Continuation of Proclamation of Local Emergency at the Anza Pump Station.
RECOMMENDED ACTION:
Accept Report and Make a Determination that Conditions of Local Emergency Continue to Exist at the Anza Pump Station at the Pacifica State Beach.
STAFF CONTACT:
Lisa Petersen, P.E., Director of Public Works
(650) 738-3767
[email protected]
Louis Sun, P.E., Plant Manager - Wastewater Public Works (650) 738-4660
[email protected]
BACKGROUND/DISCUSSION:
On Monday, March 16, 2020, the Department of Public Works received a report regarding a fire at the Anza Pump Station at Pacifica State Beach. After Public Works staff investigated the report, it was determined that the storm drain pumping system and roof/bathrooms were damaged during the fire. The engines were destroyed, and the pumps needed to be replaced.
The damage to the pump station threatened and continues to threaten the safety of persons and properties within the watershed due to the risk of flooding without an operational pump station.
The City of Pacifica’s Emergency Plan and Section 4-2.01 et seq. of the Pacifica Municipal Code empower the City Manager, acting as the Director of Emergency Services, to proclaim the existence of a local emergency when there is an actual or threatened existence of conditions of disaster or of extreme peril to the safety of persons and properties within this City.
The proclamation is subject to ratification by the City Council within 7 days, pursuant to the Pacifica Municipal Code. The proclamation of the existence of a local emergency further designates the City Manager or designated representative to act on behalf of the City for public assistance and for individual assistance for purpose of receipt, processing and coordination of all inquiries and requirements necessary to obtain available State and Federal assistance.
Additionally, pursuant to Section 3-15.09 (A) of the Pacifica Municipal Code, in cases of an emergency the City Manager is authorized to proceed at once to replace or repair any public facility without adopting plans, specifications, or working details, or giving notice for bids to let contracts. The City must comply with Public Contract Code Section 22050, which provides a process for City Council’s review of the emergency action if notice of bids to let contracts for public projects will not be given because of the emergency.
In this case, the City Manager has determined that the damaged pump station threatens the health and safety of persons and properties, including critical public infrastructure, which Pacifica City Council 2
September 11, 2023
requires immediate attention and constitutes an emergency pursuant to Pacifica Municipal Code section 4-2.02 and Public Contract Code Section 1102.
Such conditions are, or are likely to be, beyond the handling capability of the City’s services, personnel, equipment, and facilities, requiring the use of outside contractors to conduct emergency design and repair pursuant to Pacifica Municipal Code section 3-15.09 without giving notice for bids to let contracts. Immediate action is, and continues to be necessary, due to the clear and imminent danger presented by any storm event that could occur during the time the storm water pump station is non-functional. Flooding could occur to areas upstream of the pump station, causing health and safety issues, as well as extensive property damage. As such, on April 8, 2020, the City Manager did proclaim the existence of a local emergency within the City and the need to continue the emergency action continues as the repair will take approximately 8-14 months or longer. The Proclamation of Local Emergency is attached to this staff report as Attachment 1.
City staff has contracted with the civil engineering firm of Schaaf & Wheeler of San Jose, California to assist the City with the rehabilitation of the pump station. In addition, the pump station has been cleared of any fire damaged debris and the damaged pumps/engines have been removed. On July 13, 2020, the City Council approved construction services agreement for rebuild and re-installation of a pump and gear drive, the renovation of bathrooms, purchase and installation of new stainless-steel doors, and repair pump station wet-well grates. As part of the on-going maintenance for the pump station, staff purchased a new pump which was approved by the Council at the August 9, 2020 City Council meeting. An emergency purchase agreement with Herc Rental for a temporary rental engine was also approved on September 1, 2020 and will remain in place until the pump station is operational. On October 12, 2020, temporary measures were completed to allow for a non-standard system of pumping at the Anza Pump Station until final repairs are completed. This work included a new pump, transfer switch, temporary roof, portable generator connections, and exterior double doors have been installed. Staff is continuing to evaluate and monitor storm water flows and purchased two new sump pumps to accommodate flows.
On May 10, 2021, City Council approved the purchase of two new Caterpillar engines utilizing the City’s established Sourcewell Cooperative Purchase Agreement. The rehabilitation plan is currently 100% completed, and staff has completed the engineering review. The roofing plan was approved by the Building Department. Staff has also completed selection of the Construction Management firm which was from the established On-Call Construction Management list. Staff is in the process of discussing permitting requirements for the overall project with the California Coastal Commission.
Staff completed the field portion of a topographic survey to support a PG&E application to reestablish natural gas service at the Anza Pump Station to supply the natural gas to run the prepurchased natural gas engines to drive the pumps. The City entered into an agreement with PG&E to tap the gas main and install a new gas meter. The City has also engaged a gas pipeline contractor for a quotation on installing the gas service line from the gas main to the gas meter. In addition, the City has submitted the Caltrans Encroachment Permit application required for gas service line construction on Highway 1 and has obtained a separate emergency Coastal Development Permit request with the California Coastal Commission for installation of the new gas line and a redundant pump/engine that was approved.
During a storm event on the morning of December 16, 2021, the City experienced some flooding in the lower Linda Mar area due to the temporary nonstandard pumping system that has been in use at Anza pump station due to the fire damaged pump station engines in March of 2020. This temporary system has been in place because the City has been working to reach agreement with the California Coastal Commission on the remaining permitting requirements for Pacifica City Council 3
September 11, 2023
the permanent pumping system. The City faced several significant stormwater related events from October 2021 through December 2021 and will face more with the continuing storm season. Replacement of this temporary system is considered an emergency and staff is moving forward with construction of the permanent system. To further improve operations between now and when the Anza Pump Station Repair Project is completed, the City recently purchased a small diesel engine that will be used to drive one of the existing smaller stormwater pumps, thereby improving pump station resiliency in the interim. Staff issued a public request to prequalify bidders for the Anza Pump Station project in December 2021. Ultimately, two contractors were deemed qualified to bid on the project. Both contractors submitted bids for the project in February of 2022. The contractors specialize in pump stations.
As of May 1, 2022, the Anza Pump Station Repair Project’s General Contractor, DW Nicholson (DWN), has begun the work and is focusing on providing project equipment submittals and requests for information (RFIs). DWN is currently onsite and working. City consultant team members Schaaf and Wheeler (engineer of record providing construction support) and Ghirardelli and Associates (third-party construction manager) are working closely with City staff to process paperwork, respond to questions along with other issues as they arise, and manage the construction work. Active construction continues at the Anza Pump Station. Except for the roof hatches, the roof installation is complete. The Project continues to finalize electrical equipment submittals and continues coordination with the engine supplier. Two new gas engines were delivered to the site mid-December 2022 and are installed. The third new gas engine arrived at the supplier’s East Bay facilities in late May 2023 and was installed in June 2023. The most recent project schedule estimates that the Pump Station will be tested and ready for manual operation in September/October 2023. Supply chain issues with the electric controls and electric control panel will delay the Pump Station from being tested and ready for automatic operation until late 2023; however, conduit and wire installation is expected to be completed by mid-September 2023. In addition, the project to construct a new 2-inch gas service line for the new gas engines was awarded to Casey Construction. Installation of the new 2-inch gas service line in the parking lot east of the Anza Pump Station was completed in October 2022. Installation of the new 2-inch gas service line from the parking lot into the Caltrans Right of Way near the existing PG&E gas main was completed end of November 2022.
PG&E required additional utility location verification prior to moving forward with the new gas service line tie into the existing gas main, located in US 1. The City furnished PG&E this information. PG&E completed the gas service line tie-in to the gas main April 12th, 2023. The last step in this process consisted of PG&E installing their gas meter and regulator at the Anza Pump Station, which was completed May 2, 2023. In addition, two of the four Anza bathrooms were opened in time for July 4 2023, and the remaining two were opened on August 25, 2023.
Pursuant to Government Code Section 8630(c), the City Council must review the need for continuing the local emergency at least every 60 days until the City Council terminates the local emergency. Conditions of local emergency still exist since the City Council first acted to declare a local emergency on April 13, 2020, and since that time staff has brought the continuance of Proclamation confirming the existence of local emergency at the Anza Pump Station every 30 days with August 14, 2023, being the most recent.
The City is using a combination of city staff, consultants, and contractors to manage the emergency work related to the Anza Pump Station repair project. The City Manager recommends that the City Council make a determination that conditions of local emergency continue to exist at the Anza Pump Station at the Pacifica State Beach. Staff will continue to update the Council on the progress of this emergency work monthly through the emergency declaration Council reports.
FISCAL IMPACT:
Pacifica City Council 4
September 11, 2023
There is no fiscal impact to continue this local emergency.
ORIGINATED BY:
Public Works - Wastewater Division
ATTACHMENT LIST:
Attachment 1 - Resolution No. 19-2020 Ratifying Proclamation of Local Emergency at the Anza Pump Station (PDF)