBIT A
496

3.00 Detailed Scope of Work
Fredi ContrerasMatt McMillonT o: From:

MDJ Management Oxnard Housing Authority
531 Main St #611 300 N. Marquita Street
El Segundo, CA 90245 Oxnard, CA 93030
310-490-1521 805-890-8319
Work Order Number:

January 09, 2024Date Printed:
124238.00
OHA - 1070 Unit RemodelWork Order Title:

Brief Scope:

Revised FinalPreliminary X
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the items set forth below shall be considered part of this scope of work.

See attached
Subject to the terms and conditions of ezIQC Contract CA-R7-GB-101723-MDJ.

MDJ Management Date
DateOxnard Housing Authority

Page 1 of 1 ends

1/9/2024
Scope of Work
497
MDJ Management, LLC
License # 1044711
DIR # 1000061313
531 Main St. #611 El Segundo CA 90245
310-490-1521
Job Name: 1070 Colonia Conversion
Location: 1070-C E. Colonia Rd. Oxnard, CA
93030 Customer: Oxnard Housing Authority
Submission Date: 1/4/24
Detailed Scope of Work
Demolition
● Demolition of existing apartment per plans
Installation/Buildout
● Saw cutting of slab and demolition of concrete for new plumbing ● Excavation for new plumbing and new concrete footings for addition ● All framing throughout including new walls and soffits ● New rough and finish plumbing throughout
● New electrical rough including new panel per plan
● Concrete work:
○ Excavate under slab for rough plumbing and electrical needs ○ Pour new footings per structural plans
○ Pour back all open trenches inside the unit
○ Outside sidewalk as required
● New windows and doors throughout
● New Insulation
● HVAC per plans
○ Exhaust fan ducting
○ Remove existing wall heater and installation of new wall heaters per plans ● Drywall throughout
○ Patch were needed due to demolition and rough MEP requirements ○ New drywall per plans
○ Double stacked first floor ceiling with resilient channels per plans ● Lath, stucco, and color coat to match existing for stucco patching ● Interior paint
● New Flooring and MDF base
○ New underlayment and self leveling
● New kitchens, countertops, fixtures, sinks and appliances 1 of 3
498
● Newbathroomfixturesper plan● Sitework:○ Newsidewalks○ Handicaprampwithtruncateddomes○ Handicapstriping○ Newsignageat Handicapstall Installation/Buildout addedbyClient NOTincludedonplans● Removeandreplaceall outletsandswitchesthroughout, evenonall existingwalls● Install MDFbaseboards○ Insteadof calledout vinyl base● Removeandreplaceall interior doors. Completelist of doorsfromplansaswell asclientsrequest● Cleanupexistingbackyard, theweedsare5feet high○ Includesweedweedwhackingandremoval of all deadweeds● All newLEDlightingthroughout Notes:● All worktobeperformedper plansprovidedtoMDJ● Anyadditional addonitemswill beat therequest of Customer. Anyadjustment shall beanadditional cost.● Priceincludesall labor (Normal WorkingHours- DavisBaconWages), materials,equipment tocompletethisscopeof work.● ConstructionExclusions:○ NewWasher andDryer not includedincontract○ Newstove, range, dishwasher, andfridgenot includedincontract CLARIFICATIONSANDEXCLUSIONS:● Warranty○ Oneyear warrantyagainst workmanship○ Manufacturer'swarrantyvaries● Weexcludeplans, permits, permit fees, relatedfees, testing, inspection, survey, andengineeringunlessspecifiedabove● Weexcludeutilitiesandhazardousor contaminatedmaterial.● Constructionwater, power, andsanitaryfacilitiesavailableonsitefor MDJ’suseat nocost.● Weexcludepremiumtime.● Weexcludeanythingnot specificallymentionedabove.● MDJreservestheright toreview, change, and/or deleteanyprovisionsof anyprimecontract or subcontract, whichresultsfromthisquotation.● All termstobenet 30daysinfull uponreceipt of invoice. Interest will bechargedat therateof 2%monthlyontheunpaidbalance.

BIDPRICE: SeePriceProposal
All worktobecompletedinasubstantial andworkmanlikemanner accordingtostandardpracticesfor thesumof SeePriceProposal. Anyadditional addonitemswill beat therequestof Customer. Anyadjustment shall beanadditional cost.

Bidpriceisgoodfor thirty(30) daysonly.
2of 3
499
Anycontroversyor claimbasedon, arisingout of, or relatingtothisagreement, or breachthereof, includinganyclaimbasedontheworkperformedpursuant tothisagreement, shall besubmittedtotheAmericanArbitrationAssociationfor bindingarbitrationinaccordancewithitsrules. If anyarbitration, legal actionisbrought toenforcethisagreement, or arisingout of orrelatingtotheagreement, theprevailingpartyshall beentitledtorecover fromthenon-prevailingpartyreasonableattorneyfeesandcostsincurred, inadditiontoanyandall otherrelief towhichthat partymaybeentitled.

Submittedby:

MatthewMcMillonPresident [email protected] 3of 3
500

4.00 Contractor's Price Proposal - Summary
Owner PO #:

OH
A - 1070 Unit Remodel
124238.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
$50,228.90Section - 01
$2,817.60Section - 02
$24,059.94Section - 03
$46,235.58Section - 06
$26,398.68Section - 07
$36,198.70Section - 08
$132,987.65Section - 09
$3,696.32Section - 10
$717.65Section - 11
$12,661.27Section - 12
$130,110.56Section - 22
$44,057.26Section - 23
$72,198.22Section - 26
$20,358.64Section - 31
$1,778.03Section - 32
Proposal Total
Thisl total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 1 of 1 ends

1/9/2024
Contractor's Price Proposal - Summary
501

5.00 Contractor's Price Proposal - Detail
OHA - 1070 Unit Remodel
124238.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
(Excludes)Equip. MaterialLabor
Line TotalDescriptionUOMMod.ItemSect.

Section - 01
01 22 16 00 0002 Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible costs as directed by Owner. Insert the appropriate quantity to adjust the base cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees, list each one separately and add a comment in the "note" block to identify the Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended warranty, expedited shipping costs, etc.). A copy of each receipt, invoice, or proof of payment shall be submitted with the Price Proposal. 1 $13,011.90EA
Installation =x x 13,011.90
FactorUnit PriceQuantity Total

1.00 1.1000 11,829.00
Bond = $591,493 x 2%
01 22 20 00 0006 CarpenterFor tasks not included in the Construction Task Catalog® and as directed by owner only.
2 $7,623.17HR
Installation =x x 7,623.17
FactorUnit PriceQuantity Total

99.26 1.2000 64.00
2 guys for 4 days for reconfiguring framing around doors and windows to meet new sizing and ADA requirements.
01 22 20 00 0010 ElectricianFor tasks not included in the Construction Task Catalog® and as directed by owner only.
3 $866.21HR
Installation =x x 866.21
FactorUnit PriceQuantity Total

90.23 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 22 20 00 0037 PlumberFor tasks not included in the Construction Task Catalog® and as directed by owner only.
4 $1,027.78HR
Installation =x x 1,027.78
FactorUnit PriceQuantity Total
107.06 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 66 19 00 0060 Handling Material For Over 125' Per 48" x 40" x 48" Container Per 125' Segment
5 $10,586.88EA
Installation =x x 10,586.88
FactorUnit PriceQuantity Total

9.19 1.2000 960.00
4 guys, averaging 4 trips a day for 3 months for demolition hauling and delivery of purchased materials. 01 74 19 00 0016 40 CY Dumpster (5 Ton) "Construction Debris"Includes delivery of dumpster, rental cost, pick-up cost, hauling, and disposal fee. Non-hazardous material. 6 $12,743.71EA
Installation =x x 12,743.71
FactorUnit PriceQuantity Total
884.98 1.2000 12.00
10 dumpsters for demolition debris: cabinets, drywall from entire house, shower, toilet, stucco, insulation, ... 2 dumpsters for construction debris: drywall cuts, lumber cuts, basic trash 01 74 19 00 0019 15 CY Low-Boy Dumpster Mixed RecyclableFor mixed dirt, rock, concrete brick or asphalt with no trash or organics. Includes service to deliver and pick-up dumpster, hauling, rental and disposal fee.
7 $4,369.25EA
Installation =x x 4,369.25
FactorUnit PriceQuantity Total
910.26 1.2000 4.00
for removal of excavated soil for footings, slab, trenching $50,228.90Subtotal for Section - 01
Section - 02

Page 1 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
502
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 02
02 41 19 13 0063 Rod Reinforced Concrete Slab Up To 4" Depth, Saw Cut8 $2,817.60LF Installation =x x 2,817.60
FactorUnit PriceQuantity Total

5.87 1.2000 400.00
sawcut existing slab to trench for new electrical and plumbing runs as needed per plans $2,817.60Subtotal for Section - 02
Section - 03
03 21 11 00 0251 Dowels Or Hairpin, 1/2" x 30" Length, Drilled And Epoxy In Concrete, 6" Embedment
9 $6,655.50EA
Installation =x x 6,655.50
FactorUnit PriceQuantity Total

24.65 1.2000 225.00
200 LF of trenching. Epoxy and Dowel every 2'. One on each side. For reinforcement and tying into existing slab adjacent. 25 dowels to attach from porch sidewalk to existing . 03 21 13 00 0093 #6, Grade 50, Slab On Grade, Galvanized Steel Reinforcement Bar10 $2,496.00LF Installation =x x 2,496.00
FactorUnit PriceQuantity Total

2.60 1.2000 800.00
200 LF of trenching and 600 LF for slab, porch, and footings. Installation of rebar every 2'. 03 30 53 00 0009 Hand Mix And Place ConcreteFor use where conventional equipment access is limited or when directed by the owner.

Includes local aggregate, sand, bagged cement (Type I) and water. 11 $4,370.40CF
Installation =x x 4,370.40
FactorUnit PriceQuantity Total

18.21 1.2000 200.00
patch back trenching in existing slab
03 30 53 00 0009 0038 For High Early Strength, Type 3 ASTM C150, Add12 $156.00 Installation =x x 156.00
FactorUnit PriceQuantity Total

0.65 1.2000 200.00
03 30 53 00 0009 0039 For Lightweight Aggregate, ASTM C330, Add13 $544.80 Installation =x x 544.80
FactorUnit PriceQuantity Total

2.27 1.2000 200.00
03 54 16 00 0005 1/2" Thick Self Leveling Cementitious Underlayment For FloorsIncluding Surface Preparation
14 $9,837.24SF
Installation =x x 9,837.24
FactorUnit PriceQuantity Total

4.78 1.2000 1,715.00
self leveling of floors for prior to installation of new vinyl plank flooring $24,059.94Subtotal for Section - 03
Section - 06
06 11 16 00 0061 2" x 4" Wood Wall Framing At 16" On Center15 $2,321.57SF Installation =x x 1,434.24
FactorUnit PriceQuantity Total

1.66 1.2000 720.00
Demolition x x = 887.33 0.79 1.2000 936.00
for new walls. Couple walls require double stacked
06 16 33 00 0020 3/4" CD Grade Plywood Floor DeckingApplied to floor or joists.16 $6,338.64SF Installation =x x 5,083.26
FactorUnit PriceQuantity Total

2.47 1.2000 1,715.00
Demolition x x = 1,255.38 0.61 1.2000 1,715.00
for new floor decking per plans
06 16 33 00 0020 0038 For Exterior Glue, Add17 $185.22 Installation =x x 185.22
FactorUnit PriceQuantity Total

0.09 1.2000 1,715.00

Page 2 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
503
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 06
06 16 33 00 0033 5/8" Thick CDX Plywood Underlayment Grade18 $255.48SF Installation =x x 221.40
FactorUnit PriceQuantity Total

2.46 1.2000 75.00
Demolition x x = 34.08 0.71 1.2000 40.00
for countetop
06 41 13 00 0116 12" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
19 $1,245.28EA
Installation =x x 1,245.28
FactorUnit PriceQuantity Total
345.91 1.2000 3.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0116 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
20 $420.37
Installation =x x 420.37
FactorUnit PriceQuantity Total
116.77 1.2000 3.00
06 41 13 00 0116 0130 For All Plywood Box Construction, Add21 $438.19 Installation =x x 438.19
FactorUnit PriceQuantity Total
121.72 1.2000 3.00
06 41 13 00 0117 15" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
22 $882.84EA
Installation =x x 882.84
FactorUnit PriceQuantity Total
367.85 1.2000 2.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0117 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
23 $280.25
Installation =x x 280.25
FactorUnit PriceQuantity Total
116.77 1.2000 2.00
06 41 13 00 0117 0130 For All Plywood Box Construction, Add24 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0118 18" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
25 $1,846.66EA
Installation =x x 1,846.66
FactorUnit PriceQuantity Total
384.72 1.2000 4.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0118 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
26 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
116.77 1.2000 4.00
06 41 13 00 0118 0130 For All Plywood Box Construction, Add27 $584.26 Installation =x x 584.26
FactorUnit PriceQuantity Total
121.72 1.2000 4.00
06 41 13 00 0119 21" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
28 $486.41EA
Installation =x x 486.41
FactorUnit PriceQuantity Total
405.34 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0119 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
29 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00

Page 3 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
504
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 06
06 41 13 00 0119 0130 For All Plywood Box Construction, Add30 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0121 27" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
31 $579.37EA
Installation =x x 579.37
FactorUnit PriceQuantity Total
482.81 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0121 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
32 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00
06 41 13 00 0121 0130 For All Plywood Box Construction, Add33 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0124 36" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
34 $1,433.42EA
Installation =x x 1,361.04
FactorUnit PriceQuantity Total
567.10 1.2000 2.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 12" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
35 $541.33EA
Installation =x x 517.21
FactorUnit PriceQuantity Total
431.01 1.2000 1.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
36 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
467.08 1.2000 1.00
06 41 13 00 0139 0130 For All Plywood Box Construction, Add37 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0140 15" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
38 $559.45EA
Installation =x x 529.30
FactorUnit PriceQuantity Total
441.08 1.2000 1.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0140 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
39 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0140 0130 For All Plywood Box Construction, Add40 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0142 21" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
41 $1,264.40EA
Installation =x x 1,222.18
FactorUnit PriceQuantity Total
509.24 1.2000 2.00
Demolition x x = 42.23 35.19 1.2000 1.00
removal of existing cabinets, installation of new per plans

Page 4 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
505
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 06
06 41 13 00 0142 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
42 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0142 0130 For All Plywood Box Construction, Add43 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0170 30" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
44 $493.43EA
Installation =x x 433.12
FactorUnit PriceQuantity Total
360.93 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0170 0131 For All Plywood Box Construction, Add45 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0171 33" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
46 $516.13EA
Installation =x x 449.78
FactorUnit PriceQuantity Total
374.82 1.2000 1.00
Demolition x x = 66.35 55.29 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0171 0131 For All Plywood Box Construction, Add47 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0172 36" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
48 $531.48EA
Installation =x x 459.10
FactorUnit PriceQuantity Total
382.58 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0172 0131 For All Plywood Box Construction, Add49 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0174 12" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
50 $2,167.92EA
Installation =x x 2,143.80
FactorUnit PriceQuantity Total
297.75 1.2000 6.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0174 0131 For All Plywood Box Construction, Add51 $470.23 Installation =x x 470.23
FactorUnit PriceQuantity Total

65.31 1.2000 6.00
06 41 13 00 0175 15" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
52 $809.03EA
Installation =x x 778.87
FactorUnit PriceQuantity Total
324.53 1.2000 2.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0175 0131 For All Plywood Box Construction, Add53 $156.74 Installation =x x 156.74
FactorUnit PriceQuantity Total

65.31 1.2000 2.00

Page 5 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
506
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 06
06 41 13 00 0176 18" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
54 $1,282.30EA
Installation =x x 1,246.10
FactorUnit PriceQuantity Total
346.14 1.2000 3.00
Demolition x x = 36.19 30.16 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0176 0131 For All Plywood Box Construction, Add55 $235.12 Installation =x x 235.12
FactorUnit PriceQuantity Total

65.31 1.2000 3.00
06 41 13 00 0178 24" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
56 $525.71EA
Installation =x x 477.46
FactorUnit PriceQuantity Total
397.88 1.2000 1.00
Demolition x x = 48.25 40.21 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0178 0131 For All Plywood Box Construction, Add57 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0179 27" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
58 $578.09EA
Installation =x x 523.78
FactorUnit PriceQuantity Total
436.48 1.2000 1.00
Demolition x x = 54.31 45.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0179 0131 For All Plywood Box Construction, Add59 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0180 30" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
60 $597.17EA
Installation =x x 536.86
FactorUnit PriceQuantity Total
447.38 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0180 0131 For All Plywood Box Construction, Add61 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0182 36" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
62 $674.99EA
Installation =x x 602.60
FactorUnit PriceQuantity Total
502.17 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0182 0131 For All Plywood Box Construction, Add63 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 93 00 0007 7" To 8-1/2", Flat Cabinet Pull Handle64 $3,370.32EA Installation =x x 3,042.00
FactorUnit PriceQuantity Total

39.00 1.2000 65.00
Demolition x x = 328.32 8.55 1.2000 32.00
removal of existing cabinets, installation of new per plans

Page 6 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
507
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 06
06 46 19 00 0005 4-1/2" High White Pine Base Molding, All Dimensions Are Nominal65 $8,657.40LF Installation =x x 7,389.00
FactorUnit PriceQuantity Total

8.21 1.2000 750.00
Demolition x x = 1,268.40 1.51 1.2000 700.00
new base boards throughout
$46,235.58Subtotal for Section - 06
Section - 07
07 21 16 00 0006 5-1/2" Thick, Kraft Faced, R-21 Fiberglass Flexible Insulation66 $17,600.88SF Installation =x x 14,766.84
FactorUnit PriceQuantity Total

1.98 1.2000 6,215.00
Demolition x x = 2,834.04 0.38 1.2000 6,215.00
removal of existing insulation and installation of new 4500 sqft of walls 1715 sqft of ceilings 07 26 13 00 0004 Two Ply 60 Minute Asphalt Saturated Kraft Building Paper, Grade D (Fortifiber Two Ply Super Jumbo Tex 60 Minute)
67 $1,835.40CSF
Installation =x x 1,835.40
FactorUnit PriceQuantity Total

43.70 1.2000 35.00
for stucco patchback
07 62 13 00 0033 22 Gauge, 0.034" Thick, Galvanized Steel Flashing68 $4,485.60SF Installation =x x 4,485.60
FactorUnit PriceQuantity Total

12.46 1.2000 300.00
flashing per plans for new windows
07 62 13 00 0033 0080 For Wrap Around Window Panning, Add69 $2,476.80 Installation =x x 2,476.80
FactorUnit PriceQuantity Total

6.88 1.2000 300.00
$26,398.68Subtotal for Section - 07
Section - 08
08 12 13 13 0008 3' x 6'-8" Through 7'-2" High, 4-3/4" Deep, 16 Gauge, Knock Down Hollow Metal Door Frame
70 $7,015.14EA
Installation =x x 6,170.69
FactorUnit PriceQuantity Total
571.36 1.2000 9.00
Demolition x x = 844.45 100.53 1.2000 7.00
6 frames for interior doors and 3 for exterior doors
08 13 13 13 0039 3' x 6'-8" x 1-3/4", 18 Gauge, Level 2 Heavy Duty, Honeycomb Core, Hollow Metal Door
71 $2,890.61EA
Installation =x x 2,818.22
FactorUnit PriceQuantity Total
782.84 1.2000 3.00
Demolition x x = 72.38 60.32 1.2000 1.00
for new front doors and one rear door per plans
08 13 13 13 0039 0098 For Embossed Panel Door, Add72 $572.15 Installation =x x 572.15
FactorUnit PriceQuantity Total
158.93 1.2000 3.00
08 13 13 13 0039 0099 For Baked Enamel Finish, Add73 $780.34 Installation =x x 780.34
FactorUnit PriceQuantity Total
216.76 1.2000 3.00
08 13 13 13 0039 0104 For 3 Hour Fire Rated Door, Add74 $473.40EA Installation =x x 473.40
FactorUnit PriceQuantity Total
131.50 1.2000 3.00

Page 7 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
508
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 08
08 14 16 00 0134 3'-0" x 6'-8" x 1-3/4" Thick, 5 Ply, Hollow Core (HC), Birch Faced Wood Door75 $2,524.34EA Installation =x x 2,017.66
FactorUnit PriceQuantity Total
280.23 1.2000 6.00
Demolition x x = 506.69 60.32 1.2000 7.00
5 bedroom/bathroom doors and 1 closet door
08 14 73 00 0074 5' Wide, Two 2'-6" x 6'-8" x 1-3/8" Thick, Flush, Hollow Core (HC), Birch Faced Wood Bi-Pass Doors
76 $1,872.97EA
Installation =x x 1,667.99
FactorUnit PriceQuantity Total
463.33 1.2000 3.00
Demolition x x = 204.98 85.41 1.2000 2.00
removal of 2 existing closet sliding doors, installation of 3 new closet sliding doors 08 53 13 00 0121 >60" To 73" UI, Single Hung Premium Vinyl Window (Pella 350)77 $1,415.59EA Installation =x x 1,288.92
FactorUnit PriceQuantity Total
537.05 1.2000 2.00
Demolition x x = 126.67 52.78 1.2000 2.00
replacement of all existing windows
08 53 13 00 0124 >93" To 101" UI, Single Hung Premium Vinyl Window (Pella 350)78 $993.74EA Installation =x x 912.31
FactorUnit PriceQuantity Total
760.26 1.2000 1.00
Demolition x x = 81.43 67.86 1.2000 1.00
replacement of all existing windows
08 53 13 00 0547 >93" To 101" UI, Horizontal Sliding Premium Vinyl Window (Pella 350)79 $4,338.30EA Installation =x x 3,931.14
FactorUnit PriceQuantity Total
655.19 1.2000 5.00
Demolition x x = 407.16 67.86 1.2000 5.00
replacement of all existing windows
08 71 11 00 0004 3-1/2" x 3-1/2" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
80 $550.33PR
Installation =x x 491.28
FactorUnit PriceQuantity Total

81.88 1.2000 5.00
Demolition x x = 59.05 7.03 1.2000 7.00
removal of existing and installation of new
08 71 11 00 0005 4" x 4" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
81 $485.62PR
Installation =x x 485.62
FactorUnit PriceQuantity Total

89.93 1.2000 4.50
for new front doors and one rear door per plans
08 71 11 00 0513 3" Projection, Residential Spring Type, Bright Brass Finish, Steel Wall Stop (Ives 63)
82 $252.10EA
Installation =x x 173.63
FactorUnit PriceQuantity Total

11.13 1.2000 13.00
Demolition x x = 78.47 5.03 1.2000 13.00
per plans
08 71 11 00 0655 190 Degree Angle Of View, Bright Brass Finish, Brass One-Way Wide Angle Door Viewer (Ives U698)
83 $138.60EA
Installation =x x 138.60
FactorUnit PriceQuantity Total

57.75 1.2000 2.00
for new front door per plans
08 71 11 00 2289 Passage/Closet F01 Mortise LatchsetBoth sides always unlocked.84 $1,019.63EA Installation =x x 959.32
FactorUnit PriceQuantity Total
799.43 1.2000 1.00
Demolition x x = 60.31 25.13 1.2000 2.00
removal of existing and installation of new

Page 8 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
509
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 08
08 71 11 00 2290 Bath/Bedroom Privacy F02/F19 Mortise LocksetLocked with thumb knob inside.
85 $5,939.35EA
Installation =x x 5,728.26
FactorUnit PriceQuantity Total
954.71 1.2000 5.00
Demolition x x = 211.09 25.13 1.2000 7.00
removal of existing and installation of new
08 71 11 00 2294 Entrance F08 Mortise LocksetLocked with key outside and thumb knob inside.86 $4,028.14EA Installation =x x 3,997.98
FactorUnit PriceQuantity Total
1,110.55 1.2000 3.00
Demolition x x = 30.16 25.13 1.2000 1.00
for new front doors and one rear door per plans
08 72 33 00 0155 3/8" x 3/16", Silicon Compression Bulb, Adhesive Backed Perimeter Gasketing Weather-Strip (Pemko PK33)
87 $445.68LF
Installation =x x 264.96
FactorUnit PriceQuantity Total

3.68 1.2000 60.00
Demolition x x = 180.72 2.51 1.2000 60.00
for new front doors and one rear door per plans
08 72 43 00 0011 6" Width, 1/4" Height, Aluminum Saddle Threshold (Pemko 272A)88 $442.69LF Installation =x x 442.69
FactorUnit PriceQuantity Total

40.99 1.2000 9.00
for new front doors and one rear door per plans
08 72 43 00 0011 0458 For Color Anodized Finish, Add89 $19.98 Installation =x x 19.98
FactorUnit PriceQuantity Total

5.55 1.2000 3.00
$36,198.70Subtotal for Section - 08
Section - 09
09 05 71 00 0002 5 Mil Tile And Stone Acoustical Underlayment (EasyMat)90 $8,787.66SF Installation =x x 8,787.66
FactorUnit PriceQuantity Total

4.27 1.2000 1,715.00
acoustical mat underlayment per plans
09 05 71 00 0005 2 MM Thick Resilient Plank Floor Acoustical Underlayment (Floormuffler)91 $2,881.20SF Installation =x x 2,881.20
FactorUnit PriceQuantity Total

1.40 1.2000 1,715.00
closest LI to gypsum sanded floor underlayment per plans 09 22 13 23 0008 25 Gauge, 16" On Center, Installed On Walls, Double-Leg Resilient Channel, RC2 Furring Channel
92 $4,062.18SF
Installation =x x 4,062.18
FactorUnit PriceQuantity Total

3.95 1.2000 857.00
Resilient channel per plans
09 22 13 23 0010 25 Gauge, 16" On Center, Installed On Ceilings, Double-Leg Resilient Channel, RC2 Furring Channel
93 $9,549.12SF
Installation =x x 9,549.12
FactorUnit PriceQuantity Total

4.64 1.2000 1,715.00
Resilient channel per plans
09 22 36 23 0005 3.4 LB/SY, Installed On Studs Or Furred Walls, Flat Diamond, Expanded Metal Lath
94 $1,461.60SF
Installation =x x 1,201.20
FactorUnit PriceQuantity Total

2.86 1.2000 350.00
Demolition x x = 260.40 0.62 1.2000 350.00
For stucco patch back

Page 9 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
510
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 09
09 22 36 23 0005 0020 For >100 To 500, Add95 $147.00 Installation =x x 147.00
FactorUnit PriceQuantity Total

0.35 1.2000 350.00
09 24 23 00 0002 Scratch/Brown/Finish, Three Coat Troweled StuccoExcludes lath and felt.

Interior or exterior, one side.
96 $4,956.00SF
Installation =x x 3,754.80
FactorUnit PriceQuantity Total

8.94 1.2000 350.00
Demolition x x = 1,201.20 2.86 1.2000 350.00
For Stucco patch back
09 24 23 00 0002 0024 For Walls >10' High, Add97 $112.32 Installation =x x 112.32
FactorUnit PriceQuantity Total

0.78 1.2000 120.00
09 24 23 00 0002 0031 For Color Added To Finish Coat, Add98 $21.60SF Installation =x x 21.60
FactorUnit PriceQuantity Total

0.15 1.2000 120.00
09 24 23 00 0002 0037 For >100 To 500, Add99 $282.24 Installation =x x 282.24
FactorUnit PriceQuantity Total

1.96 1.2000 120.00
09 29 10 00 0006 5/8" Gypsum Board100 $18,768.96SF Installation =x x 13,912.08
FactorUnit PriceQuantity Total

1.69 1.2000 6,860.00
Demolition x x = 4,856.88 0.59 1.2000 6,860.00
for walls and ceilings per plans. First floor ceiling requires 2 layers per plans 09 29 10 00 0038 Up To 10' High, Walls, Tape, Spackle And Finish Gypsum Board101 $5,597.76SF Installation =x x 5,597.76
FactorUnit PriceQuantity Total

0.68 1.2000 6,860.00
for walls
09 29 10 00 0038 0048 For ASTM C840 Level 5 High Quality Finish, Add102 $4,116.00 Installation =x x 4,116.00
FactorUnit PriceQuantity Total

0.50 1.2000 6,860.00
09 29 10 00 0041 Up To 10' High, Ceilings, Tape, Spackle And Finish Gypsum Board103 $1,811.04SF Installation =x x 1,811.04
FactorUnit PriceQuantity Total

0.88 1.2000 1,715.00
for ceilings
09 29 10 00 0041 0048 For ASTM C840 Level 5 High Quality Finish, Add104 $1,337.70 Installation =x x 1,337.70
FactorUnit PriceQuantity Total

0.65 1.2000 1,715.00
09 29 10 00 0044 Up To 10' High, Vertical Corners, Tape, Spackle And Finish Gypsum Board105 $2,502.05LF Installation =x x 2,502.05
FactorUnit PriceQuantity Total

1.34 1.2000 1,556.00
vertical corners @ 8' throughout both floors and windows 09 29 10 00 0044 0048 For ASTM C840 Level 5 High Quality Finish, Add106 $1,829.86 Installation =x x 1,829.86
FactorUnit PriceQuantity Total

0.98 1.2000 1,556.00
09 29 10 00 0047 Up To 10' High, Horizontal Corners, Tape, Spackle And Finish Gypsum Board107 $2,232.00LF Installation =x x 2,232.00
FactorUnit PriceQuantity Total

1.55 1.2000 1,200.00
walls and windows

Page 10 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
511
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 09
09 29 10 00 0047 0048 For ASTM C840 Level 5 High Quality Finish, Add108 $1,641.60 Installation =x x 1,641.60
FactorUnit PriceQuantity Total

1.14 1.2000 1,200.00
09 29 10 00 0051 Corner Bead, Galvanized Steel For Gypsum Board109 $10,262.74LF Installation =x x 10,262.74
FactorUnit PriceQuantity Total

3.63 1.2000 2,356.00
for walls and windows
09 65 23 00 0004 0.16" Overall Thickness, 0.020" Wear Layer, Vinyl Plank Flooring (Armstrong® Luxe Plank™)
110 $23,687.58SF
Installation =x x 23,687.58
FactorUnit PriceQuantity Total

11.51 1.2000 1,715.00
new flooring throughout per plans
09 91 13 00 0095 1 Coat Primer, Brush/Roller Work, Paint Exterior Stucco Walls111 $1,444.80SF Installation =x x 1,444.80
FactorUnit PriceQuantity Total

0.86 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 13 00 0097 2 Coats Paint, Brush/Roller Work, Paint Exterior Stucco Walls112 $3,057.60SF Installation =x x 3,057.60
FactorUnit PriceQuantity Total

1.82 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 23 00 0067 1 Coat Primer, Brush/Roller Work, Paint Interior Plaster/Drywall Walls113 $5,270.40SF Installation =x x 5,270.40
FactorUnit PriceQuantity Total

0.61 1.2000 7,200.00
for walls
09 91 23 00 0069 2 Coats Paint, Brush/Roller Work, Paint Interior Plaster/Drywall Walls114 $10,540.80SF Installation =x x 10,540.80
FactorUnit PriceQuantity Total

1.22 1.2000 7,200.00
for walls
09 91 23 00 0161 1 Coat Primer, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling115 $1,461.18SF Installation =x x 1,461.18
FactorUnit PriceQuantity Total

0.71 1.2000 1,715.00
for ceilings
09 91 23 00 0163 2 Coats Paint, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling116 $2,675.40SF Installation =x x 2,675.40
FactorUnit PriceQuantity Total

1.30 1.2000 1,715.00
for ceilings
09 91 23 00 0252 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Door Frame And Trim117 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

0.93 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0254 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Door Frame And Trime118 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

2.02 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0275 1 Coat Primer, Brush/Roller Work, Both Faces, Paint Interior Wood Door119 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total

76.57 1.2000 0.00
8 doors on first floor
7 doors on second floor

Page 11 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
512
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 09
09 91 23 00 0277 2 Coats Paint, Brush/Roller Work, Both Faces, Paint Interior Wood Door120 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total
138.02 1.2000 0.00
8 doors on first floor
7 doors on second floor
09 91 23 00 0307 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
121 $192.00LF
Installation =x x 192.00
FactorUnit PriceQuantity Total

1.25 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0309 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
122 $416.26LF
Installation =x x 416.26
FactorUnit PriceQuantity Total

2.71 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0350 1 Coat Primer, Brush Work, Paint Interior Wood Trim To 6" Wide123 $576.00LF Installation =x x 576.00
FactorUnit PriceQuantity Total

0.64 1.2000 750.00
750 LF of baseboards
09 91 23 00 0352 2 Coats Paint, Brush Work, Paint Interior Wood Trim To 6" Wide124 $1,305.00LF Installation =x x 1,305.00
FactorUnit PriceQuantity Total

1.45 1.2000 750.00
750 LF of baseboards
$132,987.65Subtotal for Section - 09
Section - 10
10 14 53 11 0078 18" x 24" Reflective Polyethylene Traffic Sign125 $165.61EA Installation =x x 165.61
FactorUnit PriceQuantity Total
138.01 1.2000 1.00
ADA parking sign
10 14 53 11 0198 Single Bracket And Post Cap For Street Sign126 $29.02EA Installation =x x 29.02
FactorUnit PriceQuantity Total

24.18 1.2000 1.00
ADA parking sign
10 14 53 11 0213 8' Galvanized Steel U-Channel Sign Post127 $165.00EA Installation =x x 165.00
FactorUnit PriceQuantity Total
137.50 1.2000 1.00
ADA parking sign
10 14 53 11 0278 2-3/8" Diameter, Galvanized, Flat Traffic Sign Post Cap (EC-2)128 $26.24EA Installation =x x 26.24
FactorUnit PriceQuantity Total

21.87 1.2000 1.00
ADA parking sign
10 28 13 13 0045 Single Roll, Surface Mounted, Stainless Steel, Satin Finish, Toilet Tissue Dispenser (Bobrick B-6857)
129 $308.30EA
Installation =x x 254.04
FactorUnit PriceQuantity Total
105.85 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans

Page 12 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
513
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 10
10 28 13 13 0170 36" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x36)130 $401.44EA Installation =x x 401.44
FactorUnit PriceQuantity Total
111.51 1.2000 3.00
per plans
10 28 13 13 0170 0148 For Peened Grip, Add131 $24.73 Installation =x x 24.73
FactorUnit PriceQuantity Total

6.87 1.2000 3.00
10 28 13 13 0171 42" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x42)132 $136.87EA Installation =x x 136.87
FactorUnit PriceQuantity Total
114.06 1.2000 1.00
per plans
10 28 13 13 0171 0148 For Peened Grip, Add133 $8.52 Installation =x x 8.52
FactorUnit PriceQuantity Total

7.10 1.2000 1.00
10 28 13 13 0217 Telescoping 60" To 72" Length, 20-Gauge, 1" Diameter, Stainless Steel Curved Shower Rod With Concealed Mounting (Kohler Expanse K-9349) 134 $389.23EA
Installation =x x 334.97
FactorUnit PriceQuantity Total
139.57 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0322 24" Length, 3/4" Diameter, Stainless Steel Towel Bar (Bobrick B-674)135 $333.74EA Installation =x x 279.48
FactorUnit PriceQuantity Total
116.45 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0390 20" x 26", Surface Mounted, Aluminum Medicine Cabinet (Kohler K-CB)136 $1,707.62EA Installation =x x 1,587.05
FactorUnit PriceQuantity Total
661.27 1.2000 2.00
Demolition x x = 120.58 50.24 1.2000 2.00
per plans
$3,696.32Subtotal for Section - 10
Section - 11
11 30 13 13 0015 30" Venting Range Hood (Broan 40000)137 $717.65EA Installation =x x 637.08
FactorUnit PriceQuantity Total
265.45 1.2000 2.00
Demolition x x = 80.57 67.14 1.2000 1.00
removal of existing and installation of 2 new
$717.65Subtotal for Section - 11
Section - 12
12 36 61 19 0005 1-1/4" Thick, Quartz Agglomerate Countertop With Backsplash138 $12,198.00SF Installation =x x 11,117.34
FactorUnit PriceQuantity Total
142.53 1.2000 65.00
Demolition x x = 1,080.66 25.73 1.2000 35.00
kitchen countertops

Page 13 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
514
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 12
12 36 61 19 0006 Quartz Agglomerate Countertop End Splash For Quartz Agglomerate Countertops
139 $101.54LF
Installation =x x 91.30
FactorUnit PriceQuantity Total

19.02 1.2000 4.00
Demolition x x = 10.25 4.27 1.2000 2.00
for end where fridges meet
12 36 61 19 0007 Cutout For Sink And/Or Faucet In Quartz Agglomerate Countertop140 $361.73EA Installation =x x 361.73
FactorUnit PriceQuantity Total
150.72 1.2000 2.00
2 kitchen sinks
$12,661.27Subtotal for Section - 12
Section - 22
22 01 40 81 0004 Removal And Replacement Of Chrome Supply Lines To Sink/Lavatory, Pair141 $335.04EA Installation =x x 335.04
FactorUnit PriceQuantity Total

27.92 1.2000 10.00
replace supply lines in kitchens and bathrooms
22 01 40 81 0006 Removal And Replacement Of Double Bowl Sink/Lavatory Drain Line142 $289.97EA Installation =x x 289.97
FactorUnit PriceQuantity Total

60.41 1.2000 4.00
new drain lines
22 11 16 00 0003 3/4" Schedule 40 Threaded Galvanized Steel Pipe With 150 LB Malleable Iron Fitting AssemblyIncludes all hangers and all galvanized malleable iron fittings (couplings, elbows, tees and reducer fittings). All hangers are complete assemblies. Not for use where detail is available.
143 $13,959.60LF
Installation =x x 12,930.00
FactorUnit PriceQuantity Total

21.55 1.2000 500.00
Demolition x x = 1,029.60 4.29 1.2000 200.00
gas line piping
22 11 16 00 0003 0304 For Work In Restricted Working Space, Add144 $1,010.40 Installation =x x 1,010.40
FactorUnit PriceQuantity Total

4.21 1.2000 200.00
22 11 16 00 0901 3/4" Inside Diameter Copper Pipe/Tubing Type L AssemblyIncludes all hangers and couplings, elbow, tee, reducer fittings. All hangers are complete assemblies. Not for use where detail is available.
145 $32,443.80LF
Installation =x x 29,628.60
FactorUnit PriceQuantity Total

25.99 1.2000 950.00
Demolition x x = 2,815.20 3.91 1.2000 600.00
water line copper piping
22 11 16 00 0901 0315 For Work In Restricted Working Space, Add146 $1,384.80 Installation =x x 1,384.80
FactorUnit PriceQuantity Total

5.77 1.2000 200.00
22 12 23 13 0002 80 Gallon ASME Rated Tank, 150PSI, Jacketed, Insulated, Glass Lined Water Heater Storage Tank (TJ-80A)
147 $479.41EA
Installation =x x 0.00
FactorUnit PriceQuantity Total
2,554.73 1.2000 0.00
Demolition x x = 479.41 399.51 1.2000 1.00
removal of existing water heater

Page 14 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
515
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 22
22 13 16 00 0518 4" Aboveground Schedule 40 Polyvinyl Chloride (PVC) DWV Pipe AssemblyIncludes all fittings, couplings and hangers. Fittings are assumed every 10'. Not for use where detail is available.
148 $48,884.70LF
Installation =x x 46,314.00
FactorUnit PriceQuantity Total

51.46 1.2000 750.00
Demolition x x = 2,570.70 7.79 1.2000 275.00
new Sewer and vent piping
22 13 16 00 0518 0304 For Work In Restricted Working Space, Add149 $2,175.00 Installation =x x 2,175.00
FactorUnit PriceQuantity Total

7.25 1.2000 250.00
22 34 13 00 0011 7.4 GPM, Outdoor Mount, Instantaneous, Tankless, Gas Domestic Water Heater (Rheem RTG-74XN)
150 $10,037.42EA
Installation =x x 10,037.42
FactorUnit PriceQuantity Total
4,182.26 1.2000 2.00
installation of 2 new water heaters
22 41 16 16 0003 33" x 21" x 6-1/2" Stainless Steel Kitchen Sink, Double Bowl, 20 Gauge (Elkay D233213)
151 $1,768.56EA
Installation =x x 1,640.30
FactorUnit PriceQuantity Total
683.46 1.2000 2.00
Demolition x x = 128.26 106.88 1.2000 1.00
removal of existing and installation of new.
22 41 39 00 0006 Chrome Two Handle Kitchen Faucet With Spray, Three Hole Installation, 8" Center (Delta 2402LF-LHP+H215)
152 $565.87EA
Installation =x x 505.94
FactorUnit PriceQuantity Total
210.81 1.2000 2.00
Demolition x x = 59.93 49.94 1.2000 1.00
removal of existing and installation of new.
22 42 13 13 0026 2 Piece Tank Type, Pressure Assisted, Siphon Jet, Floor Mounted, Back Outlet, Handicap Accessible, Elongated Vitreous China Water Closet (American Standard Yorkville™ ADA)
153 $2,811.37EA
Installation =x x 2,686.73
FactorUnit PriceQuantity Total
1,119.47 1.2000 2.00
Demolition x x = 124.64 103.87 1.2000 1.00
remove existing and install new ADA toilet
22 42 16 13 0009 27" x 20" Wheelchair Accessible, Vitreous China Wall Hung Lavatory (American Standard Wheel Chair Users)
154 $1,701.89EA
Installation =x x 1,621.58
FactorUnit PriceQuantity Total
675.66 1.2000 2.00
Demolition x x = 80.30 66.92 1.2000 1.00
remove existing and install new ADA sink, faucet, and drain cover. 22 42 19 00 0027 3 Piece Tub/Shower Surrounds, 32" x 72" Side Walls, 48" x 72" Back, (Swanstone SK-324872)
155 $8,454.49EA
Installation =x x 8,071.78
FactorUnit PriceQuantity Total
3,363.24 1.2000 2.00
Demolition x x = 382.72 318.93 1.2000 1.00
new tub/shower for bathrooms
22 42 39 00 0042 Single Supply EcoPower® Faucet, Polished Chrome Finish (Toto TEL3LS10#CP)
156 $1,885.78EA
Installation =x x 1,885.78
FactorUnit PriceQuantity Total
785.74 1.2000 2.00
ADA sink, faucet, and drain cover.

Page 15 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
516
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 22
22 42 39 00 0064 Three Lever Handle, Chrome Shower And Tub Filler (American Standard Colony Soft 3375.502)
157 $741.02EA
Installation =x x 636.98
FactorUnit PriceQuantity Total
265.41 1.2000 2.00
Demolition x x = 104.04 43.35 1.2000 2.00
per plans
22 42 39 00 0064 0147 For Faucet With Metal Cross Handles, Add158 $109.80EA Installation =x x 109.80
FactorUnit PriceQuantity Total

45.75 1.2000 2.00
22 42 39 00 0211 Lavatory Protective Enclosure (IPS Truebro Lav Shield)159 $390.86EA Installation =x x 390.86
FactorUnit PriceQuantity Total
162.86 1.2000 2.00
drain cover for ADA kitchen and bathroom sink
22 42 39 00 0218 1/2" NPT x 3/8" Compression Chrome, Quarter Turn Dual Angle Stop (SharkBite 25558)
160 $680.78EA
Installation =x x 580.08
FactorUnit PriceQuantity Total

48.34 1.2000 10.00
Demolition x x = 100.70 10.49 1.2000 8.00
new angle stops installed in bathrooms and kitchens
$130,110.56Subtotal for Section - 22
Section - 23
23 09 23 53 0284 Scheduling Program, HVAC (AHU, RTU, AC Units, Etcetera) Programming Measures
161 $8,755.06EA
Installation =x x 8,755.06
FactorUnit PriceQuantity Total
3,647.94 1.2000 2.00
required setup, balancing, and charging for new system
23 31 13 16 0063 4" Diameter, 26 Gauge, Seal Class C, Galvanized Sheet Metal Round And Flat-Oval Connector
162 $3,117.60EA
Installation =x x 3,117.60
FactorUnit PriceQuantity Total

17.32 1.2000 150.00
exhaust ducting per plans
23 33 13 13 0006 12" Diameter Radial Opposed Blade Damper Round, Steel Construction, Manual Operated
163 $696.79EA
Installation =x x 682.22
FactorUnit PriceQuantity Total
142.13 1.2000 4.00
Demolition x x = 14.57 12.14 1.2000 1.00
HVAC per plans
23 33 46 00 0008 12" Diameter Flexible Duct, R8.0 Insulated With Polyester Inner Liner Over Fiberglass Insulation And Metallized Outer Jacket
164 $12,610.20LF
Installation =x x 11,491.20
FactorUnit PriceQuantity Total

21.28 1.2000 450.00
Demolition x x = 1,119.00 3.73 1.2000 250.00
HVAC per plans - exhaust ducting
23 33 46 00 0020 12" Diameter Flexible Duct Collar, Spin In Type, Sheet Metal, With Damper165 $739.63EA Installation =x x 706.03
FactorUnit PriceQuantity Total

98.06 1.2000 6.00
Demolition x x = 33.60 14.00 1.2000 2.00
HVAC per plans

Page 16 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
517
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 23
23 34 16 00 0272 109 CFM, Ceiling/Wall Mounted, Metal Intake Grille, Heavy Duty/Continuous Operation Exhaust Fan (Broan® LoSone® Ventilator L100MG) 166 $2,212.13EA
Installation =x x 2,168.35
FactorUnit PriceQuantity Total
451.74 1.2000 4.00
Demolition x x = 43.78 36.48 1.2000 1.00
Laundry room and bathroom exhaust fan per plans
23 54 16 13 0007 120 MBH, 2,000 CFM Up/Horizontal Flow Multi-Speed, Two Stage 96% AFUE Gas FurnaceBlower cooling capacity up to 5 tons.
167 $15,925.85EA
Installation =x x 15,770.64
FactorUnit PriceQuantity Total
2,628.44 1.2000 5.00
Demolition x x = 155.21 129.34 1.2000 1.00
per plans. wall mounted furnaces
$44,057.26Subtotal for Section - 23
Section - 26
26 01 20 91 0002 Lock Out/Tag Out Local DisconnectExcludes tag or padlock See CSI section 26 01 20 91-0004 for padlock, 26 01 20 91-0005 for tag(s). 168 $590.94EA
Installation =x x 590.94
FactorUnit PriceQuantity Total

32.83 1.2000 15.00
LOTO of existing circuits
26 05 19 16 0402 #12 AWG, 3 Conductors, 600 Volt, Type NM, Copper, Non-Metallic Sheathed Cable
169 $24,763.20MLF
Installation =x x 24,763.20
FactorUnit PriceQuantity Total
4,127.20 1.2000 5.00
for new electrical runs per plans
26 05 19 16 0402 0377 For Installation In Wood Stud Wall (Includes Drilling), Add170 $1,795.14 Installation =x x 1,795.14
FactorUnit PriceQuantity Total
299.19 1.2000 5.00
26 09 23 00 0144 Wall Switch Replacement Occupancy Sensor, Single GangIncludes integral occupancy sensor and relay.
171 $1,483.80EA
Installation =x x 1,483.80
FactorUnit PriceQuantity Total
123.65 1.2000 10.00
per plans
26 09 23 00 0270 Passive Infrared, Wall Switch Mounted, Wired Occupancy Sensor (Encelium PW-100-24)Excludes GB II cable.
172 $725.28EA
Installation =x x 725.28
FactorUnit PriceQuantity Total
302.20 1.2000 2.00
for bathrooms
26 24 13 00 0213 800 Amperes, 480 Volt, 4 Wire, Switchboard Incoming No Switch Circuit173 $6,313.51EA Installation =x x 5,324.36
FactorUnit PriceQuantity Total
4,436.97 1.2000 1.00
Demolition x x = 989.15 824.29 1.2000 1.00
for new main panel to new units subpanels
26 24 16 00 0470 200 Ampere Rating, Main Breaker, Indoor, 42 Circuit, 4 Wire, 120/208 Volt, Assembled Panelboard With 20 Ampere, 1 Pole Plug-In Breakers 174 $8,743.93EA
Installation =x x 7,651.92
FactorUnit PriceQuantity Total
3,188.30 1.2000 2.00
Demolition x x = 1,092.01 910.01 1.2000 1.00
1 new sub panel for each unit

Page 17 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
518
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 26
26 27 13 00 0125 Single Phase M-90 Meter, Socket, NEMA 3R Enclosure175 $8,033.33EA Installation =x x 7,705.73
FactorUnit PriceQuantity Total
1,070.24 1.2000 6.00
Demolition x x = 327.60 54.60 1.2000 5.00
installation of new meters for building
26 27 26 00 0009 20 Amperes, 1 Gang, GFI, Duplex Receptacle Assembly176 $5,103.00EA Installation =x x 4,273.08
FactorUnit PriceQuantity Total
101.74 1.2000 35.00
Demolition x x = 829.92 34.58 1.2000 20.00
All new GFI outlets throughout per clients request
26 27 26 00 0125 20 Amperes, 125 Volt Single Specification Grade Tamper Resistant ReceptaclePass & Seymour TR5351.
177 $2,554.46EA
Installation =x x 2,073.98
FactorUnit PriceQuantity Total

39.28 1.2000 44.00
Demolition x x = 480.48 9.10 1.2000 44.00
all new outlets throughout per clients request
26 27 26 00 0138 1 Gang, 20 Amperes, 120/277 Volt, SPST, Switch Assembly178 $3,774.00EA Installation =x x 2,736.60
FactorUnit PriceQuantity Total

91.22 1.2000 25.00
Demolition x x = 1,037.40 34.58 1.2000 25.00
25 switches total in both units
26 51 19 00 0269 2' x 2', 4,000 Lumens, Surface Mount, Volumetric LED Fixture (Lithonia 2RTX2)179 $7,035.98EA Installation =x x 6,106.46
FactorUnit PriceQuantity Total
212.03 1.2000 24.00
Demolition x x = 929.52 38.73 1.2000 20.00
new LED lights throughout
26 51 19 00 0477 2-1/2" Diameter x 15-1/2" High, Polished Nickel, LED Wall Sconce (Hudson Valley Lighting SHAW 1200-PN)
180 $1,281.65EA
Installation =x x 1,194.29
FactorUnit PriceQuantity Total
497.62 1.2000 2.00
Demolition x x = 87.36 36.40 1.2000 2.00
2 new wall sconces per plans in bathrooms
$72,198.22Subtotal for Section - 26
Section - 31
31 05 16 00 0002 #2 Stone Aggregate Fill (1-1/2" To 2-1/2" Clean)181 $1,650.60CY Installation =x x 1,650.60
FactorUnit PriceQuantity Total

55.02 1.2000 25.00
4" deep, 200 LF, 2' wide base for backfill for trenching. 20 CY for footings, and slabs 31 05 16 00 0002 0053 For Up To 8, Add182 $66.00
Installation =x x 66.00
FactorUnit PriceQuantity Total

11.00 1.2000 5.00
31 11 00 00 0010 Clearing By Machine - Light Brush Without Grub183 $202.36ACR Installation =x x 202.36
FactorUnit PriceQuantity Total
337.26 1.2000 0.50
clear out weeds in back yard
31 11 00 00 0019 Hand Loading Of Cleared And Grubbed Material184 $976.32CY Installation =x x 976.32
FactorUnit PriceQuantity Total

40.68 1.2000 20.00
clear out weeds in back yard

Page 18 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
519
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 31
31 23 16 13 0007 Excavation For Trenching By Hand In SoilIncludes stockpiling excess materials and trimming sides and bottom of trench.
185 $4,027.50CY
Installation =x x 4,027.50
FactorUnit PriceQuantity Total
134.25 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0011 Backfilling or Placing Subbase for Trenches with Imported or Stockpiled Materials by Hand
186 $1,118.70CY
Installation =x x 1,118.70
FactorUnit PriceQuantity Total

37.29 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0014 Compaction of Fill or Subbase for Trenches by Hand187 $1,262.10CY Installation =x x 1,262.10
FactorUnit PriceQuantity Total

42.07 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 36 0009 Excavation For Building Foundations And Other Structures By Hand in Soil188 $7,249.50CY Installation =x x 7,249.50
FactorUnit PriceQuantity Total
134.25 1.2000 45.00
for footings
31 23 16 36 0019 Backfilling Around Building Foundations And Other Structures By Hand189 $1,534.32CY Installation =x x 1,534.32
FactorUnit PriceQuantity Total

63.93 1.2000 20.00
for footings
31 23 16 36 0022 Compaction Of Fill Or Subbase For Building Foundations and Other Structures by Hand
190 $2,271.24CY
Installation =x x 2,271.24
FactorUnit PriceQuantity Total

42.06 1.2000 45.00
for footings
$20,358.64Subtotal for Section - 31
Section - 32
32 16 13 13 0016 6" x 12" Cast In Place Concrete Gutter With 6" Curb And Face - Straight191 $225.96LF Installation =x x 154.98
FactorUnit PriceQuantity Total

25.83 1.2000 5.00
Demolition x x = 70.98 11.83 1.2000 5.00
for parking lot ADA modifications
32 16 13 13 0016 0077 For Up To 20, Add192 $105.42MOD Installation =x x 105.42
FactorUnit PriceQuantity Total

17.57 1.2000 5.00
32 16 23 00 0002 4" Cast In Place Concrete Sidewalk193 $212.16SF Installation =x x 212.16
FactorUnit PriceQuantity Total

8.84 1.2000 20.00
for parking lot ADA modifications
32 16 23 00 0002 0094 For Up To 100, Add194 $92.16 Installation =x x 92.16
FactorUnit PriceQuantity Total

3.84 1.2000 20.00
32 16 23 00 0008 Finish Concrete Handicap Drop Section In SidewalkExcludes patterned (tactile) finish.
195 $167.12EA
Installation =x x 167.12
FactorUnit PriceQuantity Total
139.27 1.2000 1.00
for parking lot ADA modifications

Page 19 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
520
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124238.00
OHA - 1070 Unit Remodel
Section - 32
32 17 23 13 0074 Solid Area, Painted Pavement Marking For Parking AreasUse task for lines >12" wide, stop bars, transverse lines, diagonal lines, crossing lanes, etc. 196 $102.48SF
Installation =x x 102.48
FactorUnit PriceQuantity Total

4.27 1.2000 20.00
for parking lot ADA modifications
32 17 23 13 0088 Handicap Symbol For Van Parking Stalls, Painted Pavement Marking For Parking AreasApproximate overall dimensions: 4-1/3' width x 5' height. White or blue symbol. Excludes striping.
197 $52.66EA
Installation =x x 52.66
FactorUnit PriceQuantity Total

43.88 1.2000 1.00
for parking lot ADA modifications
32 17 26 00 0003 Embedded, VPC Truncated Dome Detectable Warning SurfaceAlso raised strips or directional bars. All colors.
198 $650.04SF
Installation =x x 650.04
FactorUnit PriceQuantity Total

54.17 1.2000 10.00
new truncated domes per
32 31 13 13 0010 12" Diameter Hole, Auger By Machine Fence Post Hole In Soil199 $80.75VLF Installation =x x 80.75
FactorUnit PriceQuantity Total

22.43 1.2000 3.00
ADA parking sign
32 31 13 13 0027 12" Diameter, Concrete Fill For Post Hole200 $89.28VLF Installation =x x 89.28
FactorUnit PriceQuantity Total

24.80 1.2000 3.00
ADA parking sign
$1,778.03Subtotal for Section - 32
Proposal Total
This total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 20 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
521
Subcontractor Listing
124238.00
OHA - 1070 Unit Remodel
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
%DutiesName of Contractor Amount
Refined Construction 86.02$520,000.00

6.00

Page 1 of 1 ends

1/9/2024
Subcontractor Listing
522
Work Order Signature Document
EZIQC Contract No.: CA-R7-GB-101723-MDJ
New Work Order
124239.00
Modify an Existing Work Order
W
ork Order Title:

Work Order Number.: Work Order Date:

X
01/09/2024
Contractor Name:

Contact:

Phone:

Contact:

Phone:

Matt McMillon
310-490-1521
Owner Name:

OHA - 1100 Unit Remodel
Oxnard Housing Authority
Fredi Contreras
805-890-8319
MDJ Management
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of Sourcewell EZIQC Contract No CA-R7-GB-101723-MDJ.

Brief Work Order Description:

Will not apply:Liquidated Damages Will apply:

Estimated Completion Date:

Estimated Start Date: Time of Performance
X
Work Order Firm Fixed Price: $604,505.00
Owner Purchase Order Number:

Approvals
Date DateMDJ ManagementOxnard Housing Authority

2.00

Page 1 of 1 ends

1/9/2024
Work Order Signature Document

EXHIBIT A
523

3.00 Detailed Scope of Work
Fredi ContrerasMatt McMillonT o: From:

MDJ Management Oxnard Housing Authority
531 Main St #611 300 N. Marquita Street
El Segundo, CA 90245 Oxnard, CA 93030
310-490-1521 805-890-8319
Work Order Number:

January 09, 2024Date Printed:
124239.00
OHA - 1100 Unit RemodelWork Order Title:

Brief Scope:

Revised FinalPreliminary X
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the items set forth below shall be considered part of this scope of work.

See attached.

Subject to the terms and conditions of ezIQC Contract CA-R7-GB-101723-MDJ.

MDJ Management Date
DateOxnard Housing Authority

Page 1 of 1 ends

1/9/2024
Scope of Work
524
MDJ Management, LLC
License # 1044711
DIR # 1000061313
531 Main St. #611 El Segundo CA 90245
310-490-1521
Job Name: 1100 Colonia Conversion
Location: 1100-B E. Colonia Rd. Oxnard, CA
93030 Customer: Oxnard Housing Authority
Submission Date: 1/4/24
Detailed Scope of Work
Demolition
● Demolition of existing apartment per plans
Installation/Buildout
● Saw cutting of slab and demolition of concrete for new plumbing ● Excavation for new plumbing and new concrete footings for addition ● All framing throughout including new walls and soffits ● New rough and finish plumbing throughout
● New electrical rough including new panel per plan
● Concrete work:
○ Excavate under slab for rough plumbing and electrical needs ○ Pour new footings per structural plans
○ Pour back all open trenches inside the unit
○ Outside sidewalk as required
● New windows and doors throughout
● New Insulation
● HVAC per plans
○ Exhaust fan ducting
○ Remove existing wall heater and installation of new wall heaters per plans ● Drywall throughout
○ Patch were needed due to demolition and rough MEP requirements ○ New drywall per plans
○ Double stacked first floor ceiling with resilient channels per plans ● Lath, stucco, and color coat to match existing for stucco patching ● Interior paint
● New Flooring and MDF base
○ New underlayment and self leveling
● New kitchens, countertops, fixtures, sinks and appliances 1 of 3
525
● Newbathroomfixturesper plan● Sitework:○ Newsidewalks○ Handicaprampwithtruncateddomes○ Handicapstriping○ Newsignageat Handicapstall Installation/Buildout addedbyClient NOTincludedonplans● Removeandreplaceall outletsandswitchesthroughout, evenonall existingwalls● Install MDFbaseboards○ Insteadof calledout vinyl base● Removeandreplaceall interior doors. Completelist of doorsfromplansaswell asclientsrequest● Cleanupexistingbackyard, theweedsare5feet high○ Includesweedweedwhackingandremoval of all deadweeds● All newLEDlightingthroughout Notes:● All worktobeperformedper plansprovidedtoMDJ● Anyadditional addonitemswill beat therequest of Customer. Anyadjustment shall beanadditional cost.● Priceincludesall labor (Normal WorkingHours- DavisBaconWages), materials,equipment tocompletethisscopeof work.● ConstructionExclusions:○ NewWasher andDryer not includedincontract○ Newstove, range, dishwasher, andfridgenot includedincontract CLARIFICATIONSANDEXCLUSIONS:● Warranty○ Oneyear warrantyagainst workmanship○ Manufacturer'swarrantyvaries● Weexcludeplans, permits, permit fees, relatedfees, testing, inspection, survey, andengineeringunlessspecifiedabove● Weexcludeutilitiesandhazardousor contaminatedmaterial.● Constructionwater, power, andsanitaryfacilitiesavailableonsitefor MDJ’suseat nocost.● Weexcludepremiumtime.● Weexcludeanythingnot specificallymentionedabove.● MDJreservestheright toreview, change, and/or deleteanyprovisionsof anyprimecontract or subcontract, whichresultsfromthisquotation.● All termstobenet 30daysinfull uponreceipt of invoice. Interest will bechargedat therateof 2%monthlyontheunpaidbalance.

BIDPRICE: SeePriceProposal
All worktobecompletedinasubstantial andworkmanlikemanner accordingtostandardpracticesfor thesumof SeePriceProposal. Anyadditional addonitemswill beat therequestof Customer. Anyadjustment shall beanadditional cost.

Bidpriceisgoodfor thirty(30) daysonly.
2of 3
526
Anycontroversyor claimbasedon, arisingout of, or relatingtothisagreement, or breachthereof, includinganyclaimbasedontheworkperformedpursuant tothisagreement, shall besubmittedtotheAmericanArbitrationAssociationfor bindingarbitrationinaccordancewithitsrules. If anyarbitration, legal actionisbrought toenforcethisagreement, or arisingout of orrelatingtotheagreement, theprevailingpartyshall beentitledtorecover fromthenon-prevailingpartyreasonableattorneyfeesandcostsincurred, inadditiontoanyandall otherrelief towhichthat partymaybeentitled.

Submittedby:

MatthewMcMillonPresident [email protected] 3of 3
527

4.00 Contractor's Price Proposal - Summary
Owner PO #:

OHA - 1100 Unit Remodel
124239.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
$50,228.90Section - 01
$2,817.60Section - 02
$24,059.94Section - 03
$46,235.58Section - 06
$26,398.68Section - 07
$36,198.70Section - 08
$132,987.65Section - 09
$3,696.32Section - 10
$717.65Section - 11
$12,661.27Section - 12
$130,110.56Section - 22
$44,057.26Section - 23
$72,198.22Section - 26
$20,358.64Section - 31
$1,778.03Section - 32
Proposal Total
Thisl total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 1 of 1 ends

1/9/2024
Contractor's Price Proposal - Summary
528

5.00 Contractor's Price Proposal - Detail
OHA - 1100 Unit Remodel
124239.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
(Excludes)Equip. MaterialLabor
Line TotalDescriptionUOMMod.ItemSect.

Section - 01
01 22 16 00 0002 Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible costs as directed by Owner. Insert the appropriate quantity to adjust the base cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees, list each one separately and add a comment in the "note" block to identify the Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended warranty, expedited shipping costs, etc.). A copy of each receipt, invoice, or proof of payment shall be submitted with the Price Proposal. 1 $13,011.90EA
Installation =x x 13,011.90
FactorUnit PriceQuantity Total

1.00 1.1000 11,829.00
Bond = $591,493 x 2%
01 22 20 00 0006 CarpenterFor tasks not included in the Construction Task Catalog® and as directed by owner only.
2 $7,623.17HR
Installation =x x 7,623.17
FactorUnit PriceQuantity Total

99.26 1.2000 64.00
2 guys for 4 days for reconfiguring framing around doors and windows to meet new sizing and ADA requirements.
01 22 20 00 0010 ElectricianFor tasks not included in the Construction Task Catalog® and as directed by owner only.
3 $866.21HR
Installation =x x 866.21
FactorUnit PriceQuantity Total

90.23 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 22 20 00 0037 PlumberFor tasks not included in the Construction Task Catalog® and as directed by owner only.
4 $1,027.78HR
Installation =x x 1,027.78
FactorUnit PriceQuantity Total
107.06 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 66 19 00 0060 Handling Material For Over 125' Per 48" x 40" x 48" Container Per 125' Segment
5 $10,586.88EA
Installation =x x 10,586.88
FactorUnit PriceQuantity Total

9.19 1.2000 960.00
4 guys, averaging 4 trips a day for 3 months for demolition hauling and delivery of purchased materials. 01 74 19 00 0016 40 CY Dumpster (5 Ton) "Construction Debris"Includes delivery of dumpster, rental cost, pick-up cost, hauling, and disposal fee. Non-hazardous material. 6 $12,743.71EA
Installation =x x 12,743.71
FactorUnit PriceQuantity Total
884.98 1.2000 12.00
10 dumpsters for demolition debris: cabinets, drywall from entire house, shower, toilet, stucco, insulation, ... 2 dumpsters for construction debris: drywall cuts, lumber cuts, basic trash 01 74 19 00 0019 15 CY Low-Boy Dumpster Mixed RecyclableFor mixed dirt, rock, concrete brick or asphalt with no trash or organics. Includes service to deliver and pick-up dumpster, hauling, rental and disposal fee.
7 $4,369.25EA
Installation =x x 4,369.25
FactorUnit PriceQuantity Total
910.26 1.2000 4.00
for removal of excavated soil for footings, slab, trenching $50,228.90Subtotal for Section - 01
Section - 02

Page 1 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
529
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 02
02 41 19 13 0063 Rod Reinforced Concrete Slab Up To 4" Depth, Saw Cut8 $2,817.60LF Installation =x x 2,817.60
FactorUnit PriceQuantity Total

5.87 1.2000 400.00
sawcut existing slab to trench for new electrical and plumbing runs as needed per plans $2,817.60Subtotal for Section - 02
Section - 03
03 21 11 00 0251 Dowels Or Hairpin, 1/2" x 30" Length, Drilled And Epoxy In Concrete, 6" Embedment
9 $6,655.50EA
Installation =x x 6,655.50
FactorUnit PriceQuantity Total

24.65 1.2000 225.00
200 LF of trenching. Epoxy and Dowel every 2'. One on each side. For reinforcement and tying into existing slab adjacent. 25 dowels to attach from porch sidewalk to existing . 03 21 13 00 0093 #6, Grade 50, Slab On Grade, Galvanized Steel Reinforcement Bar10 $2,496.00LF Installation =x x 2,496.00
FactorUnit PriceQuantity Total

2.60 1.2000 800.00
200 LF of trenching and 600 LF for slab, porch, and footings. Installation of rebar every 2'. 03 30 53 00 0009 Hand Mix And Place ConcreteFor use where conventional equipment access is limited or when directed by the owner.

Includes local aggregate, sand, bagged cement (Type I) and water. 11 $4,370.40CF
Installation =x x 4,370.40
FactorUnit PriceQuantity Total

18.21 1.2000 200.00
patch back trenching in existing slab
03 30 53 00 0009 0038 For High Early Strength, Type 3 ASTM C150, Add12 $156.00 Installation =x x 156.00
FactorUnit PriceQuantity Total

0.65 1.2000 200.00
03 30 53 00 0009 0039 For Lightweight Aggregate, ASTM C330, Add13 $544.80 Installation =x x 544.80
FactorUnit PriceQuantity Total

2.27 1.2000 200.00
03 54 16 00 0005 1/2" Thick Self Leveling Cementitious Underlayment For FloorsIncluding Surface Preparation
14 $9,837.24SF
Installation =x x 9,837.24
FactorUnit PriceQuantity Total

4.78 1.2000 1,715.00
self leveling of floors for prior to installation of new vinyl plank flooring $24,059.94Subtotal for Section - 03
Section - 06
06 11 16 00 0061 2" x 4" Wood Wall Framing At 16" On Center15 $2,321.57SF Installation =x x 1,434.24
FactorUnit PriceQuantity Total

1.66 1.2000 720.00
Demolition x x = 887.33 0.79 1.2000 936.00
for new walls. Couple walls require double stacked
06 16 33 00 0020 3/4" CD Grade Plywood Floor DeckingApplied to floor or joists.16 $6,338.64SF Installation =x x 5,083.26
FactorUnit PriceQuantity Total

2.47 1.2000 1,715.00
Demolition x x = 1,255.38 0.61 1.2000 1,715.00
for new floor decking per plans
06 16 33 00 0020 0038 For Exterior Glue, Add17 $185.22 Installation =x x 185.22
FactorUnit PriceQuantity Total

0.09 1.2000 1,715.00

Page 2 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
530
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 06
06 16 33 00 0033 5/8" Thick CDX Plywood Underlayment Grade18 $255.48SF Installation =x x 221.40
FactorUnit PriceQuantity Total

2.46 1.2000 75.00
Demolition x x = 34.08 0.71 1.2000 40.00
for countetop
06 41 13 00 0116 12" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
19 $1,245.28EA
Installation =x x 1,245.28
FactorUnit PriceQuantity Total
345.91 1.2000 3.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0116 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
20 $420.37
Installation =x x 420.37
FactorUnit PriceQuantity Total
116.77 1.2000 3.00
06 41 13 00 0116 0130 For All Plywood Box Construction, Add21 $438.19 Installation =x x 438.19
FactorUnit PriceQuantity Total
121.72 1.2000 3.00
06 41 13 00 0117 15" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
22 $882.84EA
Installation =x x 882.84
FactorUnit PriceQuantity Total
367.85 1.2000 2.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0117 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
23 $280.25
Installation =x x 280.25
FactorUnit PriceQuantity Total
116.77 1.2000 2.00
06 41 13 00 0117 0130 For All Plywood Box Construction, Add24 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0118 18" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
25 $1,846.66EA
Installation =x x 1,846.66
FactorUnit PriceQuantity Total
384.72 1.2000 4.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0118 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
26 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
116.77 1.2000 4.00
06 41 13 00 0118 0130 For All Plywood Box Construction, Add27 $584.26 Installation =x x 584.26
FactorUnit PriceQuantity Total
121.72 1.2000 4.00
06 41 13 00 0119 21" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
28 $486.41EA
Installation =x x 486.41
FactorUnit PriceQuantity Total
405.34 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0119 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
29 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00

Page 3 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
531
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 06
06 41 13 00 0119 0130 For All Plywood Box Construction, Add30 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0121 27" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
31 $579.37EA
Installation =x x 579.37
FactorUnit PriceQuantity Total
482.81 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0121 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
32 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00
06 41 13 00 0121 0130 For All Plywood Box Construction, Add33 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0124 36" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
34 $1,433.42EA
Installation =x x 1,361.04
FactorUnit PriceQuantity Total
567.10 1.2000 2.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 12" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
35 $541.33EA
Installation =x x 517.21
FactorUnit PriceQuantity Total
431.01 1.2000 1.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
36 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
467.08 1.2000 1.00
06 41 13 00 0139 0130 For All Plywood Box Construction, Add37 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0140 15" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
38 $559.45EA
Installation =x x 529.30
FactorUnit PriceQuantity Total
441.08 1.2000 1.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0140 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
39 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0140 0130 For All Plywood Box Construction, Add40 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0142 21" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
41 $1,264.40EA
Installation =x x 1,222.18
FactorUnit PriceQuantity Total
509.24 1.2000 2.00
Demolition x x = 42.23 35.19 1.2000 1.00
removal of existing cabinets, installation of new per plans

Page 4 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
532
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 06
06 41 13 00 0142 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
42 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0142 0130 For All Plywood Box Construction, Add43 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0170 30" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
44 $493.43EA
Installation =x x 433.12
FactorUnit PriceQuantity Total
360.93 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0170 0131 For All Plywood Box Construction, Add45 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0171 33" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
46 $516.13EA
Installation =x x 449.78
FactorUnit PriceQuantity Total
374.82 1.2000 1.00
Demolition x x = 66.35 55.29 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0171 0131 For All Plywood Box Construction, Add47 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0172 36" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
48 $531.48EA
Installation =x x 459.10
FactorUnit PriceQuantity Total
382.58 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0172 0131 For All Plywood Box Construction, Add49 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0174 12" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
50 $2,167.92EA
Installation =x x 2,143.80
FactorUnit PriceQuantity Total
297.75 1.2000 6.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0174 0131 For All Plywood Box Construction, Add51 $470.23 Installation =x x 470.23
FactorUnit PriceQuantity Total

65.31 1.2000 6.00
06 41 13 00 0175 15" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
52 $809.03EA
Installation =x x 778.87
FactorUnit PriceQuantity Total
324.53 1.2000 2.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0175 0131 For All Plywood Box Construction, Add53 $156.74 Installation =x x 156.74
FactorUnit PriceQuantity Total

65.31 1.2000 2.00

Page 5 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
533
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 06
06 41 13 00 0176 18" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
54 $1,282.30EA
Installation =x x 1,246.10
FactorUnit PriceQuantity Total
346.14 1.2000 3.00
Demolition x x = 36.19 30.16 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0176 0131 For All Plywood Box Construction, Add55 $235.12 Installation =x x 235.12
FactorUnit PriceQuantity Total

65.31 1.2000 3.00
06 41 13 00 0178 24" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
56 $525.71EA
Installation =x x 477.46
FactorUnit PriceQuantity Total
397.88 1.2000 1.00
Demolition x x = 48.25 40.21 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0178 0131 For All Plywood Box Construction, Add57 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0179 27" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
58 $578.09EA
Installation =x x 523.78
FactorUnit PriceQuantity Total
436.48 1.2000 1.00
Demolition x x = 54.31 45.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0179 0131 For All Plywood Box Construction, Add59 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0180 30" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
60 $597.17EA
Installation =x x 536.86
FactorUnit PriceQuantity Total
447.38 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0180 0131 For All Plywood Box Construction, Add61 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0182 36" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
62 $674.99EA
Installation =x x 602.60
FactorUnit PriceQuantity Total
502.17 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0182 0131 For All Plywood Box Construction, Add63 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 93 00 0007 7" To 8-1/2", Flat Cabinet Pull Handle64 $3,370.32EA Installation =x x 3,042.00
FactorUnit PriceQuantity Total

39.00 1.2000 65.00
Demolition x x = 328.32 8.55 1.2000 32.00
removal of existing cabinets, installation of new per plans

Page 6 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
534
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 06
06 46 19 00 0005 4-1/2" High White Pine Base Molding, All Dimensions Are Nominal65 $8,657.40LF Installation =x x 7,389.00
FactorUnit PriceQuantity Total

8.21 1.2000 750.00
Demolition x x = 1,268.40 1.51 1.2000 700.00
new base boards throughout
$46,235.58Subtotal for Section - 06
Section - 07
07 21 16 00 0006 5-1/2" Thick, Kraft Faced, R-21 Fiberglass Flexible Insulation66 $17,600.88SF Installation =x x 14,766.84
FactorUnit PriceQuantity Total

1.98 1.2000 6,215.00
Demolition x x = 2,834.04 0.38 1.2000 6,215.00
removal of existing insulation and installation of new 4500 sqft of walls 1715 sqft of ceilings 07 26 13 00 0004 Two Ply 60 Minute Asphalt Saturated Kraft Building Paper, Grade D (Fortifiber Two Ply Super Jumbo Tex 60 Minute)
67 $1,835.40CSF
Installation =x x 1,835.40
FactorUnit PriceQuantity Total

43.70 1.2000 35.00
for stucco patchback
07 62 13 00 0033 22 Gauge, 0.034" Thick, Galvanized Steel Flashing68 $4,485.60SF Installation =x x 4,485.60
FactorUnit PriceQuantity Total

12.46 1.2000 300.00
flashing per plans for new windows
07 62 13 00 0033 0080 For Wrap Around Window Panning, Add69 $2,476.80 Installation =x x 2,476.80
FactorUnit PriceQuantity Total

6.88 1.2000 300.00
$26,398.68Subtotal for Section - 07
Section - 08
08 12 13 13 0008 3' x 6'-8" Through 7'-2" High, 4-3/4" Deep, 16 Gauge, Knock Down Hollow Metal Door Frame
70 $7,015.14EA
Installation =x x 6,170.69
FactorUnit PriceQuantity Total
571.36 1.2000 9.00
Demolition x x = 844.45 100.53 1.2000 7.00
6 frames for interior doors and 3 for exterior doors
08 13 13 13 0039 3' x 6'-8" x 1-3/4", 18 Gauge, Level 2 Heavy Duty, Honeycomb Core, Hollow Metal Door
71 $2,890.61EA
Installation =x x 2,818.22
FactorUnit PriceQuantity Total
782.84 1.2000 3.00
Demolition x x = 72.38 60.32 1.2000 1.00
for new front doors and one rear door per plans
08 13 13 13 0039 0098 For Embossed Panel Door, Add72 $572.15 Installation =x x 572.15
FactorUnit PriceQuantity Total
158.93 1.2000 3.00
08 13 13 13 0039 0099 For Baked Enamel Finish, Add73 $780.34 Installation =x x 780.34
FactorUnit PriceQuantity Total
216.76 1.2000 3.00
08 13 13 13 0039 0104 For 3 Hour Fire Rated Door, Add74 $473.40EA Installation =x x 473.40
FactorUnit PriceQuantity Total
131.50 1.2000 3.00

Page 7 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
535
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 08
08 14 16 00 0134 3'-0" x 6'-8" x 1-3/4" Thick, 5 Ply, Hollow Core (HC), Birch Faced Wood Door75 $2,524.34EA Installation =x x 2,017.66
FactorUnit PriceQuantity Total
280.23 1.2000 6.00
Demolition x x = 506.69 60.32 1.2000 7.00
5 bedroom/bathroom doors and 1 closet door
08 14 73 00 0074 5' Wide, Two 2'-6" x 6'-8" x 1-3/8" Thick, Flush, Hollow Core (HC), Birch Faced Wood Bi-Pass Doors
76 $1,872.97EA
Installation =x x 1,667.99
FactorUnit PriceQuantity Total
463.33 1.2000 3.00
Demolition x x = 204.98 85.41 1.2000 2.00
removal of 2 existing closet sliding doors, installation of 3 new closet sliding doors 08 53 13 00 0121 >60" To 73" UI, Single Hung Premium Vinyl Window (Pella 350)77 $1,415.59EA Installation =x x 1,288.92
FactorUnit PriceQuantity Total
537.05 1.2000 2.00
Demolition x x = 126.67 52.78 1.2000 2.00
replacement of all existing windows
08 53 13 00 0124 >93" To 101" UI, Single Hung Premium Vinyl Window (Pella 350)78 $993.74EA Installation =x x 912.31
FactorUnit PriceQuantity Total
760.26 1.2000 1.00
Demolition x x = 81.43 67.86 1.2000 1.00
replacement of all existing windows
08 53 13 00 0547 >93" To 101" UI, Horizontal Sliding Premium Vinyl Window (Pella 350)79 $4,338.30EA Installation =x x 3,931.14
FactorUnit PriceQuantity Total
655.19 1.2000 5.00
Demolition x x = 407.16 67.86 1.2000 5.00
replacement of all existing windows
08 71 11 00 0004 3-1/2" x 3-1/2" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
80 $550.33PR
Installation =x x 491.28
FactorUnit PriceQuantity Total

81.88 1.2000 5.00
Demolition x x = 59.05 7.03 1.2000 7.00
removal of existing and installation of new
08 71 11 00 0005 4" x 4" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
81 $485.62PR
Installation =x x 485.62
FactorUnit PriceQuantity Total

89.93 1.2000 4.50
for new front doors and one rear door per plans
08 71 11 00 0513 3" Projection, Residential Spring Type, Bright Brass Finish, Steel Wall Stop (Ives 63)
82 $252.10EA
Installation =x x 173.63
FactorUnit PriceQuantity Total

11.13 1.2000 13.00
Demolition x x = 78.47 5.03 1.2000 13.00
per plans
08 71 11 00 0655 190 Degree Angle Of View, Bright Brass Finish, Brass One-Way Wide Angle Door Viewer (Ives U698)
83 $138.60EA
Installation =x x 138.60
FactorUnit PriceQuantity Total

57.75 1.2000 2.00
for new front door per plans
08 71 11 00 2289 Passage/Closet F01 Mortise LatchsetBoth sides always unlocked.84 $1,019.63EA Installation =x x 959.32
FactorUnit PriceQuantity Total
799.43 1.2000 1.00
Demolition x x = 60.31 25.13 1.2000 2.00
removal of existing and installation of new

Page 8 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
536
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 08
08 71 11 00 2290 Bath/Bedroom Privacy F02/F19 Mortise LocksetLocked with thumb knob inside.
85 $5,939.35EA
Installation =x x 5,728.26
FactorUnit PriceQuantity Total
954.71 1.2000 5.00
Demolition x x = 211.09 25.13 1.2000 7.00
removal of existing and installation of new
08 71 11 00 2294 Entrance F08 Mortise LocksetLocked with key outside and thumb knob inside.86 $4,028.14EA Installation =x x 3,997.98
FactorUnit PriceQuantity Total
1,110.55 1.2000 3.00
Demolition x x = 30.16 25.13 1.2000 1.00
for new front doors and one rear door per plans
08 72 33 00 0155 3/8" x 3/16", Silicon Compression Bulb, Adhesive Backed Perimeter Gasketing Weather-Strip (Pemko PK33)
87 $445.68LF
Installation =x x 264.96
FactorUnit PriceQuantity Total

3.68 1.2000 60.00
Demolition x x = 180.72 2.51 1.2000 60.00
for new front doors and one rear door per plans
08 72 43 00 0011 6" Width, 1/4" Height, Aluminum Saddle Threshold (Pemko 272A)88 $442.69LF Installation =x x 442.69
FactorUnit PriceQuantity Total

40.99 1.2000 9.00
for new front doors and one rear door per plans
08 72 43 00 0011 0458 For Color Anodized Finish, Add89 $19.98 Installation =x x 19.98
FactorUnit PriceQuantity Total

5.55 1.2000 3.00
$36,198.70Subtotal for Section - 08
Section - 09
09 05 71 00 0002 5 Mil Tile And Stone Acoustical Underlayment (EasyMat)90 $8,787.66SF Installation =x x 8,787.66
FactorUnit PriceQuantity Total

4.27 1.2000 1,715.00
acoustical mat underlayment per plans
09 05 71 00 0005 2 MM Thick Resilient Plank Floor Acoustical Underlayment (Floormuffler)91 $2,881.20SF Installation =x x 2,881.20
FactorUnit PriceQuantity Total

1.40 1.2000 1,715.00
closest LI to gypsum sanded floor underlayment per plans 09 22 13 23 0008 25 Gauge, 16" On Center, Installed On Walls, Double-Leg Resilient Channel, RC2 Furring Channel
92 $4,062.18SF
Installation =x x 4,062.18
FactorUnit PriceQuantity Total

3.95 1.2000 857.00
Resilient channel per plans
09 22 13 23 0010 25 Gauge, 16" On Center, Installed On Ceilings, Double-Leg Resilient Channel, RC2 Furring Channel
93 $9,549.12SF
Installation =x x 9,549.12
FactorUnit PriceQuantity Total

4.64 1.2000 1,715.00
Resilient channel per plans
09 22 36 23 0005 3.4 LB/SY, Installed On Studs Or Furred Walls, Flat Diamond, Expanded Metal Lath
94 $1,461.60SF
Installation =x x 1,201.20
FactorUnit PriceQuantity Total

2.86 1.2000 350.00
Demolition x x = 260.40 0.62 1.2000 350.00
For stucco patch back

Page 9 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
537
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 09
09 22 36 23 0005 0020 For >100 To 500, Add95 $147.00 Installation =x x 147.00
FactorUnit PriceQuantity Total

0.35 1.2000 350.00
09 24 23 00 0002 Scratch/Brown/Finish, Three Coat Troweled StuccoExcludes lath and felt.

Interior or exterior, one side.
96 $4,956.00SF
Installation =x x 3,754.80
FactorUnit PriceQuantity Total

8.94 1.2000 350.00
Demolition x x = 1,201.20 2.86 1.2000 350.00
For Stucco patch back
09 24 23 00 0002 0024 For Walls >10' High, Add97 $112.32 Installation =x x 112.32
FactorUnit PriceQuantity Total

0.78 1.2000 120.00
09 24 23 00 0002 0031 For Color Added To Finish Coat, Add98 $21.60SF Installation =x x 21.60
FactorUnit PriceQuantity Total

0.15 1.2000 120.00
09 24 23 00 0002 0037 For >100 To 500, Add99 $282.24 Installation =x x 282.24
FactorUnit PriceQuantity Total

1.96 1.2000 120.00
09 29 10 00 0006 5/8" Gypsum Board100 $18,768.96SF Installation =x x 13,912.08
FactorUnit PriceQuantity Total

1.69 1.2000 6,860.00
Demolition x x = 4,856.88 0.59 1.2000 6,860.00
for walls and ceilings per plans. First floor ceiling requires 2 layers per plans 09 29 10 00 0038 Up To 10' High, Walls, Tape, Spackle And Finish Gypsum Board101 $5,597.76SF Installation =x x 5,597.76
FactorUnit PriceQuantity Total

0.68 1.2000 6,860.00
for walls
09 29 10 00 0038 0048 For ASTM C840 Level 5 High Quality Finish, Add102 $4,116.00 Installation =x x 4,116.00
FactorUnit PriceQuantity Total

0.50 1.2000 6,860.00
09 29 10 00 0041 Up To 10' High, Ceilings, Tape, Spackle And Finish Gypsum Board103 $1,811.04SF Installation =x x 1,811.04
FactorUnit PriceQuantity Total

0.88 1.2000 1,715.00
for ceilings
09 29 10 00 0041 0048 For ASTM C840 Level 5 High Quality Finish, Add104 $1,337.70 Installation =x x 1,337.70
FactorUnit PriceQuantity Total

0.65 1.2000 1,715.00
09 29 10 00 0044 Up To 10' High, Vertical Corners, Tape, Spackle And Finish Gypsum Board105 $2,502.05LF Installation =x x 2,502.05
FactorUnit PriceQuantity Total

1.34 1.2000 1,556.00
vertical corners @ 8' throughout both floors and windows 09 29 10 00 0044 0048 For ASTM C840 Level 5 High Quality Finish, Add106 $1,829.86 Installation =x x 1,829.86
FactorUnit PriceQuantity Total

0.98 1.2000 1,556.00
09 29 10 00 0047 Up To 10' High, Horizontal Corners, Tape, Spackle And Finish Gypsum Board107 $2,232.00LF Installation =x x 2,232.00
FactorUnit PriceQuantity Total

1.55 1.2000 1,200.00
walls and windows

Page 10 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
538
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 09
09 29 10 00 0047 0048 For ASTM C840 Level 5 High Quality Finish, Add108 $1,641.60 Installation =x x 1,641.60
FactorUnit PriceQuantity Total

1.14 1.2000 1,200.00
09 29 10 00 0051 Corner Bead, Galvanized Steel For Gypsum Board109 $10,262.74LF Installation =x x 10,262.74
FactorUnit PriceQuantity Total

3.63 1.2000 2,356.00
for walls and windows
09 65 23 00 0004 0.16" Overall Thickness, 0.020" Wear Layer, Vinyl Plank Flooring (Armstrong® Luxe Plank™)
110 $23,687.58SF
Installation =x x 23,687.58
FactorUnit PriceQuantity Total

11.51 1.2000 1,715.00
new flooring throughout per plans
09 91 13 00 0095 1 Coat Primer, Brush/Roller Work, Paint Exterior Stucco Walls111 $1,444.80SF Installation =x x 1,444.80
FactorUnit PriceQuantity Total

0.86 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 13 00 0097 2 Coats Paint, Brush/Roller Work, Paint Exterior Stucco Walls112 $3,057.60SF Installation =x x 3,057.60
FactorUnit PriceQuantity Total

1.82 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 23 00 0067 1 Coat Primer, Brush/Roller Work, Paint Interior Plaster/Drywall Walls113 $5,270.40SF Installation =x x 5,270.40
FactorUnit PriceQuantity Total

0.61 1.2000 7,200.00
for walls
09 91 23 00 0069 2 Coats Paint, Brush/Roller Work, Paint Interior Plaster/Drywall Walls114 $10,540.80SF Installation =x x 10,540.80
FactorUnit PriceQuantity Total

1.22 1.2000 7,200.00
for walls
09 91 23 00 0161 1 Coat Primer, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling115 $1,461.18SF Installation =x x 1,461.18
FactorUnit PriceQuantity Total

0.71 1.2000 1,715.00
for ceilings
09 91 23 00 0163 2 Coats Paint, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling116 $2,675.40SF Installation =x x 2,675.40
FactorUnit PriceQuantity Total

1.30 1.2000 1,715.00
for ceilings
09 91 23 00 0252 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Door Frame And Trim117 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

0.93 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0254 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Door Frame And Trime118 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

2.02 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0275 1 Coat Primer, Brush/Roller Work, Both Faces, Paint Interior Wood Door119 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total

76.57 1.2000 0.00
8 doors on first floor
7 doors on second floor

Page 11 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
539
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 09
09 91 23 00 0277 2 Coats Paint, Brush/Roller Work, Both Faces, Paint Interior Wood Door120 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total
138.02 1.2000 0.00
8 doors on first floor
7 doors on second floor
09 91 23 00 0307 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
121 $192.00LF
Installation =x x 192.00
FactorUnit PriceQuantity Total

1.25 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0309 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
122 $416.26LF
Installation =x x 416.26
FactorUnit PriceQuantity Total

2.71 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0350 1 Coat Primer, Brush Work, Paint Interior Wood Trim To 6" Wide123 $576.00LF Installation =x x 576.00
FactorUnit PriceQuantity Total

0.64 1.2000 750.00
750 LF of baseboards
09 91 23 00 0352 2 Coats Paint, Brush Work, Paint Interior Wood Trim To 6" Wide124 $1,305.00LF Installation =x x 1,305.00
FactorUnit PriceQuantity Total

1.45 1.2000 750.00
750 LF of baseboards
$132,987.65Subtotal for Section - 09
Section - 10
10 14 53 11 0078 18" x 24" Reflective Polyethylene Traffic Sign125 $165.61EA Installation =x x 165.61
FactorUnit PriceQuantity Total
138.01 1.2000 1.00
ADA parking sign
10 14 53 11 0198 Single Bracket And Post Cap For Street Sign126 $29.02EA Installation =x x 29.02
FactorUnit PriceQuantity Total

24.18 1.2000 1.00
ADA parking sign
10 14 53 11 0213 8' Galvanized Steel U-Channel Sign Post127 $165.00EA Installation =x x 165.00
FactorUnit PriceQuantity Total
137.50 1.2000 1.00
ADA parking sign
10 14 53 11 0278 2-3/8" Diameter, Galvanized, Flat Traffic Sign Post Cap (EC-2)128 $26.24EA Installation =x x 26.24
FactorUnit PriceQuantity Total

21.87 1.2000 1.00
ADA parking sign
10 28 13 13 0045 Single Roll, Surface Mounted, Stainless Steel, Satin Finish, Toilet Tissue Dispenser (Bobrick B-6857)
129 $308.30EA
Installation =x x 254.04
FactorUnit PriceQuantity Total
105.85 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans

Page 12 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
540
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 10
10 28 13 13 0170 36" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x36)130 $401.44EA Installation =x x 401.44
FactorUnit PriceQuantity Total
111.51 1.2000 3.00
per plans
10 28 13 13 0170 0148 For Peened Grip, Add131 $24.73 Installation =x x 24.73
FactorUnit PriceQuantity Total

6.87 1.2000 3.00
10 28 13 13 0171 42" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x42)132 $136.87EA Installation =x x 136.87
FactorUnit PriceQuantity Total
114.06 1.2000 1.00
per plans
10 28 13 13 0171 0148 For Peened Grip, Add133 $8.52 Installation =x x 8.52
FactorUnit PriceQuantity Total

7.10 1.2000 1.00
10 28 13 13 0217 Telescoping 60" To 72" Length, 20-Gauge, 1" Diameter, Stainless Steel Curved Shower Rod With Concealed Mounting (Kohler Expanse K-9349) 134 $389.23EA
Installation =x x 334.97
FactorUnit PriceQuantity Total
139.57 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0322 24" Length, 3/4" Diameter, Stainless Steel Towel Bar (Bobrick B-674)135 $333.74EA Installation =x x 279.48
FactorUnit PriceQuantity Total
116.45 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0390 20" x 26", Surface Mounted, Aluminum Medicine Cabinet (Kohler K-CB)136 $1,707.62EA Installation =x x 1,587.05
FactorUnit PriceQuantity Total
661.27 1.2000 2.00
Demolition x x = 120.58 50.24 1.2000 2.00
per plans
$3,696.32Subtotal for Section - 10
Section - 11
11 30 13 13 0015 30" Venting Range Hood (Broan 40000)137 $717.65EA Installation =x x 637.08
FactorUnit PriceQuantity Total
265.45 1.2000 2.00
Demolition x x = 80.57 67.14 1.2000 1.00
removal of existing and installation of 2 new
$717.65Subtotal for Section - 11
Section - 12
12 36 61 19 0005 1-1/4" Thick, Quartz Agglomerate Countertop With Backsplash138 $12,198.00SF Installation =x x 11,117.34
FactorUnit PriceQuantity Total
142.53 1.2000 65.00
Demolition x x = 1,080.66 25.73 1.2000 35.00
kitchen countertops

Page 13 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
541
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 12
12 36 61 19 0006 Quartz Agglomerate Countertop End Splash For Quartz Agglomerate Countertops
139 $101.54LF
Installation =x x 91.30
FactorUnit PriceQuantity Total

19.02 1.2000 4.00
Demolition x x = 10.25 4.27 1.2000 2.00
for end where fridges meet
12 36 61 19 0007 Cutout For Sink And/Or Faucet In Quartz Agglomerate Countertop140 $361.73EA Installation =x x 361.73
FactorUnit PriceQuantity Total
150.72 1.2000 2.00
2 kitchen sinks
$12,661.27Subtotal for Section - 12
Section - 22
22 01 40 81 0004 Removal And Replacement Of Chrome Supply Lines To Sink/Lavatory, Pair141 $335.04EA Installation =x x 335.04
FactorUnit PriceQuantity Total

27.92 1.2000 10.00
replace supply lines in kitchens and bathrooms
22 01 40 81 0006 Removal And Replacement Of Double Bowl Sink/Lavatory Drain Line142 $289.97EA Installation =x x 289.97
FactorUnit PriceQuantity Total

60.41 1.2000 4.00
new drain lines
22 11 16 00 0003 3/4" Schedule 40 Threaded Galvanized Steel Pipe With 150 LB Malleable Iron Fitting AssemblyIncludes all hangers and all galvanized malleable iron fittings (couplings, elbows, tees and reducer fittings). All hangers are complete assemblies. Not for use where detail is available.
143 $13,959.60LF
Installation =x x 12,930.00
FactorUnit PriceQuantity Total

21.55 1.2000 500.00
Demolition x x = 1,029.60 4.29 1.2000 200.00
gas line piping
22 11 16 00 0003 0304 For Work In Restricted Working Space, Add144 $1,010.40 Installation =x x 1,010.40
FactorUnit PriceQuantity Total

4.21 1.2000 200.00
22 11 16 00 0901 3/4" Inside Diameter Copper Pipe/Tubing Type L AssemblyIncludes all hangers and couplings, elbow, tee, reducer fittings. All hangers are complete assemblies. Not for use where detail is available.
145 $32,443.80LF
Installation =x x 29,628.60
FactorUnit PriceQuantity Total

25.99 1.2000 950.00
Demolition x x = 2,815.20 3.91 1.2000 600.00
water line copper piping
22 11 16 00 0901 0315 For Work In Restricted Working Space, Add146 $1,384.80 Installation =x x 1,384.80
FactorUnit PriceQuantity Total

5.77 1.2000 200.00
22 12 23 13 0002 80 Gallon ASME Rated Tank, 150PSI, Jacketed, Insulated, Glass Lined Water Heater Storage Tank (TJ-80A)
147 $479.41EA
Installation =x x 0.00
FactorUnit PriceQuantity Total
2,554.73 1.2000 0.00
Demolition x x = 479.41 399.51 1.2000 1.00
removal of existing water heater

Page 14 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
542
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 22
22 13 16 00 0518 4" Aboveground Schedule 40 Polyvinyl Chloride (PVC) DWV Pipe AssemblyIncludes all fittings, couplings and hangers. Fittings are assumed every 10'. Not for use where detail is available.
148 $48,884.70LF
Installation =x x 46,314.00
FactorUnit PriceQuantity Total

51.46 1.2000 750.00
Demolition x x = 2,570.70 7.79 1.2000 275.00
new Sewer and vent piping
22 13 16 00 0518 0304 For Work In Restricted Working Space, Add149 $2,175.00 Installation =x x 2,175.00
FactorUnit PriceQuantity Total

7.25 1.2000 250.00
22 34 13 00 0011 7.4 GPM, Outdoor Mount, Instantaneous, Tankless, Gas Domestic Water Heater (Rheem RTG-74XN)
150 $10,037.42EA
Installation =x x 10,037.42
FactorUnit PriceQuantity Total
4,182.26 1.2000 2.00
installation of 2 new water heaters
22 41 16 16 0003 33" x 21" x 6-1/2" Stainless Steel Kitchen Sink, Double Bowl, 20 Gauge (Elkay D233213)
151 $1,768.56EA
Installation =x x 1,640.30
FactorUnit PriceQuantity Total
683.46 1.2000 2.00
Demolition x x = 128.26 106.88 1.2000 1.00
removal of existing and installation of new.
22 41 39 00 0006 Chrome Two Handle Kitchen Faucet With Spray, Three Hole Installation, 8" Center (Delta 2402LF-LHP+H215)
152 $565.87EA
Installation =x x 505.94
FactorUnit PriceQuantity Total
210.81 1.2000 2.00
Demolition x x = 59.93 49.94 1.2000 1.00
removal of existing and installation of new.
22 42 13 13 0026 2 Piece Tank Type, Pressure Assisted, Siphon Jet, Floor Mounted, Back Outlet, Handicap Accessible, Elongated Vitreous China Water Closet (American Standard Yorkville™ ADA)
153 $2,811.37EA
Installation =x x 2,686.73
FactorUnit PriceQuantity Total
1,119.47 1.2000 2.00
Demolition x x = 124.64 103.87 1.2000 1.00
remove existing and install new ADA toilet
22 42 16 13 0009 27" x 20" Wheelchair Accessible, Vitreous China Wall Hung Lavatory (American Standard Wheel Chair Users)
154 $1,701.89EA
Installation =x x 1,621.58
FactorUnit PriceQuantity Total
675.66 1.2000 2.00
Demolition x x = 80.30 66.92 1.2000 1.00
remove existing and install new ADA sink, faucet, and drain cover. 22 42 19 00 0027 3 Piece Tub/Shower Surrounds, 32" x 72" Side Walls, 48" x 72" Back, (Swanstone SK-324872)
155 $8,454.49EA
Installation =x x 8,071.78
FactorUnit PriceQuantity Total
3,363.24 1.2000 2.00
Demolition x x = 382.72 318.93 1.2000 1.00
new tub/shower for bathrooms
22 42 39 00 0042 Single Supply EcoPower® Faucet, Polished Chrome Finish (Toto TEL3LS10#CP)
156 $1,885.78EA
Installation =x x 1,885.78
FactorUnit PriceQuantity Total
785.74 1.2000 2.00
ADA sink, faucet, and drain cover.

Page 15 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
543
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 22
22 42 39 00 0064 Three Lever Handle, Chrome Shower And Tub Filler (American Standard Colony Soft 3375.502)
157 $741.02EA
Installation =x x 636.98
FactorUnit PriceQuantity Total
265.41 1.2000 2.00
Demolition x x = 104.04 43.35 1.2000 2.00
per plans
22 42 39 00 0064 0147 For Faucet With Metal Cross Handles, Add158 $109.80EA Installation =x x 109.80
FactorUnit PriceQuantity Total

45.75 1.2000 2.00
22 42 39 00 0211 Lavatory Protective Enclosure (IPS Truebro Lav Shield)159 $390.86EA Installation =x x 390.86
FactorUnit PriceQuantity Total
162.86 1.2000 2.00
drain cover for ADA kitchen and bathroom sink
22 42 39 00 0218 1/2" NPT x 3/8" Compression Chrome, Quarter Turn Dual Angle Stop (SharkBite 25558)
160 $680.78EA
Installation =x x 580.08
FactorUnit PriceQuantity Total

48.34 1.2000 10.00
Demolition x x = 100.70 10.49 1.2000 8.00
new angle stops installed in bathrooms and kitchens
$130,110.56Subtotal for Section - 22
Section - 23
23 09 23 53 0284 Scheduling Program, HVAC (AHU, RTU, AC Units, Etcetera) Programming Measures
161 $8,755.06EA
Installation =x x 8,755.06
FactorUnit PriceQuantity Total
3,647.94 1.2000 2.00
required setup, balancing, and charging for new system
23 31 13 16 0063 4" Diameter, 26 Gauge, Seal Class C, Galvanized Sheet Metal Round And Flat-Oval Connector
162 $3,117.60EA
Installation =x x 3,117.60
FactorUnit PriceQuantity Total

17.32 1.2000 150.00
exhaust ducting per plans
23 33 13 13 0006 12" Diameter Radial Opposed Blade Damper Round, Steel Construction, Manual Operated
163 $696.79EA
Installation =x x 682.22
FactorUnit PriceQuantity Total
142.13 1.2000 4.00
Demolition x x = 14.57 12.14 1.2000 1.00
HVAC per plans
23 33 46 00 0008 12" Diameter Flexible Duct, R8.0 Insulated With Polyester Inner Liner Over Fiberglass Insulation And Metallized Outer Jacket
164 $12,610.20LF
Installation =x x 11,491.20
FactorUnit PriceQuantity Total

21.28 1.2000 450.00
Demolition x x = 1,119.00 3.73 1.2000 250.00
HVAC per plans - exhaust ducting
23 33 46 00 0020 12" Diameter Flexible Duct Collar, Spin In Type, Sheet Metal, With Damper165 $739.63EA Installation =x x 706.03
FactorUnit PriceQuantity Total

98.06 1.2000 6.00
Demolition x x = 33.60 14.00 1.2000 2.00
HVAC per plans

Page 16 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
544
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 23
23 34 16 00 0272 109 CFM, Ceiling/Wall Mounted, Metal Intake Grille, Heavy Duty/Continuous Operation Exhaust Fan (Broan® LoSone® Ventilator L100MG) 166 $2,212.13EA
Installation =x x 2,168.35
FactorUnit PriceQuantity Total
451.74 1.2000 4.00
Demolition x x = 43.78 36.48 1.2000 1.00
Laundry room and bathroom exhaust fan per plans
23 54 16 13 0007 120 MBH, 2,000 CFM Up/Horizontal Flow Multi-Speed, Two Stage 96% AFUE Gas FurnaceBlower cooling capacity up to 5 tons.
167 $15,925.85EA
Installation =x x 15,770.64
FactorUnit PriceQuantity Total
2,628.44 1.2000 5.00
Demolition x x = 155.21 129.34 1.2000 1.00
per plans. wall mounted furnaces
$44,057.26Subtotal for Section - 23
Section - 26
26 01 20 91 0002 Lock Out/Tag Out Local DisconnectExcludes tag or padlock See CSI section 26 01 20 91-0004 for padlock, 26 01 20 91-0005 for tag(s). 168 $590.94EA
Installation =x x 590.94
FactorUnit PriceQuantity Total

32.83 1.2000 15.00
LOTO of existing circuits
26 05 19 16 0402 #12 AWG, 3 Conductors, 600 Volt, Type NM, Copper, Non-Metallic Sheathed Cable
169 $24,763.20MLF
Installation =x x 24,763.20
FactorUnit PriceQuantity Total
4,127.20 1.2000 5.00
for new electrical runs per plans
26 05 19 16 0402 0377 For Installation In Wood Stud Wall (Includes Drilling), Add170 $1,795.14 Installation =x x 1,795.14
FactorUnit PriceQuantity Total
299.19 1.2000 5.00
26 09 23 00 0144 Wall Switch Replacement Occupancy Sensor, Single GangIncludes integral occupancy sensor and relay.
171 $1,483.80EA
Installation =x x 1,483.80
FactorUnit PriceQuantity Total
123.65 1.2000 10.00
per plans
26 09 23 00 0270 Passive Infrared, Wall Switch Mounted, Wired Occupancy Sensor (Encelium PW-100-24)Excludes GB II cable.
172 $725.28EA
Installation =x x 725.28
FactorUnit PriceQuantity Total
302.20 1.2000 2.00
for bathrooms
26 24 13 00 0213 800 Amperes, 480 Volt, 4 Wire, Switchboard Incoming No Switch Circuit173 $6,313.51EA Installation =x x 5,324.36
FactorUnit PriceQuantity Total
4,436.97 1.2000 1.00
Demolition x x = 989.15 824.29 1.2000 1.00
for new main panel to new units subpanels
26 24 16 00 0470 200 Ampere Rating, Main Breaker, Indoor, 42 Circuit, 4 Wire, 120/208 Volt, Assembled Panelboard With 20 Ampere, 1 Pole Plug-In Breakers 174 $8,743.93EA
Installation =x x 7,651.92
FactorUnit PriceQuantity Total
3,188.30 1.2000 2.00
Demolition x x = 1,092.01 910.01 1.2000 1.00
1 new sub panel for each unit

Page 17 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
545
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 26
26 27 13 00 0125 Single Phase M-90 Meter, Socket, NEMA 3R Enclosure175 $8,033.33EA Installation =x x 7,705.73
FactorUnit PriceQuantity Total
1,070.24 1.2000 6.00
Demolition x x = 327.60 54.60 1.2000 5.00
installation of new meters for building
26 27 26 00 0009 20 Amperes, 1 Gang, GFI, Duplex Receptacle Assembly176 $5,103.00EA Installation =x x 4,273.08
FactorUnit PriceQuantity Total
101.74 1.2000 35.00
Demolition x x = 829.92 34.58 1.2000 20.00
All new GFI outlets throughout per clients request
26 27 26 00 0125 20 Amperes, 125 Volt Single Specification Grade Tamper Resistant ReceptaclePass & Seymour TR5351.
177 $2,554.46EA
Installation =x x 2,073.98
FactorUnit PriceQuantity Total

39.28 1.2000 44.00
Demolition x x = 480.48 9.10 1.2000 44.00
all new outlets throughout per clients request
26 27 26 00 0138 1 Gang, 20 Amperes, 120/277 Volt, SPST, Switch Assembly178 $3,774.00EA Installation =x x 2,736.60
FactorUnit PriceQuantity Total

91.22 1.2000 25.00
Demolition x x = 1,037.40 34.58 1.2000 25.00
25 switches total in both units
26 51 19 00 0269 2' x 2', 4,000 Lumens, Surface Mount, Volumetric LED Fixture (Lithonia 2RTX2)179 $7,035.98EA Installation =x x 6,106.46
FactorUnit PriceQuantity Total
212.03 1.2000 24.00
Demolition x x = 929.52 38.73 1.2000 20.00
new LED lights throughout
26 51 19 00 0477 2-1/2" Diameter x 15-1/2" High, Polished Nickel, LED Wall Sconce (Hudson Valley Lighting SHAW 1200-PN)
180 $1,281.65EA
Installation =x x 1,194.29
FactorUnit PriceQuantity Total
497.62 1.2000 2.00
Demolition x x = 87.36 36.40 1.2000 2.00
2 new wall sconces per plans in bathrooms
$72,198.22Subtotal for Section - 26
Section - 31
31 05 16 00 0002 #2 Stone Aggregate Fill (1-1/2" To 2-1/2" Clean)181 $1,650.60CY Installation =x x 1,650.60
FactorUnit PriceQuantity Total

55.02 1.2000 25.00
4" deep, 200 LF, 2' wide base for backfill for trenching. 20 CY for footings, and slabs 31 05 16 00 0002 0053 For Up To 8, Add182 $66.00
Installation =x x 66.00
FactorUnit PriceQuantity Total

11.00 1.2000 5.00
31 11 00 00 0010 Clearing By Machine - Light Brush Without Grub183 $202.36ACR Installation =x x 202.36
FactorUnit PriceQuantity Total
337.26 1.2000 0.50
clear out weeds in back yard
31 11 00 00 0019 Hand Loading Of Cleared And Grubbed Material184 $976.32CY Installation =x x 976.32
FactorUnit PriceQuantity Total

40.68 1.2000 20.00
clear out weeds in back yard

Page 18 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
546
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 31
31 23 16 13 0007 Excavation For Trenching By Hand In SoilIncludes stockpiling excess materials and trimming sides and bottom of trench.
185 $4,027.50CY
Installation =x x 4,027.50
FactorUnit PriceQuantity Total
134.25 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0011 Backfilling or Placing Subbase for Trenches with Imported or Stockpiled Materials by Hand
186 $1,118.70CY
Installation =x x 1,118.70
FactorUnit PriceQuantity Total

37.29 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0014 Compaction of Fill or Subbase for Trenches by Hand187 $1,262.10CY Installation =x x 1,262.10
FactorUnit PriceQuantity Total

42.07 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 36 0009 Excavation For Building Foundations And Other Structures By Hand in Soil188 $7,249.50CY Installation =x x 7,249.50
FactorUnit PriceQuantity Total
134.25 1.2000 45.00
for footings
31 23 16 36 0019 Backfilling Around Building Foundations And Other Structures By Hand189 $1,534.32CY Installation =x x 1,534.32
FactorUnit PriceQuantity Total

63.93 1.2000 20.00
for footings
31 23 16 36 0022 Compaction Of Fill Or Subbase For Building Foundations and Other Structures by Hand
190 $2,271.24CY
Installation =x x 2,271.24
FactorUnit PriceQuantity Total

42.06 1.2000 45.00
for footings
$20,358.64Subtotal for Section - 31
Section - 32
32 16 13 13 0016 6" x 12" Cast In Place Concrete Gutter With 6" Curb And Face - Straight191 $225.96LF Installation =x x 154.98
FactorUnit PriceQuantity Total

25.83 1.2000 5.00
Demolition x x = 70.98 11.83 1.2000 5.00
for parking lot ADA modifications
32 16 13 13 0016 0077 For Up To 20, Add192 $105.42MOD Installation =x x 105.42
FactorUnit PriceQuantity Total

17.57 1.2000 5.00
32 16 23 00 0002 4" Cast In Place Concrete Sidewalk193 $212.16SF Installation =x x 212.16
FactorUnit PriceQuantity Total

8.84 1.2000 20.00
for parking lot ADA modifications
32 16 23 00 0002 0094 For Up To 100, Add194 $92.16 Installation =x x 92.16
FactorUnit PriceQuantity Total

3.84 1.2000 20.00
32 16 23 00 0008 Finish Concrete Handicap Drop Section In SidewalkExcludes patterned (tactile) finish.
195 $167.12EA
Installation =x x 167.12
FactorUnit PriceQuantity Total
139.27 1.2000 1.00
for parking lot ADA modifications

Page 19 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
547
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124239.00
OHA - 1100 Unit Remodel
Section - 32
32 17 23 13 0074 Solid Area, Painted Pavement Marking For Parking AreasUse task for lines >12" wide, stop bars, transverse lines, diagonal lines, crossing lanes, etc. 196 $102.48SF
Installation =x x 102.48
FactorUnit PriceQuantity Total

4.27 1.2000 20.00
for parking lot ADA modifications
32 17 23 13 0088 Handicap Symbol For Van Parking Stalls, Painted Pavement Marking For Parking AreasApproximate overall dimensions: 4-1/3' width x 5' height. White or blue symbol. Excludes striping.
197 $52.66EA
Installation =x x 52.66
FactorUnit PriceQuantity Total

43.88 1.2000 1.00
for parking lot ADA modifications
32 17 26 00 0003 Embedded, VPC Truncated Dome Detectable Warning SurfaceAlso raised strips or directional bars. All colors.
198 $650.04SF
Installation =x x 650.04
FactorUnit PriceQuantity Total

54.17 1.2000 10.00
new truncated domes per
32 31 13 13 0010 12" Diameter Hole, Auger By Machine Fence Post Hole In Soil199 $80.75VLF Installation =x x 80.75
FactorUnit PriceQuantity Total

22.43 1.2000 3.00
ADA parking sign
32 31 13 13 0027 12" Diameter, Concrete Fill For Post Hole200 $89.28VLF Installation =x x 89.28
FactorUnit PriceQuantity Total

24.80 1.2000 3.00
ADA parking sign
$1,778.03Subtotal for Section - 32
Proposal Total
This total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 20 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
548
Subcontractor Listing
124239.00
OHA - 1100 Unit Remodel
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
%DutiesName of Contractor Amount
Refined Construction 86.02$520,000.00

6.00

Page 1 of 1 ends

1/9/2024
Subcontractor Listing
549
Work Order Signature Document
EZIQC Contract No.: CA-R7-GB-101723-MDJ
New Work Order
124236.00
Modify an Existing W
ork Order
Work Order Title:

Work Order Number.: Work Order Date:

X
01/09/2024
Contractor Name:

Contact:

Phone:

Contact:

Phone:

Matt McMillon
310-490-1521
Owner Name:

OHA - 1130 Unit Remodel
Oxnard Housing Authority
Fredi Contreras
805-890-8319
MDJ Management
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of Sourcewell EZIQC Contract No CA-R7-GB-101723-MDJ.

Brief Work Order Description
:

Will not apply:Liquidated Damages Will apply:

Estimated Completion Date:

Estimated Start Date: Time of Performance
X
Work Order Firm Fixed Price: $604,505.00
Owner Purchase Order Number:

Approvals
Date DateMDJ ManagementOxnard Housing Authority

2.00

Page 1 of 1 ends

1/9/2024
Work Order Signature Document

EXHIBIT A
550

3.00 Detailed Scope of Work
Fredi ContrerasMatt McMillonT o: From:

MDJ Management Oxnard Housing Authority
531 Main St #611 300 N. Marquita Street
El Segundo, CA 90245 Oxnard, CA 93030
310-490-1521 805-890-8319
Work Order Number:

January 09, 2024Date Printed:
124236.00
OHA - 1130 Unit RemodelWork Order Title:

Brief Scope:

Revised FinalPreliminary X
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the items set forth below shall be considered part of this scope of work.

See Attached.

Subject to the terms and conditions of ezIQC Contract CA-R7-GB-101723-MDJ.

MDJ Management Date
DateOxnard Housing Authority

Page 1 of 1 ends

1/9/2024
Scope of Work
551
MDJ Management, LLC
License # 1044711
DIR # 1000061313
531 Main St. #611 El Segundo CA 90245
310-490-1521
Job Name: 1130 Colonia Conversion
Location: 1130 E. Colonia Rd. Oxnard, CA 93030
Customer: Oxnard Housing Authority
Submission Date: 1/4/24
Detailed Scope of Work
Demolition
● Demolition of existing apartment per plans
Installation/Buildout
● Saw cutting of slab and demolition of concrete for new plumbing ● Excavation for new plumbing and new concrete footings for addition ● All framing throughout including new walls and soffits ● New rough and finish plumbing throughout
● New electrical rough including new panel per plan
● Concrete work:
○ Excavate under slab for rough plumbing and electrical needs ○ Pour new footings per structural plans
○ Pour back all open trenches inside the unit
○ Outside sidewalk as required
● New windows and doors throughout
● New Insulation
● HVAC per plans
○ Exhaust fan ducting
○ Remove existing wall heater and installation of new wall heaters per plans ● Drywall throughout
○ Patch were needed due to demolition and rough MEP requirements ○ New drywall per plans
○ Double stacked first floor ceiling with resilient channels per plans ● Lath, stucco, and color coat to match existing for stucco patching ● Interior paint
● New Flooring and MDF base
○ New underlayment and self leveling
● New kitchens, countertops, fixtures, sinks and appliances 1 of 3
552
● Newbathroomfixturesper plan● Sitework:○ Newsidewalks○ Handicaprampwithtruncateddomes○ Handicapstriping○ Newsignageat Handicapstall Installation/Buildout addedbyClient NOTincludedonplans● Removeandreplaceall outletsandswitchesthroughout, evenonall existingwalls● Install MDFbaseboards○ Insteadof calledout vinyl base● Removeandreplaceall interior doors. Completelist of doorsfromplansaswell asclientsrequest● Cleanupexistingbackyard, theweedsare5feet high○ Includesweedweedwhackingandremoval of all deadweeds● All newLEDlightingthroughout Notes:● All worktobeperformedper plansprovidedtoMDJ● Anyadditional addonitemswill beat therequest of Customer. Anyadjustment shall beanadditional cost.● Priceincludesall labor (Normal WorkingHours- DavisBaconWages), materials,equipment tocompletethisscopeof work.● ConstructionExclusions:○ NewWasher andDryer not includedincontract○ Newstove, range, dishwasher, andfridgenot includedincontract CLARIFICATIONSANDEXCLUSIONS:● Warranty○ Oneyear warrantyagainst workmanship○ Manufacturer'swarrantyvaries● Weexcludeplans, permits, permit fees, relatedfees, testing, inspection, survey, andengineeringunlessspecifiedabove● Weexcludeutilitiesandhazardousor contaminatedmaterial.● Constructionwater, power, andsanitaryfacilitiesavailableonsitefor MDJ’suseat nocost.● Weexcludepremiumtime.● Weexcludeanythingnot specificallymentionedabove.● MDJreservestheright toreview, change, and/or deleteanyprovisionsof anyprimecontract or subcontract, whichresultsfromthisquotation.● All termstobenet 30daysinfull uponreceipt of invoice. Interest will bechargedat therateof 2%monthlyontheunpaidbalance.

BIDPRICE: SeePriceProposal
All worktobecompletedinasubstantial andworkmanlikemanner accordingtostandardpracticesfor thesumof SeePriceProposal. Anyadditional addonitemswill beat therequestof Customer. Anyadjustment shall beanadditional cost.

Bidpriceisgoodfor thirty(30) daysonly.
2of 3
553
Anycontroversyor claimbasedon, arisingout of, or relatingtothisagreement, or breachthereof, includinganyclaimbasedontheworkperformedpursuant tothisagreement, shall besubmittedtotheAmericanArbitrationAssociationfor bindingarbitrationinaccordancewithitsrules. If anyarbitration, legal actionisbrought toenforcethisagreement, or arisingout of orrelatingtotheagreement, theprevailingpartyshall beentitledtorecover fromthenon-prevailingpartyreasonableattorneyfeesandcostsincurred, inadditiontoanyandall otherrelief towhichthat partymaybeentitled.

Submittedby:

MatthewMcMillonPresident [email protected] 3of 3
554

4.00 Contractor's Price Proposal - Summary
Owner PO #:

OHA - 1130 Unit Remodel
124236.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
$50,228.90Section - 01
$2,817.60Section - 02
$24,059.94Section - 03
$46,235.58Section - 06
$26,398.68Section - 07
$36,198.70Section - 08
$132,987.65Section - 09
$3,696.32Section - 10
$717.65Section - 11
$12,661.27Section - 12
$130,110.56Section - 22
$44,057.26Section - 23
$72,198.22Section - 26
$20,358.64Section - 31
$1,778.03Section - 32
Proposal Total
Thisl total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 1 of 1 ends

1/9/2024
Contractor's Price Proposal - Summary
555

5.00 Contractor's Price Proposal - Detail
OHA - 1130 Unit Remodel
124236.00
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
(Excludes)Equip. MaterialLabor
Line TotalDescriptionUOMMod.ItemSect.

Section - 01
01 22 16 00 0002 Reimbursable FeesReimbursable Fees will be paid to the contractor for eligible costs as directed by Owner. Insert the appropriate quantity to adjust the base cost to the actual Reimbursable Fee. If there are multiple Reimbursable Fees, list each one separately and add a comment in the "note" block to identify the Reimbursable Fee (e.g. sidewalk closure, road cut, various permits, extended warranty, expedited shipping costs, etc.). A copy of each receipt, invoice, or proof of payment shall be submitted with the Price Proposal. 1 $13,011.90EA
Installation =x x 13,011.90
FactorUnit PriceQuantity Total

1.00 1.1000 11,829.00
Bond = $591,493 x 2%
01 22 20 00 0006 CarpenterFor tasks not included in the Construction Task Catalog® and as directed by owner only.
2 $7,623.17HR
Installation =x x 7,623.17
FactorUnit PriceQuantity Total

99.26 1.2000 64.00
2 guys for 4 days for reconfiguring framing around doors and windows to meet new sizing and ADA requirements.
01 22 20 00 0010 ElectricianFor tasks not included in the Construction Task Catalog® and as directed by owner only.
3 $866.21HR
Installation =x x 866.21
FactorUnit PriceQuantity Total

90.23 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 22 20 00 0037 PlumberFor tasks not included in the Construction Task Catalog® and as directed by owner only.
4 $1,027.78HR
Installation =x x 1,027.78
FactorUnit PriceQuantity Total
107.06 1.2000 8.00
1 guy one day for investigation and into existing and create plan for new connections 01 66 19 00 0060 Handling Material For Over 125' Per 48" x 40" x 48" Container Per 125' Segment
5 $10,586.88EA
Installation =x x 10,586.88
FactorUnit PriceQuantity Total

9.19 1.2000 960.00
4 guys, averaging 4 trips a day for 3 months for demolition hauling and delivery of purchased materials. 01 74 19 00 0016 40 CY Dumpster (5 Ton) "Construction Debris"Includes delivery of dumpster, rental cost, pick-up cost, hauling, and disposal fee. Non-hazardous material. 6 $12,743.71EA
Installation =x x 12,743.71
FactorUnit PriceQuantity Total
884.98 1.2000 12.00
10 dumpsters for demolition debris: cabinets, drywall from entire house, shower, toilet, stucco, insulation, ... 2 dumpsters for construction debris: drywall cuts, lumber cuts, basic trash 01 74 19 00 0019 15 CY Low-Boy Dumpster Mixed RecyclableFor mixed dirt, rock, concrete brick or asphalt with no trash or organics. Includes service to deliver and pick-up dumpster, hauling, rental and disposal fee.
7 $4,369.25EA
Installation =x x 4,369.25
FactorUnit PriceQuantity Total
910.26 1.2000 4.00
for removal of excavated soil for footings, slab, trenching $50,228.90Subtotal for Section - 01
Section - 02

Page 1 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
556
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 02
02 41 19 13 0063 Rod Reinforced Concrete Slab Up To 4" Depth, Saw Cut8 $2,817.60LF Installation =x x 2,817.60
FactorUnit PriceQuantity Total

5.87 1.2000 400.00
sawcut existing slab to trench for new electrical and plumbing runs as needed per plans $2,817.60Subtotal for Section - 02
Section - 03
03 21 11 00 0251 Dowels Or Hairpin, 1/2" x 30" Length, Drilled And Epoxy In Concrete, 6" Embedment
9 $6,655.50EA
Installation =x x 6,655.50
FactorUnit PriceQuantity Total

24.65 1.2000 225.00
200 LF of trenching. Epoxy and Dowel every 2'. One on each side. For reinforcement and tying into existing slab adjacent. 25 dowels to attach from porch sidewalk to existing . 03 21 13 00 0093 #6, Grade 50, Slab On Grade, Galvanized Steel Reinforcement Bar10 $2,496.00LF Installation =x x 2,496.00
FactorUnit PriceQuantity Total

2.60 1.2000 800.00
200 LF of trenching and 600 LF for slab, porch, and footings. Installation of rebar every 2'. 03 30 53 00 0009 Hand Mix And Place ConcreteFor use where conventional equipment access is limited or when directed by the owner.

Includes local aggregate, sand, bagged cement (Type I) and water. 11 $4,370.40CF
Installation =x x 4,370.40
FactorUnit PriceQuantity Total

18.21 1.2000 200.00
patch back trenching in existing slab
03 30 53 00 0009 0038 For High Early Strength, Type 3 ASTM C150, Add12 $156.00 Installation =x x 156.00
FactorUnit PriceQuantity Total

0.65 1.2000 200.00
03 30 53 00 0009 0039 For Lightweight Aggregate, ASTM C330, Add13 $544.80 Installation =x x 544.80
FactorUnit PriceQuantity Total

2.27 1.2000 200.00
03 54 16 00 0005 1/2" Thick Self Leveling Cementitious Underlayment For FloorsIncluding Surface Preparation
14 $9,837.24SF
Installation =x x 9,837.24
FactorUnit PriceQuantity Total

4.78 1.2000 1,715.00
self leveling of floors for prior to installation of new vinyl plank flooring $24,059.94Subtotal for Section - 03
Section - 06
06 11 16 00 0061 2" x 4" Wood Wall Framing At 16" On Center15 $2,321.57SF Installation =x x 1,434.24
FactorUnit PriceQuantity Total

1.66 1.2000 720.00
Demolition x x = 887.33 0.79 1.2000 936.00
for new walls. Couple walls require double stacked
06 16 33 00 0020 3/4" CD Grade Plywood Floor DeckingApplied to floor or joists.16 $6,338.64SF Installation =x x 5,083.26
FactorUnit PriceQuantity Total

2.47 1.2000 1,715.00
Demolition x x = 1,255.38 0.61 1.2000 1,715.00
for new floor decking per plans
06 16 33 00 0020 0038 For Exterior Glue, Add17 $185.22 Installation =x x 185.22
FactorUnit PriceQuantity Total

0.09 1.2000 1,715.00

Page 2 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
557
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 06
06 16 33 00 0033 5/8" Thick CDX Plywood Underlayment Grade18 $255.48SF Installation =x x 221.40
FactorUnit PriceQuantity Total

2.46 1.2000 75.00
Demolition x x = 34.08 0.71 1.2000 40.00
for countetop
06 41 13 00 0116 12" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
19 $1,245.28EA
Installation =x x 1,245.28
FactorUnit PriceQuantity Total
345.91 1.2000 3.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0116 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
20 $420.37
Installation =x x 420.37
FactorUnit PriceQuantity Total
116.77 1.2000 3.00
06 41 13 00 0116 0130 For All Plywood Box Construction, Add21 $438.19 Installation =x x 438.19
FactorUnit PriceQuantity Total
121.72 1.2000 3.00
06 41 13 00 0117 15" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
22 $882.84EA
Installation =x x 882.84
FactorUnit PriceQuantity Total
367.85 1.2000 2.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0117 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
23 $280.25
Installation =x x 280.25
FactorUnit PriceQuantity Total
116.77 1.2000 2.00
06 41 13 00 0117 0130 For All Plywood Box Construction, Add24 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0118 18" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
25 $1,846.66EA
Installation =x x 1,846.66
FactorUnit PriceQuantity Total
384.72 1.2000 4.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0118 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
26 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
116.77 1.2000 4.00
06 41 13 00 0118 0130 For All Plywood Box Construction, Add27 $584.26 Installation =x x 584.26
FactorUnit PriceQuantity Total
121.72 1.2000 4.00
06 41 13 00 0119 21" Wide, 35" High x 23-3/4" Deep, Single Drawer and Single Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
28 $486.41EA
Installation =x x 486.41
FactorUnit PriceQuantity Total
405.34 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0119 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
29 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00

Page 3 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
558
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 06
06 41 13 00 0119 0130 For All Plywood Box Construction, Add30 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0121 27" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
31 $579.37EA
Installation =x x 579.37
FactorUnit PriceQuantity Total
482.81 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0121 0126 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
32 $140.12
Installation =x x 140.12
FactorUnit PriceQuantity Total
116.77 1.2000 1.00
06 41 13 00 0121 0130 For All Plywood Box Construction, Add33 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0124 36" Wide, 35" High x 23-3/4" Deep, Single Drawer and Double Door, Solid Oak Face Frame, Door and Drawer Front, Base Cabinet
34 $1,433.42EA
Installation =x x 1,361.04
FactorUnit PriceQuantity Total
567.10 1.2000 2.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 12" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
35 $541.33EA
Installation =x x 517.21
FactorUnit PriceQuantity Total
431.01 1.2000 1.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0139 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
36 $560.50
Installation =x x 560.50
FactorUnit PriceQuantity Total
467.08 1.2000 1.00
06 41 13 00 0139 0130 For All Plywood Box Construction, Add37 $146.06 Installation =x x 146.06
FactorUnit PriceQuantity Total
121.72 1.2000 1.00
06 41 13 00 0140 15" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
38 $559.45EA
Installation =x x 529.30
FactorUnit PriceQuantity Total
441.08 1.2000 1.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0140 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
39 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0140 0130 For All Plywood Box Construction, Add40 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0142 21" Wide, 35" High x 23-3/4" Deep, Four Drawer Base, Solid Oak Face Frame and Drawer Fronts, Base Cabinet
41 $1,264.40EA
Installation =x x 1,222.18
FactorUnit PriceQuantity Total
509.24 1.2000 2.00
Demolition x x = 42.23 35.19 1.2000 1.00
removal of existing cabinets, installation of new per plans

Page 4 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
559
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 06
06 41 13 00 0142 0129 For Solid Wood Drawers, Dovetail Joints And Full Extension Drawer Guides, Add
42 $1,120.99
Installation =x x 1,120.99
FactorUnit PriceQuantity Total
467.08 1.2000 2.00
06 41 13 00 0142 0130 For All Plywood Box Construction, Add43 $292.13 Installation =x x 292.13
FactorUnit PriceQuantity Total
121.72 1.2000 2.00
06 41 13 00 0170 30" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
44 $493.43EA
Installation =x x 433.12
FactorUnit PriceQuantity Total
360.93 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0170 0131 For All Plywood Box Construction, Add45 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0171 33" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
46 $516.13EA
Installation =x x 449.78
FactorUnit PriceQuantity Total
374.82 1.2000 1.00
Demolition x x = 66.35 55.29 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0171 0131 For All Plywood Box Construction, Add47 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0172 36" Wide, 18" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
48 $531.48EA
Installation =x x 459.10
FactorUnit PriceQuantity Total
382.58 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0172 0131 For All Plywood Box Construction, Add49 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0174 12" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
50 $2,167.92EA
Installation =x x 2,143.80
FactorUnit PriceQuantity Total
297.75 1.2000 6.00
Demolition x x = 24.12 20.10 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0174 0131 For All Plywood Box Construction, Add51 $470.23 Installation =x x 470.23
FactorUnit PriceQuantity Total

65.31 1.2000 6.00
06 41 13 00 0175 15" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
52 $809.03EA
Installation =x x 778.87
FactorUnit PriceQuantity Total
324.53 1.2000 2.00
Demolition x x = 30.16 25.13 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0175 0131 For All Plywood Box Construction, Add53 $156.74 Installation =x x 156.74
FactorUnit PriceQuantity Total

65.31 1.2000 2.00

Page 5 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
560
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 06
06 41 13 00 0176 18" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
54 $1,282.30EA
Installation =x x 1,246.10
FactorUnit PriceQuantity Total
346.14 1.2000 3.00
Demolition x x = 36.19 30.16 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0176 0131 For All Plywood Box Construction, Add55 $235.12 Installation =x x 235.12
FactorUnit PriceQuantity Total

65.31 1.2000 3.00
06 41 13 00 0178 24" Wide, 30" High x 12" Deep, Single Door, Solid Oak Face Frame and Door, Wall Cabinet
56 $525.71EA
Installation =x x 477.46
FactorUnit PriceQuantity Total
397.88 1.2000 1.00
Demolition x x = 48.25 40.21 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0178 0131 For All Plywood Box Construction, Add57 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0179 27" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
58 $578.09EA
Installation =x x 523.78
FactorUnit PriceQuantity Total
436.48 1.2000 1.00
Demolition x x = 54.31 45.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0179 0131 For All Plywood Box Construction, Add59 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0180 30" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
60 $597.17EA
Installation =x x 536.86
FactorUnit PriceQuantity Total
447.38 1.2000 1.00
Demolition x x = 60.31 50.26 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0180 0131 For All Plywood Box Construction, Add61 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 13 00 0182 36" Wide, 30" High x 12" Deep, Double Door, Solid Oak Face Frame and Door, Wall Cabinet
62 $674.99EA
Installation =x x 602.60
FactorUnit PriceQuantity Total
502.17 1.2000 1.00
Demolition x x = 72.38 60.32 1.2000 1.00
removal of existing cabinets, installation of new per plans 06 41 13 00 0182 0131 For All Plywood Box Construction, Add63 $78.37 Installation =x x 78.37
FactorUnit PriceQuantity Total

65.31 1.2000 1.00
06 41 93 00 0007 7" To 8-1/2", Flat Cabinet Pull Handle64 $3,370.32EA Installation =x x 3,042.00
FactorUnit PriceQuantity Total

39.00 1.2000 65.00
Demolition x x = 328.32 8.55 1.2000 32.00
removal of existing cabinets, installation of new per plans

Page 6 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
561
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 06
06 46 19 00 0005 4-1/2" High White Pine Base Molding, All Dimensions Are Nominal65 $8,657.40LF Installation =x x 7,389.00
FactorUnit PriceQuantity Total

8.21 1.2000 750.00
Demolition x x = 1,268.40 1.51 1.2000 700.00
new base boards throughout
$46,235.58Subtotal for Section - 06
Section - 07
07 21 16 00 0006 5-1/2" Thick, Kraft Faced, R-21 Fiberglass Flexible Insulation66 $17,600.88SF Installation =x x 14,766.84
FactorUnit PriceQuantity Total

1.98 1.2000 6,215.00
Demolition x x = 2,834.04 0.38 1.2000 6,215.00
removal of existing insulation and installation of new 4500 sqft of walls 1715 sqft of ceilings 07 26 13 00 0004 Two Ply 60 Minute Asphalt Saturated Kraft Building Paper, Grade D (Fortifiber Two Ply Super Jumbo Tex 60 Minute)
67 $1,835.40CSF
Installation =x x 1,835.40
FactorUnit PriceQuantity Total

43.70 1.2000 35.00
for stucco patchback
07 62 13 00 0033 22 Gauge, 0.034" Thick, Galvanized Steel Flashing68 $4,485.60SF Installation =x x 4,485.60
FactorUnit PriceQuantity Total

12.46 1.2000 300.00
flashing per plans for new windows
07 62 13 00 0033 0080 For Wrap Around Window Panning, Add69 $2,476.80 Installation =x x 2,476.80
FactorUnit PriceQuantity Total

6.88 1.2000 300.00
$26,398.68Subtotal for Section - 07
Section - 08
08 12 13 13 0008 3' x 6'-8" Through 7'-2" High, 4-3/4" Deep, 16 Gauge, Knock Down Hollow Metal Door Frame
70 $7,015.14EA
Installation =x x 6,170.69
FactorUnit PriceQuantity Total
571.36 1.2000 9.00
Demolition x x = 844.45 100.53 1.2000 7.00
6 frames for interior doors and 3 for exterior doors
08 13 13 13 0039 3' x 6'-8" x 1-3/4", 18 Gauge, Level 2 Heavy Duty, Honeycomb Core, Hollow Metal Door
71 $2,890.61EA
Installation =x x 2,818.22
FactorUnit PriceQuantity Total
782.84 1.2000 3.00
Demolition x x = 72.38 60.32 1.2000 1.00
for new front doors and one rear door per plans
08 13 13 13 0039 0098 For Embossed Panel Door, Add72 $572.15 Installation =x x 572.15
FactorUnit PriceQuantity Total
158.93 1.2000 3.00
08 13 13 13 0039 0099 For Baked Enamel Finish, Add73 $780.34 Installation =x x 780.34
FactorUnit PriceQuantity Total
216.76 1.2000 3.00
08 13 13 13 0039 0104 For 3 Hour Fire Rated Door, Add74 $473.40EA Installation =x x 473.40
FactorUnit PriceQuantity Total
131.50 1.2000 3.00

Page 7 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
562
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 08
08 14 16 00 0134 3'-0" x 6'-8" x 1-3/4" Thick, 5 Ply, Hollow Core (HC), Birch Faced Wood Door75 $2,524.34EA Installation =x x 2,017.66
FactorUnit PriceQuantity Total
280.23 1.2000 6.00
Demolition x x = 506.69 60.32 1.2000 7.00
5 bedroom/bathroom doors and 1 closet door
08 14 73 00 0074 5' Wide, Two 2'-6" x 6'-8" x 1-3/8" Thick, Flush, Hollow Core (HC), Birch Faced Wood Bi-Pass Doors
76 $1,872.97EA
Installation =x x 1,667.99
FactorUnit PriceQuantity Total
463.33 1.2000 3.00
Demolition x x = 204.98 85.41 1.2000 2.00
removal of 2 existing closet sliding doors, installation of 3 new closet sliding doors 08 53 13 00 0121 >60" To 73" UI, Single Hung Premium Vinyl Window (Pella 350)77 $1,415.59EA Installation =x x 1,288.92
FactorUnit PriceQuantity Total
537.05 1.2000 2.00
Demolition x x = 126.67 52.78 1.2000 2.00
replacement of all existing windows
08 53 13 00 0124 >93" To 101" UI, Single Hung Premium Vinyl Window (Pella 350)78 $993.74EA Installation =x x 912.31
FactorUnit PriceQuantity Total
760.26 1.2000 1.00
Demolition x x = 81.43 67.86 1.2000 1.00
replacement of all existing windows
08 53 13 00 0547 >93" To 101" UI, Horizontal Sliding Premium Vinyl Window (Pella 350)79 $4,338.30EA Installation =x x 3,931.14
FactorUnit PriceQuantity Total
655.19 1.2000 5.00
Demolition x x = 407.16 67.86 1.2000 5.00
replacement of all existing windows
08 71 11 00 0004 3-1/2" x 3-1/2" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
80 $550.33PR
Installation =x x 491.28
FactorUnit PriceQuantity Total

81.88 1.2000 5.00
Demolition x x = 59.05 7.03 1.2000 7.00
removal of existing and installation of new
08 71 11 00 0005 4" x 4" Standard Duty, Full Mortise, Plain Bearing, Brass/Bronze, Satin Chrome Finish Hinge
81 $485.62PR
Installation =x x 485.62
FactorUnit PriceQuantity Total

89.93 1.2000 4.50
for new front doors and one rear door per plans
08 71 11 00 0513 3" Projection, Residential Spring Type, Bright Brass Finish, Steel Wall Stop (Ives 63)
82 $252.10EA
Installation =x x 173.63
FactorUnit PriceQuantity Total

11.13 1.2000 13.00
Demolition x x = 78.47 5.03 1.2000 13.00
per plans
08 71 11 00 0655 190 Degree Angle Of View, Bright Brass Finish, Brass One-Way Wide Angle Door Viewer (Ives U698)
83 $138.60EA
Installation =x x 138.60
FactorUnit PriceQuantity Total

57.75 1.2000 2.00
for new front door per plans
08 71 11 00 2289 Passage/Closet F01 Mortise LatchsetBoth sides always unlocked.84 $1,019.63EA Installation =x x 959.32
FactorUnit PriceQuantity Total
799.43 1.2000 1.00
Demolition x x = 60.31 25.13 1.2000 2.00
removal of existing and installation of new

Page 8 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
563
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 08
08 71 11 00 2290 Bath/Bedroom Privacy F02/F19 Mortise LocksetLocked with thumb knob inside.
85 $5,939.35EA
Installation =x x 5,728.26
FactorUnit PriceQuantity Total
954.71 1.2000 5.00
Demolition x x = 211.09 25.13 1.2000 7.00
removal of existing and installation of new
08 71 11 00 2294 Entrance F08 Mortise LocksetLocked with key outside and thumb knob inside.86 $4,028.14EA Installation =x x 3,997.98
FactorUnit PriceQuantity Total
1,110.55 1.2000 3.00
Demolition x x = 30.16 25.13 1.2000 1.00
for new front doors and one rear door per plans
08 72 33 00 0155 3/8" x 3/16", Silicon Compression Bulb, Adhesive Backed Perimeter Gasketing Weather-Strip (Pemko PK33)
87 $445.68LF
Installation =x x 264.96
FactorUnit PriceQuantity Total

3.68 1.2000 60.00
Demolition x x = 180.72 2.51 1.2000 60.00
for new front doors and one rear door per plans
08 72 43 00 0011 6" Width, 1/4" Height, Aluminum Saddle Threshold (Pemko 272A)88 $442.69LF Installation =x x 442.69
FactorUnit PriceQuantity Total

40.99 1.2000 9.00
for new front doors and one rear door per plans
08 72 43 00 0011 0458 For Color Anodized Finish, Add89 $19.98 Installation =x x 19.98
FactorUnit PriceQuantity Total

5.55 1.2000 3.00
$36,198.70Subtotal for Section - 08
Section - 09
09 05 71 00 0002 5 Mil Tile And Stone Acoustical Underlayment (EasyMat)90 $8,787.66SF Installation =x x 8,787.66
FactorUnit PriceQuantity Total

4.27 1.2000 1,715.00
acoustical mat underlayment per plans
09 05 71 00 0005 2 MM Thick Resilient Plank Floor Acoustical Underlayment (Floormuffler)91 $2,881.20SF Installation =x x 2,881.20
FactorUnit PriceQuantity Total

1.40 1.2000 1,715.00
closest LI to gypsum sanded floor underlayment per plans 09 22 13 23 0008 25 Gauge, 16" On Center, Installed On Walls, Double-Leg Resilient Channel, RC2 Furring Channel
92 $4,062.18SF
Installation =x x 4,062.18
FactorUnit PriceQuantity Total

3.95 1.2000 857.00
Resilient channel per plans
09 22 13 23 0010 25 Gauge, 16" On Center, Installed On Ceilings, Double-Leg Resilient Channel, RC2 Furring Channel
93 $9,549.12SF
Installation =x x 9,549.12
FactorUnit PriceQuantity Total

4.64 1.2000 1,715.00
Resilient channel per plans
09 22 36 23 0005 3.4 LB/SY, Installed On Studs Or Furred Walls, Flat Diamond, Expanded Metal Lath
94 $1,461.60SF
Installation =x x 1,201.20
FactorUnit PriceQuantity Total

2.86 1.2000 350.00
Demolition x x = 260.40 0.62 1.2000 350.00
For stucco patch back

Page 9 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
564
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 09
09 22 36 23 0005 0020 For >100 To 500, Add95 $147.00 Installation =x x 147.00
FactorUnit PriceQuantity Total

0.35 1.2000 350.00
09 24 23 00 0002 Scratch/Brown/Finish, Three Coat Troweled StuccoExcludes lath and felt.

Interior or exterior, one side.
96 $4,956.00SF
Installation =x x 3,754.80
FactorUnit PriceQuantity Total

8.94 1.2000 350.00
Demolition x x = 1,201.20 2.86 1.2000 350.00
For Stucco patch back
09 24 23 00 0002 0024 For Walls >10' High, Add97 $112.32 Installation =x x 112.32
FactorUnit PriceQuantity Total

0.78 1.2000 120.00
09 24 23 00 0002 0031 For Color Added To Finish Coat, Add98 $21.60SF Installation =x x 21.60
FactorUnit PriceQuantity Total

0.15 1.2000 120.00
09 24 23 00 0002 0037 For >100 To 500, Add99 $282.24 Installation =x x 282.24
FactorUnit PriceQuantity Total

1.96 1.2000 120.00
09 29 10 00 0006 5/8" Gypsum Board100 $18,768.96SF Installation =x x 13,912.08
FactorUnit PriceQuantity Total

1.69 1.2000 6,860.00
Demolition x x = 4,856.88 0.59 1.2000 6,860.00
for walls and ceilings per plans. First floor ceiling requires 2 layers per plans 09 29 10 00 0038 Up To 10' High, Walls, Tape, Spackle And Finish Gypsum Board101 $5,597.76SF Installation =x x 5,597.76
FactorUnit PriceQuantity Total

0.68 1.2000 6,860.00
for walls
09 29 10 00 0038 0048 For ASTM C840 Level 5 High Quality Finish, Add102 $4,116.00 Installation =x x 4,116.00
FactorUnit PriceQuantity Total

0.50 1.2000 6,860.00
09 29 10 00 0041 Up To 10' High, Ceilings, Tape, Spackle And Finish Gypsum Board103 $1,811.04SF Installation =x x 1,811.04
FactorUnit PriceQuantity Total

0.88 1.2000 1,715.00
for ceilings
09 29 10 00 0041 0048 For ASTM C840 Level 5 High Quality Finish, Add104 $1,337.70 Installation =x x 1,337.70
FactorUnit PriceQuantity Total

0.65 1.2000 1,715.00
09 29 10 00 0044 Up To 10' High, Vertical Corners, Tape, Spackle And Finish Gypsum Board105 $2,502.05LF Installation =x x 2,502.05
FactorUnit PriceQuantity Total

1.34 1.2000 1,556.00
vertical corners @ 8' throughout both floors and windows 09 29 10 00 0044 0048 For ASTM C840 Level 5 High Quality Finish, Add106 $1,829.86 Installation =x x 1,829.86
FactorUnit PriceQuantity Total

0.98 1.2000 1,556.00
09 29 10 00 0047 Up To 10' High, Horizontal Corners, Tape, Spackle And Finish Gypsum Board107 $2,232.00LF Installation =x x 2,232.00
FactorUnit PriceQuantity Total

1.55 1.2000 1,200.00
walls and windows

Page 10 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
565
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 09
09 29 10 00 0047 0048 For ASTM C840 Level 5 High Quality Finish, Add108 $1,641.60 Installation =x x 1,641.60
FactorUnit PriceQuantity Total

1.14 1.2000 1,200.00
09 29 10 00 0051 Corner Bead, Galvanized Steel For Gypsum Board109 $10,262.74LF Installation =x x 10,262.74
FactorUnit PriceQuantity Total

3.63 1.2000 2,356.00
for walls and windows
09 65 23 00 0004 0.16" Overall Thickness, 0.020" Wear Layer, Vinyl Plank Flooring (Armstrong® Luxe Plank™)
110 $23,687.58SF
Installation =x x 23,687.58
FactorUnit PriceQuantity Total

11.51 1.2000 1,715.00
new flooring throughout per plans
09 91 13 00 0095 1 Coat Primer, Brush/Roller Work, Paint Exterior Stucco Walls111 $1,444.80SF Installation =x x 1,444.80
FactorUnit PriceQuantity Total

0.86 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 13 00 0097 2 Coats Paint, Brush/Roller Work, Paint Exterior Stucco Walls112 $3,057.60SF Installation =x x 3,057.60
FactorUnit PriceQuantity Total

1.82 1.2000 1,400.00
paint front and side of building for affected areas corner to corner 09 91 23 00 0067 1 Coat Primer, Brush/Roller Work, Paint Interior Plaster/Drywall Walls113 $5,270.40SF Installation =x x 5,270.40
FactorUnit PriceQuantity Total

0.61 1.2000 7,200.00
for walls
09 91 23 00 0069 2 Coats Paint, Brush/Roller Work, Paint Interior Plaster/Drywall Walls114 $10,540.80SF Installation =x x 10,540.80
FactorUnit PriceQuantity Total

1.22 1.2000 7,200.00
for walls
09 91 23 00 0161 1 Coat Primer, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling115 $1,461.18SF Installation =x x 1,461.18
FactorUnit PriceQuantity Total

0.71 1.2000 1,715.00
for ceilings
09 91 23 00 0163 2 Coats Paint, Brush/Roller Work, Paint Interior Drywall/Plaster Ceiling116 $2,675.40SF Installation =x x 2,675.40
FactorUnit PriceQuantity Total

1.30 1.2000 1,715.00
for ceilings
09 91 23 00 0252 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Door Frame And Trim117 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

0.93 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0254 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Door Frame And Trime118 $0.00LF Installation =x x 0.00
FactorUnit PriceQuantity Total

2.02 1.2000 0.00
15 total doors. 40 LF of trim per door
09 91 23 00 0275 1 Coat Primer, Brush/Roller Work, Both Faces, Paint Interior Wood Door119 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total

76.57 1.2000 0.00
8 doors on first floor
7 doors on second floor

Page 11 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
566
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 09
09 91 23 00 0277 2 Coats Paint, Brush/Roller Work, Both Faces, Paint Interior Wood Door120 $0.00EA Installation =x x 0.00
FactorUnit PriceQuantity Total
138.02 1.2000 0.00
8 doors on first floor
7 doors on second floor
09 91 23 00 0307 1 Coat Primer, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
121 $192.00LF
Installation =x x 192.00
FactorUnit PriceQuantity Total

1.25 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0309 2 Coats Paint, Brush/Roller Work, Paint Interior Wood Window Frame And Trim
122 $416.26LF
Installation =x x 416.26
FactorUnit PriceQuantity Total

2.71 1.2000 128.00
8 windows with 128 LF of trim
09 91 23 00 0350 1 Coat Primer, Brush Work, Paint Interior Wood Trim To 6" Wide123 $576.00LF Installation =x x 576.00
FactorUnit PriceQuantity Total

0.64 1.2000 750.00
750 LF of baseboards
09 91 23 00 0352 2 Coats Paint, Brush Work, Paint Interior Wood Trim To 6" Wide124 $1,305.00LF Installation =x x 1,305.00
FactorUnit PriceQuantity Total

1.45 1.2000 750.00
750 LF of baseboards
$132,987.65Subtotal for Section - 09
Section - 10
10 14 53 11 0078 18" x 24" Reflective Polyethylene Traffic Sign125 $165.61EA Installation =x x 165.61
FactorUnit PriceQuantity Total
138.01 1.2000 1.00
ADA parking sign
10 14 53 11 0198 Single Bracket And Post Cap For Street Sign126 $29.02EA Installation =x x 29.02
FactorUnit PriceQuantity Total

24.18 1.2000 1.00
ADA parking sign
10 14 53 11 0213 8' Galvanized Steel U-Channel Sign Post127 $165.00EA Installation =x x 165.00
FactorUnit PriceQuantity Total
137.50 1.2000 1.00
ADA parking sign
10 14 53 11 0278 2-3/8" Diameter, Galvanized, Flat Traffic Sign Post Cap (EC-2)128 $26.24EA Installation =x x 26.24
FactorUnit PriceQuantity Total

21.87 1.2000 1.00
ADA parking sign
10 28 13 13 0045 Single Roll, Surface Mounted, Stainless Steel, Satin Finish, Toilet Tissue Dispenser (Bobrick B-6857)
129 $308.30EA
Installation =x x 254.04
FactorUnit PriceQuantity Total
105.85 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans

Page 12 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
567
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 10
10 28 13 13 0170 36" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x36)130 $401.44EA Installation =x x 401.44
FactorUnit PriceQuantity Total
111.51 1.2000 3.00
per plans
10 28 13 13 0170 0148 For Peened Grip, Add131 $24.73 Installation =x x 24.73
FactorUnit PriceQuantity Total

6.87 1.2000 3.00
10 28 13 13 0171 42" Length, 1-1/2" Diameter, Stainless Steel Grab Bar (Bobrick B-6806x42)132 $136.87EA Installation =x x 136.87
FactorUnit PriceQuantity Total
114.06 1.2000 1.00
per plans
10 28 13 13 0171 0148 For Peened Grip, Add133 $8.52 Installation =x x 8.52
FactorUnit PriceQuantity Total

7.10 1.2000 1.00
10 28 13 13 0217 Telescoping 60" To 72" Length, 20-Gauge, 1" Diameter, Stainless Steel Curved Shower Rod With Concealed Mounting (Kohler Expanse K-9349) 134 $389.23EA
Installation =x x 334.97
FactorUnit PriceQuantity Total
139.57 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0322 24" Length, 3/4" Diameter, Stainless Steel Towel Bar (Bobrick B-674)135 $333.74EA Installation =x x 279.48
FactorUnit PriceQuantity Total
116.45 1.2000 2.00
Demolition x x = 54.26 22.61 1.2000 2.00
per plans
10 28 13 13 0390 20" x 26", Surface Mounted, Aluminum Medicine Cabinet (Kohler K-CB)136 $1,707.62EA Installation =x x 1,587.05
FactorUnit PriceQuantity Total
661.27 1.2000 2.00
Demolition x x = 120.58 50.24 1.2000 2.00
per plans
$3,696.32Subtotal for Section - 10
Section - 11
11 30 13 13 0015 30" Venting Range Hood (Broan 40000)137 $717.65EA Installation =x x 637.08
FactorUnit PriceQuantity Total
265.45 1.2000 2.00
Demolition x x = 80.57 67.14 1.2000 1.00
removal of existing and installation of 2 new
$717.65Subtotal for Section - 11
Section - 12
12 36 61 19 0005 1-1/4" Thick, Quartz Agglomerate Countertop With Backsplash138 $12,198.00SF Installation =x x 11,117.34
FactorUnit PriceQuantity Total
142.53 1.2000 65.00
Demolition x x = 1,080.66 25.73 1.2000 35.00
kitchen countertops

Page 13 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
568
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 12
12 36 61 19 0006 Quartz Agglomerate Countertop End Splash For Quartz Agglomerate Countertops
139 $101.54LF
Installation =x x 91.30
FactorUnit PriceQuantity Total

19.02 1.2000 4.00
Demolition x x = 10.25 4.27 1.2000 2.00
for end where fridges meet
12 36 61 19 0007 Cutout For Sink And/Or Faucet In Quartz Agglomerate Countertop140 $361.73EA Installation =x x 361.73
FactorUnit PriceQuantity Total
150.72 1.2000 2.00
2 kitchen sinks
$12,661.27Subtotal for Section - 12
Section - 22
22 01 40 81 0004 Removal And Replacement Of Chrome Supply Lines To Sink/Lavatory, Pair141 $335.04EA Installation =x x 335.04
FactorUnit PriceQuantity Total

27.92 1.2000 10.00
replace supply lines in kitchens and bathrooms
22 01 40 81 0006 Removal And Replacement Of Double Bowl Sink/Lavatory Drain Line142 $289.97EA Installation =x x 289.97
FactorUnit PriceQuantity Total

60.41 1.2000 4.00
new drain lines
22 11 16 00 0003 3/4" Schedule 40 Threaded Galvanized Steel Pipe With 150 LB Malleable Iron Fitting AssemblyIncludes all hangers and all galvanized malleable iron fittings (couplings, elbows, tees and reducer fittings). All hangers are complete assemblies. Not for use where detail is available.
143 $13,959.60LF
Installation =x x 12,930.00
FactorUnit PriceQuantity Total

21.55 1.2000 500.00
Demolition x x = 1,029.60 4.29 1.2000 200.00
gas line piping
22 11 16 00 0003 0304 For Work In Restricted Working Space, Add144 $1,010.40 Installation =x x 1,010.40
FactorUnit PriceQuantity Total

4.21 1.2000 200.00
22 11 16 00 0901 3/4" Inside Diameter Copper Pipe/Tubing Type L AssemblyIncludes all hangers and couplings, elbow, tee, reducer fittings. All hangers are complete assemblies. Not for use where detail is available.
145 $32,443.80LF
Installation =x x 29,628.60
FactorUnit PriceQuantity Total

25.99 1.2000 950.00
Demolition x x = 2,815.20 3.91 1.2000 600.00
water line copper piping
22 11 16 00 0901 0315 For Work In Restricted Working Space, Add146 $1,384.80 Installation =x x 1,384.80
FactorUnit PriceQuantity Total

5.77 1.2000 200.00
22 12 23 13 0002 80 Gallon ASME Rated Tank, 150PSI, Jacketed, Insulated, Glass Lined Water Heater Storage Tank (TJ-80A)
147 $479.41EA
Installation =x x 0.00
FactorUnit PriceQuantity Total
2,554.73 1.2000 0.00
Demolition x x = 479.41 399.51 1.2000 1.00
removal of existing water heater

Page 14 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
569
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 22
22 13 16 00 0518 4" Aboveground Schedule 40 Polyvinyl Chloride (PVC) DWV Pipe AssemblyIncludes all fittings, couplings and hangers. Fittings are assumed every 10'. Not for use where detail is available.
148 $48,884.70LF
Installation =x x 46,314.00
FactorUnit PriceQuantity Total

51.46 1.2000 750.00
Demolition x x = 2,570.70 7.79 1.2000 275.00
new Sewer and vent piping
22 13 16 00 0518 0304 For Work In Restricted Working Space, Add149 $2,175.00 Installation =x x 2,175.00
FactorUnit PriceQuantity Total

7.25 1.2000 250.00
22 34 13 00 0011 7.4 GPM, Outdoor Mount, Instantaneous, Tankless, Gas Domestic Water Heater (Rheem RTG-74XN)
150 $10,037.42EA
Installation =x x 10,037.42
FactorUnit PriceQuantity Total
4,182.26 1.2000 2.00
installation of 2 new water heaters
22 41 16 16 0003 33" x 21" x 6-1/2" Stainless Steel Kitchen Sink, Double Bowl, 20 Gauge (Elkay D233213)
151 $1,768.56EA
Installation =x x 1,640.30
FactorUnit PriceQuantity Total
683.46 1.2000 2.00
Demolition x x = 128.26 106.88 1.2000 1.00
removal of existing and installation of new.
22 41 39 00 0006 Chrome Two Handle Kitchen Faucet With Spray, Three Hole Installation, 8" Center (Delta 2402LF-LHP+H215)
152 $565.87EA
Installation =x x 505.94
FactorUnit PriceQuantity Total
210.81 1.2000 2.00
Demolition x x = 59.93 49.94 1.2000 1.00
removal of existing and installation of new.
22 42 13 13 0026 2 Piece Tank Type, Pressure Assisted, Siphon Jet, Floor Mounted, Back Outlet, Handicap Accessible, Elongated Vitreous China Water Closet (American Standard Yorkville™ ADA)
153 $2,811.37EA
Installation =x x 2,686.73
FactorUnit PriceQuantity Total
1,119.47 1.2000 2.00
Demolition x x = 124.64 103.87 1.2000 1.00
remove existing and install new ADA toilet
22 42 16 13 0009 27" x 20" Wheelchair Accessible, Vitreous China Wall Hung Lavatory (American Standard Wheel Chair Users)
154 $1,701.89EA
Installation =x x 1,621.58
FactorUnit PriceQuantity Total
675.66 1.2000 2.00
Demolition x x = 80.30 66.92 1.2000 1.00
remove existing and install new ADA sink, faucet, and drain cover. 22 42 19 00 0027 3 Piece Tub/Shower Surrounds, 32" x 72" Side Walls, 48" x 72" Back, (Swanstone SK-324872)
155 $8,454.49EA
Installation =x x 8,071.78
FactorUnit PriceQuantity Total
3,363.24 1.2000 2.00
Demolition x x = 382.72 318.93 1.2000 1.00
new tub/shower for bathrooms
22 42 39 00 0042 Single Supply EcoPower® Faucet, Polished Chrome Finish (Toto TEL3LS10#CP)
156 $1,885.78EA
Installation =x x 1,885.78
FactorUnit PriceQuantity Total
785.74 1.2000 2.00
ADA sink, faucet, and drain cover.

Page 15 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
570
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 22
22 42 39 00 0064 Three Lever Handle, Chrome Shower And Tub Filler (American Standard Colony Soft 3375.502)
157 $741.02EA
Installation =x x 636.98
FactorUnit PriceQuantity Total
265.41 1.2000 2.00
Demolition x x = 104.04 43.35 1.2000 2.00
per plans
22 42 39 00 0064 0147 For Faucet With Metal Cross Handles, Add158 $109.80EA Installation =x x 109.80
FactorUnit PriceQuantity Total

45.75 1.2000 2.00
22 42 39 00 0211 Lavatory Protective Enclosure (IPS Truebro Lav Shield)159 $390.86EA Installation =x x 390.86
FactorUnit PriceQuantity Total
162.86 1.2000 2.00
drain cover for ADA kitchen and bathroom sink
22 42 39 00 0218 1/2" NPT x 3/8" Compression Chrome, Quarter Turn Dual Angle Stop (SharkBite 25558)
160 $680.78EA
Installation =x x 580.08
FactorUnit PriceQuantity Total

48.34 1.2000 10.00
Demolition x x = 100.70 10.49 1.2000 8.00
new angle stops installed in bathrooms and kitchens
$130,110.56Subtotal for Section - 22
Section - 23
23 09 23 53 0284 Scheduling Program, HVAC (AHU, RTU, AC Units, Etcetera) Programming Measures
161 $8,755.06EA
Installation =x x 8,755.06
FactorUnit PriceQuantity Total
3,647.94 1.2000 2.00
required setup, balancing, and charging for new system
23 31 13 16 0063 4" Diameter, 26 Gauge, Seal Class C, Galvanized Sheet Metal Round And Flat-Oval Connector
162 $3,117.60EA
Installation =x x 3,117.60
FactorUnit PriceQuantity Total

17.32 1.2000 150.00
exhaust ducting per plans
23 33 13 13 0006 12" Diameter Radial Opposed Blade Damper Round, Steel Construction, Manual Operated
163 $696.79EA
Installation =x x 682.22
FactorUnit PriceQuantity Total
142.13 1.2000 4.00
Demolition x x = 14.57 12.14 1.2000 1.00
HVAC per plans
23 33 46 00 0008 12" Diameter Flexible Duct, R8.0 Insulated With Polyester Inner Liner Over Fiberglass Insulation And Metallized Outer Jacket
164 $12,610.20LF
Installation =x x 11,491.20
FactorUnit PriceQuantity Total

21.28 1.2000 450.00
Demolition x x = 1,119.00 3.73 1.2000 250.00
HVAC per plans - exhaust ducting
23 33 46 00 0020 12" Diameter Flexible Duct Collar, Spin In Type, Sheet Metal, With Damper165 $739.63EA Installation =x x 706.03
FactorUnit PriceQuantity Total

98.06 1.2000 6.00
Demolition x x = 33.60 14.00 1.2000 2.00
HVAC per plans

Page 16 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
571
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 23
23 34 16 00 0272 109 CFM, Ceiling/Wall Mounted, Metal Intake Grille, Heavy Duty/Continuous Operation Exhaust Fan (Broan® LoSone® Ventilator L100MG) 166 $2,212.13EA
Installation =x x 2,168.35
FactorUnit PriceQuantity Total
451.74 1.2000 4.00
Demolition x x = 43.78 36.48 1.2000 1.00
Laundry room and bathroom exhaust fan per plans
23 54 16 13 0007 120 MBH, 2,000 CFM Up/Horizontal Flow Multi-Speed, Two Stage 96% AFUE Gas FurnaceBlower cooling capacity up to 5 tons.
167 $15,925.85EA
Installation =x x 15,770.64
FactorUnit PriceQuantity Total
2,628.44 1.2000 5.00
Demolition x x = 155.21 129.34 1.2000 1.00
per plans. wall mounted furnaces
$44,057.26Subtotal for Section - 23
Section - 26
26 01 20 91 0002 Lock Out/Tag Out Local DisconnectExcludes tag or padlock See CSI section 26 01 20 91-0004 for padlock, 26 01 20 91-0005 for tag(s). 168 $590.94EA
Installation =x x 590.94
FactorUnit PriceQuantity Total

32.83 1.2000 15.00
LOTO of existing circuits
26 05 19 16 0402 #12 AWG, 3 Conductors, 600 Volt, Type NM, Copper, Non-Metallic Sheathed Cable
169 $24,763.20MLF
Installation =x x 24,763.20
FactorUnit PriceQuantity Total
4,127.20 1.2000 5.00
for new electrical runs per plans
26 05 19 16 0402 0377 For Installation In Wood Stud Wall (Includes Drilling), Add170 $1,795.14 Installation =x x 1,795.14
FactorUnit PriceQuantity Total
299.19 1.2000 5.00
26 09 23 00 0144 Wall Switch Replacement Occupancy Sensor, Single GangIncludes integral occupancy sensor and relay.
171 $1,483.80EA
Installation =x x 1,483.80
FactorUnit PriceQuantity Total
123.65 1.2000 10.00
per plans
26 09 23 00 0270 Passive Infrared, Wall Switch Mounted, Wired Occupancy Sensor (Encelium PW-100-24)Excludes GB II cable.
172 $725.28EA
Installation =x x 725.28
FactorUnit PriceQuantity Total
302.20 1.2000 2.00
for bathrooms
26 24 13 00 0213 800 Amperes, 480 Volt, 4 Wire, Switchboard Incoming No Switch Circuit173 $6,313.51EA Installation =x x 5,324.36
FactorUnit PriceQuantity Total
4,436.97 1.2000 1.00
Demolition x x = 989.15 824.29 1.2000 1.00
for new main panel to new units subpanels
26 24 16 00 0470 200 Ampere Rating, Main Breaker, Indoor, 42 Circuit, 4 Wire, 120/208 Volt, Assembled Panelboard With 20 Ampere, 1 Pole Plug-In Breakers 174 $8,743.93EA
Installation =x x 7,651.92
FactorUnit PriceQuantity Total
3,188.30 1.2000 2.00
Demolition x x = 1,092.01 910.01 1.2000 1.00
1 new sub panel for each unit

Page 17 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
572
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 26
26 27 13 00 0125 Single Phase M-90 Meter, Socket, NEMA 3R Enclosure175 $8,033.33EA Installation =x x 7,705.73
FactorUnit PriceQuantity Total
1,070.24 1.2000 6.00
Demolition x x = 327.60 54.60 1.2000 5.00
installation of new meters for building
26 27 26 00 0009 20 Amperes, 1 Gang, GFI, Duplex Receptacle Assembly176 $5,103.00EA Installation =x x 4,273.08
FactorUnit PriceQuantity Total
101.74 1.2000 35.00
Demolition x x = 829.92 34.58 1.2000 20.00
All new GFI outlets throughout per clients request
26 27 26 00 0125 20 Amperes, 125 Volt Single Specification Grade Tamper Resistant ReceptaclePass & Seymour TR5351.
177 $2,554.46EA
Installation =x x 2,073.98
FactorUnit PriceQuantity Total

39.28 1.2000 44.00
Demolition x x = 480.48 9.10 1.2000 44.00
all new outlets throughout per clients request
26 27 26 00 0138 1 Gang, 20 Amperes, 120/277 Volt, SPST, Switch Assembly178 $3,774.00EA Installation =x x 2,736.60
FactorUnit PriceQuantity Total

91.22 1.2000 25.00
Demolition x x = 1,037.40 34.58 1.2000 25.00
25 switches total in both units
26 51 19 00 0269 2' x 2', 4,000 Lumens, Surface Mount, Volumetric LED Fixture (Lithonia 2RTX2)179 $7,035.98EA Installation =x x 6,106.46
FactorUnit PriceQuantity Total
212.03 1.2000 24.00
Demolition x x = 929.52 38.73 1.2000 20.00
new LED lights throughout
26 51 19 00 0477 2-1/2" Diameter x 15-1/2" High, Polished Nickel, LED Wall Sconce (Hudson Valley Lighting SHAW 1200-PN)
180 $1,281.65EA
Installation =x x 1,194.29
FactorUnit PriceQuantity Total
497.62 1.2000 2.00
Demolition x x = 87.36 36.40 1.2000 2.00
2 new wall sconces per plans in bathrooms
$72,198.22Subtotal for Section - 26
Section - 31
31 05 16 00 0002 #2 Stone Aggregate Fill (1-1/2" To 2-1/2" Clean)181 $1,650.60CY Installation =x x 1,650.60
FactorUnit PriceQuantity Total

55.02 1.2000 25.00
4" deep, 200 LF, 2' wide base for backfill for trenching. 20 CY for footings, and slabs 31 05 16 00 0002 0053 For Up To 8, Add182 $66.00
Installation =x x 66.00
FactorUnit PriceQuantity Total

11.00 1.2000 5.00
31 11 00 00 0010 Clearing By Machine - Light Brush Without Grub183 $202.36ACR Installation =x x 202.36
FactorUnit PriceQuantity Total
337.26 1.2000 0.50
clear out weeds in back yard
31 11 00 00 0019 Hand Loading Of Cleared And Grubbed Material184 $976.32CY Installation =x x 976.32
FactorUnit PriceQuantity Total

40.68 1.2000 20.00
clear out weeds in back yard

Page 18 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
573
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 31
31 23 16 13 0007 Excavation For Trenching By Hand In SoilIncludes stockpiling excess materials and trimming sides and bottom of trench.
185 $4,027.50CY
Installation =x x 4,027.50
FactorUnit PriceQuantity Total
134.25 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0011 Backfilling or Placing Subbase for Trenches with Imported or Stockpiled Materials by Hand
186 $1,118.70CY
Installation =x x 1,118.70
FactorUnit PriceQuantity Total

37.29 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 13 0014 Compaction of Fill or Subbase for Trenches by Hand187 $1,262.10CY Installation =x x 1,262.10
FactorUnit PriceQuantity Total

42.07 1.2000 25.00
20" deep, 200 LF, 2' wide
31 23 16 36 0009 Excavation For Building Foundations And Other Structures By Hand in Soil188 $7,249.50CY Installation =x x 7,249.50
FactorUnit PriceQuantity Total
134.25 1.2000 45.00
for footings
31 23 16 36 0019 Backfilling Around Building Foundations And Other Structures By Hand189 $1,534.32CY Installation =x x 1,534.32
FactorUnit PriceQuantity Total

63.93 1.2000 20.00
for footings
31 23 16 36 0022 Compaction Of Fill Or Subbase For Building Foundations and Other Structures by Hand
190 $2,271.24CY
Installation =x x 2,271.24
FactorUnit PriceQuantity Total

42.06 1.2000 45.00
for footings
$20,358.64Subtotal for Section - 31
Section - 32
32 16 13 13 0016 6" x 12" Cast In Place Concrete Gutter With 6" Curb And Face - Straight191 $225.96LF Installation =x x 154.98
FactorUnit PriceQuantity Total

25.83 1.2000 5.00
Demolition x x = 70.98 11.83 1.2000 5.00
for parking lot ADA modifications
32 16 13 13 0016 0077 For Up To 20, Add192 $105.42MOD Installation =x x 105.42
FactorUnit PriceQuantity Total

17.57 1.2000 5.00
32 16 23 00 0002 4" Cast In Place Concrete Sidewalk193 $212.16SF Installation =x x 212.16
FactorUnit PriceQuantity Total

8.84 1.2000 20.00
for parking lot ADA modifications
32 16 23 00 0002 0094 For Up To 100, Add194 $92.16 Installation =x x 92.16
FactorUnit PriceQuantity Total

3.84 1.2000 20.00
32 16 23 00 0008 Finish Concrete Handicap Drop Section In SidewalkExcludes patterned (tactile) finish.
195 $167.12EA
Installation =x x 167.12
FactorUnit PriceQuantity Total
139.27 1.2000 1.00
for parking lot ADA modifications

Page 19 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
574
Contractor's Price Proposal - Detail Continues..

Work Order Title:

Work Order Number: 124236.00
OHA - 1130 Unit Remodel
Section - 32
32 17 23 13 0074 Solid Area, Painted Pavement Marking For Parking AreasUse task for lines >12" wide, stop bars, transverse lines, diagonal lines, crossing lanes, etc. 196 $102.48SF
Installation =x x 102.48
FactorUnit PriceQuantity Total

4.27 1.2000 20.00
for parking lot ADA modifications
32 17 23 13 0088 Handicap Symbol For Van Parking Stalls, Painted Pavement Marking For Parking AreasApproximate overall dimensions: 4-1/3' width x 5' height. White or blue symbol. Excludes striping.
197 $52.66EA
Installation =x x 52.66
FactorUnit PriceQuantity Total

43.88 1.2000 1.00
for parking lot ADA modifications
32 17 26 00 0003 Embedded, VPC Truncated Dome Detectable Warning SurfaceAlso raised strips or directional bars. All colors.
198 $650.04SF
Installation =x x 650.04
FactorUnit PriceQuantity Total

54.17 1.2000 10.00
new truncated domes per
32 31 13 13 0010 12" Diameter Hole, Auger By Machine Fence Post Hole In Soil199 $80.75VLF Installation =x x 80.75
FactorUnit PriceQuantity Total

22.43 1.2000 3.00
ADA parking sign
32 31 13 13 0027 12" Diameter, Concrete Fill For Post Hole200 $89.28VLF Installation =x x 89.28
FactorUnit PriceQuantity Total

24.80 1.2000 3.00
ADA parking sign
$1,778.03Subtotal for Section - 32
Proposal Total
This total represents the correct total for the proposal. Any discrepancy between line totals, sub-totals and the proposal total is due to rounding.
$604,505.00
The Percentage of NPP on this Proposal: %

Page 20 of 20 ends

1/9/2024
Contractor's Price Proposal - Detail
575
Subcontractor Listing
124236.00
OHA - 1130 Unit Remodel
CA-R7-GB-101723-MDJIQC Master Contract #:

Work Order #:

Owner PO #:

Title:

Re:

January 09, 2024Date:

Proposal Value:

Contractor: MDJ Management
$604,505.00
%DutiesName of Contractor Amount
Refined Construction 86.02$520,000.00

6.00

Page 1 of 1 ends

1/9/2024
Subcontractor Listing
576

General Conditions for Construction
Contracts - Public Housing Programs
U.S. Department of Housing and Urban
Development
Office of Public and Indian Housing
OMB Approval No. 2577-0157 (exp. 11/30/202 3)
Applicability. This form is applicable to any
construction/development contract greater than $250,000.

Public reporting burden for this collection of information is estimated to average 1 hour. This includes the time for collecting, reviewing, and reporting the data. The information requested is required to obtain a benefit. This form includes those clauses required by OMB's common rule on grantee procurement, implemented at HUD in 2 CFR 200, and those requirements set forth in Section 3 of the Housing and Urban Development Act of 1968 and its amendment by the Housing and Community Development Act of 1992, implemented by HUD at 24 CFR Part 75. The form is required for construction contracts awarded by Public Housing Agencies (PHAs). The form is used by Housing Authorities in solicitations to provide necessary contract clauses. If the form were not used, PHAs would be unable to enforce their contracts. There are no assurances of confidentiality. HUD may not conduct or sponsor, and an applicant is not required to respond to a collection of information unless it displays a currently valid OMB control number.

T
Clause Page Clause Page

1. Definitions 2 Administrative Requirements

2. Contractor’s Responsibility for Work 2 25. Contract Period 9

3. Architect’s Duties, Responsibilities and Authority 2 26. Order of Precedence 9

4. Other Contracts 3 27. Payments 9
Construction Requirements 28. Contract Modifications 10

5. Preconstruction Conference and Notice to Proceed 3 29. Changes 10

6. Construction Progress Schedule 3 30. Suspension of Work 11

7. Site Investigation and Conditions Affecting the Work 3 31. Disputes 11

8. Differing Site Conditions 4 32. Default 11

9. Specifications and Drawings for Construction 4 33. Liquidated 12

10. As-Built Drawings 5 34. Termination of Convenience 12

11. Material and Workmanship 5 35. Assignment of Contract 12

12. Permits and Codes 5 36. Insurance 12

13. Health, Safety, and Accident Prevention 6 37. Subcontracts 13

14. Temporary Buildings and Transportation Materials 6 38. Subcontracting with Small and Minority Firms, Women’s Business Enterprise, and Labor Surplus Area Firms 13

15. Availability and Use of Utility Services 6 39. Equal Employment Opportunity 13

16. Protection of Existing Vegetation, Structures,
Equipment, Utilities, and Improvements 6

40. Employment, Training, and Contracting Opportunities for Low-Income Persons, Section 3 of the Housing and
Urban Development Act of 1968
14 17. Temporary Buildings and Transportation Materials 7 41. Interest of Members of Congress 15

18. Clean Air and Water 7 42. Interest of Members, Officers, or Employees and Former Members, Officers, or Employees
15 19. Energy Efficiency 7 43. Limitations on Payments Made to Influence 15

20. Inspection and Acceptance of Construction 7 44. Royalties and Patents 15

21. Use and Possession Prior to 8 45. Examination and Retention of Contractor’s Records 15

22. Warranty of Title 8 46. Labor Standards-Davis-Bacon and Related Acts 15

23. Warranty of 8 47. Non-Federal Prevailing Wage Rates 19

24. Prohibition Against 9 48. Procurement of Recovered 19 Liens Materials
Previous editions are obsolete Page 1 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
577

1. Definitions (a) The Contractor shall furnish all necessary labor, materials, tools, equipment, and transportation necessary (a) “Architect” means the person or other entity engaged by for performance of the work. The Contractor shall also the PHA to perform architectural, engineering, design, furnish all necessary water, heat, light, and power not and other services related to the work as provided for in made available to the Contractor by the PHA pursuant to the contract. When a PHA uses an engineer to act in this the clause entitled Availability and Use of Utility Services capacity, the terms “architect” and “engineer” shall be herein. synonymous. The Architect shall serve as a technical (b) The Contractor shall perform on the site, and with its own representative of the Contracting Officer. The Architect’s organization, work equivalent to at least [ ] (12 percent authority is as set forth elsewhere in this contract. unless otherwise indicated) of the total amount of work to (b) “Contract” means the contract entered into between the be performed under the order. This percentage may be PHA and the Contractor. It includes the forms of Bid, the reduced by a supplemental agreement to this order if, Bid Bond, the Performance and Payment Bond or Bonds during performing the work, the Contractor requests a or other assurance of completion, the Certifications, reduction and the Contracting Officer determines that the Representations, and Other Statements of Bidders (form reduction would be to the advantage of the PHA.

HUD-5370), these General Conditions of the Contract for (c) At all times during performance of this contract and until Construction (form HUD-5370), the applicable wage rate the work is completed and accepted, the Contractor shall determinations from the U.S. Department of Labor, any directly superintend the work or assign and have on the special conditions included elsewhere in the contract, the work site a competent superintendent who is satisfactory specifications, and drawings. It includes all formal to the Contracting Officer and has authority to act for the changes to any of those documents by addendum, Contractor. change order, or other modification. (d) The Contractor shall be responsible for all damages to (c) “Contracting Officer” means the person delegated the au- persons or property that occur as a result of the thority by the PHA to enter into, administer, and/or Contractor’s fault or negligence, and shall take proper terminate this contract and designated as such in writing safety and health precautions to protect the work, the to the Contractor. The term includes any successor workers, the public, and the property of others. The Contracting Officer and any duly authorized Contractor shall hold and save the PHA, its officers and representative of the Contracting Officer also designated agents, free and harmless from liability of any nature in writing. The Contracting Officer shall be deemed the occasioned by the Contractor’s performance. The authorized agent of the PHA in all dealings with the Contractor shall also be responsible for all materials Contractor. delivered and work performed until completion and (d) “Contractor” means the person or other entity entering acceptance of the entire work, except for any completed into the contract with the PHA to perform all of the work unit of work which may have been accepted under the required under the contract. contract.
(e) “Drawings” means the drawings enumerated in the (e) The Contractor shall lay out the work from base lines and schedule of drawings contained in the Specifications and bench marks indicated on the drawings and be as described in the contract clause entitled Specifications responsible for all lines, levels, and measurements of all and Drawings for Construction herein. work executed under the contract. The Contractor shall (f) “HUD” means the United States of America acting through verify the figures before laying out the work and will be the Department of Housing and Urban Development held responsible for any error resulting from its failure to including the Secretary, or any other person designated to do so. act on its behalf. HUD has agreed, subject to the provisions of an (f) The Contractor shall confine all operations (including Annual Contributions Terms and Conditions (ACC), to storage of materials) on PHA premises to areas provide financial assistance to the PHA, which includes authorized or approved by the Contracting Officer. assistance in financing the work to be performed under (g) The Contractor shall at all times keep the work area, this contract. As defined elsewhere in these General including storage areas, free from accumulations of Conditions or the contract documents, the determination waste materials. After completing the work and before of HUD may be required to authorize changes in the work final inspection, the Contractor shall (1) remove from the or for release of funds to the PHA for payment to the premises all scaffolding, equipment, tools, and materials Contractor. Notwithstanding HUD’s role, nothing in this (including rejected materials) that are not the property of contract shall be construed to create any contractual the PHA and all rubbish caused by its work; (2) leave the relationship between the Contractor and HUD. work area in a clean, neat, and orderly condition (g) “Project” means the entire project, whether construction satisfactory to the Contracting Officer; (3) perform all or rehabilitation, the work for which is provided for in specified tests; and, (4) deliver the installation in whole or in part under this contract. complete and operating condition. (h) “PHA” means the Public Housing Agency organized (h) The Contractor’s responsibility will terminate when all under applicable state laws which is a party to this work has been completed, the final inspection made, and contract. the work accepted by the Contracting Officer. The (j) “Specifications” means the written description of the Contractor will then be released from further obligation technical requirements for construction and includes the except as required by the warranties specified elsewhere criteria and tests for determining whether the in the contract. requirements are met.
(l) “Work” means materials, workmanship, and manufacture 3. Architect’s Duties, Responsibilities, and Authority and fabrication of components.
(a) The Architect for this contract, and any successor, shall

2. Contractor’s Responsibility for Work be designated in writing by the Contracting Officer.

Previous editions are obsolete Page 2 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
578
(b) The Architect shall serve as the Contracting Officer’s technical representative with respect to architectural, 6. Construction Progress Schedule engineering, and design matters related to the work performed under the contract. The Architect may provide (a) The Contractor shall, within five days after the work direction on contract performance. Such direction shall be commences on the contract or another period of time within the scope of the contract and may not be of a determined by the Contracting Officer, prepare and nature which: (1) institutes additional work outside the submit to the Contracting Officer for approval three copies scope of the contract; (2) constitutes a change as defined of a practicable schedule showing the order in which the in the Changes clause herein; (3) causes an increase or Contractor proposes to perform the work, and the dates decrease in the cost of the contract; (4) alters the on which the Contractor contemplates starting and Construction Progress Schedule; or (5) changes any of completing the several salient features of the work the other express terms or conditions of the contract. (including acquiring labor, materials, and equipment). The (c) The Architect’s duties and responsibilities may include but schedule shall be in the form of a progress chart of shall not be limited to: suitable scale to indicate appropriately the percentage of (1) Making periodic visits to the work site, and on the work scheduled for completion by any given date during basis of his/her on-site inspections, issuing written the period. If the Contractor fails to submit a schedule reports to the PHA which shall include all observed within the time prescribed, the Contracting Officer may deficiencies. The Architect shall file a copy of the withhold approval of progress payments or take other report with the Contractor’s designated representative remedies under the contract until the Contractor submits at the site; the required schedule.
(2) Making modifications in drawings and technical (b) The Contractor shall enter the actual progress on the specifications and assisting the Contracting Officer in chart as required by the Contracting Officer, and the preparation of change orders and other contract immediately deliver three copies of the annotated modifications for issuance by the Contracting Officer; schedule to the Contracting Officer. If the Contracting (3) Reviewing and making recommendations with respect Officer determines, upon the basis of inspection to - (i) the Contractor’s construction progress conducted pursuant to the clause entitled Inspection and schedules; (ii) the Contractor’s shop and detailed Acceptance of Construction, herein that the Contractor is drawings; (iii) the machinery, mechanical and other not meeting the approved schedule, the Contractor shall equipment and materials or other articles proposed take steps necessary to improve its progress, including for use by the Contractor; and, (iv) the Contractor’s those that may be required by the Contracting Officer, price breakdown and progress payment estimates; without additional cost to the PHA. In this circumstance, and, the Contracting Officer may require the Contractor to (4) Assisting in inspections, signing Certificates of increase the number of shifts, overtime operations, days Completion, and making recommendations with of work, and/or the amount of construction plant, and to respect to acceptance of work completed under the submit for approval any supplementary schedule or contract. schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of

4. Other Contracts progress will be regained.
(c) Failure of the Contractor to comply with the requirements The PHA may undertake or award other contracts for of the Contracting Officer under this clause shall be additional work at or near the site of the work under this grounds for a determination by the Contracting Officer that contract. The Contractor shall fully cooperate with the the Contractor is not prosecuting the work with sufficient other contractors and with PHA employees and shall diligence to ensure completion within the time carefully adapt scheduling and performing the work under specified in the Contract. Upon making this this contract to accommodate the additional work, heeding determination, the Contracting Officer may terminate the any direction that may be provided by the Contracting Contractor’s right to proceed with the work, or any Officer. The Contractor shall not commit or permit any act separable part of it, in accordance with the Default clause that will interfere with the performance of work by any of this contract. other contractor or by PHA employees

7. Site Investigation and Conditions Affecting the Work Construction Requirements (a) The Contractor acknowledges that it has taken steps

5. Pre-construction Conference and Notice to Proceed reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself (a) Within ten calendar days of contract execution, and prior as to the general and local conditions which can affect the to the commencement of work, the Contractor shall work or its cost, including but not limited to, (1) conditions attend a preconstruction conference with representatives bearing upon transportation, disposal, handling, and of the PHA, its Architect, and other interested parties storage of materials; (2) the availability of labor, water, convened by the PHA. The conference will serve to electric power, and roads;(3) uncertainties of weather, acquaint the participants with the general plan of the river stages, tides, or similar physical conditions at the construction operation and all other requirements of the site; (4) the conformation and conditions of the ground; contract. The PHA will provide the Contractor with the and (5) the character of equipment and facilities needed date, time, and place of the conference. preliminary to and during work performance. The (b) The contractor shall begin work upon receipt of a written Contractor also acknowledges that it has satisfied itself as Notice to Proceed from the Contracting Officer or to the character, quality, and quantity of surface and designee. The Contractor shall not begin work prior to subsurface materials or obstacles to be encountered receiving such notice. insofar as this information is
Previous editions are obsolete Page 3 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
579
reasonably ascertainable from an inspection of the site, promptly submitted to the Contracting Officer, who shall including all exploratory work done by the PHA, as well as from the drawings and specifications made a part of
this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph
will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully
perform the work without additional expense to the PHA. (b) The PHA assumes no responsibility for any conclusions or interpretations made by the Contractor based on the
information made available by the PHA. Nor does the
PHA assume responsibility for any understanding
reached or representation made concerning conditions
which can affect the work by any of its officers or agents before the execution of this contract, unless that
understanding or representation is expressly stated in
this contract.

8. Differing Site Conditions
(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site(s), of an unusual nature, which differ materially from those ordinarily
encountered and generally recognized as inhering in work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site
conditions promptly after receiving the notice. Work shall not proceed at the affected site, except at the
Contractor’s risk, until the Contracting Officer has
provided written instructions to the Contractor. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time
required for, performing any part of the work under this contract, whether or not changed as a result of the
conditions, the Contractor shall file a claim in writing to the PHA within ten days after receipt of such instructions and, in any event, before proceeding with the work. An
equitable adjustment in the contract price, the delivery schedule, or both shall be made under this clause and
the contract modified in writing accordingly.
(c) No request by the Contractor for an equitable
adjustment to the contract under this clause shall be
allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in (a) above for giving written notice may be extended by the Contracting Officer.
(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

9. Specifications and Drawings for Construction
(a) The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything
mentioned in the specifications and not shown on the
drawings, or shown on the drawings and not mentioned
in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between
drawings and specifications, the specifications shall
govern. In case of discrepancy in the figures, in the
drawings, or in the specifications, the matter shall be promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense. The Contracting Officer shall furnish from time to time such detailed drawings and other information as considered necessary, unless
otherwise provided.
(b) Wherever in the specifications or upon the drawings the words “directed”, “required”, “ordered”, “designated”,
“prescribed”, or words of like import are used, it shall be understood that the “direction”, “requirement”, “order”, “designation”, or “prescription”, of the Contracting Officer is intended and similarly the words “approved”, “acceptable”, “satisfactory”, or words of like import shall mean “approved by”, or “acceptable to”, or “satisf actory to” the Contracting Officer, unless otherwise expressly stated.
(c) Where “as shown” “as indicated”, “as detailed”, or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this
contract unless stated otherwise. The word “provided” as used herein shall be understood to mean “provide
complete in place” that is “furnished and installed”.
(d) “Shop drawings” means drawings, submitted to the PHA by the Contractor, subcontractor, or any lower tier
subcontractor, showing in detail (1) the proposed fabrication and assembly of structural elements and (2) the installation (i.e., form, fit, and attachment details) of materials of equipment. It includes drawings, diagrams, layouts,
schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract. The PHA may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.
(e) If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with other contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor’s approval may be returned for resubmission.

The Contracting Officer will indicate an approval or
disapproval of the shop drawings and if not approved as submitted shall indicate the PHA’s reasons therefore. Any work done before such approval shall be at the Contractor’s risk. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract, except with respect to
variations described and approved in accordance with (f) below.
(f) If shop drawings show variations from the contract
requirements, the Contractor shall describe such variations in writing, separate from the drawings, at the time of
submission. If the Architect approves any such variation and the Contracting Officer concurs, the Contracting Officer shall issue an appropriate modification to the contract, except that, if the variation is minor or does not involve a change in price or in time of performance, a modification need not be issued. (g) It shall be the responsibility of the Contractor to make timely requests of the PHA for such large scale and full size drawings, color schemes, and other additional information, not already in his possession, which shall be
Previous editions are obsolete Page 4 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
580
required in the planning and production of the work. Such machinery and mechanical and other equipment. requests may be submitted as the need arises, but each When required by this contract or by the Contracting such request shall be filed in ample time to permit Officer, the Contractor shall also obtain the appropriate action to be taken by all parties involved so Contracting Officer’s approval of the material or as to avoid delay. articles which the Contractor contemplates (h) The Contractor shall submit to the Contracting Officer for incorporating into the work. When requesting approval four copies (unless otherwise indicated) of all approval, the Contractor shall provide full information shop drawings as called for under the various headings concerning the material or articles. Machinery, of these specifications. Three sets (unless otherwise equipment, material, and articles that do not have the indicated) of all shop drawings, will be retained by the required approval shall be installed or used at the risk PHA and one set will be returned to the Contractor. As of subsequent rejection. required by the Contracting Officer, the Contractor, upon (2) When required by the specifications or the completing the work under this contract, shall furnish a Contracting Officer, the Contractor shall submit complete set of all shop drawings as finally approved. appropriately marked samples (and certificates These drawings shall show all changes and revisions related to them) for approval at the Contractor’s made up to the time the work is completed and accepted. expense, with all shipping charges prepaid. The (i) This clause shall be included in all subcontracts at any tier. Contractor shall label, or otherwise properly mark on It shall be the responsibility of the Contractor to ensure the container, the material or product represented, its that all shop drawings prepared by subcontractors are place of origin, the name of the producer, the submitted to the Contracting Officer. Contractor’s name, and the identification of the construction project for which the material or product

10. As-Built Drawings is intended to be used.
(3) Certificates shall be submitted in triplicate, describing (a) “As-built drawings,” as used in this clause, means each sample submitted for approval and certifying drawings submitted by the Contractor or subcontractor at that the material, equipment or accessory complies any tier to show the construction of a particular structure with contract requirements. The certificates shall or work as actually completed under the contract. “As-built include the name and brand of the product, name of drawings” shall be synonymous with “Record manufacturer, and the location where produced. drawings.” (4) Approval of a sample shall not constitute a waiver of (b) As required by the Contracting Officer, the Contractor the PHA right to demand full compliance with contract shall provide the Contracting Officer accurate information requirements. Materials, equipment and accessories to be used in the preparation of permanent as-built may be rejected for cause even though samples have drawings. For this purpose, the Contractor shall record on been approved. one set of contract drawings all changes from the (5) Wherever materials are required to comply with installations originally indicated, and record final locations recognized standards or specifications, such of underground lines by depth from finish grade and by specifications shall be accepted as establishing the accurate horizontal offset distances to permanent surface technical qualities and testing methods, but shall not improvements such as buildings, curbs, or edges of govern the number of tests required to be made nor walks. modify other contract requirements. The Contracting (c) This clause shall be included in all subcontracts at any Officer may require laboratory test reports on items tier. It shall be the responsibility of the Contractor to submitted for approval or may approve materials on ensure that all as-built drawings prepared by the basis of data submitted in certificates with subcontractors are submitted to the Contracting Officer. samples. Check tests will be made on materials delivered for use only as frequently as the Contracting

11. Material and Workmanship Officer determines necessary to insure compliance of materials with the specifications. The Contractor will
(a) All equipment, material, and articles furnished under this assume all costs of retesting materials which fail to contract shall be new and of the most suitable grade for meet contract requirements and/or testing materials the purpose intended, unless otherwise specifically offered in substitution for those found deficient. provided in this contract. References in the contract to (6) After approval, samples will be kept in the Project equipment, material, articles, or patented processes by office until completion of work. They may be built into trade name, make, or catalog number, shall be regarded the work after a substantial quantity of the materials as establishing a standard of quality and shall not be they represent has been built in and accepted. construed as limiting competition. The Contractor may, at (c) Requirements concerning lead-based paint. The its option, use any equipment, material, article, or Contractor shall comply with the requirements concerning process that, in the judgment of, and as approved by the lead-based paint contained in the Lead-Based Paint Contracting Officer, is equal to that named in the Poisoning Prevention Act (42 U.S.C. 4821-4846) as specifications, unless otherwise specifically provided in implemented by 24 CFR Part 35. this contract.
(b) Approval of equipment and materials. 12. Permits and Codes (1) The Contractor shall obtain the Contracting Officer’s approval of the machinery and mechanical and other (a) The Contractor shall give all notices and comply with all equipment to be incorporated into the work. When applicable laws, ordinances, codes, rules and regulations. requesting approval, the Contractor shall furnish to the Notwithstanding the requirement of the Contractor to Contracting Officer the name of the manufacturer, the comply with the drawings and specifications in the model number, and other information concerning the contract, all work installed shall comply with all applicable performance, capacity, nature, and rating of the codes and regulations as amended by any Previous editions are obsolete Page 5 of 19 form HUD -5370 (1/2014) Replaces form HUD-5370-A
581
waivers. Before installing the work, the Contractor shall examine the drawings and the specifications for 14. Temporary Heating compliance with applicable codes and regulations
bearing on the work and shall immediately report any The Contractor shall provide and pay for temporary discrepancy it may discover to the Contracting Officer. heating, covering, and enclosures necessary to properly Where the requirements of the drawings and protect all work and materials against damage by specifications fail to comply with the applicable code or dampness and cold, to dry out the work, and to facilitate regulation, the Contracting Officer shall modify the the completion of the work. Any permanent heating contract by change order pursuant to the clause entitled equipment used shall be turned over to the PHA in the Changes herein to conform to the code or regulation. condition and at the time required by the specifications. (b) The Contractor shall secure and pay for all permits, fees, and licenses necessary for the proper execution and 15. Availability and Use of Utility Services completion of the work. Where the PHA can arrange for
the issuance of all or part of these permits, fees and (a) The PHA shall make all reasonably required amounts of licenses, without cost to the Contractor, the contract utilities available to the Contractor from existing outlets amount shall be reduced accordingly. and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each

13. Health, Safety, and Accident Prevention utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the PHA or, (a) In performing this contract, the Contractor shall: where the utility is produced by the PHA, at reasonable (1) Ensure that no laborer or mechanic shall be required rates determined by the Contracting Officer. The to work in surroundings or under working conditions Contractor shall carefully conserve any utilities furnished which are unsanitary, hazardous, or dangerous to without charge. his/her health and/or safety as determined under (b) The Contractor, at its expense and in a manner construction safety and health standards promulgated satisfactory to the Contracting Officer, shall install and by the Secretary of Labor by regulation; maintain all necessary temporary connections and (2) Protect the lives, health, and safety of other persons; distribution lines, and all meters required to measure the (3) Prevent damage to property, materials, supplies, and amount of each utility used for the purpose of equipment; and, determining charges. Before final acceptance of the work (4) Avoid work interruptions. by the PHA, the Contractor shall remove all the (b) For these purposes, the Contractor shall: temporary connections, distribution lines, meters, and (1) Comply with regulations and standards issued by the associated paraphernalia.

Secretary of Labor at 29 CFR Part 1926. Failure to
comply may result in imposition of sanctions pursuant 16. Protection of Existing Vegetation, Structures, to the Contract Work Hours and Safety Standards Act Equipment, Utilities, and Improvements (Public Law 91-54, 83 Stat. 96), 40 U.S.C. 3701 et
seq.; and (a) The Contractor shall preserve and protect all structures, (2) Include the terms of this clause in every subcontract equipment, and vegetation (such as trees, shrubs, and so that such terms will be binding on each grass) on or adjacent to the work site, which are not to be subcontractor. removed under this contract, and which do not (c) The Contractor shall maintain an accurate record of unreasonably interfere with the work required under this exposure data on all accidents incident to work performed contract. under this contract resulting in death, traumatic injury, (b) The Contractor shall only remove trees when specifically occupational disease, or damage to property, materials, authorized to do so, and shall avoid damaging vegetation supplies, or equipment, and shall report this data in the that will remain in place. If any limbs or branches of trees manner prescribed by 29 CFR Part are broken during performance of this contract, or by the 1904. careless operation of equipment, or by workmen, the (d) The Contracting Officer shall notify the Contractor of any Contractor shall trim those limbs or branches with a clean noncompliance with these requirements and of the cut and paint the cut with a tree-pruning compound as corrective action required. This notice, when delivered to directed by the Contracting Officer. the Contractor or the Contractor’s representative at the (c) The Contractor shall protect from damage all existing site of the work, shall be deemed sufficient notice of the improvements and utilities (1) at or near the work site and noncompliance and corrective action required. After (2) on adjacent property of a third party, the locations of receiving the notice, the Contractor shall immediately which are made known to or should be known by the take corrective action. If the Contractor fails or refuses to Contractor. Prior to disturbing the ground at the take corrective action promptly, the Contracting Officer construction site, the Contractor shall ensure that all may issue an order stopping all or part of the work until underground utility lines are clearly marked. satisfactory corrective action has been taken. The (d) The Contractor shall shore up, brace, underpin, secure, Contractor shall not base any claim or request for and protect as necessary all foundations and other parts equitable adjustment for additional time or money on any of existing structures adjacent to, adjoining, and in the stop order issued under these circumstances. vicinity of the site, which may be affected by the (e) The Contractor shall be responsible for its subcontractors’ excavations or other operations connected with the compliance with the provisions of this clause. The construction of the project.

Contractor shall take such action with respect to any (e) Any equipment temporarily removed as a result of work subcontract as the PHA, the Secretary of Housing and under this contract shall be protected, cleaned, and Urban Development, or the Secretary of Labor shall replaced in the same condition as at the time of award of direct as a means of enforcing such provisions. this contract.

Previous editions are obsolete Page 6 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
582
(f) New work which connects to existing work shall The contactor shall comply with the Clean Air Act, as correspond in all respects with that to which it connects amended, 42 USC 7401 et seq., the Federal Water and/or be similar to existing work unless otherwise Pollution Control Water Act, as amended, 33 U.S.C. 1251 required by the specifications. et seq., and standards issued pursuant thereto in the (g) No structural members shall be altered or in any way facilities in which this contract is to be performed. weakened without the written authorization of the
Contracting Officer, unless such work is clearly specified 19. Energy Efficiency in the plans or specifications.
(h) If the removal of the existing work exposes discolored or The Contractor shall comply with mandatory standards unfinished surfaces, or work out of alignment, such and policies relating to energy efficiency which are surfaces shall be refinished, or the material replaced as contained in the energy conservation plan issued in necessary to make the continuous work uniform and compliance with the Energy Policy and Conservation Act harmonious. This, however, shall not be construed to (Pub.L. 94-163) for the State in which the work under the require the refinishing or reconstruction of dissimilar contract is performed. finishes previously exposed, or finished surfaces in good condition, but in different planes or on different levels 20. Inspection and Acceptance of Construction when brought together by the removal of intervening work, unless such refinishing or reconstruction is (a) Definitions. As used in this clause - specified in the plans or specifications. (1) “Acceptance” means the act of an authorized (i) The Contractor shall give all required notices to any representative of the PHA by which the PHA approves adjoining or adjacent property owner or other party before and assumes ownership of the work performed under this the commencement of any work. contract. Acceptance may be partial or complete. (j) The Contractor shall indemnify and save harmless the (2) “Inspection” means examining and testing the work PHA from any damages on account of settlement or the performed under the contract (including, when loss of lateral support of adjoining property, any damages appropriate, raw materials, equipment, components, and from changes in topography affecting drainage, and from intermediate assemblies) to determine whether it all loss or expense and all damages for which the PHA conforms to contract requirements. may become liable in consequence of such injury or (3) “Testing” means that element of inspection that damage to adjoining and adjacent structures and their determines the properties or elements, including premises. functional operation of materials, equipment, or their (k) The Contractor shall repair any damage to vegetation, components, by the application of established scientific structures, equipment, utilities, or improvements, principles and procedures. including those that are the property of a third party, (b) The Contractor shall maintain an adequate inspection resulting from failure to comply with the requirements of system and perform such inspections as will ensure that this contract or failure to exercise reasonable care in the work performed under the contract conforms to performing the work. If the Contractor fails or refuses to contract requirements. All work is subject to PHA repair the damage promptly, the Contracting Officer may inspection and test at all places and at all reasonable have the necessary work performed and charge the cost times before acceptance to ensure strict compliance with to the Contractor. the terms of the contract.
(c) PHA inspections and tests are for the sole benefit of the

17. Temporary Buildings and Transportation of Materials PHA and do not: (1) relieve the Contractor of responsibility for providing adequate quality control
(a) Temporary buildings (e.g., storage sheds, shops, offices, measures; (2) relieve the Contractor of responsibility for sanitary facilities) and utilities may be erected by the loss or damage of the material before acceptance; (3) Contractor only with the approval of the Contracting constitute or imply acceptance; or, (4) affect the Officer and shall be built with labor and materials continuing rights of the PHA after acceptance of the furnished by the Contractor without expense to the PHA. completed work under paragraph (j) below.

The temporary buildings and utilities shall remain the (d) The presence or absence of the PHA inspector does not property of the Contractor and shall be removed by the relieve the Contractor from any contract requirement, nor Contractor at its expense upon completion of the work. is the inspector authorized to change any term or With the written consent of the Contracting Officer, the condition of the specifications without the Contracting buildings and utilities may be abandoned and need not Officer’s written authorization. All instructions and be removed. approvals with respect to the work shall be given to the (b) The Contractor shall, as directed by the Contracting Contractor by the Contracting Officer.

Officer, use only established roadways, or use temporary (e) The Contractor shall promptly furnish, without additional roadways constructed by the Contractor when and as charge, all facilities, labor, and material reasonably authorized by the Contracting Officer. When materials are needed for performing such safe and convenient transported in prosecuting the work, vehicles shall not be inspections and tests as may be required by the loaded beyond the loading capacity recommended by the Contracting Officer. The PHA may charge to the manufacturer of the vehicle or prescribed by any federal, Contractor any additional cost of inspection or test when state, or local law or regulation. When it is necessary to work is not ready at the time specified by the Contractor cross curbs or sidewalks, the Contractor shall protect them for inspection or test, or when prior rejection makes from damage. The Contractor shall repair or pay for the reinspection or retest necessary. The PHA shall perform repair of any damaged curbs, sidewalks, or roads. all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and

18. Clean Air and Water performance tests shall be performed as described in the contract.

Previous editions are obsolete Page 7 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
583
(f) The PHA may conduct routine inspections of the occupied without proper remuneration therefore. If prior construction site on a daily basis. possession or use by the PHA delays the progress of the (g) The Contractor shall, without charge, replace or correct work or causes additional expense to the Contractor, an work found by the PHA not to conform to contract equitable adjustment shall be made in the contract price requirements, unless the PHA decides that it is in its or the time of completion, and the contract shall be interest to accept the work with an appropriate modified in writing accordingly. adjustment in contract price. The Contractor shall
promptly segregate and remove rejected material from 22. Warranty of Title the premises.
(h) If the Contractor does not promptly replace or correct The Contractor warrants good title to all materials, rejected work, the PHA may (1) by contract or otherwise, supplies, and equipment incorporated in the work and replace or correct the work and charge the cost to the agrees to deliver the premises together with all Contractor, or (2) terminate for default the Contractor’s improvements thereon free from any claims, liens or right to proceed. charges, and agrees further that neither it nor any other (i) If any work requiring inspection is covered up without ap- person, firm or corporation shall have any right to a lien proval of the PHA, it must, if requested by the Contracting upon the premises or anything appurtenant thereto.

Officer, be uncovered at the expense of the Contractor. If at any time before final acceptance of the entire work, the 23. Warranty of Construction PHA considers it necessary or advisable, to examine work already completed by removing or tearing it out, the (a) In addition to any other warranties in this contract, the Contractor, shall on request, promptly furnish all Contractor warrants, except as provided in paragraph (j) necessary facilities, labor, and material. If such work is of this clause, that work performed under this contract found to be defective or nonconforming in any material conforms to the contract requirements and is free of any respect due to the fault of the Contractor or its defect in equipment, material, or workmanship performed subcontractors, the Contractor shall defray all the by the Contractor or any subcontractor or supplier at any expenses of the examination and of satisfactory tier. This warranty shall continue for a period of __________ reconstruction. If, however, such work is found to meet (one year unless otherwise indicated) from the date of final the requirements of the contract, the Contracting Officer acceptance of the work. If the PHA takes possession of shall make an equitable adjustment to cover the cost of any part of the work before final acceptance, this warranty the examination and reconstruction, including, if shall continue for a period of (one year unless otherwise completion of the work was thereby delayed, an indicated) from the date that the PHA takes extension of time. possession.
(j) The Contractor shall notify the Contracting Officer, in (b) The Contractor shall remedy, at the Contractor’s writing, as to the date when in its opinion all or a expense, any failure to conform, or any defect. In designated portion of the work will be substantially addition, the Contractor shall remedy, at the Contractor’s completed and ready for inspection. If the Architect expense, any damage to PHA-owned or controlled real or determines that the state of preparedness is as personal property when the damage is the result of— represented, the PHA will promptly arrange for the (1) The Contractor’s failure to conform to contract require- inspection. Unless otherwise specified in the contract, the merits; or PHA shall accept, as soon as practicable after completion (2) Any defects of equipment, material, workmanship or and inspection, all work required by the contract or that design furnished by the Contractor. portion of the work the Contracting Officer determines and (c) The Contractor shall restore any work damaged in designates can be accepted separately. Acceptance shall fulfilling the terms and conditions of this clause. The be final and conclusive except for latent defects, fraud, Contractor’s warranty with respect to work repaired or gross mistakes amounting to fraud, or the PHA’s right replaced will run for (one year unless otherwise indicated) under any warranty or guarantee. from the date of repair or replacement. (d) The Contracting Officer shall notify the Contractor, in

21. Use and Possession Prior to Completion writing, within a reasonable time after the discovery of any failure, defect or damage.
(a) The PHA shall have the right to take possession of or use (e) If the Contractor fails to remedy any failure, defect, or any completed or partially completed part of the work. damage within a reasonable time after receipt of notice, Before taking possession of or using any work, the the PHA shall have the right to replace, repair or Contracting Officer shall furnish the Contractor a list of otherwise remedy the failure, defect, or damage at the items of work remaining to be performed or corrected on Contractor’s expense. those portions of the work that the PHA intends to take (f) With respect to all warranties, express or implied, from possession of or use. However, failure of the Contracting subcontractors, manufacturers, or suppliers for work Officer to list any item of work shall not relieve the performed and materials furnished under this contract, Contractor of responsibility for complying with the terms of the Contractor shall:
the contract. The PHA’s possession or use shall not be (1) Obtain all warranties that would be given in normal deemed an acceptance of any work under the contract. commercial practice; (b) While the PHA has such possession or use, the (2) Require all warranties to be executed in writing, for the Contractor shall be relieved of the responsibility for (1) the benefit of the PHA; and, loss of or damage to the work resulting from the PHA’s (3) Enforce all warranties for the benefit of the PHA. possession or use, notwithstanding the terms of the (g) In the event the Contractor’s warranty under paragraph clause entitled Permits and Codes herein; (2) all (a) of this clause has expired, the PHA may bring suit at maintenance costs on the areas occupied; and, (3) its own expense to enforce a subcontractor’s, furnishing heat, light, power, and water used in the areas manufacturer’s or supplier’s warranty.

Previous editions are obsolete Page 8 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
584
Administrative Requirements
(h) Unless a defect is caused by the negligence of the basis for determining progress payments. The breakdown Contractor or subcontractor or supplier at any tier, the shall be approved by the Contracting Officer and must be Contractor shall not be liable for the repair of any defect of acceptable to HUD. If the contract covers more than one material or design furnished by the PHA nor for the repair project, the Contractor shall furnish a separate of any damage that results from any defect in PHA breakdown for each. The values and quantities employed furnished material or design. in making up this breakdown are for determining the (i) Notwithstanding any provisions herein to the contrary, the amount of progress payments and shall not be construed establishment of the time periods in paragraphs (a) and as a basis for additions to or deductions from the contract (c) above relate only to the specific obligation of the price. The Contractor shall prorate its overhead and profit Contractor to correct the work, and have no relationship over the construction period of the contract. to the time within which its obligation to comply with the (d) The Contractor shall submit, on forms provided by the contract may be sought to be enforced, nor to the time PHA, periodic estimates showing the value of the work within which proceedings may be commenced to performed during each period based upon the approved establish the Contractor’s liability with respect to its obligation other than specifically to correct the work. submitted not later than ___________ days in advance of (j) This warranty shall not limit the PHA’s rights under the the date set for payment and are subject to correction and Inspection and Acceptance of Construction clause of this revision as required. The estimates must be approved by contract with respect to latent defects, gross mistakes or the Contracting Officer with the concurrence of the fraud. Architect prior to payment. If the contract covers more than one project, the Contractor shall furnish a

24. Prohibition Against Liens separate progress payment estimate for each. (e) Along with each request for progress payments and the The Contractor is prohibited from placing a lien on the required estimates, the Contractor shall furnish the PHA’s property. This prohibition shall apply to all following certification, or payment shall not be made: I subcontractors at any tier and all materials suppliers. hereby certify, to the best of my knowledge and belief, that:
(1) The amounts requested are only for performance in
accordance with the specifications, terms, and

25. Contract Period conditions of the contract;
(2) Payments to subcontractors and suppliers have been
made from previous payments received under the
this contract within calendar days of the contract, and timely payments will be made from the effective date of the contract, or within the time schedule proceeds of the payment covered by this certification, established in the notice to proceed issued by the in accordance with subcontract agreements; and, Contracting Officer. (3) This request for progress payments does not include any amounts which the prime contractor intends to

26. Order of Provisions withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the
In the event of a conflict between these General subcontract.

Conditions and the Specifications, the General
Conditions shall prevail. In the event of a conflict between the contract and any applicable state or local law or Name:
regulation, the state or local law or regulation shall
prevail; provided that such state or local law or regulation does not conflict with, or is less restrictive than applicable Title:
federal law, regulation, or Executive Order. In the event of such a conflict, applicable federal law, regulation, and Executive Order shall prevail. Date:

27. Payments (f) Except as otherwise provided in State law, the PHA shall retain ten (10) percent of the amount of progress
(a) The PHA shall pay the Contractor the price as provided in payments until completion and acceptance of all work this contract. under the contract; except, that if upon completion of 50 (b) The PHA shall make progress payments approximately percent of the work, the Contracting Officer, after every 30 days as the work proceeds, on estimates of consulting with the Architect, determines that the work accomplished which meets the standards of quality Contractor’s performance and progress are satisfactory, established under the contract, as approved by the the PHA may make the remaining payments in full for the Contracting Officer. The PHA may, subject to written work subsequently completed. If the Contracting Officer determination and approval of the Contracting Officer, subsequently determines that the Contractor’s make more frequent payments to contractors which are performance and progress are unsatisfactory, the PHA qualified small businesses. shall reinstate the ten (10) percent (or other percentage (c) Before the first progress payment under this contract, the as provided in State law) retainage until such time as the Contractor shall furnish, in such detail as requested by Contracting Officer determines that performance and the Contracting Officer, a breakdown of the total contract progress are satisfactory. price showing the amount included therein for each (g) The Contracting Officer may authorize material delivered principal category of the work, which shall substantiate on the site and preparatory work done to be taken into the payment amount requested in order to provide a consideration when computing progress payments.

Previous editions are obsolete Page 9 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
585
Material delivered to the Contractor at locations other than responsibilities of the parties (e.g., change in the PHA the site may also be taken into consideration if the address). All other contract modifications shall be in the Contractor furnishes satisfactory evidence that (1) it has form of supplemental agreements signed by the acquired title to such material; (2) the material is properly Contractor and the Contracting Officer. stored in a bonded warehouse, storage yard, or similar (c) When a proposed modification requires the approval of suitable place as may be approved by the Contracting HUD prior to its issuance (e.g., a change order that Officer; (3) the material is insured to cover its full value; exceeds the PHA’s approved threshold), such and (4) the material will be used to perform this contract. modification shall not be effective until the required Before any progress payment which includes delivered approval is received by the PHA. material is made, the Contractor shall furnish such
documentation as the Contracting Officer may require to 29. Changes assure the protection of the PHA’s interest in such
materials. The Contractor shall remain responsible for (a) The Contracting Officer may, at any time, without notice such stored material notwithstanding the transfer of title to the sureties, by written order designated or indicated to the PHA. to be a change order, make changes in the work within (h) All material and work covered by progress payments the general scope of the contract including changes:
made shall, at the time of payment become the sole (1) In the specifications (including drawings and designs); property of the PHA, but this shall not be construed as (1) (2) In the method or manner of performance of the work; relieving the Contractor from the sole responsibility for all (3) PHA-furnished facilities, equipment, materials, material and work upon which payments have been made services, or site; or, or the restoration of any damaged work; or, (2) waiving the (4) Directing the acceleration in the performance of the right of the PHA to require the fulfillment of all of the terms work. of the contract. In the event the work of the Contractor has (b) Any other written order or oral order (which, as used in been damaged by other contractors or persons other than this paragraph (b), includes direction, instruction, employees of the PHA in the course of their employment, interpretation, or determination) from the Contracting the Contractor shall restore such damaged work without Officer that causes a change shall be treated as a cost to the PHA and to seek redress for its damage only change order under this clause; provided, that the from those who directly Contractor gives the Contracting Officer written notice caused it. stating (1) the date, circumstances and source of the (i) The PHA shall make the final payment due the Contractor order and (2) that the Contractor regards the order as a under this contract after (1) completion and final change order. acceptance of all work; and (2) presentation of release of (c) Except as provided in this clause, no order, statement or all claims against the PHA arising by virtue of this contract, conduct of the Contracting Officer shall be treated as a other than claims, in stated amounts, that the Contractor change under this clause or entitle the Contractor to an has specifically excepted from the operation of the release. equitable adjustment.

Each such exception shall embrace no more than one (d) If any change under this clause causes an increase or claim, the basis and scope of which shall be clearly decrease in the Contractor’s cost of, or the time required defined. The amounts for such excepted claims shall not for the performance of any part of the work under this be included in the request for final payment. A release may contract, whether or not changed by any such order, the also be required of the assignee if the Contractor’s claim to Contracting Officer shall make an equitable adjustment amounts payable under this contract and modify the contract in writing. However, except for a has been assigned. adjustment based on defective specifications, no proposal (j) Prior to making any payment, the Contracting Officer may for any change under paragraph (b) above shall be require the Contractor to furnish receipts or other allowed for any costs incurred more than 20 days (5 days evidence of payment from all persons performing work for oral orders) before the Contractor gives written notice and supplying material to the Contractor, if the as required. In the case of defective specifications for Contracting Officer determines such evidence is which the PHA is responsible, the equitable adjustment necessary to substantiate claimed costs. shall include any increased cost reasonably incurred by (k) The PHA shall not; (1) determine or adjust any claims for the Contractor in attempting to comply with payment or disputes arising there under between the the defective specifications.

Contractor and its subcontractors or material suppliers; (e) The Contractor must assert its right to an adjustment or, (2) withhold any moneys for the protection of the under this clause within 30 days after (1) receipt of a subcontractors or material suppliers. The failure or written change order under paragraph (a) of this clause, refusal of the PHA to withhold moneys from the or (2) the furnishing of a written notice under paragraph Contractor shall in nowise impair the obligations of any (b) of this clause, by submitting a written statement surety or sureties under any bonds furnished under this describing the general nature and the amount of the contract. proposal. If the facts justify it, the Contracting Officer may extend the period for submission. The proposal may be

28. Contract Modifications included in the notice required under paragraph (b) above. No proposal by the Contractor for an equitable
(a) Only the Contracting Officer has authority to modify any adjustment shall be allowed if asserted after final term or condition of this contract. Any contract payment under this contract. modification shall be authorized in writing. (f) The Contractor’s written proposal for equitable (b) The Contracting Officer may modify the contract adjustment shall be submitted in the form of a lump sum unilaterally (1) pursuant to a specific authorization stated proposal supported with an itemized breakdown of all in a contract clause (e.g., Changes); or (2) for increases and decreases in the contract in at least the administrative matters which do not change the rights or following details:

Previous editions are obsolete Page 10 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
586
(1) Direct Costs. Materials (list individual items, the been so suspended, delayed, or interrupted by any other quantity and unit cost of each, and the aggregate cause, including the fault or negligence of the Contractor cost); Transportation and delivery costs associated or for which any equitable adjustment is provided for or with materials; Labor breakdowns by hours or unit excluded under any other provision of this contract. costs (identified with specific work to be performed); (c) A claim under this clause shall not be allowed (1) for any Construction equipment exclusively necessary for the costs incurred more than 20 days before the Contractor change; Costs of preparation and/ or revision to shop shall have notified the Contracting Officer in writing of drawings resulting from the change; Worker’s the act or failure to act involved (but this requirement Compensation and Public Liability Insurance; shall not apply as to a claim resulting from a suspension Employment taxes under FICA and FUTA; and, Bond order); and, (2) unless the claim, in an amount stated, is Costs when size of change warrants revision. asserted in writing as soon as practicable after the (2) Indirect Costs. Indirect costs may include overhead, termination of the suspension, delay, or interruption, but general and administrative expenses, and fringe not later than the date of final payment under the benefits not normally treated as direct costs. contract. (3) Profit. The amount of profit shall be negotiated and may vary according to the nature, extent, and 31. Disputes complexity of the work required by the change. The
allowability of the direct and indirect costs shall be (a) “Claim,” as used in this clause, means a written demand determined in accordance with the Contract Cost or written assertion by one of the contracting parties Principles and Procedures for Commercial Firms in Part seeking, as a matter of right, the payment of money in a 31 of the Federal Acquisition Regulation (48 CFR 1-31), sum certain, the adjustment or interpretation of contract as implemented by HUD Handbook 2210.18, in effect on terms, or other relief arising under or relating to the the date of this contract. The Contractor shall not be contract. A claim arising under the contract, unlike a allowed a profit on the profit received by any claim relating to the contract, is a claim that can be subcontractor. Equitable adjustments for deleted work resolved under a contract clause that provides for the shall include a credit for profit and may include a credit for relief sought by the claimant. A voucher, invoice, or other indirect costs. On proposals covering both increases and routine request for payment that is not in dispute when decreases in the amount of the contract, the application of submitted is not a claim. The submission may be indirect costs and profit shall be on the net-change in converted to a claim by complying with the requirements direct costs for the Contractor or subcontractor of this clause, if it is disputed either as to liability or performing the work. amount or is not acted upon in a reasonable time. (g) The Contractor shall include in the proposal its request (b) Except for disputes arising under the clauses entitled for time extension (if any), and shall include sufficient Labor Standards - Davis Bacon and Related Acts, herein, information and dates to demonstrate whether and to all disputes arising under or relating to this contract, what extent the change will delay the completion of the including any claims for damages for the alleged breach contract in its entirety. thereof which are not disposed of by agreement, shall be (h) The Contracting Officer shall act on proposals within 30 resolved under this clause. days after their receipt, or notify the Contractor of the (c) All claims by the Contractor shall be made in writing and date when such action will be taken. submitted to the Contracting Officer for a written decision. (i) Failure to reach an agreement on any proposal shall be a A claim by the PHA against the Contractor shall be dispute under the clause entitled Disputes herein. subject to a written decision by the Contracting Officer.

Nothing in this clause, however, shall excuse the (d) The Contracting Officer shall, within 60 (unless otherwise Contractor from proceeding with the contract as changed. indicated) days after receipt of the request, decide the (j) Except in an emergency endangering life or property, no claim or notify the Contractor of the date by which the change shall be made by the Contractor without a prior decision will be made. order from the Contracting Officer. (e) The Contracting Officer’s decision shall be final unless the Contractor (1) appeals in writing to a higher level in

30. Suspension of Work the PHA in accordance with the PHA’s policy and procedures, (2) refers the appeal to an independent
(a) The Contracting Officer may order the Contractor in mediator or arbitrator, or (3) files suit in a court of writing to suspend, delay, or interrupt all or any part of the competent jurisdiction. Such appeal must be made within work of this contract for the period of time that the (30 unless otherwise indicated) days after receipt of the Contracting Officer determines appropriate for the Contracting Officer’s decision. convenience of the PHA. (f) The Contractor shall proceed diligently with performance (b) If the performance of all or any part of the work is, for an of this contract, pending final resolution of any request for unreasonable period of time, suspended, delayed, or relief, claim, appeal, or action arising under or relating to interrupted (1) by an act of the Contracting Officer in the the contract, and comply with any decision of the administration of this contract, or (2) by the Contracting Contracting Officer.

Officer’s failure to act within the time specified (or within a reasonable time if not specified) in this contract an 32. Default adjustment shall be made for any increase in the cost of performance of the contract (excluding profit) necessarily (a) If the Contractor refuses or fails to prosecute the work, or caused by such unreasonable suspension, delay, or any separable part thereof, with the diligence that will interruption and the contract modified in writing insure its completion within the time specified in this accordingly. However, no adjustment shall be made contract, or any extension thereof, or fails to complete under this clause for any suspension, delay, or said work within this time, the Contracting Officer may, by interruption to the extent that performance would have written notice to the Contractor, terminate the right to Previous editions are obsolete Page 11 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
587
proceed with the work (or separable part of the work) that completion of the work together with any increased costs has been delayed. In this event, the PHA may take over occasioned the PHA in completing the work. the work and complete it, by contract or otherwise, and (c) If the PHA does not terminate the Contractor’s right to may take possession of and use any materials, proceed, the resulting damage will consist of liquidated equipment, and plant on the work site necessary for damages until the work is completed or accepted. completing the work. The Contractor and its sureties shall be liable for any damage to the PHA resulting from the 34. Termination for Convenience Contractor’s refusal or failure to complete the work within the specified time, whether or not the Contractor’s right to (a) The Contracting Officer may terminate this contract in proceed with the work is terminated. This liability includes whole, or in part, whenever the Contracting Officer any increased costs incurred by the PHA in completing determines that such termination is in the best interest of the work. the PHA. Any such termination shall be effected by (b) The Contractor’s right to proceed shall not be terminated delivery to the Contractor of a Notice of Termination or the Contractor charged with damages under this specifying the extent to which the performance of the clause if— work under the contract is terminated, and the date upon (1) The delay in completing the work arises from which such termination becomes effective. unforeseeable causes beyond the control and without (b) If the performance of the work is terminated, either in the fault or negligence of the Contractor. Examples of whole or in part, the PHA shall be liable to the Contractor such causes include (i) acts of God, or of the public for reasonable and proper costs resulting from such enemy, (ii) acts of the PHA or other governmental termination upon the receipt by the PHA of a properly entity in either its sovereign or contractual capacity, presented claim setting out in detail: (1) the total cost of (iii) acts of another contractor in the performance of a the work performed to date of termination less the total contract with the PHA, (iv) fires, (v) floods, (vi) amount of contract payments made to the Contractor; (2) epidemics, (vii) quarantine restrictions, (viii) strikes, the cost (including reasonable profit) of settling and (ix) freight embargoes, (x) unusually severe weather, paying claims under subcontracts and material orders for or (xi) delays of subcontractors or suppliers at any tier work performed and materials and supplies delivered to arising from unforeseeable causes beyond the control the site, payment for which has not been made by the and without the fault or negligence of both the PHA to the Contractor or by the Contractor to the Contractor and the subcontractors or suppliers; and subcontractor or supplier; (3) the cost of preserving and (2) The Contractor, within days (10 days unless otherwise protecting the work already performed until the PHA or indicated) from the beginning of such delay (unless assignee takes possession thereof or assumes extended by the Contracting Officer) notifies the responsibility therefore; (4) the actual or estimated cost of Contracting Officer in writing of the causes of delay. legal and accounting services reasonably necessary to The Contracting Officer shall ascertain the facts and prepare and present the termination claim to the PHA; the extent of the delay. If, in the judgment of the and (5) an amount constituting a reasonable profit on the Contracting Officer, the findings of fact warrant such value of the work performed by the Contractor. action, time for completing the work shall be extended (c) The Contracting Officer will act on the Contractor’s claim by written modification to the contract. The findings of within days (60 days unless otherwise indicated) of the Contracting Officer shall be reduced to a written receipt of the Contractor’s claim. decision which shall be subject to the provisions of (d) Any disputes with regard to this clause are expressly the Disputes clause of this contract. made subject to the provisions of the Disputes clause of (c) If, after termination of the Contractor’s right to proceed, it this contract. is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations 35. Assignment of Contract of the parties will be the same as if the termination had been for convenience of the PHA. The Contractor shall not assign or transfer any interest in this contract; except that claims for monies due or to

33. Liquidated Damages become due from the PHA under the contract may be assigned to a bank, trust company, or other financial
(a) If the Contractor fails to complete the work within the time institution. Such assignments of claims shall only be specified in the contract, or any extension, as specified in made with the written concurrence of the Contracting the clause entitled Default of this contract, the Contractor Officer. If the Contractor is a partnership, this contract shall pay to the PHA as liquidated damages, the sum of shall inure to the benefit of the surviving or remaining $ ____________ Contracting Officer insert amount] for member(s) of such partnership as approved by the each day of delay. If different completion dates are Contracting Officer. specified in the contract for separate parts or stages of the work, the amount of liquidated damages shall be 36. Insurance assessed on those parts or stages which are delayed. To the extent that the Contractor’s delay or nonperformance (a) Before commencing work, the Contractor and each is excused under another clause in this contract, subcontractor shall furnish the PHA with certificates of liquidated damages shall not be due the PHA. The insurance showing the following insurance is in force and Contractor remains liable for damages caused other than will insure all operations under the Contract:
by delay. (1) Workers’ Compensation, in accordance with state or (b) If the PHA terminates the Contractor’s right to proceed, Territorial Workers’ Compensation laws. the resulting damage will consist of liquidated damages (2) Commercial General Liability with a combined single until such reasonable time as may be required for final limit for bodily injury and property damage of not less than $ __________ [Contracting Officer insert amount] Previous editions are obsolete Page 12 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
588
per occurrence to protect the Contractor and each (2) “Subcontractor” means any supplier, vendor, or firm subcontractor against claims for bodily injury or death that furnishes supplies, materials, equipment, or and damage to the property of others. This shall cover services to or for the Contractor or another the use of all equipment, hoists, and vehicles subcontractor. on the site(s) not covered by Automobile Liability (b) The Contractor shall not enter into any subcontract with under (3) below. If the Contractor has a "claims made” any subcontractor who has been temporarily denied policy, then the following additional requirements participation in a HUD program or who has been apply: the policy must provide a “retroactive date” suspended or debarred from participating in contracting which must be on or before the programs by any agency of the United States execution date of the Contract; and the extended Government or of the state in which the work under this reporting period may not be less than five years contract is to be performed. following the completion date of the Contract. (c) The Contractor shall be as fully responsible for the acts or (3) Automobile Liability on owned and non -owned motor omissions of its subcontractors, and of persons either vehicles used on the site(s) or in connection therewith directly or indirectly employed by them as for the acts or for a combined single limit for bodily injury and omissions of persons directly employed by the property damage of not less than $ ______________________________ Contractor. [Contracting Officer insert amount] per occurrence. (d) The Contractor shall insert appropriate clauses in all (b) Before commencing work, the Contractor shall furnish the subcontracts to bind subcontractors to the terms and PHA with a certificate of insurance evidencing that conditions of this contract insofar as they are applicable Builder’s Risk (fire and extended coverage) Insurance on to the work of subcontractors. all work in place and/or materials stored at the building (e) Nothing contained in this contract shall create any site(s), including foundations and building equipment, is contractual relationship between any subcontractor and in force. The Builder’s Risk Insurance shall be for the the PHA or between the subcontractor and HUD. benefit of the Contractor and the PHA as their interests may appear and each shall be named in the policy or 38. Subcontracting with Small and Minority Firms, policies as an insured. The Contractor in installing Women’s Business Enterprise, and Labor Surplus equipment supplied by the PHA shall carry insurance on Area Firms such equipment from the time the Contractor takes
possession thereof until the Contract work is accepted by The Contractor shall take the following steps to ensure the PHA. The Builder’s Risk Insurance need not be that, whenever possible, subcontracts are awarded to carried on excavations, piers, footings, or foundations small business firms, minority firms, women’s business until such time as work on the superstructure is started. It enterprises, and labor surplus area firms:
need not be carried on landscape work. Policies shall
furnish coverage at all times for the full cash value of all completed construction, as well as materials in place
and/or stored at the site(s), whether or not partial
payment has been made by the PHA. The Contractor
may terminate this insurance on buildings as of the date taken over for occupancy by the PHA. The Contractor is
not required to carry Builder’s Risk Insurance for
modernization work which does not involve structural
alterations or additions and where the PHA’s existing fire and extended coverage policy can be endorsed to
include such work.
(c) All insurance shall be carried with companies which are financially responsible and admitted to do business in the State in which the project is located. If any such
insurance is due to expire during the construction period, the Contractor (including subcontractors, as applicable) shall not permit the coverage to lapse and shall furnish evidence of coverage to the Contracting Officer. All
certificates of insurance, as evidence of coverage, shall provide that no coverage may be canceled or non-
renewed by the insurance company until at least 30 days prior written notice has been given to the Contracting
Officer.

37. Subcontracts
(a) Definitions. As used in this contract -
(1) “Subcontract” means any contract, purchase order, or other purchase agreement, including modifications and
change orders to the foregoing, entered into by a
subcontractor to furnish supplies, materials,
equipment, and services for the performance of the
prime contract or a subcontract.
(a) Placing qualified small and minority businesses and women’s business enterprises on solicitation lists;
(b) Ensuring that small and minority businesses and
women’s business enterprises are solicited whenever they are potential sources;
(c) Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum
participation by small and minority businesses and women’s business enterprises;
(d) Establishing delivery schedules, where the requirements of the contract permit, which encourage participation by small and minority businesses and women’s business enterprises; and
(e) Using the services and assistance of the U.S. Small Business Administration, the Minority Business
Development Agency of the U.S. Department of
Commerce, and State and local governmental small
business agencies.

39. Equal Employment Opportunity
During the performance of this contract, the Contractor/ Seller agrees as follows:
(a) The Contractor/Seller shall not discriminate against any employee or applicant for employment because of of race color, religion, sex, sexual orientation, gender identity, disability, or national origin.
(b) The Contractor/Seller shall take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, disability, or national origin. Such action shall
include, but not be limited to, (1) employment, (2) upgrading demotion, (4) transfer, (5) recruitment or
recruitment advertising, (6) layoff or termination, (7) rates of pay or other forms of compensation, and (8)
selection for training,including apprenticeship
Previous editions are obsolete Page 13 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
589
(c) The Contractor/Seller agrees to post in conspicuous places available to employees and applicants for employment the notices to be provided by the Contracting Officer setting forth the provisions of this nondiscrimination clause.
(d) The Contractor/Seller shall, in all solicitations or advertisements for employees placed by or on behalf of the Contractor/Seller, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, or national origin.
(e) The Contractor/Seller shall send, to each labor union or representative of workers with which it has a collective bargaining agreement or other contract or understanding, the notice to be provided by the Contracting Officer advising the labor union or workers’ representative of the Contractor’s commitments under this clause, and post copies of the notice in conspicuous places available to employees and applicants for employment.
(f) The Contractor/Seller shall comply with Executive Order 11246, as amended, and the rules, regulations, and orders of the Secretary of Labor.
(g) The Contractor/Seller shall furnish all information and reports required by Executive Order 11246, as amended, Section 503 of the Rehabilitation Act of 1973, as amended, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto. The Contractor/Seller shall permit
access to its books, records, and accounts by the
Secretary of Labor for purposes of investigation to
ascertain compliance with such rules, regulations, and
orders.
(h) In the event of a that the Contractor/Seller is in noncompliance with the nondiscrimination clauses of this contract or with any of such rules, regulations, or orders, this contract may be canceled, terminated or suspended in whole or in part and the
contractor/seller may be declared ineligible for further Government contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
(i)The contractor/seller will include the provisions of paragraphs (a) through (h) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each sub[contractor/seller] or vendor. The [contractor/seller] will take such action with respect to any subcontract or purchase order as may be directed by the Secretary of Labor as a means of enforcing such provisions in cluding sanctions for noncompliance: Provided, however, that in the event the [contractor/seller] becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction, the [contractor/seller] may request the United States to enter into such litigation to protect the interests of the United States.
(j) Compliance with the requirements of this clause shall be to the maximum extent consistent with, but not in
derogation of, compliance with section 7(b) of the Indian Self-Determination and Education Assistance Act and the Indian Preference clause of this contract.

40. Employment, Training, and Contracting
Opportunities for Low-Income Persons, Section 3 of the
Housing and Urban Development Act of 1968.
(a) The work to be performed under this contract is subject to the requirements of Section 3 of the Housing and Urban
Development Act of 1968, as amended, 12 U.S.C. 1701u (section 3). The purpose of section 3 is to ensure that employment and other economic opportunities generated by HUD assistance or HUD-assisted projects covered by Section 3, shall, to the greatest extent feasible, be directed to low- and very low-income persons, particularly persons who are recipients of HUD assistance for housing.
(b) The parties to this contract agree to comply with HUD's regulations in 24 CFR Part 75, which implement Section 3. As evidenced by their execution of this contract, the parties to this contract certify that they are under no contractual or other impediment that would prevent them from complying with the Part 75 regulations.
(c) The contractor agrees to send to each labor organization or representative of workers with which the contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor organization or workers'
representative of the contractor's commitments under this section 3 clause and will post copies of the notice in
conspicuous places at the work site where both employees and applicants for training and employment positions can see the notice. The notice shall describe the Section 3 prioritization requirements and shall state the minimum percentages of labor hour requirements established in the Benchmark Notice (FR- 6085 -N-04).
(d) The contractor agrees to include this section 3 clause in every subcontract subject to compliance with regulations in 24 CFR Part 75, and agrees to take appropriate action, as
provided in an applicable provision of the subcontract or in this section 3 clause, upon a finding that the subcontractor is in violation of the regulations in 24 CFR Part 75. The contractor will not subcontract with any subcontractor where the
contractor has notice or knowledge that the subcontractor has been found in violation of the regulations in 24 CFR Part 75. (e) Noncompliance with HUD's regulations in 24 CFR Part 75 may result in sanctions, termination of this contract for default, and debarment or suspension from future HUD assisted
contracts.
(f) Contracts, subcontracts, grants, or subgrants subject to Section 7(b) of the Indian Self-Determination and Education Assistance Act (25 U.S.C. 5307(b)) or subject to tribal preference requirements as authorized under 101(k) of the Native American Housing Assistance and Self-Determination Act (25 U.S.C. 4111(k)) must provide preferences in
employment, training, and business opportunities to Indians and Indian organizations, and are therefore not subject to the requirements of 24 CFR Part 75.

Previous editions are obsolete Page 14 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
590

41. Interest of Members of Congress (a) The PHA, HUD, or Comptroller General of the United States, or any of their duly authorized representatives No member of or delegate to the Congress of the United shall, until 3 years after final payment under this contract, States of America shall be admitted to any share or part of have access to and the right to examine any of the this contract or to any benefit that may arise therefrom. Contractor’s directly pertinent books, documents, papers, or other records involving transactions related to this

42. Interest of Members, Officers, or Employees and contract for the purpose of making audit, examination, Former Members, Officers, or Employees excerpts, and transcriptions. (b) The Contractor agrees to include in first-tier subcontracts No member, officer, or employee of the PHA, no member under this contract a clause substantially the same as of the governing body of the locality in which the project paragraph (a) above. “Subcontract,” as used in this is situated, no member of the governing body of the clause, excludes purchase orders not exceeding locality in which the PHA was activated, and no other $10,000. public official of such locality or localities who exercises (c) The periods of access and examination in paragraphs (a) any functions or responsibilities with respect to the and (b) above for records relating to (1) appeals under the project, shall, during his or her tenure, or for one year Disputes clause of this contract, (2) litigation or settlement thereafter, have any interest, direct or indirect, in this of claims arising from the performance of this contract, or contract or the proceeds thereof. (3) costs and expenses of this contract to which the PHA, HUD, or Comptroller General or any of their duly

43. Limitations on Payments made to Influence Certain authorized representatives has taken exception shall Federal Financial Transactions continue until disposition of such appeals, litigation, claims, or exceptions.
(a) The Contractor agrees to comply with Section 1352 of Title 31, United States Code which prohibits the use of 46. Labor Standards - Davis-Bacon and Related Acts Federal appropriated funds to pay any person for
influencing or attempting to influence an officer or If the total amount of this contract exceeds $2,000, the employee of any agency, a Member of Congress, and Federal labor standards set forth in the clause below shall officer or employee of Congress, or an employee of a apply to the development or construction work to be Member of Congress in connection with any of the performed under the contract. following covered Federal actions: the awarding of any (a) Minimum Wages.

Federal contract; the making of any Federal grant; the (1) All laborers and mechanics employed under this making of any Federal loan; the entering into of any contract in the development or construction of the cooperative agreement; or the modification of any project(s) involved will be paid unconditionally and not Federal contract, grant, loan, or cooperative agreement. less often than once a week, and without subsequent (b) The Contractor further agrees to comply with the deduction or rebate on any account (except such payroll requirement of the Act to furnish a disclosure (OMB deductions as are permitted by regulations issued by the Standard Form LLL, Disclosure of Lobbying Activities) if Secretary of Labor under the Copeland Act (29 CFR Part any funds other than Federal appropriated funds 3)), the full amount of wages and bona fide fringe benefits (including profit or fee received under a covered Federal (or cash equivalents thereof) due at time of payment transaction) have been paid, or will be paid, to any person computed at rates not less than those contained in the for influencing or attempting to influence an officer or wage determination of the Secretary of Labor which is employee of any agency, a Member of Congress, an attached hereto and made a part hereof, regardless of officer or employee of Congress, or an employee of a any contractual relationship which may be alleged to exist Member of Congress in connection with a Federal between the Contractor and such laborers and contract, grant, loan, or cooperative agreement. mechanics. Contributions made or costs reasonably anticipated for bona fide fringe benefits under Section

44. Royalties and Patents 1(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or The Contractor shall pay all royalties and license fees. It mechanics, subject to the provisions of 29 CFR shall defend all suits or claims for infringement of any 5.5(a)(1)(iv); also, regular contributions made or costs patent rights and shall save the PHA harmless from loss incurred for more than a weekly period (but not less often on account thereof; except that the PHA shall be than quarterly) under plans, funds, or programs which responsible for all such loss when a particular design, cover the regular weekly period, are deemed to be process or the product of a particular manufacturer or constructively made or incurred during such weekly manufacturers is specified and the Contractor has no period. Such laborers and mechanics shall be paid the reason to believe that the specified design, process, or appropriate wage rate and fringe benefits in the wage product is an infringement. If, however, the Contractor determination for the classification of work actually has reason to believe that any design, process or product performed, without regard to skill, except as provided in specified is an infringement of a patent, the Contractor 29 CFR 5.5(a)(4). Laborers or mechanics performing shall promptly notify the Contracting Officer. Failure to work in more than one classification may be give such notice shall make the Contractor responsible compensated at the rate specified for each classification for resultant loss. for the time actually worked therein; provided, that the employer’s payroll records accurately set forth the time

45. Examination and Retention of Contractor’s Records spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under 29 CFR 5.5(a)(1)(ii) and the Davis-Bacon poster (WH-1321) shall
Previous editions are obsolete Page 15 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
591
be posted at all times by the Contractor and its amount of any costs reasonably anticipated in subcontractors at the site of the work in a prominent and providing bona fide fringe benefits under a plan or accessible place where it can be easily seen by the program; provided, that the Secretary of Labor has workers. found, upon the written request of the Contractor, that (2) (i) Any class of laborers or mechanics, including the applicable standards of the Davis-Bacon Act have helpers, which is not listed in the wage been met. The Secretary of Labor may require the determination and which is to be employed under Contractor to set aside in a separate account assets the contract shall be classified in conformance with for the meeting of obligations under the plan or the wage determination. HUD shall approve an program.
additional classification and wage rate and fringe (b) Withholding of funds. HUD or its designee shall, upon its benefits therefor only when all the following criteria own action or upon written request of an authorized have been met: (A) The work to be performed by representative of the Department of Labor, withhold or the classification requested is not performed by a cause to be withheld from the Contractor under this classification in the wage determination; and (B) contract or any other Federal contract with the same The classification is utilized in the area by the prime Contractor, or any other Federally-assisted construction industry; and (C) The proposed wage contract subject to Davis-Bacon prevailing wage rate, including any bona fide fringe benefits, bears requirements, which is held by the same prime a reasonable relationship to the wage rates Contractor, so much of the accrued payments or contained in the wage advances as may be considered necessary to pay determination. laborers and mechanics, including apprentices, trainees, (ii) If the Contractor and the laborers and mechanics and helpers, employed by the Contractor or any to be employed in the classification (if known), or subcontractor the full amount of wages required by the their representatives, and HUD or its designee contract. In the event of failure to pay any laborer or agree on the classification and wage rate mechanic, including any apprentice, trainee, or helper, (including the amount designated for fringe employed or working in the construction or development benefits where appropriate), a report of the action of the project, all or part of the wages required by the taken shall be sent by HUD or its designee to the contract, HUD or its designee may, after written notice to Administrator of the Wage and Hour Division, the Contractor, take such action as may be necessary to Employee Standards Administration, U.S. cause the suspension of any further payment, advance, Department of Labor, Washington, DC 20210. or guarantee of funds until such violations have ceased.

The Administrator, or an authorized HUD or its designee may, after written notice to the representative, will approve, modify, or disapprove Contractor, disburse such amounts withheld for and on every additional classification action within 30 days account of the Contractor or subcontractor to the of receipt and so advise HUD or its designee or will respective employees to whom they are due. notify HUD or its designee within the 30-day period (c) Payrolls and basic records. that additional time is necessary. (1) Payrolls and basic records relating thereto shall be (iii) In the event the Contractor, the laborers or maintained by the Contractor during the course of the mechanics to be employed in the classification or work and preserved for a period of three years their representatives, and HUD or its designee do thereafter for all laborers and mechanics working in not agree on the proposed classification and wage the construction or development of the project. Such rate (including the amount designated for fringe records shall contain the name, address, and social benefits, where appropriate), HUD or its designee security number of each such worker, his or her shall refer the questions, including the views of all correct classification, hourly rates of wages paid interested parties and the recommendation of HUD (including rates of contributions or costs anticipated or its designee, to the Administrator of the Wage for bona fide fringe benefits or cash equivalents and Hour Division for determination. The thereof of the types described in section 1(b)(2)(B) of Administrator, or an authorized representative, will the Davis-Bacon Act), daily and weekly number of issue a determination within 30 days of receipt and hours worked, deductions made, and actual wages so advise HUD or its designee or will notify HUD or paid. Whenever the Secretary of Labor has found, its designee within the 30-day period that under 29 CFR 5.5(a)(1)(iv), that the wages of any additional time is necessary. laborer or mechanic include the amount of costs (iv) The wage rate (including fringe benefits where reasonably anticipated in providing benefits under a appropriate) determined pursuant to plan or program described in section 1(b)(2)(B) of the subparagraphs (a)(2)(ii) or (iii) of this clause shall Davis-Bacon Act, the Contractor shall maintain be paid to all workers performing work in the records which show that the commitment to provide classification under this contract from the first day such benefits is enforceable, that the plan or program on which work is performed in classification. is financially responsible, and that the plan or (3) Whenever the minimum wage rate prescribed in the program has been communicated in writing to the contract for a class of laborers or mechanics includes laborers or mechanics affected, and records which a fringe benefit which is not expressed as an hourly show the costs anticipated or the actual cost incurred rate, the Contractor shall either pay the benefit as in providing such benefits. Contractors employing stated in the wage determination or shall pay another apprentices or trainees under approved programs bona fide fringe benefit or an hourly cash equivalent shall maintain written evidence of the registration of thereof. apprenticeship programs and certification of trainee (4) If the Contractor does not make payments to a trustee programs, the registration of the apprentices and or other third person, the Contractor may consider as trainees, and the ratios and wage rates prescribed in part of the wages of any laborer or mechanic the the applicable programs.

Previous editions are obsolete Page 16 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
592
(2) (i) The Contractor shall submit weekly for each week make such records available may be grounds for in which any contract work is performed a copy of debarment action pursuant to 29 CFR 5.12. all payrolls to the Contracting Officer for (d) (1) Apprentices. Apprentices will be permitted to work at transmission to HUD or its designee. The payrolls less than the predetermined rate for the work they submitted shall set out accurately and completely performed when they are employed pursuant to and all of the information required to be maintained individually registered in a bona fide apprenticeship under subparagraph (c)(1) of this clause. This program registered with the U.S. Department of information may be submitted in any form desired. Labor, Employment and Training Administration, Optional Form WH-347 (Federal Stock Number Office of Apprenticeship and Training, Employer and 029-005-00014-1) is available for this purpose and Labor Services (OATELS), or with a State may be purchased from the Superintendent of Apprenticeship Agency recognized by OATELS, or if a Documents, U.S. Government Printing Office, person is employed in his or her first 90 days of Washington, D.C. 20402. The Contractor is probationary employment as an apprentice in such an responsible for the submission of copies of apprenticeship program, who is not individually payrolls by all subcontractors. (Approved by the registered in the program, but who has been certified Office of Management and Budget under OMB by OATELS or a State Apprenticeship Agency (where Control Number 1214-0149.) appropriate) to be eligible for probationary (ii) Each payroll submitted shall be accompanied by a employment as an apprentice. The allowable ratio of “Statement of Compliance,” signed by the apprentices to journeymen on the job site in any craft Contractor or subcontractor or his or her agent classification shall not be greater than the ratio who pays or supervises the payment of the permitted to the Contractor as to the entire work force persons employed under the contract and shall under the registered program. Any worker listed on a certify the following: payroll at an apprentice wage rate, who is not (A) That the payroll for the payroll period contains registered or otherwise employed as stated in this the information required to be maintained paragraph, shall be paid not less than the applicable under paragraph (c) (1) of this clause and that wage rate on the wage determination for the such information is correct and complete; classification of work actually performed. In addition, (B) That each laborer or mechanic (including each any apprentice performing work on the job site in helper, apprentice, and trainee) employed on excess of the ratio permitted under the registered the contract during the payroll period has been program shall be paid not less than the applicable paid the full weekly wages earned, without wage rate on the wage determination for the work rebate, either directly or indirectly, and that no actually performed. Where a contractor is performing deductions have been made either directly or construction on a project in a locality other than that in indirectly from the full wages earned, other which its program is registered, the ratios and wage than permissible deductions as set forth in 29 rates (expressed in percentages of the journeyman’s CFR Part 3; and hourly rate) specified in the Contractor’s or (C) That each laborer or mechanic has been paid subcontractor’s registered program shall be observed. not less than the applicable wage rates and Every apprentice must be paid at not less than the rate fringe benefits or cash equivalents for the specified in the registered program for the apprentice’s classification of work performed, as specified level of progress, expressed as a percentage of the in the applicable wage determination journeyman hourly rate specified in the applicable incorporated into the contract. wage determination. Apprentices shall be paid fringe (iii) The weekly submission of a properly executed benefits in accordance with the provisions of the certification set forth on the reverse side of apprenticeship program. If the apprenticeship program Optional Form WH-347 shall satisfy the does not specify fringe benefits, apprentices must be requirements for submission of the “Statement of paid the full amount of fringe benefits listed on the Compliance” required by subparagraph (c)(2)(ii) of wage determination for the applicable classification. If this clause. the Administrator of the Wage and Hour Division (iv) The falsification of any of the above certifications determines that a different practice prevails for the may subject the Contractor or subcontractor to civil applicable apprentice classification, fringes shall be or criminal prosecution under Section 1001 of Title paid in accordance with that determination. In the 18 and Section 3729 of Title 31 of the United event OATELS, or a State Apprenticeship Agency States Code. recognized by OATELS, withdraws approval of an (3) The Contractor or subcontractor shall make the apprenticeship program, the Contractor will no longer records required under subparagraph (c)(1) available be permitted to utilize apprentices at less than the for inspection, copying, or transcription by authorized applicable predetermined rate for the work performed representatives of HUD or its designee, the until an acceptable Contracting Officer, or the Department of Labor and program is approved. shall permit such representatives to interview (2) Trainees. Except as provided in 29 CFR 5.16, employees during working hours on the job. If the trainees will not be permitted to work at less than the Contractor or subcontractor fails to submit the predetermined rate for the work performed unless they required records or to make them available, HUD or are employed pursuant to and individually registered in its designee may, after written notice to the a program which has received prior approval, Contractor, take such action as may be necessary to evidenced by formal certification by the U.S. cause the suspension of any further payment, Department of Labor, Employment and Training advance, or guarantee of funds. Furthermore, failure Administration. The ratio of trainees to journeymen on to submit the required records upon request or to the job site shall not be greater than permitted under Previous editions are obsolete Page 17 of 19 form HUD-5370 (1/2014) Replaces form HUD-5370-A
593
(2) No part of this contract shall be subcontracted to any person or firm ineligible for award of a United States
Government contract by virtue of section 3(a) of the
Davis-Bacon Act or 29 CFR 5.12(a)(1).
(3) The penalty for making false statements is prescribed in the U. S. Criminal Code, 18 U.S.C. 1001.
(j) Contract Work Hours and Safety Standards Act. As used in this paragraph, the terms “laborers” and “mechanics” include watchmen and guards.
(1) Overtime requirements. No contractor or
subcontractor contracting for any part of the contract
work which may require or involve the employment of
laborers or mechanics, including watchmen and
guards, shall require or permit any such laborer or
mechanic in any workweek in which the individual is
employed on such work to work in excess of 40 hours
in such workweek unless such laborer or mechanic
receives compensation at a rate not less than one and
one-half times the basic rate of pay for all hours
worked in excess of 40 hours in such workweek.
(2) Violation; liability for unpaid wages; liquidated
damages. In the event of any violation of the
provisions set forth in subparagraph (j)(1) of this
clause, the Contractor and any subcontractor
responsible therefor shall be liable for the unpaid
wages. In addition, such Contractor and
subcontractor shall be liable to the United States (in
the case of work done under contract for the District
of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated
damages shall be computed with respect to each
individual laborer or mechanic (including watchmen
and guards) employed in violation of the provisions
set forth in subparagraph (j)(1) of this clause, in the sum of $27 for each calendar day on which such
individual was required or permitted to work in excess
of the standard workweek of 40 hours without
payment of the overtime wages required by
provisions set forth in subparagraph (j)(1) of this
clause. DOL posts current fines at: https://www.dol.gov/whd/ govcontracts/cwhssa.htm#cmp
(3) Withholding for unpaid wages and liquidated
damages. HUD or its designee shall upon its own
action or upon written request of an authorized
representative of the Department of Labor withhold or
cause to be withheld, from any moneys payable on
account of work performed by the Contractor or
subcontractor under any such contract or any Federal
contract with the same prime Contractor, or any other
Federally-assisted contract subject to the Contract
Work Hours and Safety Standards Act, which is held
by the same prime Contractor, such sums as may be
determined to be necessary to satisfy any liabilities of such Contractor or subcontractor for unpaid wages
and liquidated damages as provided in the provisions
set forth in subparagraph (j)(2) of this clause.
(k) Subcontracts. The Contractor or subcontractor shall insert in any subcontracts all the provisions contained in this clause, and such other clauses as HUD or its designee
may by appropriate instructions require, and also a
clause requiring the subcontractors to include these
provisions in any lower tier subcontracts. The prime
Contractor shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all these provisions.
the plan approved by the Employment and Training
Administration. Every trainee must be paid at not less
than the rate specified in the approved program for the trainee’s level of progress, expressed as a percentage
of the journeyman hourly rate specified in the
applicable wage determination. Trainees shall be paid
fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not
mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed in the wage
determination unless the Administrator of the Wage
and Hour Division determines that there is an
apprenticeship program associated with the
corresponding journeyman wage rate in the wage
determination which provides for less than full fringe
benefits for apprentices. Any employee listed on the
payroll at a trainee rate who is not registered and
participating in a training plan approved by the
Employment and Training Administration shall be paid
not less than the applicable wage rate in the wage
determination for the classification of work actually
performed. In addition, any trainee performing work on
the job site in excess of the ratio permitted under the registered program shall be paid not less than the
applicable wage rate in the wage determination for the
work actually performed. In the event the Employment
and Training Administration withdraws approval of a
training program, the Contractor will no longer be
permitted to utilize trainees at less than the applicable predetermined rate for the work performed
until an acceptable program is approved.
(3) Equal employment opportunity. The utilization of
apprentices, trainees, and journeymen under this
clause shall be in conformity with the equal
employment opportunity requirements of Executive
Order 11246, as amended, and 29 CFR Part 30.
(e) Compliance with Copeland Act requirements. The
Contractor shall comply with the requirements of 29 CFR Part 3, which are hereby incorporated by reference in this contract.

(f) Contract termination; debarment. A breach of this contract clause may be grounds for termination of the contract and for debarment as a Contractor and a subcontractor as
provided in 29 CFR 5.12.
(g) Compliance with Davis-Bacon and related Act
requirements. All rulings and interpretations of the Davis- Bacon and related Acts contained in 29 CFR Parts 1, 3,
and 5 are herein incorporated by reference in this
contract.
(h) Disputes concerning labor standards. Disputes arising out of the labor standards provisions of this clause shall not be subject to the general disputes clause of this contract.

Such disputes shall be resolved in accordance with the
procedures of the Department of Labor set forth in 29
CFR Parts 5, 6, and 7. Disputes within the meaning of
this clause include disputes between the Contractor (or any of its subcontractors) and the PHA, HUD, the U.S.

Department of Labor, or the employees or their
representatives.
(i) Certification of eligibility.
(1) By entering into this contract, the Contractor certifies that neither it (nor he or she) nor any person or firm
who has an interest in the Contractor’s firm is a
person or firm ineligible to be awarded contracts by
the United States Government by virtue of section
3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1).

Previous editions are obsolete
Replaces form HUD-5370-A
Previous editions are obsolete
Replaces form HUD-5370-A

Page 18 of 19 ends