SECTION VI

CONTRACT FOR CONSTRUCTION
1 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 VL. CONTRACT FOR CONSTRUCTION
LOWER LINDA MAR REHABILITATION AND REPAIR PROJECT C044
This Contract for construction is made this 3rd day of May, 2024 between the City of Pacifica (Owner or City) and Ranger Pipelines Incorporated (Contractor). The work described below shall be performed in accordance with all plans, specifications and other Contract Documents attached to or incorporated into this Agreement.
[NOTE: the following section must be modified for each project to include ALL documents that are part of the Contract Documents.]
The following documents are incorporated into and made part of this Contract by this reference:

Notice to Bidders
• Information for Bidders
Contract Proposal (including list of subcontractors, proposed material suppliers, Bidder's Experience, and Bid Schedule)
• Statement of Responsibility
Certificates of Insurance
• Lien Waivers, Bid Bond, Non-Collusion Affidavit, Faithful Performance Bond, Bond for Payment of Labor and Materials, Guarantee
• General Condition
Special Provisions
• Technical Specifications
• Project Plans
General Specifications
The documents shall be referred to collectively as the "Contract Documents".

SECTION 1 - SCOPE
Contractor shall furnish all necessary management, supervision, labor, materials, tools, supplies, equipment, plant, services, engineering, testing and/or any other act or thing required to diligently and fully perform and complete the work generally described as follows:

Replacement of replacing sewer mainlines throughout the Lower Linda Mar neighborhood in the City of Pacifica (City). The approximate length of sewer mainlines to be replaced are listed below:
• Base Bid = 18,359 linear feet
• Additive Bid Item #1 = 3,450 linear feet
• Additive Bid Item #2 = 7,048 linear feet
The project includes replacement of existing sanitary sewer mains with pipe bursting and open trench construction methods. New sanitary sewer piping ranges from 8-inch to 16-inch HDPE 2 | Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 pipe for pipe bursting methods, and 8-inch to 12-inch for open trench methods. The work includes reconnection of sanitary sewer laterals, connection to existing manholes, construction of new manholes, manhole modifications, manhole rehabilitation, and lamp hole replacement.

The project includes, but is not limited to the following additional items:
• Bypass pumping and/or routing of sewage.
• Prepare and implement a water pollution control plan (WPCP) and site protection. • Traffic and pedestrian control
Dewatering and the construction of all temporary shoring and slope protection measures.
• Replacement of disturbed landscaping, private improvements, curb & gutter, sidewalks, curb ramps, monuments, AC pavement rehabilitation, and other miscellaneous items.

The project includes additive bid items that may or may not be awarded by the City depending on the bid results and available funding. The project also includes provisions for the contractor to replace private laterals under separate contracts with individual property owners.

LOWER LINDA MAR REHABILITATION AND REPAIR PROJECT C044
Contractor shall comply with all requirements of the Contract Documents. Where there is a conflict between the requirements of the several Contract Documents, the more stringent requirements shall govern.

Without limiting the foregoing description, Contractor's scope of work includes, but is not limited to, the following:
• Submit all required samples, product data, certificates, operations, and maintenance instructions, guarantees, and other submittals no later than five (5) days after the date the City issues a Notice to Proceed.

Obtain all necessary permits and approvals for the Work. • Comply with all applicable federal, state, and local laws and guidelines. • Protect all materials to be used in the Work in accordance with the specifications.

Protect existing facilities and personal property. Contractor shall be solely responsible for all damage to the building or contents.
• Attend a preconstruction conference with City to discuss schedule, access, sequence of construction plan (to be submitted), and other issues.

Prepare and submit a written daily activity report to City for each day on which work is performed, including weekends and holidays when worked, and submit the reports to the City no 3 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 later than the next business day. The daily reports shall, at a minimum, include the following information: construction activities and locations, construction crew sizes of general and subcontractors, start or completion of activities, progress on construction activities (including units or portions of work completed), tests or inspections performed, deliveries of material or equipment, delays or potential delays, visitors to the site, weather conditions, construction equipment used, and personal injuries or damage to property.

The Contractor shall be responsible for unloading, hoisting, and otherwise handling its own materials, supplies and equipment.

Coordinate with owner-scheduled use or events at the Project site.

The Contractor is responsible for researching and complying with all local codes, agencies and jurisdictions that regulate and govern the Work. • Contractor shall set up, identify, coordinate, provide safe access, and obtain all inspections for its work, as required by any authorized agency or applicable code, prior to covering up work
SECTION 2 - PRICE
A. City agrees to pay, and Contractor agrees to accept, the sum of Eight Million Four-Hundred Seventy-Eight Thousand and fifteen Dollars ($8,478,015) (the "Contract Price") subject to adjustments for changes in the work as may be directed in writing by City, as payment in full for the Contractor shall submit a payment application in the amount of the contract sum upon completion of the Work and satisfaction of all conditions of the Contract Documents. City shall make payment within 30 days of receipt of application, less five percent retention. City shall release the retained funds no less than thirty-five (35) days after the date the City accepts the Work.

B. Pursuant to Public Contract Code Section 22300, for monies earned by the Contractor and withheld by the City to ensure the performance of the Contract, the Contractor may, at its option, choose to substitute securities meeting the requirements of Public Contract Code Section 22300.

C. Contractor agrees to furnish, as a condition of payment, payroll affidavits, receipts, vouchers, and other documents, in form satisfactory to City, prior to receipt of any payment. Contractor shall submit Conditional and Unconditional waivers and release of lien upon (as provided in Civil Code Section 3262) on behalf of itself and suppliers that furnished labor, material, equipment, or services to the Project.

SECTION 3 - ENTIRE AGREEMENT
This Contract for Construction, including the documents incorporated herein, represents the entire agreement between City and Contractor and supersedes any prior written or oral representations.
4 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 SECTION 4 - TIME
A. Contract will be awarded within 60 days from the bid opening. Notice to Proceed will be issued within two weeks of contract award. Project must commence as soon as the Notice to Proceed is given. Project is to be completed within three hundred calendar days from the Notice to Proceed (Contract Time). The Contractor shall pay to the City of Pacifica Fifteen Hundred Dollars ($1,500) for each and every calendar days delay in finishing the work in excess of the Contract Time, as modified in accordance with the Contract Documents.

B. Time is of the essence of this Agreement.

C. Contractor shall provide City with scheduling information in a form acceptable to City, including any changes made by City in the scheduling of work. Contractor shall coordinate its work with that of all other contractors, subcontractors, and suppliers so as not to delay or damage their performance.

D. It is further agreed that in case Contractor fails to complete the Work in all parts and requirements within the Contract Time, the City shall have the right to extend the Contract Time or not, as may seem best to serve the interest of the City, and if it decides to extend Contract Time, City shall further have the right to charge to the Contractor, his heirs, assigns or sureties, and to deduct from the final payment for the Work, all or any part, as it may deem proper, of the actual cost of engineering, inspection, superintendence, and other overhead expenses which are directly chargeable to the Contract, and which accrue during the period of such extension.

The Contractor will not be assessed with liquidated damages or the cost of engineering and inspection during the delay in the completion of the Work caused by acts of God or of the public enemy, fire, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes; provided, that the Contractor shall within five (5) days from the beginning of any such delay, notify the City, in writing of the causes of delay. The City shall ascertain the facts and the extent of delay, and his findings thereon shall be final and conclusive.

E. In the event that Contractor's work is delayed for any reason, including acts of City, Contractor's sole remedy shall be an extension of time equal to the period of delay, provided Contractor has given City written notice of the commencement of delay within 48 hours of its occurrence.

SECTION 5 - LABOR
A. The Contract is subject to the provisions of Part 7 of Division 2 of the California Labor Code (Sections 1720 and following), and Contractor and any subcontractor shall pay not less than the specified prevailing rates of wage to all workers employed in performance of the Work.

Pursuant to the provisions of Section 1770 of the Labor Code of the State of California, the City 5 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 Council of the City of Pacifica has obtained the general prevailing rate of wages and employer payments for health and welfare, vacation, pension and similar purposes in the City, a copy of which is on file at the Calera Creek Water Recycling Plant and shall be made available for viewing to any interested party upon request.

B. Contractor's attention is directed to the provisions in Section 1777.5 and 1777.6 of the Labor Code concerning the employment of apprentices by the Contractor or any subcontractor under the Contractor. It shall be the responsibility of the Contractor to effectuate compliance on the part of itself and any subcontractors with the requirements of said sections in the employment of apprentices. Information relative to apprenticeship standards, wage schedules, and other requirements may be obtained from the Director of Industrial Relations, ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.

C. Pursuant to the requirements of Division 4 of the Labor Code, the Contractor will be required to secure the payment of worker's compensation to its employees in accordance with the provisions of Section 3700 of the Labor Code. Prior to commencement of work, the Contractor shall sign and file with the City a certification in the following form:
"I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions before commencing the performance of the work of this contract."
D. The Contractor or subcontractor shall, as a penalty to the state or political subdivision on whose behalf the contract is made or awarded, forfeit twenty-five dollars ($25) for each worker employed in the execution of the contract by the respective contractor or subcontractor for each calendar day during which the worker is required or permitted to work more than 8 hours in any one calendar day and 40 hours in any one calendar week in violation of the provisions of this article.

E. Contractor certifies that it is aware of and has complied with the provisions of California Labor Code Section 6401.7, which requires every employer to adopt a written injury and illness prevention program.

SECTION 6 - CHANGES IN WORK
A. Contractor shall make no changes in the Work without written direction from the City.

Contractor shall not be compensated for any change made without any such written direction.

No changes in the work covered by this Agreement shall exonerate any surety or any bond giver in connection with this Agreement
B. If the City directs the Contractor in writing to make changes in the Work that materially affect the cost of performing the Work, the Contract Price will be adjusted based on one of the following:
6 | Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 i. Where the Work involved is covered by unit prices contained in the Contract Documents, by application of unit prices to the quantities involved in the changed Work; ii. By establishment of new unit prices and related quantities for the changed Work; iii. By a combination of existing and new unit prices and related quantities for the changed Work; or
iv. By mutual acceptance of a lump sum.

C. If the City directs the Contractor in writing to make changes in the Work that materially affect the time required to perform the Work, the City will make a reasonable adjustment to the Contract Time.

D. There is no allowable mark-up for extra work or changes in work.

SECTION 7 - CLAIMS
A. If any dispute shall arise between City and Contractor regarding performance of the Work, or any alleged change in the work, Contractor shall timely perform the disputed work and shall give written notice of a claim for additional compensation for the work to City within ten (10) days after commencement of the disputed work. Contractor's failure to give written notice within the ten (10) day period constitutes an agreement by Contractor that it will receive no extra compensation for the disputed work.

No claim, potential claim, dispute or controversy shall interfere with the progress and performance of the Work or any changes thereto, and Contractor shall proceed as directed by Owner in all instances with its Work, including any disputed Work, or any changes thereto and that any failure of Contractor to comply herewith and to proceed with its work shall automatically be deemed a material breach of this Contract entitling Owner to all remedies available under Section 10 or other provision of this Contract and applicable law. Except as provided elsewhere in the Contract Documents, Owner shall continue to make payments in accordance with the Contract.

SECTION 8 - INSPECTION AND PROTECTION OF WORK
A. Contractor shall make the Work accessible at all reasonable times for inspection by the City.

Contractor shall, at the first opportunity, inspect all material and equipment delivered to the jobsite by others to be used or incorporated in the Contractor's work and give prompt notice of any defect therein. Contractor assumes full responsibility to protect the work done hereunder until final acceptance by the City.

B. When the Work is completed, Contractor shall request, in writing, a final inspection. Within 7|Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 ten (10) days of the receipt of such request, the City shall make a final inspection. The Contractor or its representatives may be present at the final inspection. The purpose of such final inspection shall be to determine whether the Work has been completed in accordance with the Contract Documents, including all change orders and all interpretations and instructions previously issued.

C. All materials the City has determined do not conform to the requirements of the Contract Documents will be rejected, whether in place or not. They shall be removed immediately from the site of the work, unless otherwise permitted by the City. No rejected material shall be used in the Work, unless the defects have been corrected and approval in writing has been given by the City. The cost of re-testing material or workmanship that fails to pass the first test shall be borne by the Contractor. Upon failure of the Contractor to comply promptly with any order of the City made under the provisions in this section, the City shall have authority to cause the removal and replacement of rejected material and to deduct the cost thereof from any monies due or to become due the Contractor.

SECTION 9 - ASSIGNMENT AND SUBCONTRACTING
A. Contractor shall give personal attention to the performance of the Work and shall keep the Work under its control.

B. No subcontractors will be recognized as such, and all persons engaged in the work of construction will be considered as employees of the Contractor, who will be held responsible for their work which shall be subject to the provisions of the Contract and specifications.

C. No subcontractor who is ineligible to bid work on, or be awarded, a public works project under Labor Code Sections 1771.1 or 1777.7 can bid on, be awarded, or perform work as a subcontractor on the Project. The Contractor is prohibited from performing work on the Project with a subcontractor who is ineligible to perform work on a public works project under these sections of the Labor Code.

When a portion of the work which has been subcontracted by the Contractor is not being prosecuted in a manner satisfactory to the Engineer or Collection Manager or they're representative, the subcontractor shall be removed immediately on the request of the Engineer or Collection Manager and shall not again be employed on the work.

D. Contractor may not assign performance of the Contract except upon written consent of the City.

SECTION 10 - TERMINATION
A. Should Contractor fail within three (3) calendar days from receipt of City's written notice to correct any contractual deficiencies, including but not limited to failure perform the Work in accordance with the Contract Documents, failure to comply with the directions of City, or failure 8 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 pay its creditors, City may terminate this Agreement. Following a termination for default, City shall have the right to take whatever steps it deems necessary to correct and complete the Work and charge the cost thereof to Contractor, who shall be liable for the full cost of City's corrective action, including reasonable overhead, profit, and attorneys' fees.

B. City may at any time terminate the Contract at City's convenience upon five days written notice to Contractor; in the event of termination for convenience, Contractor shall recover only the actual cost of work completed to the date of termination, which costs are documented to City's satisfaction, plus a reasonable amount not to exceed fifteen percent (15%) of the actual cost of the Work performed for overhead and profit. Contractor shall not be entitled to any claim or lien against City for any additional compensation or damages in the event of such termination.

C. If City terminates Contractor for cause, and if it is later determined that the termination was wrongful, such default termination shall automatically be converted to and treated as a termination for convenience. In such event, Contractor shall be entitled to receive only the amounts payable under this section, and Contractor specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits.

SECTION 11 - HOLD HARMLESS AND INDEMNIFICATION
A. The City of Pacifica and all officers and employees thereof connected with the Work, including but not limited to the Director of Wastewater, Collection Manager, Engineer, Inspector, the City Council, elected and appointed officials, City volunteers and servants, City contractors and agents (collectively the "Indemnitees"), shall not be answerable or accountable in any manner: for any loss or damage that may happen to the Work or any part thereof; for any loss or damage to any of the materials or other things used or employed in performing the Work; for injury to or death of any person; or for damage to property from any cause except losses due to sole or active negligence of the City of Pacifica' officers or employees.

To the fullest extent allowed by law, Contractor shall defend, indemnify and hold harmless the Indemnitees from all lability, penalties, costs, losses, damages, expenses, causes of action, claims or judgments, including attorney's fees and other defense costs, resulting from injury to or death sustained by any person (including Contractor's employees), or damage to property of any kind, or any other injury or damage whatsoever, which injury, death or damage arises out of or is in any way connected with the performance of the Work, regardless of the Contractor's fault or negligence, including any of the same resulting from City's alleged or actual negligent act or omission, or its agents, contractors or employees; except that said indemnity shall not be applicable to injury, death or damage to property arising from the sole or active negligence or willful misconduct of City, its officers, agents, or servants who are directly responsible to City.

This indemnification shall extend to claims asserted after termination of this Contract for whatever reason.

B. In addition to any remedy authorized by law, so much of the money due the Contractor under and by virtue of the contract as shall be considered necessary by the City, may be retained by the 9 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 City of Pacifica until disposition has been made of such suits or claims for damage.

SECTION 12 - BONDS AND INSURANCE
A. Bonds.
i. Within ten (10) days after being notified of the award of the contract, and before the City will execute the agreement for construction, the Contractor to whom the Contract is awarded shall furnish and file with the City Performance and Payment Surety bonds as set forth below.
il. Contractor shall submit a faithful performance bond on the form provided with the Contract Documents, duly executed by a responsible corporate surety listed in the United States Department of the Treasury circular entitled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies," authorized to do business in the State of California and acceptable to City conditioned upon the faithful performance by the Contractor of all requirements of the Contract Documents. The amount of said bond shall be in a sum no less than one hundred percent (100%) of the total Contract Price.
il1. Contractor shall also submit a bond on the form provided with the Contract Documents, duly executed by a responsible corporate surety listed in the United States Department of the Treasury circular entitled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies," authorized to do business in the State of California and acceptable to City, which in all respects complies with Civil Code sections 3247-3252, inclusive. This bond, hereinafter referred to as a "payment bond," shall be in a sum no less than one hundred percent (100%) of the Contract Price.

B. Insurance.

1. Contractor shall obtain, at its sole cost and expense, all insurance required by this section 12.B. Certificates of such insurance and copies of the insurance policies and endorsements shall be delivered to City within ten (10) days after being notified of the award of the contract, and before execution of the agreement for construction by the City.

11. The insurance requirements specified herein shall apply to all subcontractors. The Contractor shall designate appropriate insurance limits for subcontractors. It shall be the responsibility of the Contractor to ensure that all subcontractors comply with this provision, and to verify their compliance when requested by the City. The Contractor shall not allow any subcontractor to commence work until all insurance required of the subcontractor has been obtained and verified by the Contractor and submitted to the City. Subcontractors shall furnish original certificates and endorsements as verification of insurance coverage. Upon request, Contractor shall deliver certificates of insurance or copies of the insurance policies and endorsements of all subcontractors; provided, however, that this authority shall not relieve Contractor of its obligation to ascertain the existence of such insurance. 10 |P age

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 111. The insurance required by this article shall be maintained by Contractor in full force and effect at all times during prosecution of the Work and until the expiration of the warranty period following the final completion and acceptance thereof by City, and every policy shall be endorsed to state that it shall not be assigned, cancelled, or reduced in coverage without thirty (30) days' prior written notice to City. Every policy shall also be endorsed to state that the City shall be given written notice of nonrenewable at least thirty (30) days prior to the nonrenewable date.

The parties defined as "Indemnitees" above in Section I1, are collectively defined herein as the "Additional Insureds."
V. Liability Insurance. This insurance shall protect the Contractor from claims for bodily injury and property damage which may arise because of the nature of the work or from operations under this Contract.
a. Commercial General Liability
(i) Vendor shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than five million dollars coverage, and be endorsed using Insurance Services Office forn CG 20 10 (or equivalent) to provide that City and its officers (ii) Any failure to comply with reporting provisions of the policies by Vendor shall not affect coverage provided the City.
(iii) Coverage shall state that Vendor insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability. (iv) Coverage shall contain a waiver of subrogation in favor of the City.

Workers' Compensation and Employers' Liability- Statutory Vendor shall maintain Workers' Compensation Insurance and Employer's Liability Insurance with limits of at least one million dollars ($1,000,000). Vendor shall submit to City, along with the certificate of insurance, a waiver of subrogation endorsement in 11 Pace

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 favor of City, its officers, agents, employees, and volunteers. (ii) (Proof of Worker's Compensation is not required if Consultant provides written verification that they have no employees). c. Business Automobile Liability
(iii) Vendor shall provide auto liability coverage for owned, non- owned, and hired autos using ISO Business Auto Coverage form CA 00 01 (or equivalent) with a limit of no less than five million dollars ($5,000,000) per accident.
d. Builders Risk Insurance
(i) Contractor shall obtain and maintain Builders Risk/Course of Construction insurance. Policy shall be provided for replacement value on an "all-risk" basis, including earthquake and flood. The City shall be named as Loss Payee on the policy and there shall be no coinsurance penalty provision in any such policy. Policy Pollution Liability Insurance
e.
(i) Sudden, Coveral ahal be pal pidd ion and remediation. the policy limit shall be no less than two million dollars ($2,000,000) project site to the final disposal location, including non-owned (ii) The policy shall be endorsed to include the City, its officers, employees, and agents as insureds.
f. All Coverages
It shall be a requirement under this agreement that any available insurance proceeds broader than or in excess of the specified available Surance Arional insured lur limose l be
requirements for coverage and limits shall be (1) the minimum coverage and limits specified in this Agreement; or (2) the broader coverage and maximum limits of coverage of any
Insurance policy or proceeds available to the named insured; whichever is greater. No representation is made that the minimum insurance requirements of this agreement are sufficient to cover the obligations of the Contractor under this agreement. 12 ! agg

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 (ii) Each insurance policy required by the agreement shall be endorsed to (iii) All self-insurance, self-insured retentions, and deductibles must b leclared and approved by the City
(iv)
endorsements, and waivers of subrogation evidencing complianc with the insurance requirements above. The Vendor must agree to provide complete, certified copies of all required insurance policie if requested by the City
(v) Acceptability of Insurers - Insurance shall be placed with insurers admitted in the State of California and with an A.M. Best rating of g.
(i) Contractors shall require and verify that all subcontractors, or ther parties hired for this work, purchase and maintain coverag or indemnity and insurance requirements as least as broad a specified in this agreement to the extent they apply to the scope of the subcontractor's work with the same certificate of insurance requirements and naming as additional insureds all parties to this contract. Contractor shall include the following language in their agreement with Subcontractors: Subcontractors hired by
Contractor agree to be bound to Contractor and City in the same manner and to the same extent as Contractor is bound to City under the contract documents and provide a valid certificate of insurance and the required endorsements included in the agreement as proof of compliance prior to commencement of any work and to include this same requirement for any subcontractors they hire for this work. A copy of the owner contract document indemnity and insurance provisions will be given to the provide proot o
ubcontractor upon regres Contacter shall provide s
C. Waiver of Subrogation. City and Contractor waive all rights against each other and against all other subcontractors for loss or damage to the extent covered by Builder's Risk or any other property or equipment insurance applicable to the Project, except such rights as they may have to the proceeds of such insurance less their pro-rata share of the deductible. If the policies of insurance referred to in this section require an endorsement or consent of the insurance company to provide for continued coverage where there is a waiver of subrogation, the owners of such policies will cause them to be so endorsed or obtain such consent.

D. Insurance Requirements are Material Elements of Performance. In the event of the breach of any provision of this paragraph, or in the event of any notices received which indicate any required insurance coverage will be diminished or canceled, City, at its option, may, 13| Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 notwithstanding any other provisions of this Agreement to the contrary, immediately declare a material breach of this Agreement and suspend all further work pursuant to this Agreement.

SECTION 13 - CLAIMS RESOLUTION
Disputes arising under this Agreement shall be resolved in accordance with the procedures set forth in Sections 9204 and 20104.50 of the Public Contract Code.

SECTION 14 - WARRANTY
Contractor warrants to City that all materials and equipment furnished shall be new, free from faults and defects and of good quality. Contractor hereby warrants its work against all deficiencies and defects for the period required by the Special Provisions or the longest period permitted by the law of this State, whichever is less.

SECTION 15 - LAWS TO BE OBSERVED
A. Contractor shall keep itself fully informed of all existing and future state and federal laws and county and municipal ordinances and regulations which in any manner affect those engaged or employed in the work, or the materials used in the work, or which in any way affect the conduct of the Work, and of all such orders and decrees of bodies or tribunals having any jurisdiction or authority over the same.

B. Contractor shall at all times observe and comply with, and shall cause all of its agents and employees to observe and comply with all such existing and future laws, ordinances, regulations, orders, and decrees of bodies or tribunals having any jurisdiction or authority over the work; and shall protect and indemnify the City, and all officers and employees thereof connected with the work, including but not limited to the Deputy Director of Public Works - Wastewater, against any claim or liability arising from or based on the violation of any such law, ordinance, regulation. order, or decree, whether by the City's representative or their employees. If any discrepancy or inconsistency is discovered in the plans, drawings, specifications, or contract for the work in relation to any such law, ordinance, regulation, order or d-cree, Contractor shall forthwith report the same to the City in writing.

SECTION 16 - MISCELLANEOUS
A. Utility Facilities.

The Contractor shall protect from damage any utility facilities that are to remain in place, be installed, relocated, or otherwise rearranged.

If Contractor while performing the Work discovers utility facilities not identified in the Contract Documents, Contractor shall immediately notify the City and the utility owner.

City shall arrange the removal, relocation, or protection of existing main or trunk line utility

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 facilities located at the site of the Work but not identified in the Contract.

If the Contractor is required to locate, repair damage not due to the Contractor's failure to exercise reasonable care, and remove or relocate existing main or trunk line utility facilities, it shall be compensated under the Changes section of this Contract, including payment for equipment on the Project necessarily idled during such work. iv. Contractor will not be entitled to damages or additional payment for delays caused solely by the failure of City, or the owner of the utility, to provide for removal or relocation of existing main or trunk line utility facilities not identified in the Contract Documents, except for equipment necessarily idled during such work.

V. Contractor shall not be assessed liquidated damages for delay in completing the Work solely attributable to the failure of City, or the owner of the utility, to provide for removal or relocation of existing main or trunk line utility facilities not indicated in the Contract Documents with reasonable accuracy.

The right is reserved by the City and the owners of facilities or their authorized agents, to enter the Project site for the purpose of making such changes as are necessary for the rearrangement of their facilities or for making necessary connections or repairs to their properties. Contractor shall cooperate with forces engaged in such work and shall conduct its operations in such a manner as to avoid any delay or hindrance to the work being performed by such other forces.
vii. Attention is directed to the possible existence of underground facilities not known to the City of Pacifica, or in a location different from that which is shown on the plans or in the Contract Documents. The Contractor shall take all steps reasonably necessary to ascertain the exact location of all underground facilities prior to doing work that may damage such facilities or interfere with their service, including but not limited to calling USA to mark utilities.

B. Differing Site Conditions
i. The Contractor shall promptly, and before the following conditions are disturbed, notify the City in writing of any:
a. Material that the Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code that is required to be removed to a Class I disposal site in accordance with provisions of existing law.

All costs associated with removing, hauling, and disposing of materials in a Class II or Class III landfill/disposal site shall be included in the contractor's bid. This includes disposal of 15 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 excavated materials, sludge and debris removed from the sewer system, and any other material to be removed from the site.

Subsurface or latent physical conditions at the site differing materially from those indicated in this Contract, or
c. Unknown physical conditions at the site of any unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Contract.

The City shall promptly investigate the conditions, and if it finds that such conditions do materially so differ, or do involve hazardous waste, and cause an increase or decrease in the Contractor's cost of, or the time required for, performance of any part of the Work, it shall issue a change order under the provisions described in the Contract Documents. ili. No claim of the Contractor under this clause shall be allowed unless the Contractor has given the notice required in the Contract Documents. iv. In the event a dispute arises between the City and the Contractor as to whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the Contractor's cost of, or time required for, performance of any part of the work, Contractor shall not be excused from completing the Work as provided in the Contract Documents. The Contractor shall proceed with all work to be performed under the Contract. The Contractor shall retain any and all rights provided either by this Contract or by law which pertain to the resolution of disputes and protests.

C. Records and Audits.
i. Contractor and its subcontractors shall establish and maintain records pertaining to this contract. Contractor's and subcontractors' accounting systems shall conform to generally accepted accounting principles and all records shall provide a breakdown of total costs charged under this contract, including properly executed payrolls, time records, invoices, and vouchers. ii. Contractor shall permit City and its authorized representatives to inspect and examine Contractor's books, records, accounts, and any and all data relevant to this Contract at any reasonable time for the purpose of auditing and verifying statements, invoices, or bills submitted by Contractor pursuant to this contract and shall provide such assistance as may be reasonably required in the course of such inspection. City further reserves the right to examine and re-examine said books, records, accounts, and data during the three (3) year period following the termination of this Contract; and Contractor shall in no event dispose of, destroy, alter, or mutilate said books, records, accounts, and data in any manner whatever for three (3) years after the termination of this Contract.
16| Pag

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 i11. Pursuant to California Government Code Section 10532, the parties to this Contract shall be subject to the examination and audit of representative of the Auditor General of the State of California for a period of three (3) years after final payment under the contract. The examination and audit shall be confined to those matters connected with the performance of this contract including, but not limited to, the cost of adininistering the contract SECTION 17 - WAIVERS OF LIEN
Upon request the Contractor shall submit a complete list of major suppliers and/or subcontractors who will be providing material and/or labor for the performance of the Work, and shall submit with each payment request waivers of lien from each major supplier and/or subcontractor. A sample of this form to be used will be furnished by the City.

SECTION 18 - BACK CHARGES
Charges from Contractor to City will not be honored or paid by City unless the charges are authorized and approved by City at the time the work is being performed for which a charge is to be submitted.

SECTION 19 - CLEAN-UP
Contractor will remove from the project site all debris resulting from performance of the Work no less often than daily. If Contractor fails to do so, City may, after twenty-four (24) hours" notice to Contractor, clean up the site and deduct the cost from the Contract Price.

SECTION 20 - LICENSE REQUIREMENT
Contractor's attention is directed to Business and Professions Code Sections 7000 et seq. concerning the licensing of contractors. At the time Contractor enters into this Contract and all times Contractor is performing the Work, Contractor shall have a valid license issued by the Contractors State License Board in the classification stated in the Contract Documents.

Contractor and all subcontractors shall be licensed in accordance with the laws of this State and any contractor or subcontractor not so licensed is subject to penalties imposed by such laws.

CONTRACTORS ARE REQUIRED BY LAW TO BE LICENSED AND REGULATED

BY THE CONTRACTORS' STATE LICENSE BOARD WHICH HAS JURISDICTION

TO INVESTIGATE COMPLAINTS AGAINST CONTRACTORS IF A COMPLAINT

REGARDING A PATENT ACT OR OMISSION IS FILED WITHIN FOUR YEARS OF THE DATE OF THE ALLEGED VIOLATION. A COMPLAINT REGARDING A

LATENT ACT OR OMISSION PERTAINING TO STRUCTURAL DEFECTS MUST BE FILED WITHIN 10 YEARS OF THE DATE OF THE ALLEGED VIOLATION. ANY

QUESTIONS CONCERNING A CONTRACTOR MAY BE REFERRED TO THE REGISTRAR, CONTRACTORS' STATE LICENSE BOARD, P.O. BOX 26000, SACRAMENTO, CALIFORNIA 95826.
17| Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 SECTION 21 - NOTICES
All notices required by this Agreement shall be given to the City and Contractor in writing, by first class mail, postage prepaid, addressed as follows:

CITY: City Manager
540 Crespi Dr.

Pacifica, CA 94404
Phone: (650) 738-7409
Facsimile: (650) 359-6038
Email: [email protected]
CONTRACTOR: Ranger Pipelines Incorporated
1790 Yosemite Avenue
San Francisco, Ca 94124
Phone: 415-822-3700
Attention: Thomas Hunt
Email Address: [email protected]
SECTION 22 - GOVERNING LAW AND VENUE
This Agreement shall be deemed to have been executed in the County of San Mateo, California. The 18 Page

CONTRACT FOR CONSTRUCTION
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 IN WITNESS THEREOF, three identical counterparts of this Agreement, each of which shall for all purposes be deemed an original thereof, have been fully executed by the parties hereinabove named. on the day and vear first hereinabove written.

CITY OF PACIFICA,
A Municipal Corporation:

Kevin Woodhouse, City Manager
ATTEST:

Sarah Coffey, City Clerk
APPROVED AS TO FORM:

Michelle Kenyon, City Attorney
CONTRACTOR:

Ranger Pipelines Incorporated
Peter Cuddihy, VP - Operations
19 Page

SECTION IV

CONTRACT PROPOSAL
16 | Page
IV. CONTRACT PROPOSAL
TO

CITY OF PACIFICA

SAN MATEO COUNTY
FOR
LOWER LINDA MAR REHABILITATION AND REPAIR PROJECT C044
Name of Bidder Ranger Pipelines Incorporated _of
Business Address 1790 Yosemite Ave
San Francisco, CA 94124
Telephone L 415-822-3700
TO THE CITY COUNCIL OF THE CITY OF PACIFICA:

Pursuant to and in compliance with your Notice to Bidders for the Project identified above and the other Contract Documents relating thereto, the undersigned Bidder, being fully familiar with the terms of the Contract Documents, the current general prevailing wage rates, local conditions affecting the performance of the Project, the character, quality, quantities and scope of the work and the cost of the work at the place of performance, hereby proposes and agrees, within the time stipulated in the Contract Documents, to furnish to the City of Pacifica all of the transportation, materials, equipment, tools, excavation, sheeting, shoring, bracing, supports, plant and other facilities, labor, services, permits, utilities, and other items necessary to conduct and complete the Project, all in strict conformity with the Contract Documents, including Addenda identified herein for the price set forth in the Bid Schedule.

Bidder declares that the only persons or parties interested in this proposal are those named herein, and that this proposal is made without collusion with any person, firm, or corporation Bidder proposes and agrees, if the proposal is accepted, that Bidder will execute a contract wit the City, in strict conformity to the Contract Documents including providing acceptable insurance, security, and labor and materials and performance bonds, in the form set forth in the Contract Documents, and will perform the entire work for the prices set forth in the attached Bid Schedule, upon which the award of contract is made.
17| Page

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044

PROPOSED SUBCONTRACTORS
Pursuant to California Public Contract Code Section 4100 et seq., the following list gives the name, contractor's license number, business address, and portion of work (description of work to be done) for each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvements, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specifically fabricates and installs a portion of the work or improvement according to detailed drawings contained in the plans and specifications, in an amount in excess of one-half of 1 percent of the prime contractor's total bid or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of 1 percent of the prime contractor's total bid or ten thousand dollars ($10,000), whichever is greater. Additional supporting data may be attached to hi presenced shas be serach page shall be sequentialy numbered, headed "Proposed Subcontractors" and

CONTRACTORS BUSINESS

NAME LICENSE ADDRESS PORTION OF WORK
DARCY * HARTY 1300 Carroll Are.

CONSTRUCTION, INC. 474146 SanFrancisco, RA 94124 PIPEBURSTING - PARTIAL DIR
# 1000000621
WESTLAND LIC.# 1018057 3100E. E.10**St. #A
CONTRACTORS, INC. DIR # (00004247| Oakland, CA 94601 PIPEDURSTING - PARTIAL / MANHOLES CHRISP LIC. # 374600 43650 Osgood Rd.

COMPANY DIR # 10000000306 fremant CA 94539 STRIPING
The Prime Contractor shall perform at least 50% of the work with its own forces.

After the award of contract, substitutions of the above-listed proposed subcontractors may only be made with the prior approval of the Engineer in accordance with Public Contract Code section The above information is part of the proposal. Signing this proposal on the signature portion thereof shall also constitute signature of this list of Proposed Subcontractors 18 Page

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044

CON RACIORS

EXPERIENCE AND QUALIFICATIONS
NOTE: EACH BIDDER MUST MEET THE EXPERIENCE REQUIREMENTS AND

SAFETY QUALIFICATIONS PRESENTED IN THE BIDDER'S STATEMENT OF

RESPONSIBILITY AND CONTRACT DOCUMENTS IN ORDER TO BE
CONSIDERED A RESPONSIVE BIDDER.

The following statements as to the experience and financial qualifications of the bidder are to be submitted with the Contract Proposal, as a part thereof. The truthfulness and accuracy of the information is guaranteed by the bidder.

The bidder has been engaged in the contracting business, under the present business name, for years. Experience in work of a nature similar to the Project extends over a period of 42 years.

The bidder, as a contractor, has successfully completed at least 500 _ projects of like magnitude, comparable difficulty and rates of progress to the work in the past 42 years, including: (list two or more projects).

City of Albany - Sanitary Sewer Rehabilitation Project / Albany, CA Ross Valley Sanitary District - Gravity Sewer Rehabilitation Project / San Rafael. CA SI, 413,126. 64 The City shall have the sole discretion to determine whether listed projects are of like magnitude, comparable difficulty, or rates of progress. Bidders shall provide such additional information regarding the listed projects as the City may request.

The bidder, as a contractor, has never failed to satisfactorily complete a contract except as follows: (name any and all exceptions and reasons therefore.

N/A
The bidder has satisfactorily completed the following contracts in the last three years, for the ersons, firm or authority indicated, and to whom reference is made (list five contracts). (Provid contact person and telephone number for each project.)

CONTRACT YEAR TYPE OF WORK AMOUNT CONTACT
Central Contra Costa Sanitary Distret
son Fitch. Project Manage
2021-2022 Sewer S4,894,583.00 25) 229-711
Town of Tiburon
David Eshoo. Project Engineer
2021-2022 Undergrounding S5,071,299.02 (416) 435-7354
19 | Pagc

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 City of Sunnyvale
2022 Water $6,091,315.00 Steve Sun, Construction Engineer (408) 345-3775
City of Palo Aito
Water S7.722,613.02 Nanette O'Brien. Contrict Admmistrator 2022-2023 (650) 838-2716
SEMTA
2019-2023 Sewer, Water, Streetscape Cathal Hennesy, PM
$28.530.468.00 1415) 701-4548
Contractor's License Number: 417996
License Renewal Business name of bidder: Ranger Pipelines Incorporated 20 Page

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044

SCHEDULE OF BID PRICES
Bid Bid Item Est. Unit Unit Bid Amount
Item Quan. Price
No.
1 Mobilization/Demobilization LS 50,0000* 50,000.00
Pedestrian Control, Traffic Control, and LS
2 Notifications 40,000.0 40,000.0
3 Sheeting, Shoring, and Bracing 1 LS 40,000.00 40.000.° 4 Temporary Bypass Pumping and Piping 1 LS 40,0000 40,00.00 5 Water Pollution Control Plan (WPCP) LS 6,000.-
1 6,000.°*
6 8-inch Pipe Burst 16,084 42.- 2,283,928.0
12-Inch Pipe Burst LF 300° 447, 3000-
1,491
8 16-Inch Pipe Burst LF 3200° 140,480.
439
9 8-Inch Open Trench Replace 235 LF 5000° 117,500.°
10 12-Inch Open Trench Replace 5500° 60,500°
110 LF
Replace Lateral Connection 390 EA 3,000." 1,170,000.0
12 6-Inch Sewer Abandonment 155 LF 15.00 2,325.°°
13 Modify Manhole for Pipe Bursting 74 EA 1,000.0 74,000.° 14 Remove & Replace Lamphole 12 EA 2,000.0 24,000.%
Remove Manhole Ladder Rungs (per 124 EA
15 40° 4,960.°
rung)
16 Rehabilitate Manhole 66 EA 3,000.- 198,000.0
17 Reset Manhole Frame 1 EA 1,500.00 7,500.00
18 Remove & Replace Manhole 5 EA 4,000 ° 45,000.°
New Manhole 1 EA 7,000.- 9. 000.00
20 Street Monument Replacement 13 EA 500.00 6,500.0
Additional Open Cut in Pipe Bursting 300 LF
21 150.0 45,0000
Locations (Revocable)
Additional AC Pavement Replacement 2,000 SF
22 (Revocable) 000 20,0000
23 Bursting Head Recovery (Revocable) 1,000.0 3,000.°
3 EA
24 City Pavement Cut Fee (Allowance) AL $580,000 $580,000 1 TOTAL BASE BID (Bid Items 1 thru 24) 5,408, 993.°
21| Page
BID ADDENDUM 2 6 of 8

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 Bid Bid Item Est. Unit Unit Bid Amount
Item Quan. Price
No.

ADDITIVE BID ITEM #1
A1-1 Mobilization/Demobilization, Traffic 1
Control, Shoring. Bypass, and WPCP LS 3,000." 33,000.°
A1-2 8-inch Pipe Burst 3,313 LF 1420 470,4460°
A1-3 8-Inch Open Trench Replace 137 LF 500.° 68,500.0
A14 Replace Lateral Connection 96 EA 3,000." 288,000.00 A1-5 Modify Manhole for Pipe Bursting 13 EA 1,000.° 13,000." A1-6 Remove & Replace Lamphole 4 EA 2,000.0 3,000.°
A1-7 Remove Manhole Ladder Rungs (per 44
rung) EA 400° 1, 760.°
A1-8 Manhole Rehabilitation 12 EA 3,000.* 36,000.0
A1-9 Street Monument Replacement 2 EA 500.0 1000.00
A1-10 New Manhole 1 EA 9,0000 9,000.0
A1-11 City Pavement Cut Fee (Allowance) AL $90,000 $90,000 TOTAL ADDITIVE BID ITEM #1 (Bid Items A l-1 thru A1-11) 1,018,706.00 ADDITIVE BID ITEM #2
A2-1 Mobilization/Demobilization, Traffic 1
Control, Shoring, Bypass, and WPCP LS 57,000.- 67,000." A2-2 8-inch Pipe Burst 7,048 LF 142. 1,0006.

A2-3 Replace Lateral Connection 179 EA 3,000.%
A2-4 Modify Manhole for Pipe Bursting 15 EA 1,000.° 15,000.00 A2-5 Remove & Replace Lamphole 2 EA 2,000.00 4,000.0
A2-6 Remove & Replace Manhole 16 EA 9,000. 0° 144,000.0 A2-7 Street Monument Replacement 5 EA 500.°° 2,500.0
A2-8 City Pavement Cut Fee (Allowance) 1 AL $280,000 $280,000 TOTAL ADDITIVE BID ITEM #2 (Bid Items A2-1 thru A2-8) 2,050,3/6.° PRIVATE LATERAL REPLACEMENT BID ITEMS (Separate Contract) B-1 Private Lateral Replacement, Pipe 40 EA 4,000°0 160,000.° BurstingR
B-1A Private Lateral Replacement, Open 10 EA 5,000.0
Trench 50,000.0
B-2 Private Lateral - Additional Length, Pipe 280 LF 20000 Bursting 56,0000
B-2A Private Lateral - Additional Length, Open 70 LF
Trench 3000° 21,000.°
B-3 Private Lateral - Additional Cleanout 5 EA 1,20000 6,000.° B-4 Private Lateral - Tree Protection 30 EA 50.° 1,500.00 B-5 Private Lateral - Permit and Inspection 50 EA $1,250 $62,500 Fees (Reimbursement)
22| Page
BID ADDENDUM 2 7 of 8

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project CO44 Bid Item Bid Item Est. Unit Unit Bid Amount
No. Quan. Price
B-6 Private Lateral - Additive Item for 30.0
21,000.°°
Concrete Surface
TOTAL BID PRICE (Total Base Bid + Additive Bid Item #1 + Additive Bid Item #2 + Lateral Replacement Bid Items) 8,856,015.00 TOTAL BID PRICE: Items 1 through 24, Al-I thorough A1-11, A2-1 through A2-8, and B-1 through B-6, inclusive, and all work incidental thereto and connected herewith: (In Words)

EIGHT MINION EIGHT AUNORED FRTY-SIX THOUSAND FIFTEEN
23 Page
BID ADDENDUM 2 8 of 8

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044

EVALUATION OF BIDS AND AWARD OF CONTRACT
This Contract includes descriptions of bid items for Lateral Replacement of private homeowner laterals to be performed under separate contracts) with home owners. Lateral Replacement bid item prices are included within the TOTAL BID PRICE. The lowest responsive, responsible bidder will be selected based on the lowest TOTAL BID PRICE. The awarded value of the Contract will be the TOTAL BASE BID plus any ADDITIVE BID ITEMS the City decides to include in the Contract after receiving Bids.

Private property Lateral Replacement work is independent of this Contract. Lateral Replacement Bid Item unit prices will be used to reimburse the Contractor for private property owner latera replacement performed under separate contract(s) with homeowners as described by Bid Items B-1 through B-5.

The Contractor shall be obligated to use the Lateral Replacement Bid Item unit prices for performance of the Lateral Replacement Bid Items under separate contracts) with private homeowners.

In the event of a conflict between the TOTAL BID PRICE stated in figures and the TOTAL BID PRICE stated in words, the words shall gover. In the event of a conflict between the Item prices and the TOTAL BID PRICE, the TOTAL BID PRICE shall govern.

If the proposal is made by a corporation, the proposal shall show the name of the corporation and dentify the state in which the corporation is incorporated, the post office address of th orporation, and the signature of at least two officers authorized to sign on behalf of th corporation. Additionally, the proposal shall include a document empowering the signator(s) to execute the proposal and bind the corporation.

BID AMOUNT OF EACH OF THE ABOVE BID ITEMS MUST BE FILLED IN AND

COMPLETED IN INK
• If corporation, two officer's signatures are required.

Company Name (printed):_ Ranger Pipelines Incorporated
The total amount bid includes the summation of Bid Items 1 through 24, plus Additive Bid Item #1, plus Additive Bid Item #2, and Private Lateral Replacement. The Contract amount is th Base Bid (Bid Items #1 though #24) with the City's option to include or not include Additive Bic Item #1 and/or Additive Bid Item #2. The Contract amount represents the total price bid to provide the work as shown in the C pntract Docaments
/ homes
Name: Thomas Hunt Thomas Grover
Title: President VP - Estimating
23 | Page

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project C044 Bidder acknowledges receipt of Addendum:

Addendum Number Received
-
•
THE BIDDER MUST ACKNOWLEDGE RECEIPT OF ALL ADDENDA. Not checking the box for all issued addenda will disqualify the bid.

The undersigned agrees, if awarded the Contract, that said Bidder and all of said Bidder's shall be available for review at City's principal office.

The Project is a public work. Therefore, the prime contractor and all subcontractors for the Project must be registered with the California Department of Industrial Relations pursuant to the provisions of Labor Code Section 1725.5 in order to be qualified to bid on, be listed in a bid proposal, or engage in the performance of any work under the Contract for the Project. A bid shall not be accepted nor any contract or subcontract be entered into without proof of the contractor or subcontractor's current registrations to perform public work pursuant to Labor Code Section 1725.5. The undersigned Bidder hereby certifies that she/he/it, and all subcontractors listed in the Proposed Subcontractors form included with this proposal form are registered pursuant to that Section. The undersigned Bidder hereby further certifies that his/her/its Department of Industrial Relations registration number is listed below.

Pursuant to Labor Code Section 1771.4, the Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. The prime contractor shall post jobsite notices as prescribed by regulation and the prime contractor and each subcontractor shall furnish the records specified in Labor Code Section 1776 directly to the Labor Commissioner as specified in said Section 1771.4. Pursuant to Labor Code Section 1773.3, the City shall provide notice to the Department of Industrial Relations of the award of the contract for the Project within five days of the award.
24| Page

CONTRACT FOR PROPOSAL
Project Title: Lower Linda Mar Rehabilitation and Repair Project CO44 This sheet must accompany bid.

Thom that
Signature Thomas Grover Signature Thomas Hunt
VP - Estimating President
Title Title
April 24, 2024 April 24, 2024
Date Date
1000003604