Rev. 0
Bid Set - February 25, 2022
Agreement 00 5200 - 1 Civic Center Campus Facilities Project OAK #4865-8320-3589 v2
DOCUMENT 00 5200
AGREEMENT
THIS AGREEMENT, dated this 25th day of April, 2022, by and between W.E. Lyons Construction Co. whose place of business is located at 1301 Ygnacio Valley Road, Walnut Creek, CA 94598 (Contractor), and CITY OF PACIFICA, a political subdivision of the State of California (Owner), acting under and by virtue of the authority vested in Owner by the laws of the State of California.
WHEREAS, the City Council of the CITY OF PACIFICA (Owner), on the 25th day of April, 2022 awarded to Contractor the following Contract:
CIVIC CENTER CAMPUS FACILITIES PROJECT
at 170 SANTA MARIA AVENUE AND 1810 FRANCISCO BOULEVARD, PACIFICA, CA 94044 PROJECT NUMBER PW #2021-023
NOW, THEREFORE, in consideration of the mutual covenants hereinafter set forth, Contractor and Owner agree as follows:
ARTICLE 1 SCOPE OF WORK OF THE CONTRACT
1.01 Work of the Contract
A. Contractor shall complete all Work specified in the Contract Documents, in accordance with the Specifications, Drawings, and all other terms and conditions of the Contract Documents (Work).
1.02 Price for Completion of the Work
A. Owner shall pay Contractor the following Contract Sum (Contract Sum) for completion of Work in accordance with Contract Documents as set forth in Contractor’s Bid, attached hereto.
B. The Contract Sum includes all allowances (if any).
Refer to Document 01 2100 (Allowances).
C. The Contract Sum is all inclusive and includes all Work; all federal, state, and local taxes on materials and equipment, and labor furnished by Contractor, its subcontractors, subconsultants, architects, engineers, and" vendors or otherwise arising out of Contractor's performance of the Work, including any increases in any such taxes during the term of this Agreement; and any duties, fees, and royalties imposed with respect to any materials and equipment, labor or services. The taxes covered hereby include (but are not limited' to) occupational, sales, use, excise, unemployment, FICA, and income taxes, customs, duties, and any and all other taxes on any item or service that is part of the Work, whether such taxes are normally included in the price of such item or service or are normally stated separately. Notwithstanding the foregoing, each party shall bear such state or local inventory, real property, personal property or fixtures taxes as may be properly assessed against it by applicable taxing authorities.
COMMENCEMENT AND COMPLETION OF WORK
1.03 Commencement of Work
A. Contractor shall commence Work on the date established in the Notice to Proceed (Commencement Date).
B. Owner reserves the right to modify or alter the Commencement Date.
ATTACHMENT "A"
Rev. 0
Bid Set - February 25, 2022
Agreement 00 5200 - 2 Civic Center Campus Facilities Project OAK #4865-8320-3589 v2
1.04 Completion of Work
A. Contractor shall achieve Substantial Completion of the entire Work within 326 Calendar Days from the Commencement Date.
B. Contractor shall achieve Final Completion of the entire Work within 366 Calendar Days from the Commencement Date.
ARTICLE 2 PROJECT REPRESENTATIVES
2.01 Owner’s Project Manager
A. Owner has designated Sam Bautista, P.E., City Engineer, as its Project Manager to act as Owner’s Representative in all matters relating to the Contract Documents. If Project Manager is an employee of Owner, Project Manager is the beneficiary of all Contractor obligations to Owner including, without limitation, all releases and indemnities.
B. Project Manager shall have final authority over all matters pertaining to the Contract Documents and shall have sole authority to modify the Contract Documents on behalf of Owner, to accept work, and to make decisions or actions binding on Owner, and shall have sole signature authority on behalf of Owner.
C. Owner may assign all or part of the Project Manager’s rights, responsibilities and duties to a Construction Manager, or other Owner Representative.
2.02 Contractor’s Project Manager and Other Key Personnel A. Contractor has designated Siddhesh (Sid) Maniyar ([email protected], 408-695-2240) as its Project Manager to act as Contractor’s Representative in all matters relating to the Contract Documents.
B. Contractor has designated the following other Key Personnel for the Project:
Name Position
Nicholas (Nick) Gooding Project Engineer ([email protected], 925-708-0134) Vinson Heine Project Executive ([email protected], 415-748-1628)
ARTICLE 3 LIQUIDATED DAMAGES FOR DELAY IN COMPLETION OF WORK
3.01 Liquidated Damage Amounts
A. As liquidated damages for delay Contractor shall pay Owner Nine Hundred and Fifty dollars ($950.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.
3.02 Scope of Liquidated Damages
A. Measures of liquidated damages shall apply cumulatively.
B. Limitations and stipulations regarding liquidated damages are set forth in Document 00 7200 (General Conditions).
ARTICLE 4 LIQUIDATED DAMAGES FOR UNAUTHORIZED CHANGES OF KEY PERSONNEL
4.01 Liquidated Damage Amounts
A. See Document 00 7200 (General Conditions) Paragraph 11.07.D for liquidated damages provisions pertaining to Key Personnel.
ARTICLE 5 CONTRACT DOCUMENTS
5.01 Contract Documents consist of the following documents, including all changes, Addenda, and Modifications thereto:
Rev. 0
Bid Set - February 25, 2022
Agreement 00 5200 - 3 Civic Center Campus Facilities Project OAK #4865-8320-3589 v2
Document 00 5100 Notice of Award
Document 00 5200 Agreement
Document 00 5500 Notice to Proceed
Document 00 6113.13 Construction Performance Bond
Document 00 6113.16 Construction Labor and Material Payment Bond Document 00 6290 Escrow Agreement for Security Deposits Document 00 6325 Substitution Request Form
Document 00 6530 Release of Claims
Document 00 6536 Guaranty
Document 00 7200 General Conditions
Document 00 7301 Supplemental General Conditions
Document 00 7316 Supplemental Conditions – Insurance and Indemnification
Document 00 7320 COVID Requirements
Document 00 7380 Apprenticeship Program
Document 00 9113 Addenda
Document 00 0115 Drawings, Table, Schedules, and Tech. Specifications
5.02 There are no Contract Documents other than those listed above. The Contract Documents may only be amended, modified or supplemented as provided in Document 00 7200 (General Conditions).
ARTICLE 6 MISCELLANEOUS
6.01 Terms and abbreviations used in this Agreement are defined in Document 00 7200 (General Conditions) and Section 01 4200 (References and Definitions) and will have the meaning indicated therein.
6.02 Contractor and Owner understand and agree that in no instance are the persons signing this Agreement for or on behalf of Owner or acting as an employee, agent, or representative of Owner, liable on this Agreement or any of the Contract Documents, or upon any warranty of authority, or otherwise. Contractor and Owner further understand and agree that liability of Owner is limited and confined to such liability as authorized or imposed by the Contract Documents or applicable law.
6.03 Pursuant to Labor Code Section 1771(a), Contractor represents that it and all of its Subcontractors are currently registered and qualified to perform public work pursuant to Labor Code Section 1725.5. Contractor covenants that any additional or substitute Subcontractors will be similarly registered and qualified.
6.04 In entering into a public works contract or a subcontract to supply goods, services or materials pursuant to a public works contract, Contractor or Subcontractor offers and agrees to assign to the awarding body all rights, title and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. § 15) or under the Cartwright Act (Chapter 2 (commencing with § 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time Owner tenders final payment to Contractor, without further acknowledgment by the parties.
6.05 Copies of the general prevailing rates of per diem wages for each craft, classification, or type of worker needed to execute the Contract, as determined by Director of the State of California Department of Industrial Relations, are on file at the Owner’s Office of the City Engineer, may be obtained from the California Department of Industrial Relations website [http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm] and are deemed included in the Contract Documents, and shall be made available to any interested party on request. Pursuant to Labor Code Sections 1860 and 1861, in accordance with Labor Code Section 3700, every contractor will be required to secure the payment of compensation to Contractor’s employees.
Contractor represents that it is aware of the provisions of Labor Code Section 3700 that require every employer to be insured against liability for workers’ compensation or to undertake self-
Rev. 0
Bid Set - February 25, 2022
Notice to Proceed – Phase I 00 5500 - 1 Civic Center Campus Facilities Project OAK #4862-1744-7173 v2
DOCUMENT 00 5500
NOTICE TO PROCEED
Dated: May 16, 2022
To: W.E. Lyons Construction
Address: 1301 Ygnacio Valley Road. Walnut Creek, CA 94598 CONTRACT FOR: CIVIC CENTER CAMPUS FACILITIES PROJECT
AT 170 SANTA MARIA AVENUE AND 1810 FRANCISCO BOULEVARD, PACIFICA, CA 94044
You are notified that the Contract Time under the above Contract will commence to run on June 6, 2022. On that date, you are to start performing your obligations with respect to Work at the Site under the Contract Documents. In accordance with Article 2 of Document 00 5200 (Agreement), the dates of Substantial Completion and Final Completion for the entire Work are April 28, 2023 and June 7, 2023, respectively.
Before you may start any Work at the Site, you must:
1. Submit certified Safety Program and related information
2. Submit copies of applicable permits
3. Schedule
OWNER: CITY OF PACIFICA
By: _______________________________________________
Sam Bautista, P.E., Dep. Dir. of Public Works/City Engineer
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Notice to Proceed – Phase I 00 5500 - 2 Civic Center Campus Facilities Project OAK #4862-1744-7173 v2
(This page intentionally left blank)
Rev. 0
Bid Set - February 25, 2022
Construction Performance Bond 00 6113.13 - 1 Civic Center Campus Facilities Project OAK #4875-7889-2037 v2
DOCUMENT 00 6113.13
CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND
THIS CONSTRUCTION PERFORMANCE BOND (Bond) is dated [Month, Day], 202_ is in the amount of Nine Million Two Hundred Twenty Two Nine Hundred Seventy Two Dollars ($9,222,972.00) (Penal Sum), which is 100% of the Contract Sum and is entered into by and between the parties listed below to ensure the faithful performance of the Contract identified below. This Bond consists of this page and the Bond Terms and Conditions, Paragraphs 1 through 14 attached to this page. Any singular reference to W.E. Lyons Construction Co. (Contractor), ______________________ (Surety), CITY OF PACIFICA (Owner), or other party shall be considered plural where applicable.
CONTRACTOR: SURETY:
W.E. Lyons Construction Co. ________________________________ Name of Surety
1301 Ygnacio Valley Rd.
Address Principal Place of Business
Walnut Creek, CA 94598
City/State/Zip City/State/Zip
CONSTRUCTION CONTRACT: Agreement for the City of Pacifica, Civic Center Campus Facilities Project, located at 170 Santa Maria Avenue and 1810 Francisco Boulevard, Pacifica, CA 94044, dated April 25, 2022, in the amount of $9,222,972.00.
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corp. Seal) Company: (Corp. Seal)
Signature: Signature:
Name: Name:
Title: Title:
Rev. 0
Bid Set - February 25, 2022
Construction Performance Bond 00 6113.13 - 2 Civic Center Campus Facilities Project OAK #4875-7889-2037 v2
BOND TERMS AND CONDITIONS
1. Contractor and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to Owner and the State of California for the complete and proper performance of the Construction Contract, which is incorporated herein by reference.
2. If Contractor completely and properly performs all of its obligations under the Construction Contract, Surety and Contractor shall have no obligation under this Bond.
3. If there is no Owner Default, Surety’s obligation under this Bond shall arise after:
3.1 Owner provides Surety with written notice that Owner has declared a Contractor Default under the Construction Contract pursuant to the terms of the Construction Contract; and
3.2 Owner has agreed to pay the Balance of Contract Sum:
3.2.1 To Surety in accordance with the terms of this Bond and the Construction Contract; or
3.2.2 To a Contractor selected to perform the Construction Contract in accordance with the terms of this Bond and the Construction Contract.
4. When Owner has satisfied the conditions of Paragraph 3 above, Surety shall promptly (within 40 Days) and at Surety’s expense elect to take one of the following actions:
4.1 Arrange for Contractor, with consent of Owner, to perform and complete the Construction Contract (but Owner may withhold consent, in which case the Surety must elect an option described in Paragraphs 4.2, 4.3 or 4.4 below); or
4.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors or Construction entities; provided, that Surety may not select Contractor as its agent or independent contractor or Contractor without Owner’s consent; or
4.3 Undertake to perform and complete the Construction Contract by obtaining bids from qualified contractors or Construction entities acceptable to Owner for a contract for performance and completion of the Construction Contract and, upon determination by Owner of the lowest responsive and responsible Bidder, arrange for a contract to be prepared for execution by Owner and the contractor or Contractor selected with Owner’s concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract; and, if Surety’s obligations defined in Paragraph 6 below, exceed the Balance of Contract Sum, then Surety shall pay to Owner the amount of such excess; or
4.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor or Contractor, and with reasonable promptness under the circumstances and, after investigation and consultation with Owner, determine in good faith its monetary obligation to Owner under Paragraph 6 below, for the performance and completion of the Construction Contract and, as soon as practicable after the amount is determined, tender payment therefor to Owner with full explanation of the payment’s calculation. If Owner accepts Surety’s tender under this Paragraph 4.4, Owner may still hold Surety liable for future damages then unknown or unliquidated resulting from the Contractor Default, as agreed by Owner and Surety at the time of tender. If Owner disputes the amount of Rev. 0
Bid Set - February 25, 2022
Construction Performance Bond 00 6113.13 - 3 Civic Center Campus Facilities Project OAK #4875-7889-2037 v2
Surety’s tender under this Paragraph 4.4, Owner may exercise all remedies available to it at law to enforce Surety’s liability under Paragraphs 6 and 7 below.
5. At all times Owner shall be entitled to enforce any remedy available to Owner at law or under the Construction Contract including, without limitation, and by way of example only, rights to perform work, protect Work, mitigate damages, advance critical Work to mitigate schedule delay, and coordinate Work with other consultants or contractors.
6. If Surety elects to act under Paragraphs 4.1, 4.2 or 4.3 above, within the time period provided in Paragraph 4, above, and complies with its obligations under this Bond, Surety’s obligations under this Bond are commensurate with Contractor’s Construction Contract obligations. Surety’s obligations include, but are not limited to:
6.1 Contractor’s obligations to complete the Construction Contract and correct Defective Work;
6.2 Contractor’s obligations to pay liquidated damages; and
6.3 To the extent otherwise required of Contractor under the Construction Contract, Contractor’s obligations to pay additional legal, design professional, and other costs not included within liquidated damages resulting from Contractor Default (but excluding attorney’s fees incurred to enforce this Bond).
7. If Surety does not elect to act under Paragraphs 4.1, 4.2, 4.3, or 4.4, above, within the time period provided in Paragraph 4, above, or comply with its obligations under this Bond, then Surety shall be deemed to be in default on this Bond ten Days after receipt of an additional written notice from Owner to Surety demanding that Surety perform its obligations under this Bond. Such Surety default shall be independent of the Contractor Default. To the extent Surety’s independent default causes Owner to suffer damages including, but not limited to, delay damages, which are different from, or in addition to (but not duplicative of) damages which Owner is entitled to receive under the Construction Contract, Surety shall also be liable for such damages. In the event any Surety obligation following its independent default is inconsistent or conflicts with California Civil Code Section 2809, or any other law which either prohibits, restricts, limits or modifies in any way any obligation of a surety which is larger in amount or in any other respect more burdensome than that of the principal, Surety hereby waives the provisions of such laws to that extent.
8. If Surety elects to act under Paragraphs 4.1, 4.3 or 4.4 above, within the time period provided in Paragraph 4, above, and complies with all obligations under this Bond, Surety’s monetary obligation under this Bond is limited to the Penal Sum.
9. No right of action shall accrue on this Bond to any person or entity other than Owner or its successors or assigns.
10. Surety hereby waives notice of any change, alteration or addition to the Construction Contract or to related subcontracts, design agreements, purchase orders and other obligations, including changes of time, and of any Owner action in accordance with Paragraph 5 above. Surety consents to all terms of the Construction Contract, including provisions on changes to the Contract. No extension of time, change, alteration, Modification, deletion, or addition to the Contract Documents, or of the Work (including services) required thereunder, or any Owner action in accordance with Paragraph 5 above shall release or exonerate Surety on this Bond or in any way affect the obligations of Surety on this Bond, unless such action is an Owner Default.
11. Any proceeding, legal or equitable, under this Bond shall be instituted in any court of competent jurisdiction where a proceeding is pending between Owner and Contractor regarding the Construction Contract, or in the Superior Court of the County of San Mateo, California, or in a Rev. 0
Bid Set - February 25, 2022
Construction Performance Bond 00 6113.13 - 4 Civic Center Campus Facilities Project OAK #4875-7889-2037 v2
court of competent jurisdiction in the location in which the Work is located. Communications from Owner to Surety under Paragraph 3.1 above shall be deemed to include the necessary agreements under Paragraph 3.2 above unless expressly stated otherwise.
12. All notices to Surety or Contractor shall be mailed or delivered (at the address set forth on the signature page of this Bond), and all notices to Owner shall be mailed or delivered as provided in Document 00 5200 (Agreement). Actual receipt of notice by Surety, Owner or Contractor, however accomplished, shall be sufficient compliance as of the date received at the foregoing addresses.
13. Any provision in this Bond conflicting with any statutory or regulatory requirement shall be deemed deleted herefrom and provisions conforming to such statutory requirement shall be deemed incorporated herein.
14. Definitions
14.1 Balance of Contract Sum: The total amount payable by Owner to Contractor pursuant to the terms of the Construction Contract after all proper adjustments have been made under the Construction Contract, for example, deductions for progress payments made, and increases/decreases for approved Modifications to the Construction Contract.
14.2 Construction Contract: The agreement between Owner and Contractor identified on the signature page of this Bond, including all Contract Documents and changes thereto.
14.3 Contractor Default: Material failure of Contractor, which has neither been remedied nor waived, to perform or otherwise to comply with the terms of the Construction Contract, limited to “default” or any other condition allowing a termination for cause as provided in Document 00 7200 (General Conditions).
14.4 Owner Default: Material failure of Owner, which has neither been remedied nor waived, to pay Contractor progress payments due under the Construction Contract or to perform other material terms of the Construction Contract, if such failure is the cause of the asserted Contractor Default and is sufficient to justify Contractor termination of the Construction Contract.
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Construction Labor and Material 00 6113.16 - 1 Civic Center Campus Facilities Project Payment Bond
OAK #4860-8748-9541 v2
DOCUMENT 00 6113.16
CONSTRUCTION LABOR AND MATERIAL PAYMENT BOND
KNOW ALL PERSONS BY THESE PRESENTS:
1.01 THAT WHEREAS, CITY OF PACIFICA (Owner) has awarded to W.E. Lyons Construction Co. as Principal, Contract Number PW2021-23 dated the 25th day of April, 2022 (the Contract), titled the City of Pacifica Civic Center Campus Facilities Project in the amount of $9,222,972, which Contract is by this reference made a part hereof, for the work of the following Contract:
Project Number PW #2021-23 to construct the Civic Center Campus Facilities Project located at 170 Santa Maria Avenue and 1810 Francisco Boulevard, Pacifica, CA 94044.
1.02 AND WHEREAS, Principal is required to furnish a bond in connection with the Contract to secure the payment of claims of laborers, mechanics, material suppliers, and other persons as provided by law;
1.03 NOW, THEREFORE, we, the undersigned Principal and
, as Surety, are held and firmly bound unto Owner in the sum of 100% OF THE CONTRACT PRICE ($9,222,972), for which payment well and truly to be made we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.
1.04 THE CONDITION OF THIS OBLIGATION IS SUCH, that if Principal, or its executors, administrators, successors, or assigns approved by Owner, or its subcontractors shall fail to pay any of the persons named in California Civil Code Section 9100, or amounts due under the State of California Unemployment Insurance Code with respect to work or labor performed under the Contract, or for any amounts required to be deducted, withheld, and paid over to the State of California Employment Development Department from the wages of employees of Principal and subcontractors pursuant to Section 13020 of the State of California Unemployment Insurance Code with respect to such work and labor, that Surety will pay for the same in an amount not exceeding the sum specified in this bond, plus reasonable attorneys’ fees, otherwise the above obligation shall become and be null and void.
1.05 This bond shall inure to the benefit of any of the persons named in California Civil Code Section 9100, as to give a right of action to such persons or their assigns in any suit brought upon this bond. The intent of this bond is to comply with the California Mechanic’s Lien Law.
1.06 Surety, for value received, hereby expressly agrees that no extension of time, change, modification, alteration, or addition to the undertakings, covenants, terms, conditions, and agreements of the Contract, or to the work to be performed thereunder, shall in any way affect the obligation of this bond; and it does hereby waive notice of any such extension of time, change, modification, alteration, or addition to the undertakings, covenants, terms, conditions, and agreements of the Contract, or to the work to be performed thereunder.
1.07 Surety’s obligations hereunder are independent of the obligations of any other surety for the payment of claims of laborers, mechanics, material suppliers, and other persons in connection with Contract; and suit may be brought against Surety and such other sureties, jointly and severally, or against any one or more of them, or against less than all of them without impairing Owner’s rights against the other.
Rev. 0
Bid Set - February 25, 2022
Construction Labor and Material 00 6113.16 - 2 Civic Center Campus Facilities Project Payment Bond
OAK #4860-8748-9541 v2
1.08 Correspondence or claims relating to this bond shall be sent to Surety at the address set forth below.
IN WITNESS WHEREOF, we have hereunto set our hands this day of , 20___.
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corp. Seal) Company: (Corp. Seal)
Signature Signature
Name Name
Title Title
Street Address Street Address
City, State, Zip Code City, State, Zip Code
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Escrow Agreement for Security 00 6290 - 1 Civic Center Campus Facilities Project Deposits in Lieu of Retention
OAK #4887-9012-8901 v2
DOCUMENT 00 6290
ESCROW AGREEMENT FOR SECURITY DEPOSIT IN LIEU OF RETENTION Public Contract Code Section 22300
THIS ESCROW AGREEMENT (“Escrow Agreement”) is made and entered into this day of ________________, 202_, by and between City of Pacifica (“Owner”), whose address is 170 Santa Maria Avenue, Pacifica, CA 94044, W.E. Lyons Construction Co. (“Contractor”), whose principal place of business is located at 1301 Ygnacio Valley Rd. Walnut Creek, CA 94598, and Owner, as escrow agent ____________________________ a state or federally chartered bank in the State of California, whose place of business is located at ____________________________. (“Escrow Agent”).
For the consideration hereinafter set forth, Owner, Contractor and Escrow Agent agree as follows:
1. Pursuant to Public Contract Code Section 22300, Contractor has the option to deposit securities with Escrow Agent as a substitute for retention earnings required to be withheld by Owner pursuant to Contract Number PW2021-23 entered into between Owner and Contractor for the Civic Center Campus Facilities Project in the amount of $9,222,972 dated April 25, 2022 (the “Contract”). Alternatively, on written request of Contractor, Owner shall make payments of the retention earnings directly to Escrow Agent. When Contractor deposits the securities as a substitute for Contract earnings, Escrow Agent shall notify Owner within ten Days of the deposit.
The market value of the securities at the time of substitution shall be at least equal to the cash amount then required to be withheld as retention under terms of Contract between Owner and Contractor. Securities shall be held in name of , and shall designate Contractor as the beneficial owner.
2. Owner shall make progress payments to Contractor for those funds which otherwise would be withheld from progress payments pursuant to Contract provisions, provided that Escrow Agent holds securities in form and amount specified in Paragraph 1 of this Document 00 6290.
3. When Owner makes payment(s) of retention earned directly to Escrow Agent, Escrow Agent shall hold said payment(s) for the benefit of Contractor until the time that the escrow created under this Escrow Agreement is terminated. Contractor may direct the investment of the payments into securities. All terms and conditions of this Escrow Agreement and the rights and responsibilities of the parties shall be equally applicable and binding when Owner pays Escrow Agent directly.
4. Contractor shall be responsible for paying all fees for the expenses incurred by Escrow Agent in administering the Escrow Account, and all expenses of Owner. Such expenses and payment terms shall be determined by Owner, Contractor, and Escrow Agent.
5. Interest earned on securities or money market accounts held in escrow and all interest earned on that interest shall be for sole account of Contractor and shall be subject to withdrawal by Contractor at any time and from time to time without notice to Owner.
6. Contractor shall have the right to withdraw all or any part of the principal in the Escrow Account only by written notice to Escrow Agent accompanied by written authorization from Owner to Escrow Agent that Owner consents to withdrawal of amount sought to be withdrawn by Contractor.
7. Owner shall have the right to draw upon the securities in event of default by Contractor. Upon seven Days written notice to Escrow Agent from Owner of the default, Escrow Agent shall immediately convert the securities to cash and shall distribute the cash as instructed by Owner.
8. Upon receipt of written notification from Owner certifying that the Contract is final and complete, and that Contractor has complied with all requirements and procedures applicable to the Contract, Escrow Agent shall release to Contractor all securities and interest on deposit less escrow fees and charges of the Escrow Account. The escrow shall be closed immediately upon disbursement of all moneys and securities on deposit and payments of fees and charges.
Rev. 0
Bid Set - February 25, 2022
Escrow Agreement for Security 00 6290 - 2 Civic Center Campus Facilities Project Deposits in Lieu of Retention
OAK #4887-9012-8901 v2
9. Escrow Agent shall rely on written notifications from Owner and Contractor pursuant to Paragraphs 5 through 8, inclusive, of this Document 00 6290 and Owner and Contractor shall hold Escrow Agent harmless from Escrow Agent’s release and disbursement of securities and interest as set forth.
10. Names of persons who are authorized to give written notice or to receive written notice on behalf of Owner and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:
ON BEHALF OF OWNER: ON BEHALF OF CONTRACTOR:
____________________________________ ___________________________________ Title Title
____________________________________ ___________________________________ Name Name
____________________________________ ___________________________________ Signature Signature
____________________________________ ___________________________________ Address Address
____________________________________ ___________________________________ City/State/Zip Code City/State/Zip Code
ON BEHALF OF ESCROW AGENT:
____________________________________
Title
____________________________________
Name
____________________________________
Signature
____________________________________
Address
____________________________________
City/State/Zip Code
IN WITNESS WHEREOF, the parties have executed this Escrow Agreement by their proper officers on the date first set forth above.
OWNER: CONTRACTOR
CITY OF PACIFICA W.E. Lyons Construction Co.
________________________________ _____________________________________ Title Title
________________________________ _____________________________________ Name Name
________________________________ _____________________________________ Signature Signature
Rev. 0
Bid Set - February 25, 2022
Escrow Agreement for Security 00 6290 - 3 Civic Center Campus Facilities Project Deposits in Lieu of Retention
OAK #4887-9012-8901 v2
ATTEST
_____________________________________
Signature
_____________________________________
Print Name
Secretary
ESCROW AGENT
_____________________________________
_____________________________________
Title
_____________________________________
Print Name
_____________________________________
Signature
[IF REQUIRED] REVIEWED AS TO FORM:
_____________________________________
Counsel for Owner
_____________________________________
Print Name
_____________________________________
Date
At the time the Escrow Account is opened, Owner and Contractor shall deliver to Escrow Agent a fully executed counterpart of this Document 00 6290.
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Escrow Agreement for Security 00 6290 - 4 Civic Center Campus Facilities Project Deposits in Lieu of Retention
OAK #4887-9012-8901 v2
(This page intentionally left blank)
Rev. 0
Bid Set - February 25, 2022
Substitution Request Form 00 6325 - 1 Civic Center Campus Facilities Project OAK #4893-9666-4581 v2
DOCUMENT 00 6325
SUBSTITUTION REQUEST FORM
To: CITY OF PACIFICA, Owner
PROJECT: CITY OF PACIFICA, CIVIC CENTER
CAMPUS FACILITIES PROJECT
Owner Project No: PW #2021-23
Contractor:
W.E. Lyons Construction Co.
Substitution
Request By:
Firm:
Transmittal Record Attn: Firm: Date Sent: Date
Rec’d:
Date
Due:
Contractor to Owner
Contractor to Architect
Owner / Architect to Consultant
Architect to Owner Representative
Owner Representative to Contractor
We hereby submit for your consideration the following product instead of the specified item for the Project:
Section / Drawing Article Specified Item
Proposed Substitution:
We have (a) attached manufacturer’s literature, including complete technical data and laboratory test results, if applicable, (b) attached an explanation of why proposed substitution is a true equivalent to specified item, (c) included complete information on changes to Contract Documents that the proposed substitution will require for its proper installation, and (d) filled in the blanks below:
Rev. 0
Bid Set - February 25, 2022
Substitution Request Form 00 6325 - 2 Civic Center Campus Facilities Project OAK #4893-9666-4581 v2
Contractor to complete questions that follow and certify to the accuracy of all answers:
A. Does the substitution affect dimensions shown on Drawings? Yes __ / No __. If No, please explain proposed mitigation and why substitution is equivalent to originally specified item:
B. Will the undersigned pay for changes to the building design, including engineering and detailing costs caused by the requested substitution? Yes __ / No __. If No, please state reasons explain why substitution is equivalent to originally specified item:
C. What effect does the substitution have on other trades? No effect: __ / Some effect__. If substitution will affect other trades, please explain the effect and why substitution is equivalent to originally specified item:
D. Will substitution cause change to Project Schedule, or to critical delivery dates? Add? Shorten? If the substitution will add to schedule dates or affect critical activities, please explain why substitution is equivalent to originally specified item:
E. Please describe differences between proposed substitution and specified item? Please explain and identify any and all differences, and please explain why substitution is equivalent to originally specified item:
F. What is the Cost Differential to Contractor in original specified item and proposed substitution including all mark-ups? [If substitution requested during bid period, skip this question.] G. Are Manufacturer's guarantees for the proposed item the same as for item specified? Yes ____; No____. If No, please explain why substitution is equivalent to originally specified item:
Rev. 0
Bid Set - February 25, 2022
Substitution Request Form 00 6325 - 3 Civic Center Campus Facilities Project OAK #4893-9666-4581 v2
H. Contractor accepts full responsibility for delays caused by redesign of other items of the Work necessitated by substitution? Yes __ / No __. If No, please state reasons and explain why substitution is equivalent to originally specified item:
I. Contractor states that the function, appearance and quality are equivalent or superior to the specified item? Yes __ / No __. If No, please explain why substitution is equivalent to originally specified item:
We certify that the function, appearance, and quality of the proposed substitution are equivalent or superior to those of the specified item, except as we may specifically state otherwise in this request.
Submitted by: __________________________
Firm: _________________________________
Address: ______________________________
Signature: __________________________
Date: _________________________________
Phone / Fax: ______________________________
Remarks:
Consultant Response
__Accepted
__ Not Accepted
__ Accepted As Noted
__ Received Too Late
Owner Representative Response
__Accepted
__ Not Accepted
__ Accepted As Noted
__ Received Too Late
Remarks: ______________________
______________________________
______________________________
By: ___________________________
Remarks: ______________________
______________________________
______________________________
By: ___________________________
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Substitution Request Form 00 6325 - 4 Civic Center Campus Facilities Project OAK #4893-9666-4581 v2
(This page intentionally left blank)
Rev. 0
Bid Set - February 25, 2022
Agreement and Release of All Claims 00 6530 - 1 Civic Center Campus Facilities Project OAK #4884-7503-1813 v2
DOCUMENT 00 6530
AGREEMENT AND RELEASE OF ANY AND ALL CLAIMS
[Public Contract Code Section 7100]
THIS AGREEMENT AND RELEASE OF ANY AND ALL CLAIMS (Agreement and Release), made and entered into this day of , 202__, by and between CITY OF PACIFICA (Owner), and W.E. Lyons Construction Co. (Contractor), whose place of business is at 1301 Ygnacio Valley Rd. Walnut Creek, CA 94598.
RECITALS
A. Owner and Contractor entered into Contract (the “Contract”) for construction of Civic Center Campus Facilities Project, located at 170 Santa Maria Avenue and 1810 Francisco Boulevard, Pacifica, CA 94044.
B. The Work under the Contract has been completed.
AGREEMENT
NOW THEREFORE, it is mutually agreed between Owner and Contractor as follows:
1. Contractor will not be assessed liquidated damages except as detailed below:
Original Contract Sum $ ___________________________________ Modified Contract Sum $ ___________________________________ Payment to Date $ ___________________________________
Liquidated Damages $ ___________________________________ Payment Due Contractor $ ___________________________________
2. Subject to the provisions of this Agreement and Release, Owner will forthwith pay to Contractor the sum of [________________________________________________________ Dollars and ____________ Cents ($_____________________)] under the Contract, less any amounts withheld under the Contract or represented by any Notice to Withhold Funds on file with Owner as of the date of such payment.
3. Contractor acknowledges and hereby agrees that there are no unresolved or outstanding claims in dispute against Owner arising from the Contract, except for the claims described in Paragraph 4 of this Document 00 6530. It is the intention of the parties in executing this Agreement and Release that this Agreement and Release shall be effective as a full, final and general release of all claims, demands, actions, causes of action, obligations, costs, expenses, damages, losses and liabilities of Contractor against Owner, and all if its agents, employees, consultants, inspectors, representatives, assignees and transferees, except for the Disputed Claims set forth in Paragraph 4 of this Document 00 6530. Nothing in this Agreement and Release shall limit or modify Contractor’s continuing obligations described in Paragraph 6 of this Document 00 6530.
4. The following claims submitted under Document 00 7200 (General Conditions), Article 12, are disputed (Disputed Claims) and are specifically excluded from the operation of this Agreement and Release.
Rev. 0
Bid Set - February 25, 2022
Agreement and Release of All Claims 00 6530 - 2 Civic Center Campus Facilities Project OAK #4884-7503-1813 v2
CLAIM NO. DATE
SUBMITTED
DESCRIPTION OF CLAIM AMOUNT OF
CLAIM
5. Consistent with California Public Contract Code Section 7100, Contractor hereby agrees that, in consideration of the payment set forth in Paragraph 2 of this Document 00 6530, Contractor hereby releases and forever discharges Owner, and all of its agents, employees, consultants, inspectors, assignees and transferees from any and all liability, claims, demands, actions or causes of action of whatever kind or nature arising out of or in any way concerned with the Work under the Contract.
6. Guarantees and warranties for the Work, and any other continuing obligation of Contractor, shall remain in full force and effect as specified in the Contract Documents.
7. Contractor shall immediately defend, indemnify and hold harmless Owner, any of the Owner’s Representatives, Project Manager, and all of their agents, employees, consultants, inspectors, assignees and transferees, from any and all claims, demands, actions, causes of action, obligations, costs, expenses, damages, losses and liabilities that may be asserted against them by any of Contractor’s suppliers and/or Subcontractors of any tier and/or any suppliers to them for any and all labor, materials, supplies and equipment used, or contemplated to be used in the performance of the Contract, except for the Disputed Claims set forth in Paragraph 4 of this Document 00 6530.
8. Contractor hereby waives the provisions of California Civil Code Section 1542, which provide as follows:
A GENERAL RELEASE DOES NOT EXTEND TO CLAIMS THAT THE
CREDITOR OR RELEASING PARTY DOES NOT KNOW OR SUSPECT
TO EXIST IN HIS OR HER FAVOR AT THE TIME OF EXECUTING THE
RELEASE AND THAT, IF KNOWN BY HIM OR HER, WOULD HAVE
MATERIALLY AFFECTED HIS OR HER SETTLEMENT WITH THE
DEBTOR OR RELEASED PARTY.
9. The provisions of this Agreement and Release are contractual in nature and not mere recitals and shall be considered independent and severable, and if any such provision or any part thereof shall be at any time held invalid in whole or in part under any federal, state, county, municipal or other law, ruling, or regulation, then such provision, or part thereof shall remain in force and effect only to the extent permitted by law, and the remaining provisions of this Agreement and Release shall also remain in full force and effect, and shall be enforceable.
10. Contractor represents and warrants that it is the true and lawful owner of all claims and other matters released pursuant to this Agreement and Release, and that it has full right, title and authority to enter into this instrument. Each party represents and warrants that it has been represented by counsel of its own choosing in connection with this Agreement and Release.
Rev. 0
Bid Set - February 25, 2022
Agreement and Release of All Claims 00 6530 - 3 Civic Center Campus Facilities Project OAK #4884-7503-1813 v2
11. All rights of Owner shall survive completion of the Work or termination of the Contract, and execution of this Agreement and Release.
* * * CAUTION: THIS IS A RELEASE - READ BEFORE EXECUTING * * * OWNER: CITY OF PACIFICA
By: ___________________________________________________ Signature
Name: ________________________________________________
Print
Its: ___________________________________________________ Title
[W.E. Lyons Construction Co.]
By: ___________________________________________________ Signature
Name: ________________________________________________
Print
Its: ___________________________________________________ Title
[W.E. Lyons Construction Co.]
By: ___________________________________________________ Signature
Name: ________________________________________________
Print
Its: ___________________________________________________ Title
REVIEWED AS TO FORM:
Dated: ___________________________, [20__]
By: ______________________________________________________ Counsel for Owner
Name: __________________________________________________ Print
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Agreement and Release of All Claims 00 6530 - 4 Civic Center Campus Facilities Project OAK #4884-7503-1813 v2
(This page intentionally left blank)
Rev. 0
Bid Set - February 25, 2022
Guaranty 00 6536 - 1 Civic Center Campus Facilities Project OAK #4875-3832-5765 v2
DOCUMENT 00 6536
GUARANTY
TO: The CITY OF PACIFICA (Owner), for construction of the Civic Center Campus Facilities Project, located at 170 Santa Maria Avenue and 1810 Francisco Boulevard, Pacifica, CA 94044.
The undersigned guarantees all construction performed on this Project and also guarantees all material and equipment incorporated therein.
1.01 Contractor hereby grants to Owner for a period of one year following the date of Final Acceptance of the Work completed, or such longer period specified in the Contract Documents, its unconditional warranty of the quality and adequacy of all of the Work including, without limitation, all labor, materials and equipment provided by Contractor and its Subcontractors of all tiers in connection with the Work.
1.02 Neither final payment nor use nor occupancy of the Work performed by the Contractor shall constitute an acceptance of Work not done in accordance with this Guaranty or relieve Contractor of liability in respect to any express warranties or responsibilities for faulty materials or workmanship. Contractor shall remedy any defects in the Work and pay for any damage resulting therefrom, which shall appear within one year, or longer if specified, from the date of Final Acceptance of the Work completed.
1.03 If within one year after the date of Final Acceptance, or such other period of time as may be prescribed by laws or regulations, or by the terms of Contract Documents or any extended warranty or guaranty, any Work is found to be Defective, Contractor shall promptly, without cost to Owner and in accordance with Owner’s written instructions, correct such Defective Work. Contractor shall remove any Defective Work rejected by Owner and replace it with Work that is not Defective, and satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom. If Contractor fails to comply promptly with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, Owner may have the Defective Work corrected or the rejected Work removed and replaced. Contractor shall pay for all claims, costs, losses and damages caused by or resulting from such removal and replacement.
Where Contractor fails to correct Defective Work, or defects are discovered outside the correction period, Owner shall have all rights and remedies granted by law.
1.04 Contractor shall respond within 72 hours to any claim made by Owner pursuant to this guaranty.
1.05 Observation and inspection of the Work shall not relieve Contractor of any of its obligations under the Contract Documents. Even though equipment, materials, or Work required to be provided under the Contract Documents have been inspected, accepted, and estimated for payment, Contractor shall, at its own expense, replace or repair any such equipment, material, or Work found to be Defective or otherwise not to comply with the requirements of the Contract Documents up to the end of the guaranty period.
1.06 This Guaranty is in addition to any other Contractor warranties contained in the Contract Documents, and not in lieu of, any and all other Contractor liability imposed under the Contract Documents or at law. In the event of any conflict or inconsistency between the terms of this Guaranty and any Contractor warranty or obligation Contractor under the Contract Documents or at law, such inconsistency or conflict shall be resolved in favor of the greater protection to Owner. (Signature line on next page)
Rev. 0
Bid Set - February 25, 2022
Guaranty 00 6536 - 2 Civic Center Campus Facilities Project OAK #4875-3832-5765 v2
Date: _______________________________, 20___ W.E. Lyons Construction Co.
Contractor's Name
By:
Signature
Print Name
Title
Street Address
City, State, Zip code
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
DOCUMENT 00 7200
GENERAL CONDITIONS
Page
General Conditions 00 7200 - i Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
INTERPRETATION OF CONTRACT DOCUMENTS.............................................................. 1 Interpretation of Documents................................................................................................ 1 Order of Precedence of Documents ................................................................................... 1 PRE-BID INVESTIGATIONS................................................................................................... 1 Pre-Bid Investigations Required ......................................................................................... 1 Limited Reliance Permitted On Owner’s Existing Conditions Data .................................... 2 Pre-Bid Investigation Requirements For Excavation and Utilities Relocation Projects ............................................................................................................................................ 2 SUBCONTRACTORS ............................................................................................................. 3 Subcontractor Listing Law................................................................................................... 3 Subcontracts ....................................................................................................................... 3 DRAWINGS AND SPECIFICATIONS..................................................................................... 3 Intent of Drawings and Specifications................................................................................. 3 Checking of Drawings and Specifications........................................................................... 3 Interpretation of Drawings and Specifications .................................................................... 4 Use of Drawings and Specifications. .................................................................................. 4 COMMENCEMENT OF THE WORK....................................................................................... 4 Submission of Required Schedules .................................................................................... 4 Commencement Date of Contract Time ............................................................................. 5 CONTRACTOR’S ORGANIZATION AND EQUIPMENT ........................................................ 5 Contractor’s Legal Address................................................................................................. 5 Contractor’s Superintendents or Forepersons.................................................................... 5 Proficiency In English.......................................................................................................... 5 Contractor’s and Subcontractors’ Employees..................................................................... 5 Contractor’s Use of The Site............................................................................................... 5 Contractor’s Site Office ....................................................................................................... 6 OWNER’S ADMINISTRATION OF WORK ............................................................................. 6 Owner’s Representative(s) ................................................................................................. 6 Owner’s Observation of The Work...................................................................................... 6 Consultant’s Observation of Work ...................................................................................... 6 Owner’s and Consultant’s Exercise of Contract Responsibilities ....................................... 7 Owner’s Right of Access to The Work ................................................................................ 7 Rev. 0
Bid Set - February 25, 2022
DOCUMENT 00 7200
GENERAL CONDITIONS
Page
General Conditions 00 7200 - ii Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Owner’s Right of Separate Construction ............................................................................ 7 CONTRACTOR’S PROSECUTION AND PROGRESS OF THE WORK................................ 7 Contractor to Supervise The Work...................................................................................... 7 Contractor to Maintain Cost Data........................................................................................ 8 Contractor to Supply Sufficient Workers and Materials ...................................................... 8 Contractor to Maintain Project Record Documents ............................................................ 9 Contractor to Not Disrupt Owner Operation........................................................................ 9 Contractor to Provide Temporary Facilities and Controls ................................................... 9 WARRANTY, GUARANTY, AND INSPECTION OF WORK................................................... 9 Warranty and Guaranty....................................................................................................... 9 Inspection of Work ............................................................................................................ 10 Correction of Defective Work ............................................................................................ 11 Acceptance of Defective Work.......................................................................................... 12 Rights upon Inspection, Correction or Acceptance........................................................... 12 Proof of Compliance of Contract Provisions ..................................................................... 12 Correction Period and Project Warranty Period:............................................................... 13 No Waiver ......................................................................................................................... 13 MODIFICATIONS OF CONTRACT DOCUMENTS.............................................................13 Owner’s Right to Direct Changed Work............................................................................ 13 Required Documentation for Changed Work.................................................................... 14 Procedures and Pricing of Changed Work ....................................................................... 14 TIME ALLOWANCES..........................................................................................................14 Time Allowances ............................................................................................................... 14 Excusable Delay and Inexcusable Delay Defined. ........................................................... 14 Notice of Delay.................................................................................................................. 15 Compensable Time Extensions ........................................................................................ 15 Non-Compensable Time Extensions ................................................................................ 15 Adverse Weather .............................................................................................................. 15 Liquidated Damages ......................................................................................................... 16 CLAIMS BY CONTRACTOR...............................................................................................17 Obligation to File Claims for Disputed Work ..................................................................... 17 Form and Contents of Claim ............................................................................................. 17 Rev. 0
Bid Set - February 25, 2022
DOCUMENT 00 7200
GENERAL CONDITIONS
Page
General Conditions 00 7200 - iii Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Administration During/After Claim Submission ................................................................. 18 Compliance ....................................................................................................................... 18 Mediation........................................................................................................................... 18 UNDERGROUND CONDITIONS ........................................................................................19 Contractor to Locate Underground Facilities. ................................................................... 19 Contractor to Protect Underground Facilities.................................................................... 19 Concealed or Unknown Conditions................................................................................... 20 Notice of Hazardous Waste or Materials Conditions ........................................................ 21 LEGAL AND MISCELLANEOUS.........................................................................................22 Laws and Regulations....................................................................................................... 22 Permits and Taxes ............................................................................................................ 22 Communications and Information Distribution .................................................................. 23 Suspension of Work .......................................................................................................... 23 Termination of Contract for Cause.................................................................................... 23 Termination of Contract for Convenience ......................................................................... 24 Contingent Assignment of Subcontracts........................................................................... 24 Remedies and Contract Integration .................................................................................. 25 Interpretation. .................................................................................................................... 25
14.10 Patents .............................................................................................................................. 26
14.11 Substitution for Patented and Specified Articles............................................................... 26
14.12 Interest of Public Officers.................................................................................................. 26
14.13 Limit of Liability.................................................................................................................. 26 WORKING CONDITIONS AND PREVAILING WAGES......................................................26 Use of Site/Sanitary Rules ................................................................................................ 26 Protection of Work, Persons, and Property ...................................................................... 27 Responsibility For Safety and Health................................................................................ 28 Emergencies ..................................................................................................................... 28 Use of Roadways and Walkways...................................................................................... 28 Nondiscrimination.............................................................................................................. 28 Prevailing Wages and Working Hours .............................................................................. 28 Environmental Controls..................................................................................................... 30 Shoring Safety Plan .......................................................................................................... 30 Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 1 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
GENERAL CONDITIONS
INTERPRETATION OF CONTRACT DOCUMENTS
Interpretation of Documents
Contract Documents are complementary; what is called for by one is as binding as if called for by all.
Individual Contract Documents subdivide at first level into Articles, and then into paragraphs.
Order of Precedence of Documents
In the case of discrepancy or ambiguity in the Contract Documents, the following order of precedence shall prevail:
Modifications in inverse chronological order (i.e., most recent first), and in the same order as specific portions they are modifying;
Contract Forms (Document 00 5200 and other 5000 and 6000 series Documents), and terms and conditions referenced therein;
Supplemental General Conditions (Document 00 7301 and other 7300 series Documents), if included;
General Conditions (Document 00 7200);
Division 01 General Requirements, if included;
Drawings and Technical Specifications (Division 02 and above); Written words over figures, unless obviously incorrect; Figured dimensions over scaled dimensions;
Large-scale Drawings over small-scale Drawings.
Any conflict between Drawings and Technical Specifications (Division 2 and above) will be resolved in favor of the document of the latest date (i.e., the most recent document), and if the dates are the same or not determinable, then in favor of Specifications.
Any conflict between a bill or list of materials shown in the Contract Documents and the actual quantities required to complete Work required by Contract Documents, will be resolved in favor of the actual quantities.
All Technical Specifications included in the Project manual shall be included within the Contract Documents unless identified otherwise.
PRE-BID INVESTIGATIONS
Pre-Bid Investigations Required
Prior to and as a condition of submitting a Bid and executing Document 00 5200 (Agreement), Contractor shall make reasonable efforts to investigate fully the Work of the Contract. Contractor shall visit the Site, examine thoroughly and understand fully the nature and extent of the Contract Documents, Work, Site, locality, actual conditions and as-built conditions.
Contractor’s investigation shall include, without limitation, requesting and thoroughly examining of all reports of exploration and tests of subsurface conditions, as-built drawings, drawings, product specification(s) or reports, made available by Owner for pre-bidding or contracting purposes or during Contractor’s pre-bid investigations, of existing above ground and (to the extent applicable) below ground conditions (together, Existing Conditions Data), including, as applicable, Underground Facilities, geotechnical data, as-built data, utility surveys, record documents of all types, hazardous materials surveys, or similar materials which may appear or be referenced in the Project Manual or the in the Contract Documents, and all local conditions, and federal, state and local laws and regulations that in any manner may affect cost, progress, performance or furnishing of Work or which relate to any aspect of the means, methods, techniques, sequences or procedures of construction to be employed by Contractor and safety precautions and programs incident thereto.
Contractor’s investigations shall consider fully the fact that Existing Conditions Data is in many cases based on information furnished to Owner by others (e.g., the prior owner or builders), and that due to their age or their chain of custody since preparation, may not meet current industry Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 2 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
standards for accuracy. Contractor shall also: (i.) provide Owner with prompt written notice of all conflicts, errors, ambiguities, or discrepancies of any type, that it discovered in or among the Contract Documents and the Existing Conditions Data, and (ii.) subject to Owner’s approval, conduct any such additional or supplementary examinations, investigations, explorations, tests, studies and data compilations, concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site or otherwise, which Contractor may deem necessary in order to perform and furnish the Work in accordance with the terms and conditions of Contract Documents.
During performance of the Contract, Contractor will be charged with knowledge of all information that it should have learned in performing these pre-bid investigations and other obligations, and shall not be entitled to Change Orders (time or compensation) due to any information, error, inconsistency, omission, or conditions that Contractor should have known as a part of this Work.
Contractor shall be responsible for the resultant losses, including, without limitation, the cost of correcting Defective Work.
Limited Reliance Permitted On Owner’s Existing Conditions Data Regarding aboveground and as-built conditions shown on the Contract Documents or supplied by Owner, such information has been compiled in good faith, however, Owner does not expressly or impliedly warrant or represent that such information is correctly shown or indicated, or otherwise complete for construction purposes. Contractor must independently verify such information as part of its pre-bid investigations, and where conditions are not reasonably verifiable or discrepancies are identified, bring such matters to Owner’s attention through written question issued during the bid period. In executing Document 00 5200 (Agreement), Contractor shall rely on the results of its own independent investigation and shall not rely on Owner-supplied information regarding aboveground conditions and as-built conditions, and Contractor shall accept full responsibility for its verification work sufficient to complete the Work as intended.
Regarding subsurface conditions other than Underground Facilities shown on the Contract Documents or otherwise supplied by Owner, Contractor may rely only upon the general accuracy of actual reported depths, actual reported character of materials, actual reported soil types, actual reported water conditions, or actual obstructions shown or indicated in the Contract Documents.
Owner is not responsible for the completeness of any subsurface condition information, Contractor’s conclusions or opinions drawn from any subsurface condition information, or subsurface conditions that are not specifically shown. (For example, Owner is not responsible for soil conditions in areas contiguous to areas where a subsurface condition is shown.) Pre-Bid Investigation Requirements For Excavation and Utilities Relocation Projects As part of its pre-bid investigations for Projects involving excavation and/or relocation of existing utilities, Contractor shall make reasonable efforts to verify information regarding Underground Facilities including, without limitation, requesting additional information or verification of information as necessary.
Because of the nature and location of Owner and the Project, the existence of Underground Facilities is deemed inherent in the Work of the Contract, as is the fact that Underground Facilities are not always accurately shown or completely shown on as-built records, both as to their depth and location. Contractor shall, therefore, take care to note the existence and potential existence of Underground Facilities, in particular, above and below grade structures, drainage lines, storm drains, sewers, water, gas, electrical, chemical, hot water, and other similar items and utilities. Contractor shall carefully consider all supplied information, request additional information Contractor may deem necessary, and visually inspect the Site for above ground indications of Underground Facilities (such as, for example not by way of limitation, the existence of existing service laterals, appurtenances or other types of utilities, indicated by the presence of an underground transmission main or other visible facilities, such as buildings, manholes, new asphalt, meters and junction boxes, on or adjacent to the Site). Contractor shall also consider local underground conditions and typical practices for Underground Facilities, either through its own direct knowledge or through its subcontractors, and fully consider this knowledge in assessing the existing information and the reasonableness of its reliance.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 3 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
SUBCONTRACTORS
Subcontractor Listing Law
Contractor shall comply with the Subcontractor Listing law, Public Contract Code Sections 4101, et seq. Contractor shall not substitute any other person or firm in place of any Subcontractor listed in the Bid except as may be allowed by law.
Subcontractors shall not assign or transfer their subcontracts or permit them to be performed by any other contractor without Owner’s written approval. At Owner’s request, Contractor shall provide Owner with a complete copy of all executed subcontracts or final commercial agreements with Subcontractors and/or suppliers.
Subcontracts
Subcontract agreements shall preserve and protect the rights of Owner under the Contract Documents so that subcontracting will not prejudice such rights. To the extent of the Work to be performed by a Subcontractor, Contractor shall require the Subcontractor’s written agreement (i) to be bound to the terms of Contract Documents and (ii) to assume vis-à-vis Contractor all the obligations and responsibilities that Contractor assumes toward Owner under the Contract Documents. (These agreements include, without limitation, all warranties, claims procedures and rules governing submittals of all types to which Contractor is subject under the Contract Documents.)
Contractor shall provide for the assignment to Owner of all rights any Subcontractor (of any tier) may have against any manufacturer, supplier, or distributor for breach of warranties and guarantees relating to the Work performed by the Subcontractor under the Contract Documents.
Subcontracts shall provide and acknowledge Owner as an intended third-party beneficiary of each subcontract and supply contract (of any tier).
DRAWINGS AND SPECIFICATIONS
Intent of Drawings and Specifications
Contractor shall interpret words or phrases used to describe Work (including services), materials, or equipment that have well-known technical or construction industry or trade meaning in accordance with that meaning. Drawings’ intent specifically includes the intent to depict construction that complies with all applicable laws, codes and standards.
As part of the Work, Contractor shall provide all labor, materials, equipment, machinery, tools, facilities, services, employee training and testing, hoisting facilities, Shop Drawings, storage, testing, security, transportation, disposal, the securing of all necessary or required field dimensions, the cutting or patching of existing materials, notices, permits, documents, reports, agreements and any other items required or necessary to timely and fully complete Work described and the results intended by Contract Documents and, in particular, Drawings and Specifications. Divisions and Specification Sections and the identification on any Drawings shall not control Contractor in dividing Work among Subcontractors or suppliers or delineating the Work to be performed by any specific trade.
Contractor shall perform reasonably implied parts of Work as incidental work although absent from Drawings and Specifications. Incidental work includes any work not shown on Drawings or described in Specifications that is necessary or normally or customarily required as a part of the Work shown on Drawings or described in Specifications. Incidental work includes any work necessary or required to make each installation satisfactory, legally operable, functional, and consistent with the intent of Drawings and Specifications or the requirements of Contract Documents. Contractor shall perform incidental work without extra cost to Owner. Incidental work shall be treated as if fully described in Specifications and shown on Drawings, and the expense of incidental work shall be included in price Bid and Contract Sum.
Checking of Drawings and Specifications
Before undertaking each part of Work, Contractor shall carefully study and compare Contract Documents and check and verify pertinent figures shown in the Contract Documents and all applicable field measurements. Contractor shall be responsible for any errors that might have Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 4 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
been avoided by such comparison. Figures shown on Drawings shall be followed; Contractor shall not scale measurements. Contractor shall promptly report to Owner, in writing, any conflict, error, ambiguity or discrepancy that Contractor may discover. Contractor shall obtain a written interpretation or clarification from Owner before proceeding with any Work affected thereby.
Contractor shall provide Owner with a follow-up correspondence every ten Days until it receives a satisfactory interpretation or clarification.
Interpretation of Drawings and Specifications
A typical or representative detail on Drawings shall constitute the standard for workmanship and material throughout corresponding parts of Work. Where necessary, and where reasonably inferable from Drawings, Contractor shall adapt such representative detail for application to such corresponding parts of Work. The details of such adaptation shall be subject to prior approval by Owner. Repetitive features shown in outline on Drawings shall be in exact accordance with corresponding features completely shown.
Should any discrepancy appear or any misunderstanding arise as to the import of anything contained in Drawings and Specifications, or should Contractor have any questions or requests relating to Drawings or Specifications, Contractor shall refer the matter to Owner, in writing, with a copy to the Architect/Engineer. Owner will issue (or cause to be issued) with reasonable promptness written responses, clarifications or interpretations as Owner may determine necessary. All written responses, clarifications and interpretations under this Paragraph shall be consistent with the intent of and be reasonably inferable from Contract Documents, and binding upon Contractor. If Contractor believes that a written response, clarification or interpretation justifies an adjustment in the Contract Sum or Contract Time, Contractor shall give Owner prompt written notice. If the parties are unable to agree to the amount or extent of the adjustment, if any, then Contractor shall perform the Work in conformance with Owner’s response, clarification, or interpretation and may make a written claim for the adjustment as provided in Article 12.
The following general specifications shall apply wherever in the Specifications, or in any directions given by Owner in accordance with or supplementing Specifications, it is provided that Contractor shall furnish materials or manufactured articles or shall do Work for which no detailed specifications are shown. Materials or manufactured articles shall be of the best grade, in quality and workmanship, obtainable in the market from firms of established good reputation. If not ordinarily carried in stock, the materials or manufactured articles shall conform to industry standards for first class materials or articles of the kind required, with due consideration of the use to which they are to be put. Work shall conform to the usual standards or codes, such as those cited herein, for first class work of the kind required. Contractor shall specify in writing to Owner, at least 10 Business Days prior to furnishing such materials or performing such Work, the materials to be used or Work to be performed under this Paragraph.
Use of Drawings and Specifications
Drawings, Specifications and other Contract Documents were prepared for use for Work of Contract Documents only. No part of Contract Documents shall be used for any other construction or for any other purpose except with the written consent of Owner. Any unauthorized use of Contract Documents is prohibited and at the sole liability of the user.
COMMENCEMENT OF THE WORK
Submission of Required Schedules
Unless otherwise indicated in Contract Documents, Contractor shall submit to Owner in draft for review and discussion at the Preconstruction Conference, and in final prior to the first payment application, the following schedules:
Schedule of Values;
Progress Schedule, and
Schedule of Submittals.
No progress payment shall be due or owing to Contractor until such schedules are submitted to and acceptable to Owner and/or Architect/Engineer as meeting the requirements of the Contract Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 5 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Documents. In Owner’s sole discretion, Owner may elect to instead withhold a portion of any progress payment for unacceptable compliance with contract requirements for such schedules.
Owner’s acceptance of Contractor’s schedules will not create any duty of care or impose on Owner any responsibility for the sequencing, scheduling or progress of Work, nor will it interfere with or relieve Contractor from Contractor’s full responsibility therefore.
Commencement Date of Contract Time
The Contract Time will commence to run on the 30th Day after the issuance of the Notice of Award or, if a Notice to Proceed is given, on the date indicated in the Notice to Proceed.
Owner may give a Notice to Proceed at any time within 30 Days after the Notice of Award.
Contractor shall not do any Work at the Site prior to the date on which the Contract Time commences to run.
CONTRACTOR’S ORGANIZATION AND EQUIPMENT
Contractor’s Legal Address
Address and facsimile number given in Contractor’s Bid are hereby designated as Contractor’s legal address and facsimile number. Contractor may change its legal address and facsimile number by notice in writing, delivered to Owner, which in conspicuous language advises Owner of a change in legal address or facsimile number, and which Owner accepts in writing. Delivery to Contractor’s legal address or depositing in any post office or post office box regularly maintained by the United States Postal Service, in a wrapper with postage affixed, directed to Contractor at Contractor’s legal address, or of any drawings, notice, letter or other communication, shall be deemed legal and sufficient service thereof upon Contractor. Facsimile to Contractor’s designated facsimile number of any letter, memorandum, or other communication on standard or legal sized paper, with proof of facsimile transmission, shall be deemed legal and sufficient service thereof upon Contractor.
Contractor’s Superintendents or Forepersons
Contractor shall at all times be represented on Site by one or more superintendents or forepersons authorized and competent to receive and carry out any instructions that Owner may give, and shall be liable for faithful observance of instructions delivered to Contractor or to authorized representative or representatives on Site.
Proficiency In English
Supervisors, security guards, safety personnel and employees who have unescorted access to the Site shall possess proficiency in the English language in order to understand, receive and carry out oral and written communications or instructions relating to their job functions, including safety and security requirements.
Contractor’s and Subcontractors’ Employees
Contractor shall employ, and shall permit its Subcontractors to employ, only competent and skillful personnel to do Work. If Owner notifies Contractor that any of its employees, or any of its Subcontractors’ employees on Work is incompetent, unfaithful, disorderly or profane, or fails to observe customary standards of conduct or refuses to carry out any provision of the Contract Documents, or uses threatening or abusive language to any person on Work representing Owner, or violates sanitary rules, or is otherwise unsatisfactory, and if Owner requests that such person be discharged from Work, then Contractor or its Subcontractor shall immediately discharge such person from Work and the discharged person shall not be re-employed on the Work except with consent of Owner.
Contractor’s Use of The Site
Contractor shall not make any arrangements with any person to permit occupancy or use of any land, structure or building within the limits of the Work, for any purpose whatsoever, either with or without compensation, in conflict with any agreement between Owner and any Owner, former Owner or tenant of such land, structure or buildings. Contractor may not occupy Owner-owned Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 6 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
property outside the limit of the Work as indicated on the Drawings unless it obtains prior approval from Owner.
Contractor’s Site Office
Unless expressly provided otherwise in the Contract Documents, Contractor shall provide a site office staffed by a resident project manager or job superintendent.
OWNER’S ADMINISTRATION OF WORK
Owner’s Representative(s)
Owner’s Representative(s) will have limited authority to act on behalf of Owner as set forth in the Contract Documents.
Except as otherwise provided in these Contract Documents or subsequently identified in writing by Owner, Owner will issue all communications to Contractor through Owner’s Representative, and Contractor shall issue all communications to Owner through Owner’s Representative in a written document delivered to Owner.
Should any direct communications between Contractor and Owner’s consultants, architects or engineers not identified in Article 2 of Document 00 5200 (Agreement) occur during field visits or by telephone, Contractor shall immediately confirm them in a written document copied to Owner.
Owner’s Observation of The Work
Work shall be performed under Owner’s general observation and administration. Contractor shall comply with Owner’s directions and instructions in accordance with the terms of Contract Documents, but nothing contained in these General Conditions shall be taken to relieve Contractor of any obligations or liabilities under the Contract Documents. Owner’s failure to review or, upon review, failure to object to any aspect of Work reviewed, shall not be deemed a waiver or approval of any non-conforming aspect of Work.
Subject to those rights specifically reserved in the Contract Documents, Owner will not supervise, or direct, or have control over, or be responsible for, Contractor’s means, methods, techniques, sequences or procedures of construction, or the safety precautions and programs incident thereto, or Contractor’s failure to comply with laws and regulations applicable to the furnishing or performance of Work. Owner will not be responsible for Contractor’s failure to perform or furnish the Work in accordance with Contract Documents.
Consultant’s Observation of Work
Owner may engage one or more of the following to assist in administering the Work: an Architect/Engineer, Project Manager, Construction Manager, or any other independent consultant (collectively for purposes of this Article 7, Consultant). If so engaged, Consultant will advise and consult with Owner, but will have authority to act on behalf of Owner only to extent provided in the Contract Documents or as set forth in writing by Owner. Consultant will not be responsible for and will not have control or charge of construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with Work. Consultant will not be responsible for or have control over the acts or omissions of Contractor, Subcontractors or their agents or employees, or any other persons performing Work.
Consultant may review Contractor’s Submittals, such as Shop Drawings, Product Data, and Samples, but only for conformance with design concept of Work and with information given in the Contract Documents.
Consultant may visit the Site at intervals appropriate to stage of construction to become familiar generally with the progress and quality of Work and to determine in general if Work is proceeding in accordance with Contract Documents. Based on its observations, Consultant may recommend to Owner that it disapproves or rejects Work that Consultant believes to be Defective or will not produce a complete Project that conforms to Contract Documents, or will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by Contract Documents. Consultant may also recommend to Owner special inspection or testing of Work, whether or not the Work is fabricated, installed, or completed.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 7 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Consultant may conduct observations or inspections to recommend to Owner the dates that Contractor has achieved Substantial Completion and Final Completion, and will receive and forward to Owner for review written warranties and related documents required by Contract Documents.
Owner’s and Consultant’s Exercise of Contract Responsibilities Owner, Consultant, and all Owner’s representatives, in performing their duties and responsibilities under the Contract Documents, accept no duties, responsibilities or duty of care, nor may the same be implied or inferred, towards Contractor, any Subcontractor, sub-Subcontractor or supplier, except those set forth expressly in the Contract Documents.
Owner’s Right of Access to The Work
During performance of Work, Owner, Consultant, and all Owner’s representatives may at any time enter upon Work, shops or studios where any part of the Work may be in preparation, or factories where any materials for use in Work are being or are to be manufactured, and Contractor shall provide proper and safe facilities for this purpose, and shall make arrangements with manufacturers to facilitate inspection of their processes and products to such extent as Owner’s interests may require. Other contractors performing work for Owner may also enter upon Work for all purposes required by their respective contracts. Subject to the rights reserved in the Contract Documents, Contractor shall have sole care, custody, and control of the Site and its Work areas.
Owner’s Right of Separate Construction
Owner may perform with its own forces, construction or operations related to the Project, or the Site during Contractor’s operations. Owner may also award separate contracts in connection with other portions of the Project or other construction or operations, on the Site or areas contiguous to the Site, under conditions similar to these Contract Documents, or may have utility Owners perform other work.
Contractor shall adjust its schedule and fully coordinate with and shall afford all other contractors, utility districts and Owner (if Owner is performing work with its own forces), proper and safe access to the Site, and reasonable opportunity for the installation and storage of their materials.
Contractor shall ensure that the execution of its Work properly connects and coordinates with others’ work, do all cutting, fitting and patching of the Work that may be required to make its several parts come together properly and integrate with such other work, and shall cooperate with them to facilitate the progress of the Work.
To the extent that any part of Contractor’s Work is to interface with work performed or installed by other contractors or utility owners, Contractor shall inspect and measure the in-place work.
Contractor shall promptly report to Owner in writing any defect in in-place work that will impede or increase the cost of Contractor’s interface unless corrected.
CONTRACTOR’S PROSECUTION AND PROGRESS OF THE WORK
Contractor to Supervise The Work
Subject to those rights specifically reserved in the Contract Documents, Contractor shall supervise, direct, have control over, and be responsible for, Contractor’s means, methods, techniques, sequences or procedures of construction, safety precautions and programs incident thereto, and compliance with laws and regulations applicable to the furnishing or performance of Work.
Contractor shall keep on the Site at all times during Work progress a competent resident Superintendent, who shall not be replaced without Owner’s express written consent and, if applicable, payment of liquidated damages as required by Document 00 5200 (Agreement). The Superintendent shall be Contractor’s representative at the Site and shall have complete authority to act on behalf of Contractor. All communications to and from the Superintendent shall be as binding as if given to or by Contractor.
Contractor shall supervise, inspect, and direct Work competently and efficiently, devoting the attention and applying such personal skills and expertise as may be required and necessary to Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 8 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
perform Work in accordance with Contract Documents. Contractor shall be solely responsible for and have control and charge of construction means, methods, techniques, sequences and procedures, safety precautions and programs in connection with the Work. Contractor shall be responsible to see that the completed Work complies accurately with Contract Documents.
Contractor is fully responsible for Contractor’s own acts and omissions. Contractor is responsible for all acts and omissions of its Subcontractors, suppliers, and other persons and organizations performing or furnishing any of the Work, labor, materials, or equipment under a direct or indirect contract with Contractor.
Contractor shall conduct monthly Contractor Safety Committee meetings, and weekly toolbox safety talks.
Contractor to Maintain Cost Data
Contractor shall maintain full and correct information as to the number of workers employed in connection with each subdivision of Work, the classification and rate of pay of each worker in form of certified payrolls, the cost to Contractor of each class of materials, tools and appliances used by Contractor in Work, and the amount of each class of materials used in each subdivision of Work. Contractor shall provide Owner with monthly summaries of this information. If Contractor maintains or is capable of generating summaries or reports comparing actual Project costs with Bid estimates or budgets, Contractor shall provide Owner with a copy of such report upon Owner’s request.
Contractor shall maintain daily job reports recording all significant activity on the job, including the number of workers on Site, Work activities, problems encountered and delays. Contractor shall provide Owner with copies for each Day Contractor works on the Project, to be delivered to Owner either the same Day or the following morning before starting work at the Site. Contractor shall take pre-construction and monthly progress photographs of all areas of the Work.
Contractor shall maintain copies of all correspondence with Subcontractors and records of meetings with Subcontractors.
Owner shall have the right to audit and copy Contractor’s books and records of any type, nature or description relating to the Project (including, without limitation, financial records reflecting in any way costs claimed on the Project), and to inspect the Site, including Contractor’s trailer, or other job Site office, and this requirement shall be contained in the subcontracts of Subcontractors working on Site. By way of example, Owner shall have the right to inspect and obtain copies of all Contract Documents, planning and design documents, Bid proposal and negotiation documents, cost records and job cost variance reports, design modification proposals, value engineering or other cost reduction proposals, revisions made to the original design, job progress reports, photographs, and as-built drawings maintained by Contractor. Owner and any other applicable governmental entity shall have the right to inspect all information and documents maintained hereunder at any time during the Project and for a period of five years following Final Completion, in accordance with the provisions of Government Code Section 8546.7. This right of inspection shall not relieve Contractor of its duties and obligations under the Contract Documents.
This right of inspection shall be specifically enforceable in a court of law, either independently or in conjunction with enforcement of any other rights in the Contract Documents.
Contractor to Supply Sufficient Workers and Materials
Unless otherwise required by Owner under the terms of Contract Documents, Contractor shall at all times keep on the Site materials and employ qualified workers sufficient to prosecute Work at a rate and in a sequence and manner necessary to complete Work within the Contract Time.
This obligation shall remain in full force and effect notwithstanding disputes or claims of any type.
At any time during progress of Work should Contractor directly or indirectly (through Subcontractors) refuse, neglect, or be unable to supply sufficient materials or employ qualified workers to prosecute the Work as required, then Owner may require Contractor to accelerate the Work and/or furnish additional qualified workers or materials as Owner may consider necessary, at no cost to Owner. If Contractor does not comply with the notice within three Business Days of date of service thereof, Owner shall have the right (but not a duty) to provide materials and qualified workers to finish the Work or any affected portion of Work, as Owner may elect. Owner may, at its discretion, exclude Contractor from the Site, or portions of the Site or separate work Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 9 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
elements during the time period that Owner exercises this right. Owner will deduct from moneys due or which may thereafter become due under the Contract Documents, the sums necessary to meet expenses thereby incurred and paid to persons supplying materials and doing Work.
Owner will deduct from funds or appropriations set aside for purposes of Contract Documents the amount of such payments and charge them to Contractor as if paid to Contractor. Contractor shall remain liable for resulting delay, including liquidated damages and indemnification of Owner from claims of others.
Exercise by Owner of the rights conferred upon Owner in this subparagraph is entirely discretionary on the part of Owner. Owner shall have no duty or obligation to exercise the rights referred to in this subparagraph and its failure to exercise such rights shall not be deemed an approval of existing Work progress or a waiver or limitation of Owner’s right to exercise such rights in other concurrent or future similar circumstances. (The rights conferred upon Owner under this subparagraph are, like all other such rights, cumulative to Owner’s other rights under any provision of the Contract Documents.)
Contractor to Maintain Project Record Documents
As more specifically described in Section 01 7839, Contractor shall maintain in a safe place at the Site one record copy of all Drawings, Specifications, Addenda, Contract Modifications, Change Orders, Work Directives, Force Account orders, and written interpretations and clarifications in good order and annotated to show all as-built changes made during construction. These Project Record Documents, together with all approved Samples and a counterpart of all approved Shop Drawings, shall be maintained and available to Owner for reference. Upon completion of the Work, Contractor shall deliver to Owner, the Project Record Documents, Samples and Shop Drawings and as-built drawings.
Throughout Contractor’s performance of the Work of the Project, Contractor shall maintain construction records to include: shop drawings; product data/material data sheets; samples; submittal; purchases; materials; equipment; inspections; applicable handbooks; applicable codes and standards; maintenance and operating manuals and instructions; RFI Log; Submittal Log; other related documents and revisions which arise out of the Construction Contracts. Contractor shall maintain records of principal building layout lines, elevations for the bottom of footings, floor levels, and key site elevations (certified by a qualified surveyor or professional engineer).
Contractor shall make all records available to Owner. At the completion of the Project, Contractor shall deliver all such records to the Owner to have a complete set of record as-built drawings.
Contractor to Not Disrupt Owner Operation
Contractor shall schedule and execute all Work in a manner that does not interfere with or disrupt Owner operations including, without limitation, parking, utilities (electricity, gas, water), noise, access by employees and administration, access by vendors, physicians, patients and any other person or entity using Owner facilities or doing business with Owner. Contractor shall produce and supply coordination plans and requests to Owner, following Owner procedures, for all necessary interference of construction with Owner, which Owner will reasonably cooperate with.
Contractor to Provide Temporary Facilities and Controls Unless expressly provided otherwise in the Contract Documents, Contractor shall provide all temporary utilities (including without limitation electricity, water, natural gas), lighting, heating, cooling and ventilating devices, telephone, sanitary facilities, barriers, fences and enclosures, tree and plant protection, fire protection, pollution, erosion, Storm Water Pollution Prevention controls, noise and traffic control, and any other necessary services required for construction, testing or completion of the Work.
WARRANTY, GUARANTY, AND INSPECTION OF WORK
Warranty and Guaranty
General Representations and Warranties: Contractor represents and warrants that it is and will be at all times fully qualified and capable of performing every Phase of the Work and to complete Work in accordance with the terms of Contract Documents. Contractor warrants that all Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 10 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
construction services shall be performed in accordance with generally accepted professional standards of good and sound construction practices and all requirements of Contract Documents.
Contractor warrants that Work including, without limitation, each item of materials and equipment incorporated therein, shall be new, of suitable grade of its respective kind for its intended use, and free from defects in design, engineering, materials, construction and workmanship.
Contractor warrants that Work shall conform in all respects with all applicable requirements of federal, state and local laws, applicable construction codes and standards, licenses, and permits, Drawings and Specifications and all descriptions set forth therein, and all other requirements of Contract Documents. Contractor shall not be responsible, however, for the negligence of others in the specification of specific equipment, materials, design parameters and means or methods of construction where that is specifically shown and expressly required by Contract Documents.
Extended Warranties: Any warranty exceeding one year provided by the supplier or manufacturer of any equipment or materials used in the Project shall be extended for such term. Contractor expressly agrees to act as co-guarantor of such equipment and materials and shall supply Owner with all warranty and guarantee documents relative to equipment and materials incorporated in the Project and guaranteed by their suppliers or manufacturers.
Environmental and Toxics Warranty: The covenants, warranties and representations contained in this Paragraph are effective continuously during Contractor’s Work on the Project and following cessation of labor for any reason including, without limitation, Project completion. Contractor covenants, warrants and represents to Owner that:
To Contractor’s knowledge after due inquiry, no lead or Asbestos-containing materials were installed or discovered in the Project at any time during Contractor’s construction thereof. If any lead or Asbestos-containing materials were discovered, Contractor made immediate written disclosure to Owner.
To Contractor’s knowledge after due inquiry, no electrical transformers, light fixtures with ballasts or other equipment containing PCBs are or were located on the Project at any time during Contractor’s construction thereof.
To Contractor’s knowledge after due inquiry, no storage tanks for gasoline or any other toxic substance are or were located on the Project at any time during Contractor’s construction thereof. If any such materials were discovered, Contractor made immediate written disclosure to Owner.
Contractor’s operations concerning the Project are and were not in violation of any applicable environmental federal, state, or local statute, law or regulation dealing with hazardous materials substances or toxic substances and no notice from any governmental body has been served upon Contractor claiming any violation of any such law, ordinance, code or regulation, or requiring or calling attention to the need for any Work, repairs, construction, alteration, or installation on or in connection with the Project in order to comply with any such laws, ordinances, codes, or regulations, with which Contractor has not complied. If there are any such notices with which Contractor has complied, Contractor shall provide Owner with copies thereof.
Inspection of Work
Work and materials, and manufacture and preparation of materials, from beginning of construction until Final Completion and acceptance of Work, shall be subject to inspection and rejection by Owner, its agents, representatives or independent contractors retained by Owner to perform inspection services, or governmental agencies with jurisdictional interests. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s Site safety procedures and program so that they may comply therewith as applicable. Upon request or where specified, Owner shall be afforded access for inspection at the source of supply, manufacture or assembly of any item of material or equipment, with reasonable accommodations supplied for making such inspections.
Contractor shall furnish, in such quantities and sizes as may be required for proper examination and tests, Samples or test specimens of all materials to be used or offered for use in connection with Work. Contractor shall prepare Samples or test specimens at its expense and furnish them to Owner. Contractor shall submit all Samples in ample time to enable Owner to make any Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 11 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
necessary tests, examinations, or analyses before the time it is desired to incorporate the material into the Work.
Contractor shall give Owner timely notice of readiness of Work for all required inspections, tests or approvals, and shall cooperate with inspection and testing personnel to facilitate required inspections or tests.
Upon advance notice as set forth above, Owner will endeavor to schedule required inspections, but if resources are not available, Contractor may need to reschedule the Work at no additional cost to the Owner.
If applicable laws or regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested or approved by an employee or other representative of such public body, Contractor shall assume full responsibility for arranging and obtaining such inspections, tests or approvals, and furnish Owner with the required certificates of inspection, or approval. Owner will pay the cost of initial testing and Contractor shall pay all costs in connection with any follow-up or additional testing. Contractor shall also be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests or approvals required for the acceptance of materials or equipment to be incorporated in the Work, or of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
If Contractor covers any Work, or the work of others, prior to any required inspection, test or approval without written approval of Owner, Contractor shall uncover the Work at Owner’s request. Contractor shall bear the expense of uncovering Work and replacing Work. In any case where Contractor covers Work contrary to Owner’s request, Contractor shall uncover Work for Owner’s observation or inspection at Owner’s request. Contractor shall bear the cost of uncovering Work.
Whenever required by Owner, Contractor shall furnish tools, labor and materials necessary to make examination of Work that may be completed or in progress, even to extent of uncovering or taking down portions of finished Work. Should Work be found unsatisfactory, cost of making examination and of reconstruction shall be borne by Contractor. If Work is found to be satisfactory, Owner, in manner herein prescribed for paying for alterations, Modifications, and extra Work, except as otherwise herein specified, will pay for examination.
Inspection of the Work by or on behalf of Owner, or Owner’s failure to do so, shall not under any circumstances be deemed a waiver or approval of any non-conforming aspect of the Work.
Contractor shall have an absolute duty, in the absence of a written Change Order signed by Owner, to perform Work in conformance with the Contract Documents and to immediately correct Defective Work immediately upon Contractor’s knowledge.
Any inspection, evaluation, or test performed by or on behalf of Owner relating to the Work is solely for the benefit of Owner, and shall not be relied upon by Contractor. Contractor shall not be relieved of the obligation to perform Work in accordance with the Contract Documents, nor relieved of any guaranty, warranty, or other obligation, as a result of any inspections, evaluations, or tests performed by Owner, whether or not such inspections, evaluations, or tests are permitted or required under the Contract Documents. Contractor shall be solely responsible for testing and inspecting Work already performed to determine whether such Work is in proper condition to receive later Work.
Correction of Defective Work
Owner may direct Contractor to correct any Defective Work or remove it from the Site and replace it with Work that is not Defective and satisfactorily correct or remove and replace any damage to other Work or the work of others resulting from the correction or removal. Also, if Contractor fails to supply sufficient skilled workers, suitable materials or equipment, or to furnish or perform the Work in such a way that the completed Work will conform to Contract Documents, Owner may direct Contractor to perform the Work in accordance with the Contract Documents, correct or replace any such Defective Work, or stop any portion of Work.
Owner may correct and remedy the Defective Work or perform any other work, corrective or otherwise, if, after five Days’ written notice to Contractor, Contractor fails to correct Defective Work or to remove and replace rejected Work; or provide a plan for correction of Defective Work acceptable to Owner; or perform Work in accordance with Contract Documents. In connection Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 12 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
with such corrective and remedial action, Owner may exclude Contractor from all or part of the Site; take possession of all or part of Work and suspend Contractor’s Work related thereto; take possession of all or part of Contractor’s tools, appliances, construction equipment and machinery at the Site; and incorporate in Work any materials and equipment stored at the Site or for which Owner has paid Contractor but which are stored elsewhere. Contractor shall allow Owner, its representatives, agents, employees, and other contractors and consultants’ access to the Site to enable Owner to exercise the rights and remedies under this Paragraph.
Contractor shall be responsible for all claims, costs, losses, damages, expenses and liabilities incurred or sustained by Owner in exercising rights and remedies under this Paragraph.
Contractor shall be responsible for any and all claims, costs, losses and damages caused by or resulting from such correction or removal. A Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work and the Contract Sum.
If the parties are unable to agree to the amount of an appropriate decrease in the Contract Sum, Owner may decide the proper amount or, in its discretion may elect to leave the Contract Sum unchanged and deduct from monies due Contractor, all such claims, costs, losses and damages caused by or resulting from exercising its rights and remedies. If Contractor disagrees with Owner’s calculations, it may make a claim as provided in Article 12 of this Document 00 7200.
These Owner rights and remedies are entirely discretionary on the part of Owner, and shall not give rise to any duty on the part of Owner to exercise the rights for the benefit of Contractor or any other party. Owner’s rights under this Paragraph shall be in addition to any other rights it may have under the Contract Documents or by law. Owner’s failure to demand correction of defective work does not relieve the Contractor from delivering a Project that comports with the Project’s plans and specifications.
Acceptance of Defective Work
Owner may in its sole discretion elect to accept Defective Work. Contractor shall pay all claims, costs, losses and damages attributable to Owner’s evaluation of and determination to accept such Defective Work. If Owner accepts any Defective Work prior to final payment, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work and the Contract Sum. If the parties are unable to agree to the amount of an appropriate decrease in the Contract Sum, Owner may deduct from monies due Contractor, all claims, costs, losses, damages, expenses and liabilities attributable to the Defective Work. If Contractor disagrees with Owner’s calculations, Contractor may make a claim as provided in Article 12 of this Document 00 7200. If Owner accepts any Defective Work after final payment, Contractor shall pay to Owner, an appropriate amount as determined by Owner.
Rights upon Inspection, Correction or Acceptance
Contractor shall not be allowed an extension of Contract Time because of any delay in the performance of Work attributable to the exercise by Owner of its rights and remedies under this Article. Where Owner exercises its rights under this Article, it retains and may still exercise all other rights it has by law or under the Contract Documents including, without limitation, the right to terminate Contractor’s right to proceed with the Work under the Contract Documents for cause and/or make a claim or back charge where a Change Order cannot be agreed upon.
Observation or inspection by Owner or its authorized agents or representatives shall not relieve Contractor of its obligation to have furnished material and workmanship in accordance with Contract Documents. Payment for Work completed through periodic progress payments, final payment or otherwise shall not operate to waive Owner’s right to require full compliance with Contract Documents and shall in no way be deemed as acceptance of any defective Work paid therefor. Contractor’s obligation to complete the Work in accordance with Contract Documents shall be absolute, unless Owner agrees otherwise in writing.
Proof of Compliance of Contract Provisions
In order that Owner may determine whether Contractor has complied or is complying with requirements of Contract Documents not readily enforceable through inspection and tests of Work and materials, Contractor shall at any time, when requested, submit to Owner properly Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 13 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
authenticated documents or other satisfactory proofs of compliance with all applicable requirements.
Before commencing any portion of Work, Contractor shall inform Owner in writing as to time and place at which Contractor wishes to commence Work, and nature of Work to be done, in order that proper provision for inspection of Work may occur, and to assure measurements necessary for record and payment. Information shall be given to Owner a reasonable time in advance of time at which Contractor proposes to begin Work, so that Owner may complete necessary preliminary work without inconvenience or delay to Contractor.
Correction Period and Project Warranty Period
If within one year after the date of Final Acceptance, or such longer period of time as may be prescribed by laws, regulations or by the terms of Contract Documents or any extended warranty or guaranty, any Work (completed or incomplete) is found to be Defective, Contractor shall promptly without cost to Owner and in accordance with Owner’s written instructions, correct such Defective Work. Contractor shall remove any Defective Work rejected by Owner and replace it with Work that is not Defective, and satisfactorily correct or remove and replace any damage to other Work or the work of others resulting therefrom. If Contractor fails to promptly comply with the terms of such instructions, or in an emergency where delay would cause serious risk of loss or damage, Owner may have the Defective Work corrected or the rejected Work removed and replaced. Contractor shall pay for all claims, costs, losses and damages caused by or resulting from such removal and replacement. Where Contractor fails to correct Defective Work, or defects are discovered outside the correction period, Owner shall have all rights and remedies granted by law.
In special circumstances where a part of the Work is occupied or a particular item of equipment is placed in continuous service before Final Acceptance of all the Work, the correction period for that part of Work or that item may start to run from an earlier date if so provided by Change Order.
Where Defective Work or rejected Work (and damage to other Work resulting therefrom) has been corrected, removed, or replaced under this Paragraph after the commencement of the correction period, the correction period hereunder with respect to such Work shall be extended for an additional period of one year after such correction or removal and replacement has been satisfactorily completed.
No Waiver
Neither recordation of Final Acceptance, nor final certificate for payment, nor provision of the Contract, nor partial or entire use or occupancy of premises by Owner shall constitute acceptance of Work not done in accordance with Contract Documents nor relieve Contractor of liability in respect to express warranties or responsibility for faulty materials or workmanship.
If, after installation, operation, or use of materials or equipment to be provided under Contract proves to be unsatisfactory to Owner, Owner shall have the right to operate and use materials or equipment until said materials and equipment can, without damage to Owner, be taken out of service for correction or replacement. Period of use of Defective materials or equipment pending correction or replacement shall in no way decrease guarantee period required for acceptable corrected or replaced items of materials or equipment.
Nothing in the Contract Documents shall be construed to limit, relieve, or release Contractor’s, Subcontractors’, and equipment suppliers’ liability to Owner for damages sustained as result of latent defects in materials or equipment caused by negligence of Contractor, its agents, suppliers, employees, or Subcontractors.
MODIFICATIONS OF CONTRACT DOCUMENTS
Owner’s Right to Direct Changed Work
Owner may, without notice to the sureties and without invalidating the Contract, make changes in the Work (Changed Work), including without limitation: alterations, deviations, additions to, or deletions from Contract Documents; increase or decrease the quantity of any item or portion of the Work; expand, reduce or otherwise change the Contract Time; delete any item or portion of Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 14 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
the Work; and require extra Work. Contractor shall perform such Work under applicable provisions of the Contract Documents, unless specifically provided otherwise at the time the change is ordered. In the case of any ordered extra Work, Owner reserves the right to furnish all or portions of associated labor, material, and equipment, which Contractor shall accept and use without payment for costs, markup, profit, or otherwise for such Owner-furnished labor, materials, and equipment.
If Changed Work is of such a nature as to increase or decrease the time or cost of any part of Work, price fixed in Contract shall be increased or decreased by amount as the Contractor and Owner may agree upon as reasonable and proper allowance for increase or decrease in cost of Work using the cost guidelines set forth in this Article, and absent such agreement, then as Owner may direct (with Contractor retaining its rights under Article 12 herein).
Required Documentation for Changed Work
Changes affecting the Contract Time or Contract Sum of the Work shall be set forth in a written Change Order or Change Directive that shall specify:
The Work performed in connection with the change to be made; The amount of the adjustment of the Contract Sum, if any, and the basis for compensation for the Work ordered; and
The extent of the adjustment in the Contract Time, if any.
A Change Order or Change Directive will become effective when signed by Owner, notwithstanding that Contractor has not signed it. A Change Order will become effective without Contractor’s signature, provided Owner indicates same thereon (by indicating it as a “unilateral change order”).
All changes in any plans and specifications approved by any authority with jurisdiction may also require addenda or change orders approved by that authority.
Where Owner requests, a performance bond rider covering the changed Work must be executed and delivered to Owner before proceeding with the changed Work or shortly in time thereafter.
Procedures and Pricing of Changed Work
Procedures for changed work and pricing of changed work, claims and all forms of extra compensation, are set forth in Section 01 2600 (Modification Procedures).
TIME ALLOWANCES
Time Allowances
Time is of the essence. Contract Time may only be changed by Change Order, and all time limits stated in the Contract Documents are to mean that time is of the essence.
Float. Float shall be treated as a Project resource. Contractor shall not be entitled to a time extension for impacts that consume float, but do not impact the critical path.
Time extensions will not be granted unless substantiated by the Critical Path Method (CPM) Schedule, and then not until the CPM project float becomes zero. If Contractor fails to submit a Time Impact Evaluation (TIE), as required by Section 01 2600 (Modification Procedures) and Section 01 3200 (Progress Schedules and Reports), within the required time period, then Contractor shall be deemed to have agreed that there is no time impact and that Contractor has irrevocably waived its rights to any additional Contract Time.
Excusable Delay and Inexcusable Delay Defined
Excusable Delay. Subject to the provisions on Notice of Delay below, Contract Time may be adjusted in an amount equal to the time lost due to:
Changes in the Work ordered by Owner (Changes);
Acts or neglect by Owner, Architect, any Owner Representative, utility owners or other contractors performing other work, not permitted or provided for in the Contract Documents, provided that Contractor has performed its responsibilities under the Contract Documents (including, without limitation, pre-bid investigations) (Acts or Neglect); or Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 15 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Acts of God, fires, floods, earthquake, other natural disasters, epidemics and pandemics (other than COVID-19 or variants), abnormal weather conditions beyond the parameters otherwise set forth in this Article, nuclear accidents, strikes, lockouts, freight embargos, interruptions in service by a regulated utility, or governmental statutes or regulations enacted or imposed after the fact (together, “force majeure events”), provided damages or delays resulting therefrom are not the result of Contractor’s fault or negligence, including without limitation failure to protect the Work or mitigate any adverse impacts as required by Contract Documents (Force Majeure).
Inexcusable Delay. Contract Time shall not be extended for any period of time where Contractor (and/or any Subcontractor) is delayed or prevented from completing any part of the Work due to a cause that is within Contractor’s risk or responsibility under the Contract Documents. Delays attributable to or within the control of a Subcontractor, or its subcontractors, or supplier, are deemed delays within the control of Contractor.
Notice of Delay
Within seven Days of the beginning of any delay (excepting adverse weather delays), Contractor shall notify Owner in writing, by submitting a notice of delay that shall describe the anticipated delays resulting from the delay event in question. If Contractor requests an extension of time, Contractor shall submit a TIE, in accordance with by Section 01 2600 (Modification Procedures) and Section 01 3200 (Progress Schedules and Reports), within ten days of the notice of delay.
Owner will determine all claims and adjustments in the Contract Time. No claim for an adjustment in the Contract Time will be valid and such claim will be waived if not submitted in accordance with the requirements of this subparagraph. In cases of substantial compliance with the seven-day notice requirement here (but not to exceed twenty-one days from the beginning of the delay event), Owner may in its sole discretion recognize a claim for delay accompanied with the proper TIE, provided Contractor also shows good faith and a manifest lack of prejudice to Owner from the late notice.
Compensable Time Extensions
Subject to other applicable provisions of the Contract Documents, Contractor may be entitled to adjustment in Contract Sum in addition to Contract Time for:
Excusable delay caused solely by Changes in the Work ordered by Owner, as provided above, and/or
Excusable delay caused solely by Acts or Neglect by Owner or other person, as provided above.
Non-Compensable Time Extensions
Subject to other applicable provisions of the Contract Documents, Contractor may be entitled to adjustment in Contract Time only, without adjustment in Contract Sum, for Periods of excusable delay caused solely by weather or Force Majeure events as provided above in this Article, or
Periods of concurrent delay, where delay results from two or more causes, one of which is compensable (resulting from Changes or Acts or Neglect as set forth above in this Article), and the other of which is non-compensable or unexcusable, such as: acts or neglect of Contractor, Subcontractors or others for whom Contractor is responsible; other acts, omissions and conditions which would not entitle Contractor to adjustment in Contract Time; adverse weather; and/or actions of Force Majeure as provided above in this Article.
Adverse Weather
Adverse weather delays may be allowed only if the number of workdays of adverse weather exceeds the parameters listed or referenced immediately below in this subparagraph and Contractor proves that adverse weather actually caused delays to work on the critical path.
Contractor shall give written notice of intent to claim an adverse weather day within one Day of the adverse weather day occurring.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 16 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Claims for extension of time for rain delay will not be granted unless the number of days work is prevented by rain exceeds [insert either] 100% of the historical average number of rain days for the period of the Contract Time, based on the records of the National Oceanic & Atmospheric Administration (NOAA) weather station identified in Supplemental Conditions or, if not, the station closest to the Project Site (in either case, Weather Station), as measured and reported by NOAA. (For example, for California, Oregon and Washington, these figures are contained in the “>=0.10 inch” column at the applicable weather station’s “General Climate Summary Table” for “Precipitation” at http://www.wrcc.dri.edu/climate-summaries/), pro-rated in the individual month Contractor starts and finishes Work. [or] the total number of adverse weather days indicated in the Supplemental Conditions, based on the records of the National Oceanic & Atmospheric Administration National Weather Service (NOAA) weather station identified in Supplemental Conditions or, if not, the station closest to the Project Site (in either case, Weather Station). [Whichever of the above alternatives is selected, continue] Delays due to adverse weather conditions will not be allowed for weather conditions that fall within these parameters.
In order to qualify as an adverse weather delay day with respect to the foregoing parameters, daily rainfall must exceed 0.1 inch at the Weather Station, as measured and reported by NOAA.
Notwithstanding these allowances, Contractor shall at all times employ all available mitigation measures to enable Work to continue, Contractor shall take reasonable steps to mitigate potential weather delays, such as dewatering the Site, lime treatment, and covering Work and material that could be affected adversely by weather. Failure to do so shall be cause for Owner to not grant a time extension due to adverse weather, where Contractor could have avoided or mitigated the potential delay by exercising reasonable care.
Contractor shall include the foregoing precipitation parameters as a monthly activity in its progress schedule. As Work on the critical path is affected by precipitation, Contractor shall notify Owner and request that the days be moved to the affected activities. Any adverse weather days remaining shall be considered Project float available to either Owner or Contractor.
Adverse weather delay for precipitation shall be recognized for the actual period of time Contractor proves it was delayed by precipitation exceeding the specified parameters. For example, and not by way of limitation, if precipitation exceeding the specified parameters does not in fact delay Contractor’s progress on the critical path, then no time extension shall be recognized; and conversely, if Contractor proves to Owner’s satisfaction that precipitation exceeding the specified parameters causes delay to Contractor for a period longer than the number of precipitation days incurred (e.g., if it rains or snows during grading work), then Contractor shall be entitled to a time extension equal to the actual period of such delay.
During unfavorable weather, wet ground, or other unsuitable construction conditions, Contractor shall employ best practices to protect the Work, manage the construction site and rainwater during inclement weather. Persons performing the Work shall examine surfaces to receive their Work and shall report in writing to Contractor, with copy to Owner representative and the Architect conditions detrimental to the Work. Failure to examine and report discrepancies makes the Contractor responsible, at no increase in Contract Sum, for corrections Owner may require.
Commencement of Work constitutes acceptance of surface.
Liquidated Damages
Time is of the essence. Execution of Contract Documents by Contractor shall constitute its acknowledgement that Owner will actually sustain damages in the form of Contract administration expenses (such as Project management and consultant expenses) in the amount fixed in the Contract Documents for each and every Day during which completion of Work required is delayed beyond expiration of time fixed for completion plus extensions of time allowed pursuant to provisions hereof.
Contractor and Owner agree that because of the nature of the Project, it would be impractical or extremely difficult to fix the amount of such actual damages incurred by Owner because of a delay in completion of all or any part of the Work. Contractor and Owner agree that specified measures of liquidated damages shall be presumed to be the amount of such damages actually sustained by Owner, and that because of the nature of the Project, it would be impracticable or extremely difficult to fix the actual damages.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 17 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Liquidated damages for delay shall cover administrative, overhead, interest on bonds, and general loss of public use damages suffered by Owner as a result of delay. Liquidated damages shall not cover the cost of completion of the Work, damages resulting from Defective Work, lost revenues or costs of substitute facilities, or damages suffered by others who then seek to recover their damages from Owner (for example, delay claims of other contractors, subcontractors, tenants, or other third-parties), and defense costs thereof. Owner may deduct from any money due or to become due to Contractor subsequent to time for completion of entire Work and extensions of time allowed pursuant to provisions hereof, a sum representing then-accrued liquidated damages.
Contractor and Owner agree that the Key Personnel listed in Contractor’s Statement of Qualifications (Document 00 4513) were a material factor in Owner’s assessment of Contractor’s experience and the adequacy of Contactor’s supervisory personnel. Accordingly, Contractor and Owner agree that Contractor shall not remove, reassign or make changes to any of the Key Personnel without Owner’s prior written approval. In the event that any Key Personnel leaves the Project, is reassigned and/or is removed and replaced by Contractor before Project Final Completion, for any reason other than departure from Contractor, Contractor agrees to pay Owner liquidated damages as set forth in the Agreement (Document 00 5200), unless Contractor can demonstrate to Owner’s satisfaction that the Key Personnel were reassigned and/or removed and replaced for reasons beyond Contractor’s control.
CLAIMS BY CONTRACTOR
Obligation to File Claims for Disputed Work
Should it appear to Contractor that the Work to be performed or any of the matters relative to the Contract Documents are not satisfactorily detailed or explained therein, or should any questions arise as to the meaning or intent of the Contract Documents, or should any dispute arise regarding the true value of any work performed, work omitted, extra work that the Contractor may be required to perform, time extensions, payment to the Contractor during performance of this Contract, performance of the Contract, and/or compliance with Contract procedures, or should Contractor otherwise seek extra time or compensation FOR ANY REASON WHATSOEVER (collectively, Disputed Work), then Contractor shall first follow procedures set forth in the Contract Documents (including, without limitation, Paragraphs 11.03, 11.04, 13.03 and 13.04 of this Document 00 7200 and Section 01 2600.) If a dispute remains, then Contractor shall give written notice to Owner that expressly invokes this Article 12. Owner shall decide the issue in writing within 15 days; and Owner’s written decision shall be final and conclusive. If Contractor disagrees with Owner’s decision, or if Contractor contends that Owner failed to provide a decision timely, then Contractor’s SOLE AND EXCLUSIVE REMEDY is to file a written claim within the time limits set forth in Paragraph 12.02 of this Article setting forth Contractor’s position as required herein.
Duty to Work During Disputes. Notwithstanding any dispute or Disputed Work, Contractor shall continue to prosecute the Work and the Disputed Work in accordance with the Owner’s determinations. Contractor’s SOLE AND EXCLUSIVE REMEDY for Disputed Work is to file a written claim within the time limits set forth in Paragraph 12.02 of this Article setting forth Contractor’s position as required herein.
Form and Contents of Claim
Contractor’s written claim must identify itself as a Claim under this Article 12 and must include the following: (i) a narrative of pertinent events; (ii) citation to contract provisions; (iii) theory of entitlement; (iv) complete pricing of all cost impacts; (v) a Time Impact Evaluation of all time delays that shows actual time impact on the critical path; (vi) documentation supporting items (i) through (v); and (vii) a verification under penalty of perjury of the claim’s accuracy. The Claim shall be submitted to Owner within thirty (30) calendar days of receiving Owner’s written decision, or the date Contractor contends such decision was due, and shall be priced like a change order according to Section 01 2600, and must be updated monthly as to cost and entitlement if a continuing claim. Routine contract materials, for example, correspondence, RFI, Change Order Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 18 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
requests, or payment requests shall not constitute a claim. Contractor shall bear all costs incurred in the preparation and submission of a claim.
Regarding delay and impact costs of any nature, Contractor may not seek delay compensation for on-Site or off-Site costs based on formulas, e.g., “Eichleay” or other formula. Rather, Contractor shall prove actual costs resulting from such delays. If Contractor requests compensation for delay to the construction, then Contractor shall prove and document actual costs plus markup per the cost categories and procedures in Section 01 2600 (Modification Procedures) in order to request, claim or prove compensation for delay.
Administration During/After Claim Submission
Owner may render a final determination based on the Claim or may in its discretion conduct an administrative hearing on Contractor’s claim, in which case Contractor shall appear, participate, answer questions and inquiries, and present any further evidence or analysis requested by Owner prior to rendering a final determination. Should Owner take no action on the Claim within 45 days of submission, it shall be deemed denied.
Notwithstanding and pending the resolution of any claim or dispute, Contractor shall diligently prosecute the disputed work to final completion in accordance with Owner’s determination.
Public Contract Code Section 9204 specifies provisions on resolving contract claims of any size, and Public Contract Code Section 20104, et seq., specifies required provisions on resolving contract claims less than $375,000. Those statutes constitute a part of this Contract. In the event any other Contract provision violates such statutes, the applicable statute controls. See Section 01 4100.
Compliance
The provisions of this Article 12 constitute a non-judicial claim settlement procedure that, pursuant to Government Code Section 930.2, shall constitute a condition precedent to submission of a valid Government Code Claim under the Government Code. Contractor shall bear all costs incurred in the preparation, submission and administration of a claim. Any claims presented in accordance with the Government Code must affirmatively indicate Contractor’s prior compliance with the claims procedure herein and the previous dispositions under Paragraph
12.03 above of the claims asserted. No suit may be brought against Owner arising out of or in connection with the Project unless and until Contractor presents to Owner a statutory Government Code Claim, in accordance with Government Code Sections 910, et seq. Pursuant to Government Code Section 930.2, the one-year period in Government Code section 911.2 shall be reduced to 150 days from either accrual of the cause of action, substantial completion or termination of the contract, whichever occurs first; in all other respects, the Government Code shall apply unchanged.
Failure to submit and administer claims as required in Article 12 shall waive Contractor’s right to claim on any specific issues not included in a timely submitted claim. Claim(s) or issue(s) not raised in a timely protest and timely claim submitted under this Article 12 may not be asserted in any subsequent litigation, Government Code Claim, or legal action.
Contractor shall present as its claims all Subcontractor, sub-Subcontractor and supplier claims of any type, and prove them under the terms of the Contract Documents. Owner shall not be directly liable to any Subcontractor, any supplier, or any other person or organization, or to any surety for or employee or agent of any of them, for damages or extra costs of any type arising out of or resulting from the Project.
Owner shall not be deemed to waive any provision under this Article 12, if at Owner’s sole discretion, a claim is administered in a manner not in accord with this Article 12. Waivers or modifications of this Article 12 may only be made a signed change order approved as to form by legal counsel for both Owner and Contractor; oral or implied modifications shall be ineffective.
Mediation
All Contractor claims not otherwise subject to Public Contract Code Sections 20104, et seq., shall, as a condition precedent to litigation thereon, first be mediated. Mediation shall be confidential, non-binding, pursuant to the construction mediation procedures of JAMS in Pacifica, California, and utilize the services of a mediator mutually acceptable to the parties. If the parties Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 19 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
are unable to agree, the mediator will be selected by JAMS from its panel of approved construction industry mediators, having a minimum of 20 years’ experience in the construction industry.
All statutes of limitation shall be tolled from the date of the demand for mediation until a date two weeks following the mediation’s conclusion. All unresolved Contractor claims shall be submitted to the same mediator. The cost of mediation shall be equally shared by all parties to the mediation. The parties shall, prior to the commencement of a mediation pursuant to this Paragraph, upon notice of the other party, exchange relevant, non-privileged project documents in compliance with Code of Civil Procedure Sections 2031.010, et seq. Additionally, the parties may agree mutually to engage in additional discovery prior to mediation. Should the parties proceed with additional discovery, they shall, unless mutually agreed otherwise, comply with Code of Civil Procedure Sections 2019, et. seq. The Mediator will have jurisdiction to resolve any discovery disputes relating to the Mediation.
UNDERGROUND CONDITIONS
Contractor to Locate Underground Facilities
During construction, Contractor shall comply with Government Code Sections 4216 to 4216.9, and in particular Section 4216.2 which provides, in part: “Except in an emergency, an excavator planning to conduct an excavation shall notify the appropriate regional notification center of the excavator’s intent to excavate at least two working days, and not more than 14 calendar days, before beginning that excavation. The date of the notification shall not count as part of the twoworking-day notice. If an excavator gives less notice than the legal excavation start date and time and the excavation is not an emergency, the regional notification center will take the information and provide a ticket, but an operator has until the legal excavation start date and time to respond.
However, an excavator and an operator may mutually agree to a different notice and start date.
The contact information for operators notified shall be available to the excavator.” Contractor shall contact USA, and schedule the Work to allow ample time for the center to notify its members and, if necessary, for any member to field locate and mark its facilities. Contractor is charged with knowledge of all subsurface conditions reflected in USA records. Prior to commencing excavation or trenching work, Contractor shall provide Owner with copies of all USA records secured by Contractor. Contractor shall advise Owner of any conflict between information provided in Document 00 3132 (Geotechnical Data and Existing Conditions), the Drawings and that provided by USA records. Contractor’s excavation shall be subject to and comply with the Contract Documents.
Contractor shall also investigate the existence of existing service laterals, appurtenances or other types of utilities, indicated by the presence of an underground transmission main or other visible facilities, such as buildings, manholes, new asphalt, meters and junction boxes, on or adjacent to the Site, even if not shown or indicated in Existing Conditions Data, Contract Documents, or USA records, or discovered during Contractor’s pre- or post-bid investigation. Contractor shall immediately secure all such available information and notify Owner and the utility owner, in writing, of its discovery.
Contractor to Protect Underground Facilities
At all times during construction, all operating Underground Facilities shall remain in operation, unless the Contract Documents expressly indicate otherwise. Contractor shall maintain such Underground Facilities in service where appropriate; shall repair any damage to them caused by the Work; and shall incorporate them into the Work, including reasonable adjustments to the design location (including minor relocations) of the existing or new installations. Contractor shall take immediate action to restore any in service installations damaged by Contractor’s operations.
Prior to performing Work at the Site, Contractor shall lay out the locations of Underground Facilities that are to remain in service and other significant known underground installations indicated by the Existing Conditions Data, Contract Documents, USA records, or any material otherwise reasonably available to Contractor or discovered during Contractor’s pre- or post-bid investigations. Contractor shall further locate, by carefully excavating with small equipment, Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 20 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
potholing and principally by hand, all such utilities or installations that are to remain and that are subject to damage. If additional utilities whose locations are unknown are discovered, Contractor shall immediately report to Owner for disposition of the same. Additional compensation or extension of time on account of utilities not shown or otherwise brought to Contractor’s attention, including reasonable action taken to protect or repair damage, shall be determined as provided in this Document 00 7200.
If during construction, an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown, indicated, or discovered in the materials and investigations described in Paragraph 13.02B, above, then Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby (and in no event later than seven Days), and prior to performing any Work in connection therewith (except in an emergency), identify the owner of such Underground Facility and give written notice to that owner and to Owner. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility.
The cost of all of the following will be included in the Contract Sum and Contractor shall have full responsibility for (a) reviewing and checking all available information and data including, without limitation, Existing Conditions Data, and information on file at USA; (b) locating all Underground Facilities shown or indicated in the Contract Documents or reasonably available information, or indicated by visual observation including, without limitation, and by way of example only, through performance of all pre-Bid investigations required by this Document 00 7200 and Bidding Documents and post-Bid investigations required by this Document 00 7200, and by engaging qualified locating services and all necessary backhoeing and potholing; (c) coordination of the Work with the owners of such Underground Facilities during construction; and (d) the safety and protection of all such Underground Facilities and repairing any damage thereto resulting from the Work.
Consistent with Government Code Section 4215, as between Owner and Contractor, Owner will be responsible for the timely removal, relocation, or protection of existing main or trunk line utility facilities located on the Site only if such utilities are not identified in the Contract Documents or information made available for bidding. Owner will compensate for the cost of locating and repairing damage not due to Contractor’s failure to exercise reasonable care, removing and relocating such main or trunk line utility facilities not indicated in the Contract Documents or information made available for bidding with reasonable accuracy, and equipment on the Project necessarily idled during such Work. Contractor shall not be assessed liquidated damages for delay in completion of the Project, when such delay was caused by the failure of Owner or the utility to provide for removal or relocation of such utility facilities.
Concealed or Unknown Conditions
If either of the following conditions is encountered at Site when digging trenches or other excavations that extend deeper than four feet below the surface, Contractor shall give a written Notice of Differing Site Conditions to Owner promptly before conditions are disturbed, except in an emergency as set forth in this Document 00 7200, and in no event later than seven Days after first observance of:
Subsurface or Latent physical conditions which differ materially from those indicated in the Contract Documents; or
Unknown physical conditions of an unusual nature or which differ materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract Documents.
In response to Contractor’s Notice of Differing Site Conditions under this Paragraph, Owner will investigate the identified conditions, and if they differ materially and cause increase or decrease in Contractor’s cost of, or time required for, performance of any part of the Work, Owner will negotiate the appropriate change order following the procedures set forth in the Contract Documents. If Owner determines that physical conditions at the Site are not Latent or are not materially different from those indicated in Contract Documents or that no change in terms of the Contract Documents is justified, Owner will so notify Contractor in writing, stating reasons (with Contractor retaining its rights under Article 12 of this Document 00 7200.) Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 21 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Contractor shall not be entitled to any adjustment in the Contract Sum or Contract Time regarding claimed Latent or materially different Site conditions (whether above or below grade) if Contractor knew or should have known of the existence of such conditions at the time Contractor submitted its Bid, failed to give proper notice, or relied upon information, conclusions, opinions or deductions of the kind that the Contract Documents preclude reliance upon.
Regarding Underground Facilities, Contractor shall be allowed an increase in the Contract Sum or an extension of the Contract Time, or both, to the extent that they are attributable to the existence of any Underground Facility that is owned and was built by Owner only where the Underground Facility:
Was not shown or indicated in the Contract Documents or in the information supplied for bidding purposes or in information on file at USA; and
Contractor did not know of it; and
Contractor could not reasonably have been expected to be aware of it or to have anticipated it from the information available. (For example, if surface conditions such as pavement repairs, valve covers, or other markings, indicate the presence of an Underground Facility, then an increase in the Contract Sum or an extension of the Contract Time will not be due, even if the Underground Facility was not indicated in the Contract Documents, in the information supplied to Contractor for bidding purposes, in information on file at USA, or otherwise reasonably available to Contractor.) Contractor shall bear the risk that Underground Facilities not owned or built by Owner may differ in nature or locations shown in information made available by Owner for bidding purposes, in information on file at USA, or otherwise reasonably available to Contractor. Underground Facilities are inherent in construction involving digging of trenches or other excavations on Owner’s Project, and Contractor is to apply its skill and industry to verify the information available.
Contractor’s compensation for claimed Latent or materially different Site conditions shall be limited to the actual, reasonable, incremental increase in cost of that portion of the Work, resulting from the claimed Latent or materially different Site conditions. Such calculation shall take into account the estimated value of that portion of the Work and the actual value of that portion of the Work, using for guidance Contractor’s or its subcontractor’s bid amount and actual amounts incurred for that portion of the Work and the reasonable expectation (if any) of differing or difficult site conditions in the Work area based on the available records and locale of the Work. For example, if Contractor excavates in an area unexpected, then such costs would be recoverable entirely; while if Contractor extends an existing excavation, then such costs would be recoverable if the resulting excavation costs in that work area exceeded the reasonable expectations therefore.
Notice of Hazardous Waste or Materials Conditions
Contractor shall give a written Notice of Hazardous Materials Condition to Owner promptly, before any of the following conditions are disturbed (except in an emergency as set forth in this Document 00 7200), and in no event later than 24 hours after first observance of any:
Material that Contractor believes may be hazardous waste or hazardous material, as defined in Section 25117 of the California Health and Safety Code (including, without limitation, Asbestos, lead, PCBs, petroleum and related hydrocarbons, and radioactive material) that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law (hazardous material); or Other material that may present an imminent substantial danger to persons or property exposed thereto in connection with Work at the Site (other materials).
Except as otherwise provided in the Contract Documents or as provided by applicable law, Contractor shall not be required to give any notice for the disturbance or observation of any such hazardous materials or other materials where such matter is disturbed or observed as part of the scope of Work under the Contract Documents (such as hazardous waste or hazardous material investigation, remediation or disposal activities which are identified as the subject of Work under the Contract Documents), where Contractor complies with all requirements in the Contract Documents and applicable law respecting such materials.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 22 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Contractor’s Notice of Hazardous Materials Condition shall indicate whether the hazardous materials or other materials were shown or indicated in the Contract Documents to be within the scope of Work, and whether the hazardous materials or other materials were brought to the Site by Contractor, its Subcontractors, suppliers, or anyone else for whom Contractor is responsible.
Contractor shall not be entitled to any adjustment in the Contract Sum or Contract Time regarding claimed hazardous waste or materials if:
Contractor knew of the existence of such hazardous materials or other materials at the time Contractor submitted its Bid; or
Contractor should have known of the existence of such hazardous material or other materials as a result of its having the responsibility to obtain additional or supplementary examinations, investigation, explorations, tests, studies, and data concerning the conditions at or contiguous to the Site prior to submitting its Bid; or Contractor failed to give the written notice within the required timeframe set forth below.
If Owner determines that conditions involve hazardous materials or other materials and that a change in Contract Document terms is justified, Owner will issue either a Request for Proposal or Construction Change Directive under the procedures described in the Contract Documents. If Owner determines that conditions do not involve hazardous materials or other materials or that no change in Contract Document terms is justified, Owner will notify Contractor in writing, stating the reasons for its determination.
In addition to the parties’ other rights under this Document 00 7200, if Contractor does not agree to resume Work based on a reasonable belief that it is unsafe, or does not agree to resume Work under special conditions, Owner may order the disputed portion of Work deleted from the Work, or performed by others, or Owner may invoke its right to terminate Contractor’s right to proceed under the Contract Documents in whole or in part, for convenience or for cause as the facts may warrant.
If Contractor does not agree with any Owner determination of any adjustment in the Contract Sum or Contract Time under this Article, Contractor may make a claim as provided in Article 12 of this Document 00 7200.
LEGAL AND MISCELLANEOUS
Laws and Regulations
Contractor shall keep fully informed of and shall comply with all laws, ordinances, regulations and orders of any properly constituted authority affecting the Contract Documents, Work and persons connected with Work, and shall protect and indemnify Owner and its officers, employees, consultants and agents against any claim or liability, including attorney’s fees, arising from or based on violation of law, ordinance, regulation or order, whether by Contractor or by Subcontractors, employees or agents. Authorized persons may at any time enter upon any part of Work to ascertain compliance of all applicable laws, ordinances, regulations and orders.
Permits and Taxes
Contractor shall procure all permits and licenses applicable to the Work (including environmental matters to the extent applicable); pay all charges and fees, including fees for street opening permits; comply with, implement and acknowledge effectiveness of all permits; initiate and cooperate in securing all required notifications or approvals therefore; and give all notices necessary and incident to due and lawful prosecution of Work, unless otherwise provided herein.
Owner will pay applicable building permits, sanitation and water fees for the completed construction, except as otherwise provided in the Contract Documents. Contractor shall pay all sales and/or use taxes levied on materials, supplies, or equipment purchased and used on or incorporated into Work, and all other taxes properly assessed against equipment or other property used in connection with Work, without any increase in the Contract Sum. Contractor shall make necessary arrangements with proper authorities having jurisdiction over roads, streets, pipelines, navigable waterways, railroads, and other works in advance of operations, even where Owner may have already obtained permits for the Work.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 23 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Communications and Information Distribution
All communications recognized under the Contract Documents shall be in writing, in the form of a serialized document, by type of communication. For example, RFI’s shall be serialized beginning with RFI No. 1; payment applications shall be serialized beginning with Payment Application No. 1, submittals shall be serialized per specification section and transmitted with transmittal sheets beginning with Transmittal No. 1; and correspondence shall be serialized beginning with letter No.
1. Contractor may propose other record management and identification systems or protocols, intended to facilitate orderly transmittal of project information, storage and retrieval of such information, which Owner will review consistent with these stated objectives, and accept or reject in its sole discretion.
Documents Requiring Signatures. All documents requiring signatures for approval prior to implementing action, as stipulated in other portions of Contract Documents, shall require a manually signed, serialized letter delivered to the other party at its address for notice otherwise specified in the Contract Documents, either personally or by mail.
Electronic data transfer of such correspondence will serve to expedite preliminary concurrence of information, only. Receipt of “hard copy” signature on forms is required prior to implementing action or work as the conditions may require. For example, change orders and authorizations for extra cost, require signatures. A party may acknowledge receipt of PDF copies of required correspondence by e-mail, but in the absence of such acknowledgment, mail or personal delivery is required.
All emails shall be copied to Owner’s and Contractor’s Project Representative. Owner reserves the right to preclude e-mail communication, in whole or in part, as Project needs may require.
Communication between Owner and Contractor shall not be via Twitter, Facebook, or other types of instant text message systems. Any such communications shall be inadmissible for any purpose related to this Contract.
Suspension of Work
Owner may, without cause, order Contractor in writing to suspend, delay or interrupt Work in whole or in part for such period of time as Owner may determine. An adjustment shall be made for increases in cost of performance of Work of the Contract Documents caused by any such suspension, delay or interruption, calculated using the measures set forth in Section 01 2600 (Modification Procedures). No adjustment shall be made to extent that performance is, was or would have been so suspended, delayed or interrupted by another cause for which Contractor is responsible.
Termination of Contract for Cause
Owner may declare Contractor in default and terminate Contractor’s right to proceed under the Contract Documents, for cause, should Contractor be the subject of a voluntary or involuntary petition in bankruptcy or admit in writing its inability to pay debts as they may become due. The Contractor shall be in default of the Contract Documents and Owner may terminate the Contractor's right to proceed under the Contract Documents, for cause, in whole or in part, should the Contractor commit a material breach of the Contract Documents and not cure such breach within ten (10) calendar days of the date of notice from Owner to the Contractor demanding such cure; or, if such breach is curable but not curable within such ten (10) day period, within such period of time as is reasonably necessary to accomplish such cure. (In order for the Contractor to avail itself of a time period in excess of 10 calendar days, the Contractor must provide Owner within the ten (10) day period with a written cure plan acceptable to Owner that demonstrates actual resources, personnel and a schedule to promptly to cure said breach, and then diligently commence and continue such cure according to the written plan) If Owner at any time reasonably believes that Contractor is or may be in default under the Contract Documents as provided above, then Owner may in its sole discretion notify Contractor of this fact and request written assurances from Contractor of performance of Contract Documents and a written plan from Contractor to remedy any default under the terms of Contract Documents that Owner may advise Contractor of in writing. Contractor shall, within ten (10) Days of Owner’s request, deliver a written cure plan that meets the requirements of the written cure plan as Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 24 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
defined above. Failure of Contractor to provide such written assurances of performance and the required written cure plan within ten (10) Days of request will constitute a material breach of Contract Documents sufficient to justify termination for cause.
In the event of termination by Owner for cause as provided herein, the Contractor shall deliver to Owner possession of the Work in its then condition including, without limitation, all designs, engineering, Project records, cost data of all types, plans and specifications and contracts with vendors and subcontractors, all other documentation associated with the Project, and all construction supplies and aids dedicated solely to performing the Work which, in the normal course of construction, would be consumed or only have salvage value at the end of the construction period. The Contractor shall remain fully liable for the failure of any Work completed and materials and equipment provided through the date of such termination to comply with the provisions of the Contract Documents. The provisions of this Section shall not be interpreted to diminish any right that Owner may have to claim and recover damages for any breach of the Contract Documents or otherwise, but rather, the Contractor shall compensate Owner for all loss, cost, damage, expense, and/or liability suffered by Owner as a result of such termination and/or failure to comply with the Contract Documents.
In the event a termination for cause is later determined to have been made wrongfully or without cause, then the termination shall be treated as a termination for convenience, and the Contractor shall have no greater rights than it would have had following a termination for convenience. Any Contractor claim arising out of a termination for cause shall be made in accord with Article 12 herein. No other loss, cost, damage, expense or liability may be claimed, requested or recovered by the Contractor.
Termination of Contract for Convenience
Owner may terminate performance of the Work under the Contract Documents in accordance with this clause in whole, or from time to time in part, whenever Owner shall determine that termination is in Owner’s best interest. Termination shall be effected by Owner delivering to the Contractor notice of termination specifying the extent to which performance of the Work under the Contract Documents is terminated, and the effective date of the termination.
Contractor shall comply strictly with Owner’s direction regarding the effective date of the termination, the extent of the termination, and shall stop work on the date and to the extent specified.
Contractor shall be entitled to a total payment on account of the Contract work so terminated measured by (i.) the actual cost to Contractor of Work actually performed, up to the date of the termination, with profit and overhead limited to twelve percent (12%) of actual cost of work performed, up to but not exceeding the actual contract value of the work completed as measured by the Schedule of Values and Progress Schedule, (ii.) offset by payments made and other contract credits. In connection with any such calculation, however, Owner shall retain all rights under the Contract Documents including, without limitation, claims, indemnities, or setoffs.
Under no circumstances may Contractor recover legal costs of any nature, nor may Contract recover costs incurred after the date of the termination.
Contingent Assignment of Subcontracts
Contractor hereby assigns to Owner each Subcontract for a portion of the Work, provided that:
The assignment is effective only after Owner’s termination of Contractor’s right to proceed under the Contract Documents (or portion thereof relating to that Subcontract) as set forth herein.
The assignment is effective only for the Subcontracts which Owner expressly accepts by notifying the Subcontractor in writing;
The assignment is subject to the prior rights, if any, of the Surety, obligated by Document 00 6113.13 (Construction Performance Bond) provided under the Contract Documents, where the Surety exercises its rights to complete the Contract; After the effectiveness of an assignment, Contractor shall, at its sole cost and expense (except as otherwise provided in this Document 00 7200), sign all instruments and take all Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 25 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
actions reasonably requested by Owner to evidence and confirm the effectiveness of the assignment in Owner; and
Nothing in this Paragraph shall modify or limit any of Contractor’s obligations to Owner arising from acts or omissions occurring before the effectiveness of any Subcontract assignment including, without limitation, all defense, indemnity and hold-harmless obligations arising from or related to the assigned Subcontract.
Remedies and Contract Integration
Subject to Contract Documents provisions regarding Contractor claims, claim review, and claim resolution, and subject to the limitations therein, the exclusive jurisdiction and venue for resolving all claims, counter claims, disputes and other matters in question between Owner and Contractor arising out of or relating to Contract Documents, any breach thereof or the Project shall be the applicable court of competent jurisdiction located in the State and County where the Project is located. All Owner remedies provided in the Contract Documents shall be taken and construed as cumulative and not exclusive; that is, in addition to each and every other remedy herein provided; and in all instances Owner shall have any and all other equitable and legal rights and remedies which it would have according to law.
The Contract Documents, any Contract Modifications, Change Orders and Change Directives, as further described in Section 01 2600, shall represent the entire and integrated agreement between Owner and Contractor regarding the subject matters hereof and thereof and shall constitute the exclusive statement of the terms of the parties’ agreement. The Contract Documents, and any Contract Modifications and Change Orders, shall supersede any and all prior negotiations, representations or agreements, written or oral, express or implied, that relate in any way to the subject matter of the Contract Documents or written Modifications. Owner and Contractor represent and agree that, except as otherwise expressly provided in the Contract Documents, they are entering into the Contract Documents and any subsequent written Modification in sole reliance upon the information set forth or referenced in the Contract Documents or Contract Modifications; the parties are not and will not rely on any other information, which shall be inadmissible in any proceeding to enforce these documents.
Either party’s waiver of any breach or failure to enforce any of the terms, covenants, conditions or other provisions of the Contract Documents at any time shall not in any way affect, limit, modify or waive that party’s right thereafter to enforce or compel strict compliance with every term, covenant, condition or other provision hereof, any course of dealing or custom of the trade or oral representations notwithstanding.
Neither acceptance of the whole or any part of Work by Owner nor any verbal statements on behalf of Owner or its authorized agents or representatives shall operate as a waiver or modification of any provision of the Contract Documents, or of any power reserved to Owner herein nor any right to damages provided in the Contract Documents.
Interpretation
Should any part, term or provision of this Contract or any of the Contract Documents, or any document required herein or therein to be executed or delivered, be declared invalid, void or unenforceable, all remaining parts, terms and provisions shall remain in full force and effect and shall in no way be invalidated, impaired or affected thereby. If the provisions of any law causing such invalidity, illegality or unenforceability may be waived, they are hereby waived to the end that this Contract and the Contract Documents may be deemed valid and binding agreements, enforceable in accordance with their terms to the greatest extent permitted by applicable law. In the event any provision not otherwise included in the Contract Documents is required to be included by any applicable law, that provision is deemed included herein by this reference (or, if such provision is required to be included in any particular portion of the Contract Documents, that provision is deemed included in that portion).
Contract Documents shall not be construed to create a contractual relationship of any kind between (i) Project Manager or any Owner’s representative and Contractor; (ii) Owner and/or its Representatives and a Subcontractor, sub-Subcontractor, or supplier of any Project labor, materials, or equipment; or (iii) between any persons or entities other than Owner and Contractor.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 26 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
14.10 Patents
Fees or claims for any patented invention, article or arrangement that may be used upon or in any manner connected with performance of the Work or any part thereof shall be included in the Bid price for doing the Work. Contractor shall defend, indemnify and hold harmless Owner and each of its officers, employees, consultants and agents including, without limitation, the Board and each Owner’s Representative, from all damages, claims for damages, costs or expenses in law or equity, including attorney’s fees, arising from or relating to any claim that any article supplied or to be supplied under the Contract Documents infringes on the patent rights, copyright, trade name, trademark, service mark, trade secret or other intellectual property right of any person or persons or that the person or entity supplying the article does not have a lawful right to sell the same.
Such costs or expenses for which Contractor agrees to indemnify and hold harmless the above indemnities include but are not limited to any and all license fees, whether such fees are agreed by any indemnitee or ordered by a court or administrative body of any competent jurisdiction.
14.11 Substitution for Patented and Specified Articles
Except as noted specifically in Document 00 2113 (Instructions to Bidders) or in Contract Documents, whenever in Specifications, material or process is designated by patent or proprietary name or by name of manufacturer, such designation shall be deemed to be used for purpose of facilitating description of material and process desired, and shall be deemed to be followed by the words “or Approved Equal.” Contractor may offer any substitute material or process that Contractor considers “Equal” in every respect to that so designated and if material or process offered by Contractor is, in opinion of Owner, Equal in every respect to that so designated, its use will be approved. However, Contractor may utilize this right only by timely submitting Document 00 6325 (Substitution Request Form) as provided in Document 00 2113 (Instructions to Bidders). A substitution will be approved only if it is a true “or Equal” item in every aspect of its design and quality including, without limitation, its dimensions, weights, service requirements, durability, functioning, impact on contiguous construction elements, overall schedule and design.
14.12 Interest of Public Officers
No representative, officer, or employee of Owner no member of the governing body of the locality in which the Project is situated, no member of the locality in which Owner was activated, and no other public official of such locality or localities who exercises any functions or responsibilities with respect to the Project, during the tenure of the official or for one year thereafter, shall, as principal, agent, attorney or otherwise, be directly or indirectly interested, in the Contract Documents or the proceeds thereof.
14.13 Limit of Liability
OWNER, AND EACH OF ITS OFFICERS, BOARD MEMBERS, EMPLOYEES, CONSULTANTS
AND AGENTS INCLUDING, WITHOUT LIMITATION, PROJECT MANAGER AND EACH OTHER
OWNER REPRESENTATIVE, SHALL HAVE NO LIABILITY TO CONTRACTOR FOR SPECIAL,
CONSEQUENTIAL, OR INCIDENTAL DAMAGES, EXCEPT TO THE LIMITED EXTENT THAT
THESE CONTRACT DOCUMENTS OR APPLICABLE PUBLIC CONTRACTING STATUTES MAY SPECIFY THEIR RECOVERY.
14.14 Public Records Act.
A. Contractor is aware that this Contract and any documents provided to the Owner may be subject to the California Public Records Act and may be disclosed to members of the public upon request. It is the responsibility of Contractor to clearly identify information in those documents it considers to be confidential under the California Public Records Act. To the extent that Owner agrees with that designation, such information will be held in confidence whenever possible. All other information will be considered public.
WORKING CONDITIONS AND PREVAILING WAGES
Use of Site/Sanitary Rules
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 27 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
All portions of the Work shall be maintained at all times in neat, clean and sanitary condition.
Contractor shall furnish toilets for use of Contractor’s and Subcontractors’ employees on the Site where needed, and their use shall be strictly enforced. All toilets shall be properly secluded from public observation, and shall be located, constructed and maintained subject to Owner’s approval.
Contractor shall confine construction equipment, the storage of materials and equipment and the operations of workers to the Site and land areas identified in and permitted by Contract Documents and other land and areas permitted by applicable laws and regulations, rights of way, permits and easements or as designated by Owner, and shall not unreasonably encumber the premises with construction equipment or other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, any improvement located thereon, or to Owner or occupant thereof resulting from the performance of Work.
During the progress of the Work, Contractor shall keep the Site and the Project free from accumulations of waste materials, rubbish and other debris resulting from the Work. At the completion of the Work, Contractor shall clean the site, remove all waste materials, rubbish and debris from and about the Site as well as all tools, appliances, construction equipment and machinery and surplus materials. Contractor shall leave the premises clean and ready for occupancy by Owner at Substantial Completion of Work. Contractor shall restore to original condition all property not designated for alteration by Contract Documents.
Contractor shall not load nor permit any part of any structure or pavement to be loaded in any manner that will endanger the structure or pavement, nor shall Contractor subject any part of Work or adjacent property to stresses or pressures that will endanger it. Contractor shall conduct all necessary existing conditions investigation regarding structural, mechanical, electrical or any other system existing, shall perform Work consistent with such existing conditions, and shall have full responsibility for insufficiencies or damage resulting from insufficiencies of existing systems, equipment or structures to accommodate performing the Work.
Protection of Work, Persons, and Property
Contractor shall be responsible for initiating, maintaining and supervising all safety and site security precautions and programs in connection with Work, and shall develop and implement a site security and safety plan throughout construction. Contractor shall comply with all safety requirements specified in any safety program established by Owner, or required by state, federal or local laws and ordinances. Contractor shall be responsible for all theft or damage to Work, property or structures, and all injuries to persons, either on the Site or constituting the Work (e.g., materials in transit), arising from the performance of Work of the Contract Documents from a cause.
Contractor shall comply with all applicable laws and regulations of any public body having jurisdiction for safety of persons or property or to protect them from damage, injury or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify Owners of adjacent property and of Underground Facilities and utility Owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation and replacement of their property.
Contractor shall remedy all damage, injury or loss to any property referred to above in this Article, caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, supplier, or any other person or organization directly or indirectly employed by any of them to perform or furnish any Work or anyone for whose acts any of them may be liable. Contractor’s duties and responsibility for safety and for protection of Work shall continue until such time as all the Work is completed and Final Acceptance of the Work. Owner and its agents do not assume any responsibility for collecting any indemnity from any person or persons causing damage to Contractor’s Work.
Contractor shall designate a qualified and experienced safety representative at the Site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs.
Owner may, at its option, retain such moneys due under the Contract Documents as Owner deems necessary until any and all suits or claims against Contractor for injury to persons or property shall be settled and Owner receives satisfactory evidence to that effect.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 28 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
Work within the right-of-way lines of any City, County and/or State shall be done in accordance with the standards and specifications of the controlling agency. Permit for such work shall be obtained and paid for by the Contractor before executing the work within such right-of-ways.
Responsibility For Safety and Health
Contractor shall ensure that its and each tier of Subcontractors’ employees, agents and invitees comply with applicable health and safety laws while at the Site. These laws include the Occupational Safety and Health Act of 1970 and rules and regulations issued pursuant thereto, and Owner’s safety regulations as amended from time to time. Contractor shall comply with all Owner directions regarding protective clothing and gear.
Contractor shall be fully responsible for the safety of its and its Subcontractors’ employees, agents and invitees on the Site. Contractor shall notify Owner, in writing, of the existence of hazardous conditions, property or equipment at the Site that are not under Contractor’s control.
Contractor shall be responsible for taking all the necessary precautions against injury to persons or damage to the property of Contractor, Subcontractors or persons from recognized hazards until the responsible party corrects the hazard.
Contractor shall confine all persons acting on its or its Subcontractors’ behalf to that portion of the Site where Work under the Contract Documents is to be performed, Owner-designated routes for ingress and egress thereto, and any other Owner-designated area. Except those routes for ingress and egress over which Contractor has no right of control, within such areas, Contractor shall provide safe means of access to all places at which persons may at any time have occasion to be present.
Emergencies
In emergencies affecting the safety or protection of persons or Work or property at the Site or adjacent thereto, Contractor, without special instruction or authorization from Owner, is obligated to act to prevent threat and damage, injury or loss, until directed otherwise by Owner. Contractor shall give Owner prompt written notice if Contractor believes that any significant changes in Work or variations from Contract Documents have been caused thereby. If Owner determines that a change in the Contract Documents is required because of the action taken by Contractor in response to such an emergency, a Change Order or Construction Change Directive will be issued to document the consequences of such action.
Use of Roadways and Walkways
Contractor shall not unnecessarily interfere with use of any roadway, walkway or other facility for vehicular or pedestrian traffic. Before beginning any interference and only with Owner’s prior concurrence, Contractor may provide detour or temporary bridge for traffic to pass around or over the interference, which Contractor shall maintain in satisfactory condition as long as interference continues. Unless otherwise provided in the Contract Documents, Contractor shall bear the cost of these temporary facilities.
Nondiscrimination
No person or entity shall discriminate in the employment of persons upon public works because of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, sexual preference, or gender of such persons, except as provided in Government Code Section 12940. Every contractor for public works violating the provisions of Labor Code Section 1735 is subject to all the penalties imposed for a violation of Chapter 1, Part 7, Division 2 of the California Labor Code.
Prevailing Wages and Working Hours
Contractor shall pay to persons performing labor in and about Work provided for in the Contract Documents an amount equal to or more than the general prevailing rate of per diem wages for (i) work of a similar character in the locality in which the Work is performed and (ii) legal holiday and overtime work in said locality. The per diem wages shall be an amount equal to or more than the stipulated rates contained in a schedule that has been ascertained and determined by the Director of the State Department of Industrial Relations and Owner to be the general prevailing Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 29 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
rate of per diem wages for each craft or type of workman or mechanic needed to execute this Contract. Contractor shall also cause a copy of this determination of the prevailing rate of per diem wages to be posted at each Site.
Contractor shall forfeit, as a penalty to Owner, $200.00 for each laborer, worker, or mechanic employed in performing labor in and about the Work provided for in the Contract Documents for each Day, or portion thereof, that such laborer, worker or mechanic is paid less than the said stipulated rates for any Work done under the Contract Documents by him or her or by any Subcontractor under him or her, in violation of Articles 1 and 2 of Chapter 1 of Part 7 of Division II of the Labor Code. The sums and amounts that are forfeited pursuant to this Paragraph and the terms of the Labor Code shall be withheld and retained from payments due to Contractor under the Contract Documents, pursuant to this Document 00 7200 and the Labor Code, but no sum shall be so withheld, retained or forfeited except from the final payment without a full investigation by either the State Department of Industrial Relations or by Owner. The Labor Commissioner pursuant to Labor Code Section 1775 shall determine the final amount of forfeiture.
Contractor shall insert in every subcontract or other arrangement which Contractor may make for performance of Work or labor on Work provided for in the Contract, provision that Subcontractor shall pay persons performing labor or rendering service under subcontract or other arrangement not less than the general prevailing rate of per diem wages for work of a similar character in the locality in which the Work is performed, and not less than the general prevailing rate of per diem wages for holiday and overtime work fixed in the Labor Code.
Contractor stipulates that it shall comply with all applicable wage and hour laws, including without limitation, Labor Code Sections 1776 and 1810-1815. Failure to so comply shall constitute a default under this Contract.
Contractor and its Subcontractors shall be responsible for compliance with Labor Code Sections 1810-1815.
Eight hours of labor performed in execution of the Contract constitutes a legal day’s work.
The time of service of any worker employed on the Project is limited and restricted to 8 hours during any one calendar day, and 40 hours during any one calendar week.
Contractor and its Subcontractors shall keep an accurate record showing the name of and actual hours worked each calendar day and each calendar week by each worker employed by him or her in connection with the Project. The record shall be kept open at all reasonable hours to the inspection Owner and to the Division of Labor Standards Enforcement.
Contractor or its Subcontractors shall, as a penalty to Owner, forfeit twenty-five dollars ($25) for each worker employed in the execution of the Contract Documents by the respective Contractor or Subcontractor for each calendar day during which the worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of Labor Code Sections 1810-1815.
Work performed on the Project by employees of Contractor or its Subcontractors in excess of 8 hours per day, and 40 hours during any one week, shall be permitted upon compensation for all hours worked in excess of 8 hours per day at not less than 1 1/2 times the basic rate of pay.
Contractor and its Subcontractors shall be responsible for compliance with Labor Code Section 1776. This Project is subject to prevailing wage compliance monitoring and enforcement by the Department of Industrial Relations.
Contractor and Subcontractors must keep accurate payroll records, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the Work of the Contract Documents. Each payroll record shall contain or be verified by a written declaration as required by Labor Code Section 1776.
The payroll records enumerated above must be certified and shall be available for inspection at all reasonable hours at the principal office of the Contractor as required by Labor Code Section 1776.
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 30 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
a. Contractor shall inform Owner of the location of records enumerated above, including the street address, city and county, and shall, within five working days, provide a notice of a change of location and address.
b. Contractor or Subcontractor has 10 days in which to comply subsequent to receipt of a written notice requesting the records enumerated above. In the event that the Contractor or Subcontractor fails to comply with the ten-day period, he or she shall, as a penalty to Owner on whose behalf the contract is made or awarded, forfeit $100.00 for each calendar day, or portion thereof, for each worker, until strict compliance is effectuated. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, these penalties shall be withheld from progress payments then due. Contractor is not subject to a penalty assessment pursuant to this Paragraph due to the failure of a Subcontractor to comply with this Paragraph.
With each payment application, Contractor shall also deliver certified payrolls to Owner as set forth above in this Document 00 7200 (General Conditions), and concurrently therewith (but in no event less frequently than monthly) directly to the Labor Commissioner in the format prescribed by the Labor Commissioner.
Contractor shall post all jobsite notices if and when prescribed by regulation.
Environmental Controls
Contractor shall comply with all rules, regulations, ordinances, and statutes that apply to any Work performed under the Contract Documents including, without limitation, any toxic, water, stormwater management and soil pollution controls and air pollution controls specified in Government Code Section 11017. Contractor shall be responsible for insuring that Contractor’s Employees, Subcontractors, and the public are protected from exposure to airborne hazards or contaminated water, soil, or other toxic materials used during or generated by activities on the Site or associated with the Project.
Shoring Safety Plan
Any conflict between this Paragraph and the Technical Specifications shall be resolved in favor of the most stringent requirement.
At least five Days in advance of any excavation five feet or more in depth, Contractor shall submit to Owner a detailed plan showing the shoring, bracing and sloping design (including calculations) and other provisions to be made for worker protection from the hazard of caving ground during the excavation, as required by Labor Code Section 6705. A civil or structural engineer registered in California shall prepare and sign any plan that varies from the shoring system standards established by the State Construction Safety Orders.
During the course of Work, Contractor shall be responsible for determining where sloping, shoring, and/or bracing is necessary and the adequacy of the design, installation, and maintenance of all shoring and bracing for all excavation, including any excavation less than five feet in depth. Contractor will be solely responsible for any damage or injuries that may result from excavating or trenching. Owner’s acceptance of any drawings showing the shoring or bracing design or Work schedule shall not relieve Contractor of its responsibilities under this Paragraph.
Appoint a qualified supervisory employee who shall be responsible to determine the sloping or shoring system to be used depending on local soil type, water table, stratification, depth, etc.
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2021
General Conditions 00 7200 - 31 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
(This page intentionally left blank)
Rev. 0
February 2022
Supplemental General Conditions 00 7301 - 1 Civic Center Campus Facilities Project OAK #4886-4988-1861 v2
DOCUMENT 00 7301
SUPPLEMENTAL GENERAL CONDITIONS (NOT USED)
[Optional] Adverse Weather - Document 00 7200 [General Conditions] Paragraph 11.06. [Can (1) use this 1.01 and A. and B. below, (2) use this 1.01 and only A. below, or (3) omit this 1.01 entirely]
The Weather Station (see Document 00 7200 General Conditions) is [San Francisco International Airport] [for consideration].
The total number of adverse weather days is [City to insert]. _______________________
__________________:
__________________
___________________
__________________:
__________________
___________________
Rev. 0
Bid Set - February 25, 2021
Supplemental GC 00 7301 - 02 Civic Center Campus Facilities Project OAK #4895-3651-8405 v3
(This page intentionally left blank)
Rev. 0
Bid Set - February 25, 2022
COVID Requirements 00 07320 - 1 Civic Center Campus Facilities Project OAK #4862-8523-7511 v2
DOCUMENT 00 7320
COVID REQUIREMENTS
ARTICLE 1 DEFINITIONS
1.01 The following definitions apply to this Document 00 7320:
A. The 2019 novel coronavirus (including all variants) and the disease it causes are collectively referred to herein as COVID-19.
B. A COVID-19 Condition is something attributable to COVID-19 not caused by Contractor (which for purposes herein includes all subcontractors and suppliers) and beyond its reasonable control, including without limitation COVID-19 Proclamations and supply chain disruptions due to COVID19, and other circumstances concerning COVID-19 not caused by Contractor and which are beyond its reasonable control.
C. A COVID-19 Proclamation includes without limitation orders, directives and guidance concerning COVID-19 that have been issued, and which may be issued from time to time, by public agencies or regulatory bodies, including without limitation the CDC, OSHA, Cal/OSHA, County or Owner, including without limitation the CalOSHA COVID-19 Prevention Emergency Temporary Standards.
Contractor acknowledges that those orders, directives and guidance may require the Project to shut down or otherwise increase Contractor’s cost or time of performance by calling for things such as social distancing and the use of personal protective equipment. In the event of conflicting COVID-19 Proclamations, Contractor shall follow the most applicable, restrictive and newest COVID-19 Proclamations.
D. An Unknown COVID-19 Condition is a COVID-19 Condition Contractor did not know about, and reasonably should not have known about, as of the date Contractor submitted its Bid. The requirements contained in COVID-19 Proclamations issued before submission of a Bid are not Unknown COVID-19 Conditions, and Contractor will be deemed to have knowledge of those requirements.
E. An Unknown COVID-19 Cost is a cost that: (i) is solely attributable to an Unknown COVID-19 Condition; (ii) is reasonable under the circumstances; (iii) is not the result of Contractor’s failure to comply with the contract documents or a COVID-19 Proclamation; and (iv) is not the result of a subcontractors’ or suppliers’ failure to comply with a COVID-19 Proclamation while on the Project Site or in connection with performance of the Work.
ARTICLE 2 COVID-19 CONDITIONS AND BID.
2.01 Contractor is expected to know and is deemed to have known about COVID-19 Conditions when it submits its Bid, and COVID-19 Conditions must be accounted for in Contractor’s price and schedule. In order to be entitled to any relief from a COVID-19 Condition, Contractor must demonstrate that the issue, cost or delay is due to an Unknown COVID-19 Condition ARTICLE 3 COMPLIANCE WITH COVID-19 PROCLAMATIONS.
3.01 Contractor shall comply with COVID-19 Proclamations in performance of the Work, irrespective of when the COVID-19 Proclamations are issued, and as they pertain to performance of the Work.
The cost of such compliance is non-compensable, except as otherwise expressly stated in this Document 00 7320.
Rev. 0
Bid Set - February 25, 2022
COVID Requirements 00 07320 - 2 Civic Center Campus Facilities Project OAK #4862-8523-7511 v2
3.02 Contractor is responsible to ensure that its subcontractors and suppliers comply with COVID-19 Proclamations while they are on the Project Site and in connection with the performance of their portion of the Work.
ARTICLE 4 DELAY.
4.01 Contractor is entitled to a reasonable time extension for an Unknown COVID-19 Condition. Such time extension is non-compensable.
ARTICLE 5 OWNER DIRECTED SUSPENSION.
5.01 Owner may suspend work at the Project site due to COVID-19 health concerns, even though Contractor may be allowed to proceed with Work based on COVID-19 Proclamations. Owner may suspend the work for its convenience. Contractor is entitled to a time extension for an Owner Directed Suspension, and the contract amount will be equitably adjusted if and to the extent Contractor incurs increased costs that are Unknown COVID-19 Costs.
ARTICLE 6 COMPENSATION FOR COVID-19 COSTS.
6.01 Owner will reimburse Contractor for costs attributable to COVID-19, and which are not included in the Schedule of Values, only if the cost is an Unknown COVID-19 Cost ARTICLE 7 SAFE WORK PRACTICES.
7.01 Contractor shall implement safe work practices recommended by CDC or OSHA or Cal/OSHA, which may include, inter alia, screening all employees, subcontractors, laborers or suppliers (worker(s)) on the construction site in advance of their arrival on the job site for signs and symptoms of COVID-19; adopting staggered work schedules, e.g., providing alternating workdays or extra shifts, to reduce the total number of employees on a job site at any given time and to ensure physical distancing; identifying choke points where workers are forced to stand together, such as hallways, hoists and elevators, ingress and egress points, break areas, and buses, and implement policies to maintain social distancing; coordinating site deliveries in line with the employer's minimal contact and cleaning protocols; and instituting a rigorous housekeeping program to reduce dust levels on the job site. Contractor remains fully responsible for following and complying with changes to recommended safe work practices from time to time.
ARTICLE 8 MONITORING AND REPORTING.
8.01 Owner may require Contractor to actively monitor the health of its workers through temperature checks and questionnaires of major COVID-19 symptoms, including but not limited to cough, fever above 100.4 degrees Fahrenheit and shortness of breath. Contractor shall immediately report to Owner any outbreaks of COVID-19 among its workers. Contractor shall not knowingly allow any worker who has tested positive with COVID-19 to enter an Owner building. In the event of an outbreak or an exposure to COVID-19, Owner may impose appropriate mitigation strategies which may be in consultation with the public health officer.
ARTICLE 9 PRECEDENCE.
9.01 This Document 00 7320 shall take precedence over any other conflicting Contract Document.
Rev. 0
Bid Set - February 25, 2022
Apprenticeship Program 00 7380 - 1 Civic Center Campus Facilities Project OAK #4893-7530-0101 v2
DOCUMENT 00 7380
APPRENTICESHIP PROGRAM
ARTICLE 1 COMPLIANCE REQUIRED
1.01 Contractor and Subcontractors shall comply with the requirements of Labor Code Sections 1776, 1777.5, and 1777.6 concerning the employment of apprentices by Contractor or Subcontractors.
Willful failure to comply may result in penalties, including loss of the right to Bid on or receive public works contracts.
ARTICLE 2 CERTIFICATION OF APPROVAL
2.01 Labor Code Section 1777.5, as amended, requires a Contractor or Subcontractor employing tradespersons in any apprenticeable occupation to apply to the joint apprenticeship committee nearest the site of a public works project and which administers the apprenticeship program in that trade for a certification of approval. The certificate shall also fix the ratio of apprentices to journeypersons that will be used in performance of the Contract. The ratio of work performed by apprentices to journeypersons in such cases shall not be less than one hour of apprentices work for every five hours of labor performed by journeypersons (the minimum ratio for the land surveyor classification shall not be less than one apprentice for each five journeypersons), except:
A. When unemployment for the previous three month period in the area exceeds an average of 15 percent;
B. When the number of apprentices in training in the area exceeds a ratio of one to five; C. When a trade can show that it is replacing at least 1/30 of its membership through apprenticeship training on an annual basis state-wide or locally; or
D. Assignment of an apprentice to any work performed under a public works contract would create a condition which would jeopardize his or her life or the life, safety, or property of fellow employees or the public at large or if the specific task to which the apprentice is to be assigned is of such a nature that training cannot be provided by a journeyperson.
ARTICLE 3 FUND CONTRIBUTIONS
3.01 Contractor is required to make contributions to funds established for administration of apprenticeship programs if Contractor employs registered apprentices or journeypersons in any apprenticeable trade on such contracts and if other contractors on the public works site are making such contributions.
ARTICLE 4 APPRENTICESHIP STANDARDS
4.01 Information relative to apprenticeship standards, wage schedules, and other requirements may be obtained from the Director of the California Department of Industrial Relations, or from the Division of Apprenticeship Standards and its branch offices.
ARTICLE 5 APPRENTICESHIP STANDARDS
5.01 Information relative to apprenticeship standards, wage schedules, and other requirements may be obtained from the Director of the California Department of Industrial Relations, or from the Division of Apprenticeship Standards and its branch offices.
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Apprenticeship Program 00 7380 - 2 Civic Center Campus Facilities Project OAK #4893-7530-0101 v2
(This page intentionally left blank)
Rev. 0
Bid Set - February 25, 2022
Addenda 00 9113 - 1 Civic Center Campus Facilities Project OAK #4863-7670-0421 v2
DOCUMENT 00 9113
ADDENDA
CITY OF PACIFICA
CIVIC CENTER CAMPUS FACILITIES PROJECT
170 SANTA MARIA AVENUE AND 1810 FRANCISCO BOULEVARD, PACIFICA, CA 94044 PROJECT NUMBER PW #2021-23
The following Addenda were issued, modifying the Project Manual:
Addendum No. 1, issued on March 15, 2022
Addendum No. 2, issued on March 16, 2022
Addendum No. 3, issued on March 18, 2022
Addendum No. 4, issued on March 21, 2022
Addendum No. 5, issued on March 22, 2022
Addendum No. 6, issued on March 25, 2022
Addendum No. 7, issued on March 25, 2022
(Addenda have been incorporated into the conformed Project Manual.)
END OF DOCUMENT
Rev. 0
Bid Set - February 25, 2022
Addenda 00 9113 - 2 Civic Center Campus Facilities Project OAK #4863-7670-0421 v2
(This page intentionally left blank)
Rev. 0
February 2022
Allowances 01 2100 – 1 Civic Center Campus Facilities Project OAK #4854-5093-9397 v2
DIVISION 1 GENERAL REQUIREMENTS
SECTION 01 2100
ALLOWANCES
PART 1 GENERAL
1.01 Section Includes
A. Non-Specified Work
1.02 Related Sections
A. Section 01 1100—Summary of Work
B. Section 01 2000—Measurement and Payment
C. Section 01 3300—Submittals
1.03 Owner’s Contingency Reserve Allowance
A. Owner’s Contingency Reserve Allowance in the amount identified in the Agreement (if any) is included in Contract Sum and controlled by Owner.
B. Owner shall determine in its sole discretion which costs, if any, it will authorize in writing to be paid from this Allowance. Generally, Contingency Reserve Allowance will be used only for Owner-initiated changes in scope of Work of Contract Documents.
C. Contractor’s costs for products, delivery, installation, labor, insurance, payroll, taxes, bonding, differing site conditions and equipment rental will be included in Change Orders authorizing expenditure of funds from this Allowance.
D. Funds will be drawn from this Allowance only with Owner’s approval evidenced by deductive Change Order.
E. At Contract closeout, funds remaining in this Allowance will be credited to Owner by deductive Change Order.
1.04 Disposal of Existing Furnishings/Materials Allowance A. Disposal of Existing Furnishings/Materials Allowance in the amount of $5,000 is included in the Contract Sum.
B. Contractor’s costs for products, delivery, installation, labor, insurance, payroll, taxes, bonding, differing site conditions and equipment rental with respect to Disposal of Existing Furnishings/Materials will be included in Change Orders authorizing expenditure of funds from this Allowance.
C. Funds will be drawn from this Allowance only with Owner’s approval evidenced by Change Order.
D. At Contract closeout, funds remaining in this Allowance will be credited to Owner by Change Order.
PART 2 PRODUCTS – NOT USED
PART 3 EXECUTION- NOT USED
END OF SECTION
Rev. 0
February 2022
Allowances 01 2100 – 2 Civic Center Campus Facilities Project OAK #4854-5093-9397 v2
(This page intentionally left blank)
The ACORD name and logo are registered marks of ACORD
CERTIFICATE HOLDER
© 1988-2014 ACORD CORPORATION. All rights reserved.
ACORD 25 (2014/01)
AUTHORIZED REPRESENTATIVE
CANCELLATION
DATE (MM/DD/YYYY) CERTIFICATE OF LIABILITY INSURANCE
JECT LOC PRO- POLICY GEN'L AGGREGATE LIMIT APPLIES PER:
CLAIMS-MADE OCCUR
COMMERCIAL GENERAL LIABILITY
PREMISES (Ea occurrence) $ DAMAGE TO RENTED
EACH OCCURRENCE $
MED EXP (Any one person) $
PERSONAL & ADV INJURY $
GENERAL AGGREGATE $
PRODUCTS - COMP/OP AGG $
DED RETENTION $ CLAIMS-MADE OCCUR
$ AGGREGATE $ UMBRELLA LIAB EACH OCCURRENCE $ EXCESS LIAB DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required) INSR
LTR TYPE OF INSURANCE POLICY NUMBER
POLICY EFF
(MM/DD/YYYY) POLICY EXP(MM/DD/YYYY) LIMITS
PER
STATUTE OTH- ER
E.L. EACH ACCIDENT E.L. DISEASE - EA EMPLOYEE
E.L. DISEASE - POLICY LIMIT
$
$
$
ANY PROPRIETOR/PARTNER/EXECUTIVE
If yes, describe under DESCRIPTION OF OPERATIONS below
(Mandatory in NH) OFFICER/MEMBER EXCLUDED? WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY Y / N
AUTOMOBILE LIABILITY ANY AUTO
ALL OWNED SCHEDULED
HIRED AUTOS NON-OWNED
AUTOS AUTOS
AUTOS
COMBINED SINGLE LIMIT BODILY INJURY (Per person)
BODILY INJURY (Per accident) PROPERTY DAMAGE $$
$
$
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSD
ADDL WVDSUBR
N / A
$
$
(Ea accident)
(Per accident)
OTHER:
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
COVERAGES CERTIFICATE NUMBER: REVISION NUMBER:
INSURED
PHONE
(A/C, No, Ext): PRODUCER
ADDRESS: E-MAIL
FAX
(A/C, No): CONTACT NAME:
NAIC #
INSURER A :
INSURER B :
INSURER C :
INSURER D :
INSURER E :
INSURER F :
INSURER(S) AFFORDING COVERAGE
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.
4/15/2022
R. C. Fischer & Co.
P. O. Box 8101
Walnut Creek CA 94596
Glenda Vargas 925-627-5465 925-932-0962 [email protected] Starr Indemnity & Liability Company 38318 WELYONS-01 California Capital Insurance Company 13544 W. E. Lyons Construction Co.
Gregory Lyons
1301 Ygnacio Valley Road
Walnut Creek CA 94598
Everest Premier Insurance Company 16045 Tokio Marine Specialty Insurance Company 23850 Homesite Insurance Company 17221 Monterey Insurance Company 23540 1240021617 D X 1,000,000 X 100,000 5,000 1,000,000 2,000,000 Y Y PPK2265538 4/30/2021 4/30/2022 2,000,000
B
1,000,000 X
X X
X Hired PD X $50K Y Y 2SAA3019131 4/30/2021 4/30/2022
A X 5,000,000 X
0 1000585100211
X
5,000,000
4/30/2021 4/30/2022
C Y 7600011317211 4/30/2021 4/30/2022
X
1,000,000 1,000,000 1,000,000
E
F
F
Umbrella Second Layer
Rented/Leased Equipment
Professional Liability
CXP13737065800
2SSA3019131
ANE141171621
4/30/2021
4/30/2021
4/30/2021
4/30/2022
4/30/2022
4/30/2022
Occ/Agg Limit
Limit
Limit
4,000,000
100,000
2,000,000
General Liability Deductible $5,000
Auto - Comprehensive and Collision Deductible $1,000
Rented/Leased Equipment Deductible $1,000
*Professional Liability - Policy # ANE141171621 - Carrier is Underwriter's At Lloyd's of London RE: Civic Center Facilities Project
The City of Pacifica, including its officers, officials, employees, and volunteers, are named as Additional Insured per CG20100413, CG20370413 & 033300312.
Insurance is Primary PICGLN0201013. Waiver of Subrogation applies per CG24041219, 033300312 & WC040306.
City of Pacifica - Office if the City Engineer
151 Milagra Drive
Pacifica CA 94044
POLICY NUMBER: PPK2265538 COMMERCIAL GENERAL LIABILITY
CG 20 37 04 13
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED -- OWNERS, LESSEES OR
CONTRACTORS -- COMPLETED OPERATIONS
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART
SCHEDULE
Name Of Additional Insured Person(s)
Or Organization(s) Location And Description Of Completed Operations
AS REQUIRED BY WRITTEN
CONTRACT PRIOR TO AN
"OCCURRENCE".
ALL LOCATIONS.
Information required to complete this Schedule, if not shown above, will be shown in the Declarations.
A. Section II ----- Who Is An Insured is amended to
include as an additional insured the person(s) or
organization(s) shown in the Schedule, but only
with respect to liability for "bodily injury" or
"property damage" caused, in whole or in part, by
"your work" at the location designated and
described in the Schedule of this endorsement
performed for that additional insured and
included in the "products-completed operations
hazard".
However:
1. The insurance afforded to such additional
insured only applies to the extent permitted by
law; and
2. If coverage provided to the additional insured
is required by a contract or agreement, the
insurance afforded to such additional insured
will not be broader than that which you are
required by the contract or agreement to
provide for such additional insured.
B. With respect to the insurance afforded to these
additional insureds, the following is added to
Section III - --- Limits Of Insurance:
If coverage provided to the additional insured is
required by a contract or agreement, the most we
will pay on behalf of the additional insured is the
amount of insurance:
1. Required by the contract or agreement; or
2. Available under the applicable Limits of
Insurance shown in the Declarations;
whichever is less.
This endorsement shall not increase the applicable
Limits of Insurance shown in the Declarations.
CG 20 37 04 13 Insurance Services Office, Inc., 2012 Page 1 of 1 POLICY NUMBER:PPK2265538 COMMERCIAL GENERAL LIABILITY
CG 20 10 04 13
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
CG 20 10 04 13 © Insurance Services Office, Inc., 2012 Page 1 of 2
ADDITIONAL INSURED - OWNERS, LESSEES OR
CONTRACTORS - SCHEDULED PERSON OR
ORGANIZATION
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
SCHEDULE
Name Of Additional Insured Person(s)
Or Organization(s) Location(s) Of Covered Operations
Information required to complete this Schedule, if not shown above, will be shown in the Declarations.
A. Section II – Who Is An Insured is amended to
include as an additional insured the person(s) or
organization(s) shown in the Schedule, but only with
respect to liability for "bodily injury", "property
damage" or "personal and advertising injury"
caused, in whole or in part, by:
1. Your acts or omissions; or
2. The acts or omissions of those acting on your
behalf;
in the performance of your ongoing operations for
the additional insured(s) at the location(s)
designated above.
However:
1. The insurance afforded to such additional
insured only applies to the extent permitted by
law; and
2. If coverage provided to the additional insured is
required by a contract or agreement, the
insurance afforded to such additional insured will
not be broader than that which you are required
by the contract or agreement to provide for such
additional insured.
B. With respect to the insurance afforded to these
additional insureds, the following additional
exclusions apply:
This insurance does not apply to "bodily injury" or
"property damage" occurring after:
1. All work, including materials, parts or equipment
furnished in connection with such work, on the
project (other than service, maintenance or
repairs) to be performed by or on behalf of the
additional insured(s) at the location of the
covered operations has been completed; or
2. That portion of "your work" out of which the injury
or damage arises has been put to its intended
use by any person or organization other than
another contractor or subcontractor engaged in
performing operations for a principal as a part of
the same project.
C. With respect to the insurance afforded to these
additional insureds, the following is added to
Section III – Limits Of Insurance:
If coverage provided to the additional insured is
required by a contract or agreement, the most we
will pay on behalf of the additional insured is the
amount of insurance:
1. Required by the contract or agreement; or
2. Available under the applicable Limits of
Insurance shown in the Declarations;
whichever is less.
This endorsement shall not increase the applicable
Limits of Insurance shown in the Declarations.
*0.
6/
$#
"#
$
#$
)
#"$"%
)
%#
## %$ "
"#
$
$#
"#
$
#
#%"
"&%
"$#
)
%#
##%$&""
"&""
($
$
$
694
;/, 64465 632,? 65-2:265 :,*;065
$
(9(.9(7/
+ 0:
9,73(*,+)@;/,-6336>05.
+
+(@:),-69,;/,,--,*;0=,+(;,6-*(5*,33(;0650->,*(5*,3-69(5@6;/,99,(:65 "
$
#%"
#/,
(4,+5:<9,+:/6>505;/,,*3(9(;065:0:(4,5+,+;605*3<+, * 5@ 3,.(33@ 05*69769(;,+ :<):0+0(9@ 05 >/0*/ @6< 6>5 469, ;/(5 6- ;/, =6;05.
:;6*265;/,,--,*;0=,+(;,6-;/,7630*@ 6>,=,9;/, (4,+5:<9,++6,:56;05*3<+,
(5@ :<):0+0(9@ ;/(; 0: (5 D05:<9,+E <5+,9 (5@ 6;/,9 05:<9(5*, 7630*@ 69 >6<3+ ), (5 D05:<9,+E <5+,9 :<*/ ( 7630*@ )<; -69 0;: ;,9405(;065 69 ;/, ,?/(<:;065 6- 0;: 040; 6-
5:<9(5*,
+ 5@ 69.(50A(;065 ;/(; 0: (*8<09,+ 69 -694,+ )@ @6< (5+ 6=,9 >/0*/ @6< 4(05;(05 4(1690;@6>5,9:/07 6>,=,9 ;/,
(4,+5:<9,++6,:56;05*3<+,(5@5,>3@-694,+
69(*8<09,+69.(50A(;065
;/(;0:(1605;=,5;<9,7(9;5,9:/07693040;,+30()030;@7(9;5,9:/0769*69769(;065
;/(;0:(5D05:<9,+E<5+,9(5@6;/,97630*@
;/(;/(:,?/(<:;,+0;:
040;6-5:<9(5*,<5+,9(5@6;/,97630*@69
+(@:69469,(-;,90;:(*8<0:0;06569-694(;065)@@6<<53,::@6</(=,.0=,5 <:56;0*,6-;/,(*8<0:0;06569-694(;065
6=,9(., +6,: 56; (773@;6 D)6+03@ 051<9@E 69 D7967,9;@ +(4(.,E;/(; 9,:<3;:-964 (5 (**0+,5;;/(;6**<99,+),-69,@6<-694,+69(*8<09,+;/,69.(50A(;065
'1695A59;8.-B 6- #.,:265 @
2*+232:?6<.8*0.
*
0:(4,5+,+;6(++
5@ ,4736@,, 6- @6<9: >/03, <:05. ( *6=,9,+ D(<;6E @6< +65C; 6>5 /09, 69 )6996> 05 @6<9 )<:05,::69@6<97,9:65(3(--(09:
"%$ )#
##%#
- /09,+ D(<;6:E (9, *6=,9,+ D(<;6:E -69
0()030;@ *6=,9(., (5+ 0- 6479,/,5:0=, 69 6330:065 *6=,9(.,: (9, 796=0+,+ <5+,9 ;/0: 6=,9(., 694 -69 (5@ D(<;6E @6< 6>5 ;/,5 ;/, /@:0*(3 (4(., 6=,9(.,: 796=0+,+ (9, ,?;,5+,+ ;6 D(<;6:E @6< /09, 6- ;/, 790=(;, 7(::,5.,9 30./; 69 4,+0<4 ;9<*2 ;@7,
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
Policy # 2SAA3019131
*0.
6/
-:@4)63 69
0:30:;,+65;/,6=,9,+<;6::,*;0656-;/,7630*@+,*3(9(;065:7(.,(:(773@05. ;6 (5@ 6- ;/, 7/@:0*(3 +(4(., *6=,9(.,: ;/,5 ;/, 28.- ;:6 1?92,*3 *4*0. *6=,9(., +,:*90),+65;/0:-694+6,:56;(773@
"<)1,*;;6(4(?04<46- 7,9(**0+,5;>,>033*6=,936::6-<:,6-(/09,+D(<;6E0-0;9,:<3;:
-964(5(**0+,5;@6<(9,3,.(33@30()3,(5+;/,3,::6905*<9:(5(*;<(3-05(5*0(3D36::E "%$
$) '"
'&" ,?*,7;-69;/,!,7<)30*6-
,?0*6
69/09,+D(<;6:E/09,+-693,::;/(5
+(@:;/,*6=,9(.,;,990;69@>033),,?;,5+,+;6(5@>/,9,05 ;/, >693+ ,?*,7;-69;/, !,7<)30* 6-
,?0*6 796=0+,+;/, D05:<9,+C:E 30()030;@;6 7(@ +(4(.,: 0:
+,;,9405,+05( D:<0;E)96<./;05;/,*6=,9(.,;,990;69@+,:*90),+05 #.,:265& @ ;925.99;:6 65-2:2659
#/0:*6=,9(.,+6,:56;(773@;6D.(9(.,67,9(;065:E
%$
"
# )
$5+,9 #.,:265 @ ;925.99;:66<.8*0.684 69 #.,:265& @ *8*0.6<.8*0.684 0-( 365.;,943,(:,+ 697<9*/(:,+ D(<;6E0:(*6=,9,+D(<;6E(5+;/,3,::69 693,5+,9 0:5(4,+(:(5 D++0;065(35:<9,+ B
,::69E 69 D++0;065(35:<9,+ B
,5+,9E >,>0337(@05;/,,=,5;6-(;6;(3
D36::E@6<9(++0;065(33,.(36)30.(;065;6;/,3,::69 693,5+,9 -69(5@+0--,9,5*,),;>,,5;/,(*;<(3 *(:/=(3<,6-;/,D(<;6E(;;/,;04,6-;/,D36::E(5+;/,D6<;:;(5+05.)(3(5*,E6-;/,3,(:, 6936(5 D<;:;(5+05.)(3(5*,E4,(5:;/,(46<5; @6<6>,65;/,3,(:, 6936(5 (;;/,;04,6- D36::E 3.99 (5@ (46<5;: 9,79,:,5;05.;(?,: 6=,9+<, 7(@4,5;: 7,5(3;0,: 05;,9,:; 69 */(9.,: 9,:<3;05.-964 6=,9+<, 7(@4,5;: (++0;065(3403,(., */(9.,: ,?*,::>,(9 (5+;,(9 */(9.,: 3,(:,;,9405(;065 -,,:
&,>03356;7(@(5@(+4050:;9(;0=,*6:;:696=,9/,(+-,,:(::,::,+)@;/,-05(5*,*647(5@;/(; /(:3,(:,+;/,*6=,9,+D(<;6E;6@6<
$
#%"
'&"#%"$
#/,-6336>05.(9,(++,+(:(5 D05:<9,+E<5+,9 #.,:265 @ 2*+232:?6<.8*0. '169*5
59;8.-
#.,:265
*
5@ 7,9:65 69.(50A(;065 ;9<:;,, ,:;(;, 69 .6=,954,5;(3 ,5;0;@ >0;/ 9,:7,*;;6;/,67,9(;0654(05;,5(5*,69<:,6-(*6=,9,+D(<;6E0- * '6< (9, 6)30.(;,+ ;6 (++ ;/(; 7,9:65 69.(50A(;065 ;9<:;,, ,:;(;, 69 .6=,954,5;(3 ,5;0;@ (:(5(++0;065(305:<9,+;6;/0:7630*@)@
(5,?79,::,+796=0:0656-(5D05:<9,+*65;9(*;E69>90;;,5(.9,,4,5;69
(5 ,?79,::,+ *65+0;065 6- ( >90;;,5 7,940; 0::<,+;6 @6< )@ ( .6=,954,5;(3 69 7<)30*(<;/690;@
+ #/,D)6+03@051<9@E69D7967,9;@+(4(.,E0:*(<:,+)@(5D(**0+,5;E>/0*/;(2,:73(*, (-;,9
@6<,?,*<;,+;/,D05:<9,+*65;9(*;E69>90;;,5(.9,,4,5;69
;/,7,940;/(:),,50::<,+ ;6@6<
#/,-6336>05.0:(++,+;6 #.,:265& @ ;925.99;:665-2:2659 $8*59/.86/"201:96/ ".,6<.8?0*259::1.89:6 %9
&,>(0=, (5@ 90./;6- 9,*6=,9@>,4(@/(=,(.(05:;(5@(++0;065(3 D05:<9,+E)<;653@(:
9,:7,*;:D
6::E(90:05.6<;6-;/,67,9(;0654(05;,5(5*,69<:,6-(*6=,9,+D(<;6E7<9:<(5; ;6;/,796=0:065:69*65+0;065:6-;/, D05:<9,+*65;9(*;E>90;;,5(.9,,4,5;697,940; #/0:*6=,9(.,+6,:56;(773@;6D.(9(.,67,9(;065:E
&"($
#
#
#;773.4.5:*8? *?4.5:96- #.,:265
2*+232:?6<.8*0.0:(4,5+,+(:-6336>:
#/,9,-,9,5*,;6
-69;/,*6:;6-)(03 )65+:0:9,73(*,+)@
(5+;/,9,-,9,5*,;6
7,9+(@-69(339,(:65()3,,?7,5:,:0:9,73(*,+)@
7,9+(@
$
#%"
'&"#%"$
*0.
6/
#/0:*6=,9(.,+6,:56;(773@;6;/, *8*0.6<.8*0.684
6<.8*0. >:.59265 6- #.,:265 @ ;925.99 ;:6 6<.8*0. 684 69 #.,:265 & @ *8*0.6<.8*0.684 0: (4,5+,+;6 796=0+, ( 3040; 6- 7,9 +(@ (5+ (4(?04<4 6-
-69;,4769(9@;9(5:769;(;065,?7,5:,
%5-.8 #.,:265 @ ;925.99 ;:6 6<.8*0. 684 69 #.,:265 & @ *8*0. 6<.8*0. 684 6478.1.592<.6<.8*0.>,>0337(@-69;/,,?7,5:,6-9,;<9505.(:;63,5*6=,9,+ D(<;6E;6@6<
)
%")$
'
)(
%#
'&
#.,:265 @
2*+232:?6<.8*0. .336=4736?..>,3;9265+6,:56;(773@0-;/,D)6+03@ 051<9@E9,:<3;:-964;/,<:,6-(*6=,9,+D(<;6E@6<6>569/09, 6=,9(.,0:,?*,::6=,9(5@6;/,9 *633,*;0)3,05:<9(5*,
%
$
!%
$&"
#.,:265 @ ;925.99 ;:6 6<.8*0. 684 1?92,*3 *4*0. 6<.8*0. >0;/ 9,:7,*; ;6 ( *6=,9,+ D(<;6E +,:*90),+ 05 ;/, "*/,+<3, 69 05 ;/, ,*3(9(;065: (3:6 (7730,: ;6 D 6::E ;6 (5@
,3,*;9650* ,8<074,5; ;/(; 9,*,0=,: 69 ;9(5:40;: (<+06 =0:<(3 69 +(;( :0.5(3: (5+ ;/(; 0: 56; +,:0.5,+ :63,3@ -69 ;/, 9,796+<*;065 6- :6<5+ #/0: *6=,9(., (7730,: 653@ 0- ;/, ,8<074,5; 0:
7,94(5,5;3@05:;(33,+05;/,*6=,9,+D(<;6E(;;/,;04,6-;/,D36::E 8<074,5;>/0*/0:9,46=()3, -964 ( /6<:05. <50; >/0*/ 0: 7,94(5,5;3@ 05:;(33,+ 05 ;/, *6=,9,+ D(<;6E (5+ 0: +,:0.5,+ ;6 ), :63,3@ 67,9(;,+ )@ <:, 6- ;/, 76>,9 -964 ;/, D(<;6C:E ,3,*;90*(3 :@:;,4 05 69 <765 ;/, *6=,9,+ D(<;6E 0: *65:0+,9,+ 7,94(5,5;3@ 05:;(33,+ #/0: *6=,9(., (3:6 (7730,: ;6 (5;,55(: (5+ 6;/,9 (**,::690,:5,*,::(9@-69;/,<:,6-;/,,3,*;9650*,8<074,5; #/, /@:0*(3(4(.,+,+<*;0)3,:
30:;,+05;/,+,*3(9(;065:(:(773@05.;6;/,*6=,9,+ D(<;6E(773@;6;/0:*6=,9(.,(:>,33 #/,46:;;/(;>,>0337(@05;/,,=,5;6-(D36::E0:;/,3,::,96-
#/,(*;<(3*(:/=(3<,6-;/,+(4(.,69:;63,57967,9;@(;;/,;04,6-;/,D36::E69
#/,*6:;6-9,7(0905.699,73(*05.;/,+(4(.,+69:;63,5 7967,9;@>0;/6;/,97967,9;@6- 302,205+698<(30;@69
##
)
%$
'&" ""$"$
"
$5+,9 #.,:265 @ ;925.99 ;:6 6<.8*0. 684 69 #.,:265 & @ *8*0. 6<.8*0. 684 .-;,:2+3.;/,-6336>05. 0:(++,+
6+,+<*;0)3,(7730,:;6.3(::+(4(.,0-;/,.3(::0:9,7(09,+9(;/,9;/(59,73(*,+ "#
$#&"
"<)1,*; ;6 ( 4(?04<4 3040; 6- *6=,9(., 0: ,?;,5+,+ ;6 ;/, 7,9:65(3 ,--,*;: 6- ;/, +90=,97(::,5.,9(5+05:<9,+>/03,05:0+,(*6=,9,+ D(<;6E (5++(4(.,+(:( 9,:<3;6-(5 (**0+,5;
6::,: (9, :<)1,*; ;6 (
+,+<*;0)3,
6 :,7(9(;, +,+<*;0)3, (7730,: 0- ;/,
D36::E<5+,9;/0::,*;0650:7(9;6-(:7,*0-0,+ 7,903:*6479,/,5:0=,69*6330:065 D36::E<5+,9 ;/0:7630*@ -;/,D36::E05*3<+,:*6=,9(.,<5+,9469,;/(565,:,*;0656-;/0:,5+69:,4,5; 653@;/,/0./,:;+,+<*;0)3,>033(773@;6;/,,5;09,D36::E
&,>03356;7(@-69D36::E;67,9:65(37967,9;@6-(5@6-;/,-6336>05. * **6<5;:)033:*<99,5*@+,,+:465,@56;,::,*<90;0,:(5+,=0+,5*,6-+,); + 3,*;9650* ,8<074,5; 69 ;(7,: 9,*69+: +0:*: 69 6;/,9 :0403(9 (<+06 =0:<(3 69 +(;( ,3,*;9650*,8<074,5;
, <9:
- 504(3:)09+:69-0:/
. <3306579,*06<::;65,:1,>,39@69:0403(9=(3<()3,:7(05;05.(9;6)1,*;:4(5<:*907;:69 4,*/(50*(3+9(>05.:
/ 65;9()(5+697967,9;@05;/,*6<9:,6-033,.(3;9(5:769;(;06569;9(+,
*0.
6/
0 5D(<;6E0;:,8<074,5;69-3<0+:05*3<+05.-<,3
1 D
6::E *(<:,+)@;/,-;<53,::;/,9,(9, =0:0)3, :0.5:694(92:6--69*0)3,,5;9@ 05;6;/, *6=,9,+D(<;6E(5+;/,;/,-;0:9,769;,+;63(>,5-69*,4,5;(<;/690;0,:
#/, ,9:65(3 --,*;: 6=,9(., 0: ,?*,:: 6=,9 (5@ 6;/,9 =(30+ (5+ *633,*;0)3, 05:<9(5*, *6=,9(.,(=(03()3,-69;/,:(4,D36::E
$
%")&"
$5+,9 #.,:265 @ 1?92,*3*4*0.6<.8*0. -@6< *(99@6330:0656=,9(.,-69;/,+(4(.,+ *6=,9,+D(<;6E ;/,-6336>05. 0:(++,+
-D@6<97,;E:<:;(05:051<9@69+,(;/>/03,05:0+,(*6=,9,+(<;6(;;/,;04,6-( 36:: *6=,9,+<5+,9 6330:065696479,/,5:0=,*6=,9(., >,>0337(@-69;/,-6336>05.
<7;6 -699,(:65()3,(5+96<;05,=,;,905(9@-,,:05*<99,+)@@6<0-D@6<97,;E0:051<9,+05 69(:(+09,*;9,:<3;6-;/,*6=,9,+36::69
( +,(;/),5,-0;0-D@6<97,;E+0,:0569(:( +09,*;9,:<3;6-;/,*6=,9,+36::3,::(5@ 7(@4,5;>, 4(+,;6>(9+=,;,905(9@,?7,5:,:-69D@6<97,;E 5;/,,=,5;6-(*6=,9,+36::+<,;6;/,-;6-(*6=,9,+(<;6>,>0337(@;/,+,(;/),5,-0; :<)1,*;;6 D@6<97,;E0:05:0+,;/,*6=,9,+(<;6(;;/,;04,6-;/,-;(5+D@6<97,;E0:56;9,*6=,9,+ #/0:(++0;065(3*6=,9(.,0::<)1,*;;6(
,+<*;0)3,-69+,(;/(5+=,;,905(9@*(9,:<:;(05,+(:
( 9,:<3; 6- ( *6=,9,+ 36:: 6=,9(., (7730,: 05 ,?*,:: 6=,9 (5@ 6;/,9 =(30+ (5+ *633,*;0)3, 05:<9(5*,
#/,-6336>05.+,-050;065(7730,:;6;/0:*6=,9(.,
D'6<97,;E4,(5:(5@*(;69+6.6>5,+)@(5@05:<9,+*6=,9,+<5+,9;/0:7630*@ #/, 46:; >,>0337(@-69(33+(4(.,:05(5@65,36::0:(;6;(36- 9,.(9+3,::6-;/,5<4),96- +6.:69*(;:05=63=,+
#
&
$%$
$5+,9;/, 1?92,*3*4*0.6<.8*0. ",*;0650-;>669469,7630*0,:69*6=,9(.,-694:(773@;6 ;/,:(4,(**0+,5;;/,-6336>05.(7730,:;67(9(.9(7/ .-;,:2+3. '6<>0337(@;/,/0./,:;+,+<*;0)3,:;(;,+65;/,+,*3(9(;065:7(.,653@65*,-69+(4(.,:;6@6<9 ;9(*;69;9(03,9(5+*(9.6>/,5 (33(9,05:<9,+)@<:(5+(9,+(4(.,+)@;/,:(4,*6=,9,+*(<:, 6-36::
"
$
"
%"#
$&"
&,>0337(@-699,5;(39,04)<9:,4,5;,?7,5:,:05*<99,+)@@6<-69;/,9,5;(36-(5(<;6),*(<:, 6- 36:: ;6 ( *6=,9,+ (<;6 (@4,5; (7730,: 05 (++0;065 ;6 ;/, 6;/,9>0:, (7730*()3, (46<5; 6- ,(*/*6=,9(.,@6</(=,65(*6=,9,+(<;6
6+,+<*;0)3,:(773@;6;/0:*6=,9(.,
&,>0337(@653@-69;/6:,,?7,5:,:05*<99,++<905.;/,7630*@7,906+),.05505. /6<9:(-;,9
;/, 36:: (5+ ,5+05. 9,.(9+3,:: 6- ;/, 7630*@: ,?709(;065 >0;/ ;/, 3,::,9 6- ;/, -6336>05. 5<4),96-+(@:
* #/,5<4),96-+(@:9,(:65()3@9,8<09,+;69,7(09699,73(*,;/,*6=,9,+(<;6 -36::0:
*(<:,+)@;/,-;;/0:5<4),96-+(@:0:(++,+;6;/,5<4),96-+(@:0;;(2,:;6 36*(;,;/, *6=,9,+(<;6(5+9,;<950;;6@6<
<97(@4,5;0:3040;,+;6;/,3,::,96-;/,-6336>05.(46<5;: *
,*,::(9@(5+(*;<(3,?7,5:,:05*<99,+
+ "<)1,*;;6(4(?04<47(@4,5;6-
7,9+(@<7;6
+(@:
#/0:*6=,9(.,+6,:56;(773@>/03,;/,9, (9,:7(9,699,:,9=,(<;6:(=(03()3,;6@6<-69@6<9 67,9(;065:
*0. 6/
- 36:: 9,:<3;:-964;/,;6;(3;/,-;6-(*6=,9,+ (<;66-;/,790=(;,7(::,5.,9;@7,>,>033 7(@<5+,9;/0:*6=,9(.,653@;/(;(46<5;6-@6<99,5;(39,04)<9:,4,5;,?7,5:,:>/0*/0:56; (39,(+@796=0+,+-69<5+,9;/, /@:0*(3(4(.,6=,9(.,?;,5:065 PIC-GLN-020 (10/13)
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
PRIMARY AND NON-CONTRIBUTORY INSURANCE
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART
A. SECTION IV –COMMERCIAL GENERAL LIABILITY CONDITIONS, 4. Other Insurance, and all subparts thereof, as contained in the policy is deleted in its entirely and replaced with the following condition:
4. Other Insurance
If all of the other insurance permits contribution by equal shares, we will follow this method unless the insured is required by written contract signed by both parties, to provide insurance that is primary and noncontributory, and the “insured contract”is executed prior to any loss. Where required by a written contract signed by both parties, this insurance will be primary and non-contributing only when and to the extent as required by that contract.
However, under the contributory approach each insurer contributes equal amounts until it has paid its applicable limit of insurance or none of the loss remains, whichever comes first. If any of the other insurance does not permit contributory by equal shares, we will contribute by limits. Under this method, each insurer’s share is based on the ratio of its applicable limit if insurance to the total applicable limits of insurance of all insurers.
All other terms, conditions and exclusions under the policy are applicable to this endorsement and remain unchanged.
POLICY NUMBER: PPK2265538 COMMERCIAL GENERAL LIABILITY
CG 24 04 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
WAIVER OF TRANSFER OF RIGHTS OF RECOVERY
AGAINST OTHERS TO US (WAIVER OF SUBROGATION)
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
ELECTRONIC DATA LIABILITY COVERAGE PART
LIQUOR LIABILITY COVERAGE PART
POLLUTION LIABILITY COVERAGE PART DESIGNATED SITES
POLLUTION LIABILITY LIMITED COVERAGE PART DESIGNATED SITES
PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART
RAILROAD PROTECTIVE LIABILITY COVERAGE PART
UNDERGROUND STORAGE TANK POLICY DESIGNATED TANKS
SCHEDULE
The following is added to Paragraph 8. Transfer Of
Rights Of Recovery Against Others To Us of
Section IV –Conditions:
We waive any right of recovery against the person(s)
or organization(s) shown in the Schedule above
because of payments we make under this Coverage
Part. Such waiver by us applies only to the extent that the insured has waived its right of recovery against
such person(s) or organization(s) prior to loss. This
endorsement applies only to the person(s) or
organization(s) shown in the Schedule above.
CG 24 04 12 19 © Insurance Services Office, Inc., 2018 Page 1 of 1 Name Of Person(s) Or Organization(s):
AS REQUIRED BY WRITTEN CONTRACT PRIOR TO AN "OCCURRENCE".
Information required to complete this Schedule, if not shown above, will be shown in the Declarations.
INSURED COPY
- 1998 by the Workers’ Compensation Insurance Rating Bureau of California. All rights reserved.
From the WCIRB’s California Workers’ Compensation Insurance Forms Manual - 1999.
WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY WC 04 03 06
WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENT -
CALIFORNIA
We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule. (This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.) You must maintain payroll records accurately segregating the remuneration of your employees while engaged in the work described in the Schedule.
The additional premium for this endorsement shall be % of the California workers’ compensation premium otherwise due on such remuneration.
SCHEDULE
PERSON OR ORGANIZATION JOB DESCRIPTION
2 ANY PERSON OR ORGANIZATION FOR BLANKET WAIVER OF SUBROGATION
WHOM THE NAMED INSURED HAS AGREED
BY WRITTEN CONTRACT TO FURNISH
THIS WAIVER