OAK #4846-8099-6918 v2
05620-0129
TASK ORDER NO. 2

CITY OF PACIFICA
AND

SCHAAF & WHEELER CONSULTING CIVIL ENGINEERS
SECTION 1 – PURPOSE
The purpose of this Task Order is to authorize and direct SCHAAF & WHEELER CONSULTING CIVIL ENGINEERS to proceed with the work specified in SECTION 2 below, in accordance with the provisions of the Master Agreement for Consultant Services between the City of Pacifica (“CITY”) and SCHAAF & WHEELER CONSULTING CIVIL ENGINEERS (“CONSULTANT”) hereto dated May 26, 2020 (“MASTER AGREEMENT”) and Amendment No. 1 dated March 3, 2022.

SECTION 2 – SCOPE OF WORK
The items authorized by this Task Order are presented in Attachment “A” – Scope of Services, which is attached hereto and incorporated by this reference.

SECTION 3 – COMPENSATION AND PAYMENT
Compensation shall be as provided in the MASTER AGREEMENT. Compensation for services as set forth in SECTION 2 shall be as set forth in Attachment “B” – Compensation, which is attached hereto and incorporated by this reference. Total compensation for all services provided under this Task Order shall not exceed One Hundred Five Thousand Six Hundred Thirty Dollars ($105,630) (“Cost Ceiling”).

SECTION 4 – TIME OF PERFORMANCE
The services described in SECTION 2 of this Task Order shall be completed by December 31, 2023, or as extended in writing by the City Manager.

SECTION 5 – ITEMS AND CONDITIONS
All terms and conditions contained in the MASTER AGREEMENT are incorporated by reference and remain in full force and effect.

Approved this 3rd day of March 2022.
[Signatures on Next Page]

ATTACHMENT D

CITY OF PACIFICA
By: Date
Kevin Woodhouse, City Manager
Approved As To Form
By: Date
Michelle Marchetta Kenyon, City Attorney

CONSULTANT

SCHAAF & WHEELER CONSULTING CIVIL ENGINEERS
By: Date 3/3/22
ATTACHMENT “A”

SCOPE OF SERVICES
1171 Homestead Rd., Ste. 255
Santa Clara, CA 95050
(408) 246-4848
FAX (408) 246-5624
[email protected]

SCOPE MEMO

VIA EMAIL
TO: Nelson Schlater
City of Pacifica
DATE: March 3, 2022
FROM: Glen Anderson, PE JOB #: S&WP
SUBJECT: Proposal for Engineering, Bid, and Construction Support Services for Anza Pump Station Repair Project (C036)
Schaaf & Wheeler is providing you with this scope and fee to perform engineering services associated with the Bid and Construction Support Services required for Anza Pump Station.

Outlined herein is the proposed scope and associated level of effort.

Task 1 – Additional Engineering Services
This task includes all engineering work associated with development of final plans and specifications as necessary to accommodate City requested changes as well as changes necessary to accommodate temporary operation of the station. These changes include:
• Changes to City preferred engine manufacturer;
• A need to provide interim pumping;
• Changes to City preferred pump replacement strategy that necessitated a redesign of the roof and revisions to the hydraulic analysis of the station • City preferred modifications to engine control and monitoring Task 2 – Bid Support Services
This task includes providing support to the City during the bidding process. The following tasks are assumed:
• Attendance at prebid meeting;
• Review and response to bidder questions;
• Preparation of up to two addenda;
To: Nelson Schlater 2 Date: March 3, 2022
• Review of bids and recommendation for award;
• Preparation of conformed bid documents.

Task 3 – Construction Support Service
This task includes providing engineering support to the City during the construction process.

Services include response to contractor issued RFIs, review of Contractor product submittals and shop drawings, preparation of necessary design clarifications, review of change order requests, and preparation of record drawings.

Schaaf & Wheeler’s fee for the above work is outlined below. Project Manager Project Engineer Junior Engineer
Schaaf & Wheeler
Subtotal
Subconsultant - Biggs
Cardosa
Subconsultant - Fehr
Engineering
Total
Task $230 $205 $165
1 Additional Engineering Services 32 40 40 $22,160 $5,750 $8,500 $36,410 2 Bid Support 12 12 12 $7,200 $3,000 $2,900 $13,100
3 Construction Support Services 50 70 38 $32,120 $13,000 $11,000 $56,120 Total 94 122 90 $61,480 $21,750 $22,400 $105,630
If you have any questions regarding this scope and budget, do not hesitate to contact me at (408) 966-5341 or [email protected].

Best regards,

SCHAAF & WHEELER
Glen M. Anderson, PE (RCE 76720)
Vice-President