July 29, 2024 City of Pacifica 1
environmental science associates
Proposal
City of Pacifica Coastal Hazard Mapping Updates
Per the City of Pacifica’s (City) request, ESA
developed this scope and fee to update the City’s
coastal hazard maps as part of its current Local
Coastal/Land Use Plan (LCLUP) update process.

Project Understanding
As part of the City’s current efforts in the LCLUP
process, we understand that the City wants to
update the coastal flood, erosion, and tsunami
hazard maps for existing and future conditions with
sea level rise using the best available science and
information. ESA developed coastal hazards maps
as part of the City’s Local Coastal Program (LCP)
update in 2018. ESA developed the maps in
compliance with the Ocean Protection Council’s
(OPC) 2018 State of California Sea Level Rise
Guidance, which was the best available science at
the time that the work was completed, as well as
the best available existing modeling and mapping,
including USGS CoSMoS flooding and wave hazards
maps, Pacific Institute erosion hazards, and
additional refined calculations of erosion hazards.

Since publication of the 2018 hazard maps, the
State updated the sea level rise guidance, and the
CoSMoS hazard maps were updated by the USGS to
include coastal erosion hazards and refined coastal
flood hazards. In general, the current CoSMoS flood
hazard maps show less flooding than the maps that
were available at the time of the 2018 mapping
effort. ESA has also refined the methods and
equations of our in-house erosion hazard model to
estimate bluff erosion hazards, which generally
show less erosion than earlier generations of the
ESA model used in the 2018 mapping. Based on our
review of the CoSMoS erosion hazards maps along
the City’s shore, additional refinement of the
erosion hazard mapping is warranted to inform
planning decisions.

We also understand that the City would like to show
maps depicting tsunami hazards for a range of risk
levels. Recent advances in tsunami modeling were
used by the State to develop the California Tsunami
Hazard Maps, which are intended for emergency
and evacuation planning. This scenario uses a very
extreme tsunami event with a very low likelihood.

However, additional data sets from the State’s
study are available that show inundation associated
with more likely events that align with expectations
for community planning (i.e., lower return period).

The proposed scope of work below is limited to
updating the City’s sea level rise and tsunami
hazard exposure maps and does not include an
updated vulnerability assessment.

Scope of Services
We have presented a scope of work to update
hazard maps and support the City with a series of
base and optional tasks. We aligned the base scope
of work to target the available budget of $50,000
PREPARED FOR:

CITY OF PACIFICA
JULY 29, 2024
ESA CONTACT: LOUIS WHITE, PE, (415) 262-2351, [email protected] City of Pacifica Coastal Hazard Mapping Updates
2 esassoc.com
and identified optional tasks that could be funded
subsequently when additional resources are
available. ESA welcomes discussion of the scope to
refine the work to best meet the needs of the City.

Task 1 Project Initiation
ESA will meet with the City to initiate the project
and conduct review of background materials to
inform the following analyses/tasks. Outcomes of
this task will be documented in Task 3 Reporting.

This task includes the following:
• Review of background material (City
vulnerability assessment, LCP update, etc.)
• Project kickoff meeting
• Establishing project goals and objectives
• Review and summarize updated sea level rise
guidance and implications for Pacifica
Task 2 Coastal Hazards
ESA will collect and summarize existing data
regarding sea level rise and coastal hazards in order
to update the City’s coastal hazard maps.
• Coastal Hazard Mapping – latest available
coastal flooding and erosion maps from USGS
CoSMoS for existing conditions and two future
sea level rise scenarios (e.g. 2050 and 2100).
• Groundwater mapping – New state guidance
recommends consideration of groundwater
levels with sea level rise, especially for low lying
areas. USGS CoSMoS groundwater maps are
available for the same sea level rise scenarios
listed above.
• Wave Hazards – We will develop a general
description of wave hazards through the
project site that can be quantified under
Optional Task 6.
• Tsunami Mapping – The California Tsunami
Hazard Maps prepared for emergency planning
include less extreme scenarios of tsunami
hazards, which may be better suited for
informing coastal planning.

ESA will develop new coastal hazard maps for the
City that incorporate the newly compiled hazard
maps listed above. Following the LCP Update map
format, each map set will consist of a series of five
individual maps that depict the various sub-areas in
the City. ESA will also compile tsunami mapping
data for a range of tsunami likelihood/intensity. We
will provide a summary in Task 3 Reporting that
describes the data and provides background
information on tsunami preparedness guidance.

Hazard maps will be developed to show the
following coastal hazards:
• Coastal Flooding and Erosion – one set for
existing conditions and each future sea level
rise amount (three sets total)
• Groundwater – one set for existing conditions,
one set for 2100 (there are limited changes
shown in the intermediate SLR scenarios)
• Tsunami – one set for existing conditions.

Task 2 Deliverables
• Draft and final coastal hazard maps based on
one set of consolidated City comments.

Task 3 Reporting
ESA will document the technical tasks and hazard
mapping updates in a brief technical report. The
technical report will include summary of sea level
rise guidance update, hazard data sources, the
updated sea level rise hazard maps, and describe
technical methods for tsunami analysis.

Task 3 Deliverables
• Draft and final report based on one set of
consolidated City comments.

Task 4 Project Management
ESA will provide project coordination to support the
technical tasks and overall progress of work,
including project meetings. This task includes the
following:
• Project management (budget and schedule
tracking, invoicing, staffing etc.)
• Regular check-ins with City staff
City of Pacifica Coastal Hazard Mapping Updates
July 29, 2024 City of Pacifica 3
environmental science associates
Optional Tasks
Optional Task 5 Agency and
City Meetings
With additional budget, ESA can support the City by
preparing for and attending the following meetings
as needed/requested:
• CA Coastal Commission meetings
• City Council meetings
Optional Task 6 Update Wave
Run-up Hazard Zones
As part of the hazard mapping updates, we
recommend computing wave hazard zones for
existing and future conditions with sea level rise
(e.g., FEMA high velocity flood zones). Wave run-up
hazard data are needed to supplement the available
USGS CoSMoS coastal flood mapping. ESA will
apply total water level data from USGS and
methods ESA developed for the Technical Methods
Manual to model and map future wave hazards.

Optional Task 7 Update Erosion
Hazard Zones
ESA recommends developing updated erosion
hazard zones and maps to support City planning.

We will apply its updated methodology for
projecting coastal bluff erosion that utilizes recent
total water level data and improves upon the
methods used to develop Pacific Institute mapping
used for the City’s LCP Update.

Optional Task 8 Update
Webmaps
If desired, ESA will update the City’s existing sea
level rise hazard map web viewers with new hazard
maps developed for this study. ESA can add/replace
the updated hazard mapping to each of the two
web viewers we prepared for the City LCP Update:
• Asset Data and Hazard Zone GIS-webviewer
• Multi-Scenario Hazard GIS-webviewer
Budget
Table 1 provides estimated budget for each of the
base and optional tasks described above. As it is
difficult to estimate the level of effort required for
this scope, we recommend compensation on a time
and materials basis, not to exceed the total
estimated budget of $50,000 without prior
authorization. Please note that actual distribution
of charges may differ from Table 1. ESA will invoice
monthly for actual time and materials according to
our standard rate schedule in effect at the time the
work is performed. We have attached a provisional
rate schedule for work that we anticipate will be
performed in 2024 (Exhibit B).

TABLE 1. ESTIMATED BUDGET BY TASK
Task Description Estimated
Budget
1 Project Initiation $8,000
2 Coastal Hazards $27,000
3 Reporting $10,000
4 Project Management $5,000
Total Base Tasks $50,000
OPT 6 Agency & City Meetings $8,000
OPT 7 Update Wave Run-up $20,000
OPT 8 Update Erosion $20,000
OPT 9 Update Webmaps $4,000
Total Base+Optional Tasks $102,000
Schedule
A preliminary schedule is presented in the attached
Table 2. Please note that significant delays in the
project schedule could affect our ability to perform
the work within the budget presented herein.

TABLE 2. PRELIMINARY SCHEDULE
Task Description Duration,
weeks
Completion,
weeks from
Start
1 Project Initiation 2 2
2 Coastal Hazards 8 10
3 Reporting 4 12
4 Project Mgt. 12 12
1 EXHIBIT B
Environmental Science Associates &
Subsidiaries: 2024 Schedule of Fees
I. Personnel Category Rates
Charges will be made at the Category hourly rates set forth below for time spent on project management, consultation or meetings related to the project, field work, report preparation and review, travel time, etc. Time spent on projects in litigation, in depositions and providing expert testimony will be charged at the Category rate times 1.5.

LABOR CATEGORY BILLING
STEP I

BILLING

STEP II

BILLING

STEP III

BILLING

STEP IV

BILLING
STEP V

BILLING

STEP VI
Senior Principal
Consultant
$255 $282 $311 $341 $371 $401
Principal Consultant $210 $238 $265 $293 $321 $349
Managing Consultant $189 $211 $234 $256 $278 $300
Senior Consultant $155 $171 $192 $212 $233 $253
Associate Consultant $137 $151 $164 $177 $190 $203
Consultant $104 $117 $129 $143 $156 $169
Project Technician $75 $97 $119 $142 $164 $186
(a) The range of rates shown for each staff category reflects ESA staff qualifications, expertise and experience levels. These rate ranges allow our project managers to assemble the best project teams to meet the unique project requirements and client expectations for each opportunity.
(b) From time to time, ESA retains outside professional and technical labor on a temporary basis to meet peak workload demands. Such contract labor may be charged at regular Employee Category rates.
(c) ESA reserves the right to revise the Personnel Category Rates periodically to reflect changes in its operating costs.

II. ESA Expenses
A. Travel Expenses

1. Transportation
a. Company vehicle – fixed rate + fee for mileage in excess of 100 miles. b. Common carrier or car rental – actual expense multiplied by 1.15 c. If company vehicle is to be used in off-road conditions, a daily $15 use fee will be added to the standard daily vehicle rate.

2. Lodging, meals and related travel expenses – direct expenses multiplied by 1.15 ESA 2024 Schedule of Fees
2 B. Technology and Data Management Fee
Non-travel expenses incurred for the duration of the agreement for project support but not itemized below. Project labor charges multiplied by 3%. Fee encompasses the following:

1. Ongoing long-term retention and retrieval, management, and security of project-related data.

2. Proprietary tools, cloud data services, data science and AI capabilities as required for project delivery.

C. Cloud-based Services

ITEM RATE/HOUR RATE/DAY RATE/WEEK RATE/MONTH
Cloud-based Services
Nearmap High Resolution Images $55/image
ArcGIS Online Hosting (Web Maps/Apps) $225
Website Hosting $200
Custom Application & Services Hosting* $300*
Modeling (GeoHECRAS, TUFLOW, Delft3D) + Drone
Processing
$7 $160 $950 $3,900
Aviation Environmental Design Tool (AEDT)
Processing
$13 $190 $1,120 $4,600
*includes support for database, SSL, IT support – costs vary by project. Contact software development services for firm pricing.

D. Printing/Reproduction Rates
If a weekly or monthly rate is not provided, equipment usage is billed at a daily rate.

ITEM RATE/PAGE SAMPLE PRICING
Black & White – 8.5 x 11 $0.15
Black & White – 11 x 17 $0.30
Color – 8.5 x 11 $0.50
Color – 11 x 17 $0.80
B&W – Plotter (Toner – ECO Quality) $0.50/sf 24x36 B/W CAD drawing would cost $3 per sheet
B&W – Plotter (Toner – Presentation
Quality)
$1.25/sf 24x36 B/W CAD drawing would
cost $7.50 per sheet
Color – Plotter (Inkjet – ECO Quality) $2.50/sf 24x36 Color Drawing would cost $15 per sheet
Color – Plotter (Inkjet – Presentation
Quality)
$5.00/sf 24x36 Color Drawing would cost
$30 per sheet
CD $10.00
Digital Photography $20.00 (up to 50 images)
All Other Items
(including bindings and covers)
At cost plus 10%
ESA 2024 Schedule of Fees
3 E. Equipment Rates

ITEM RATE/DAY RATE/WEEK RATE/MONTH
Project Specific Equipment:

Vehicles – Standard size (no off-road usage) $ 100a $ 500a Vehicles – 4x4 /Truck (light duty) 150a
Vehicles – 4x4 /Truck (heavy duty) 175a
Vehicles – ATV 150
Noise Meter 115
Hydroacoustic Noise Monitoring Equipment 175
Satellite Phone 15 70 250
Electrofisher 350 1,750
Field Traps 50
Digital Hypsometer (Nikon) 25
Backpack Sprayer 30
360-Degree 4k Camera 35 175
High Resolution Time-Lapse Camera 20 100 350
Beach Seine 60
Otter Trawl 115
Wildlife Acoustics Bat Detector 125 400
Wildlife Trail Camera 30 100
Fiber Optic Endoscope 150 750
Spotting Scope 50 200
Personal Protective Equipment (PPE) 25
Topographic/Bathymetric Survey Equipment:

Total Station 300
UAV/Drone 300 1,500
RTK-GPS 300
RTK-GPS Smartnet Subscription 75
Hypack Survey Software 150
Laser/Auto Level 50
Single-Beam Echoshounder 150 600
Sidescan Sonar 200
1m GNSS Data Collection System 85 425 1,700
Sub-meter GNSS Data Collection System 115
Sub-foot Data Collection System 230
Garmin GPS or equivalent 30
Hydrologic Data Collection, Water Current, Level and Wave Measurement Equipment:

ISCO 2150 Area Velocity Flow Logger $ 50 $ 300 $ 800
SonTek IQ-Plus Area Velocity Flow Logger 100 500 1,500
Logging Rain Gage 10 50 200
Hand-Held Current Meter 50
Surface Velocity Radar 50
Wave Pressure Sensor 115 460
Wave Buoy 175 700
Sonic Wave Sensor 35 175 500
Logging Water Level - Pressure Transducer 125
Logging Barometric Pressure Logger 60
Well Probe / Water Level Meter 25
Bottom-Mounted Tripod / Mooring 30 150 400
Stormwater Crest Sampler 20
Radar Wave Sensor with Logger Box 150 300 1000
Water Quality Equipment:

Logging Turbidimeter/Water Level Recorder $ $ $ 400
Logging Conductivity/Water Level Recorder 250
Recording Conductivity Meter w/Datalogger 20 60 200
Hand-Held Turbidimeter 50 200
Hand-Held Salinity Meter or pH meter 35
Logging Salinity Gauge 150
Logging DO/Temp Probe 150
ESA 2024 Schedule of Fees
4 ITEM RATE/DAY RATE/WEEK RATE/MONTH
Logging Water Quality Sonde 1 Sensor 50 200 700
Logging Water Quality Sonde 2 Sensor 65 250 800
Logging Water Quality Sonde 3 Sensor 75 300 900
Logging Water Quality Sonde 4 Sensor 90 350 1,000
Telemetry System Hardware 125
Water Quality Multi-Probe Depth Profiler 200
Niskin Water Sampler 50
ISCO 6712 Portable Sampler w/ISCO 2105 Module 60 350 900 Sedimentation / Geotechnical Equipment:

Peat Corer $ 85
60lb Helly-Smith Bedload Sampler 200
Mini-Ponar Grab Sampler 50
DH-76 Suspended Sediment Sampler 100
D-96 Suspended Sediment Sampler 200
Bridge Crane 150
RSET 50
AMS Soil Sampling Kit 50
Hand-Held Helley-Smith Bedload Sampler 30
Guelph Permeameter 60
Sludge Sampler 60
Shear Strength Vane 60
Handheld DH-48 Suspended Sediment Sampler 30
Boats:

Small Watercraft $ 50 $ 200
15’-17’ Boat 350 1,200
20’-21’ Boat 400 1,800
22’-25’ Boat 500 2,000
Houseboat Floating Laboratory 4,500
a Actual project charges will include the daily rate plus $0.75 per beyond 100 miles III. Subcontracts
Subcontract services will be invoiced at cost multiplied by 1.15.

IV. Other
The fees above do not include sales tax. Any applicable or potential sales tax will be charged when appropriate.

V. Payment Terms
Unless otherwise agreed in writing, ESA will submit invoices on a monthly basis. Any unpaid balances shall draw interest at one and one half percent (1.5%) per month or the highest rate allowed by law, whichever is lower, commencing thirty (30) days after date of invoice. All invoices not contested in writing within fifteen (15) business days of receipt are deemed accepted by Client as true and accurate and Client thereafter waives any objection to Clients invoices, which are payable in full.