CITY OF PACIFICA

COUNCIL AGENDA SUMMARY REPORT
11/12/2024
1 SUBJECT:

Continuation of Proclamation of Local Emergency at the Anza Pump Station.

RECOMMENDED ACTION:

Accept Report and Make a Determination that Conditions of Local Emergency Continue to Exist at the Anza Pump Station at the Pacifica State Beach.

STAFF CONTACT:

John Mullin, Interim Director of Public Works
(650) 738-3767
[email protected]
Louis Sun, P.E., Deputy Director of Public Works - Wastewater (650) 738-4660
[email protected]
BACKGROUND/DISCUSSION:

On Monday, March 16, 2020, the Department of Public Works received a report regarding a fire at the Anza Pump Station at Pacifica State Beach. After Public Works staff investigated the report, it was determined that the storm drain pumping system and roof/bathrooms were damaged during the fire. The engines were destroyed, and the pumps needed to be replaced.

The damage to the pump station threatened and continues to threaten the safety of persons and properties within the watershed due to the risk of flooding without an operational pump station.

The City of Pacifica’s Emergency Plan and Section 4-2.01 et seq. of the Pacifica Municipal Code empower the City Manager, acting as the Director of Emergency Services, to proclaim the existence of a local emergency when there is an actual or threatened existence of conditions of disaster or of extreme peril to the safety of persons and properties within this City.

The proclamation is subject to ratification by the City Council within 7 days, pursuant to the Pacifica Municipal Code. The proclamation of the existence of a local emergency further designates the City Manager or designated representative to act on behalf of the City for public assistance and for individual assistance for purpose of receipt, processing and coordination of all inquiries and requirements necessary to obtain available State and Federal assistance.

Additionally, pursuant to Section 3-15.09 (A) of the Pacifica Municipal Code, in cases of an emergency the City Manager is authorized to proceed at once to replace or repair any public facility without adopting plans, specifications, or working details, or giving notice for bids to let contracts. The City must comply with Public Contract Code Section 22050, which provides a process for City Council’s review of the emergency action if notice of bids to let contracts for public projects will not be given because of the emergency.

In this case, the City Manager has determined that the damaged pump station threatens the health and safety of persons and properties, including critical public infrastructure, which Pacifica City Council 2
November 12, 2024
requires immediate attention and constitutes an emergency pursuant to Pacifica Municipal Code section 4-2.02 and Public Contract Code Section 1102.

Such conditions are, or are likely to be, beyond the handling capability of the City’s services, personnel, equipment, and facilities, requiring the use of outside contractors to conduct emergency design and repair pursuant to Pacifica Municipal Code section 3-15.09 without giving notice for bids to let contracts. Immediate action is, and continues to be necessary, due to the clear and imminent danger presented by any storm event that could occur during the time the storm water pump station is non-functional. Flooding could occur to areas upstream of the pump station, causing health and safety issues, as well as extensive property damage. As such, on April 8, 2020, the City Manager did proclaim the existence of a local emergency within the City and the need to continue the emergency action continues as the repair will take approximately 8-14 months or longer. The Proclamation of Local Emergency is attached to this staff report as Attachment 1.

City staff contracted with the civil engineering firm of Schaaf & Wheeler of San Jose, California to assist the City with the rehabilitation of the pump station. On July 13, 2020, the City Council approved construction services agreement for rebuild and re-installation of a pump and gear drive, the renovation of bathrooms, purchase and installation of new stainless-steel doors, and repair pump station wet-well grates. As part of the on-going maintenance for the pump station, staff purchased a new pump which was approved by the Council at the August 9, 2020, City Council meeting. An emergency purchase agreement with Herc Rental for a temporary rental engine was also approved on September 1, 2020, and will remain in place until the pump station is operational. On October 12, 2020, temporary measures were completed to allow for a nonstandard system of pumping at the Anza Pump Station until final repairs are completed. This work included a new pump, transfer switch, temporary roof, portable generator connections, and exterior double doors have been installed. Staff is continuing to evaluate and monitor storm water flows and purchased two new sump pumps to accommodate flows.

On May 10, 2021, City Council approved the purchase of two new Caterpillar engines utilizing the City’s established Sourcewell Cooperative Purchase Agreement. The rehabilitation plan is currently 100% completed, and staff has completed the engineering review. The roofing plan was approved by the Building Department. The City entered into an agreement with PG&E to tap the gas main and install a new gas meter.

During a storm event on the morning of December 16, 2021, the City experienced some flooding in the lower Linda Mar area due to the temporary nonstandard pumping system that has been in use at Anza pump station due to the fire damaged pump station engines in March of 2020. This temporary system has been in place because the City had been working to reach agreement with the California Coastal Commission on the remaining permitting requirements for the permanent pumping system. The City faced several significant stormwater related events from October 2021 through December 2021 and will face more with the continuing storm season. Replacement of this temporary system is considered an emergency and staff is moving forward with construction of the permanent system. To further improve operations between now and when the Anza Pump Station Repair Project is completed, the City recently purchased a small diesel engine that will be used to drive one of the existing smaller stormwater pumps, thereby improving pump station resiliency in the interim.

The City Council approved an agreement for DW Nicholson (DWN) to construct the Anza Pump Station Repair Project. Construction began on May 1, 2022. Ghirardelli and Associates were also approved to manage the construction work. The two new gas engines were delivered and installed in December 2022; the third new gas engine was installed in June 2023 and the new 2- inch PG&E gas service line for the new gas engines was completed on May 2, 2023; All Anza Pump Station bathrooms were opened by August 25, 2023. Pump #3 was installed in early Pacifica City Council 3
November 12, 2024
January 2024. Startup and testing of the new Engine#1, Engine#3, and Engine#4 have been completed. Engine#1 and Engine#4 are now in service and operating with automation capabilities. The closure of the roof is now completed. Contractor continues to correct the sump pump which is on order. The replacement sump pump is expected to arrive and installed by the end of this year. The project will reach substantial completion when the sump pump is completed. Staff plans to bring a final project close out change order and terminate the local emergency to the November 25, 2024 City Council meeting.

Pursuant to Government Code Section 8630(c), the City Council must review the need for continuing the local emergency at least every 60 days until the City Council terminates the local emergency. Conditions of local emergency still exist since the City Council first acted to declare a local emergency on April 13, 2020, and since that time staff has brought the continuance of Proclamation confirming the existence of local emergency at the Anza Pump Station every 30 days with October 14, 2024, being the most recent.

The City is using a combination of city staff, consultants, and contractors to manage the emergency work related to the Anza Pump Station repair project. The City Manager recommends that the City Council make a determination that conditions of local emergency continue to exist at the Anza Pump Station at the Pacifica State Beach. Staff will continue to update the Council on the progress of this emergency work monthly through the emergency declaration Council reports.

FISCAL IMPACT:

There is no fiscal impact to continue this local emergency.

ORIGINATED BY:

Public Works - Wastewater Division
ATTACHMENT LIST:

Attachment 1 - Resolution No. 19-2020 Ratifying Proclamation of Local Emergency at the Anza Pump Station (PDF)