agenda-report Approval of Construction Services Agreement for Traffic Signal and Street Light Services between the City of Pacifica and St. Francis Electric, LLC.

Pacifica City Council
October 14, 2024

Document
agenda-report Approval of Construction Services Agreement for Traffic Signal and Street Light Services between the City of Pacifica and St. Francis Electric, LLC.
Meeting
October 14, 2024
Body
Pacifica City Council
Original file
102 KB
Text extracted from the city's file for reading and search. Open the original on pacificacityca.iqm2.com. That file is the official record.

CITY OF PACIFICA

COUNCIL AGENDA SUMMARY REPORT
10/14/2024
1 SUBJECT:

Approval of Construction Services Agreement for Traffic Signal and Street Light Services between the City of Pacifica and St. Francis Electric, LLC.

RECOMMENDED ACTION:

Adopt a Resolution Authorizing a Construction Services Agreement for Traffic Signal and Street Light Services between the City of Pacifica and St. Francis Electric, LLC in the amount of $52,355.00 annually ($209,420.00 for four (4) years) from Gas Tax Maintenance Fund, Fund 10; Establish a budget authority of $57,590.50, which includes a 10% contingency; and Authorize the City Manager to execute all necessary documents.

STAFF CONTACT:

Michael Pham, Parks and Facilities Superintendent
(650) 501-0305
[email protected]
Gino Assereto, Field Services Manager
(650) 438-2980
[email protected]
BACKGROUND/DISCUSSION:

The City of Pacifica requires the services of an electrical contracting firm which specializes in providing traffic signal and street light services, emergency repair, non-emergency routine preventative maintenance of traffic signal lights as well as scheduled repairs; new equipment upgrade and installation work; Underground Service Alert markings; and ad hoc electrical work billed on a time and materials basis. The City has five (5) traffic signalized intersections and two thousand seventeen (2017) streetlights.

On April 3, 2024, the Request for Proposal was issued and published on OpenGov Procurement. Proposals were received on May 2, 2024 and the results are as follows:

Bear Electric Solutions Inc.

Description Annual Cost
Traffic Signal Monthly Maintenance & Inspection $6,750.00 Estimated Streetlight Maintenance Cost $40,500.00
TOTAL ANNUAL MAINTENANCE $ 47,250.00
Pacifica City Council 2
October 14, 2024
St. Francis Electric, LLC
Description Annual Cost
Traffic Signal Maintenance & Inspection $7,355.00
Estimated Streetlight Maintenance Cost $45,000.00
TOTAL ANNUAL MAINTENANCE $52,355.00
Staff members from the Engineering and Field Services Divisions reviewed the two (2) proposals received based on Administrative Policy No. 76 and on the following criteria:

A. Responsiveness of the proposal related to the scope of work.

B. Proposer’s written understanding of the proposed scope of work.

C. Ability, capacity, and skill of firm to perform the services on a qualified and timely basis.

D. Responses of the firm’s references.

E. Experience, expertise, and qualifications of the firm and firm’s team members assigned to the Project;
F. Such other information that may be required or secured.

Both proposers submitted all required documentation, and Staff reviewed both proposals based on Administrative Policy No. 76 and by applying the criteria described above. Based on such review and grading, staff recommends St. Francis Electric, LLC. (St. Francis Electric) to perform the City’s traffic signal and street light maintenance work. Among other factors considered and weighed during the review process, staff considered the City’s experience with St. Francis Electric, who has performed as the service provider for the street signals and lights for the City of Pacifica for the past 3 years. Staff also checked St. Francis Electric’s references and they were all positive. Therefore, City Manager recommends approval of the Construction Services Agreement (Attachment 1) between the City of Pacifica and St. Francis Electric.

ALTERNATIVE ACTION:

The Council may choose not to approve the construction agreement. However, this will result in traffic signal maintenance delays and may cause traffic interruptions at those intersections and long-term outages of streetlights. Staff does not recommend this alternate action.

RELATION TO CITY COUNCIL GOALS AND WORK PLAN:

Approval of the Construction Services Agreement is consistent with the following Council adopted Goals:
• Stewardship of City Infrastructure: includes repairing/replacing outdated city facilities such as city hall, the fire stations, etc., improving streets, and responding to impacts of sea level rise. Approving the construction services agreement will help maintain the City’s existing traffic signals and streetlights.

Pacifica City Council 3
October 14, 2024
FISCAL IMPACT:

Traffic Signal Maintenance & Inspection $7,355.00
Estimated Streetlight Maintenance Cost $45,000.00
TOTAL ANNUAL MAINTENANCE $52,355.00
Total fiscal impact will be $52,355.00 annually ($209,420.00 for four (4) years). Funds are budgeted in the current and future fiscal years to cover this amount. Staff recommends adding a contingency of 10% for any unforeseen conditions that may occur due to storms or accidents.

This would establish a budget authority of $57,590.50 per year for this project.

ORIGINATED BY:

Public Works
ATTACHMENT LIST:

Attachment 1-St. Francis Contract (PDF)
Pacifica City Council 4
October 14, 2024
RESOLUTION NO. ___-2024

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PACIFICA APPROVING THE

CONSTRUCTION SERVICES AGREEMENT FOR TRAFFIC SIGNALS AND STREET

LIGHT SERVICES BETWEEN THE CITY OF PACIFICA AND ST FRANCIS ELECTRIC, LLC IN THE AMOUNT OF $52,355.00 ANNUALY ($209,420.00 FOR FOUR (4) YEARS) FROM THE GAS TAX MAINTENANCE FUND, FUND 10: ESTABLISH A BUDGET AUTHORITY OF $57,590.50, WHICH INCLUDES A 10% CONTINGENCY: AND

AUTHORIZE THE CITY MANGER TO EXECUTE ALL NECESSARY DOCUMENTS WHEREAS, staff reviewed proposals based on Administrative Policy No. 76 and by applying the criteria described above. Based on such review and grading, staff recommends St. Francis Electric, LLC. (St. Francis Electric) to perform the City’s traffic signal and street light maintenance work. Among other factors considered and weighed during the review process, Staff considered the City’s experience with St. Francis Electric, who has performed as the service provider for the street signals and lights for the City of Pacifica for the past 3 years. Staff also checked St. Francis Electric’s references and they were all positive. Therefore, City Manager recommends approval of the Construction Services Agreement between the City of Pacifica and St. Francis Electric.

THEREFORE, BE IT RESOLVED by the City Council of the City of Pacifica to authorize a Construction Services Agreement for Traffic Signal and Street Light Services between the City of Pacifica and St. Francis Electric, LLC in the amount of $52,355.00 annually ($209,420.00 for four (4) years) from Gas Tax Maintenance Fund, Fund 10. • • • • •
PASSED AND ADOPTED at a special and regular meeting of the City Council of the City of Pacifica, California, held on the 14th day of October, 2024, by the following vote:

AYES, Councilmembers:

NOES, Councilmembers:

ABSENT, Councilmembers:

ABSTAIN, Councilmembers:
_________________________________
Sue Vaterlaus, Mayor
ATTEST: APPROVED AS TO FORM:
______________________________ _________________________________ Sarah Coffey, City Clerk Michelle Kenyon, City Attorney