Path of Portola 1769 • San Francisco Bay Discovery Site 4936-1109-8373 v3
City of Pacifica
170 Santa Maria Avenue
Pacifica, CA 94044
City of Pacifica
Annual and Five-Year Impact
Fee Report
For the Fiscal Year Ending June 30, 2024
Path of Portola 1769 • San Francisco Bay Discovery Site 4936-1109-8373 v3
Table of Contents
LETTER OF TRANSMITTAL ………........................................................................................................I CITY COUNCIL AND ELECTED OFFICIALS ......................................................................................... II INTRODUCTION............................................................................................................................................ 1 LEGAL REQUIREMENTS FOR DEVELOPMENT IMPACT FEE REPORTING.............................................. 1 ANNUAL REPORT - CALIFORNIA GOVERNMENT CODE SECTION 66006(b) ........................................... 1 FIVE-YEAR REPORT - CALIFORNIA GOVERNMENT CODE SECTION 66001(d)....................................... 2

DESCRIPTION OF DEVELOPMENT IMPACT FEES, IDENTIFICATION OF PURPOSE OF FEES, AND REASONABLE RELATIONSHIP BETWEEN FEE AND THE PURPOSE FOR WHICH IT IS CHARGED ...... 4 CURRENT IMPACT FEE SCHEDULES......................................................................................................... 8 DEVELOPMENT IMPACT FEE REPORT..................................................................................................... 13 STATEMENT OF REVENUES, EXPENDITURES AND CHANGES IN FUND BALANCE............................ 13 HIGHWAY 1 IMPROVEMENTS ................................................................................................................... 14 STREET IMPROVEMENT FEE.................................................................................................................... 15 MANOR DRIVE/PALMETTO AVENUE/OCEANA BOULEVARD INTERSECTIONS.................................... 17

PLANNED DRAINAGE FACILITIES FEES AND RESERVE FOR DRAINAGE FACILITY CONSTRUCTION FUNDS ........................................................................................................................................................ 18 CAPITAL PROJECTS FUNDS..................................................................................................................... 19 HOUSING IN-LIEU FEE............................................................................................................................... 20 IN-LIEU PARKING FACILITIES FEE............................................................................................................ 21 PARK FACILITIES IMPACT FEE................................................................................................................. 22 TREE IN-LIEU FEE...................................................................................................................................... 23 SEWER CONNECTION CHARGES............................................................................................................. 24 2023/2024 Annual and Five-Year Impact Fee Report i
4936-1109-8373 v3
January 13, 2025
The Honorable Mayor, Members of the City Council and Citizens of Pacifica Dear Mayor, Members of the City Council and Citizens of Pacifica:

State law requires any local agency that imposes development impact fees to prepare an annual report providing specific information about those fees. Therefore, in accordance with the provisions of the California Government Code Sections 66006(b), 66001(d), and 66013(d), I hereby submit the Annual Report of Development Impact Fees (“Report”) for the City of Pacifica, California for the fiscal year (FY) ended June 30, 2024.

Development impact fees are charged by local governmental agencies in connection with approval of development projects. The purpose of these fees is to defray all or a portion of the cost of public facilities related to the development project. The legal requirements for enactment of a development impact fee program are set forth in Government Code §§ 66000‐66025 (the "Mitigation Fee Act"), the bulk of which was adopted as 1987’s AB 1600 and thus commonly referred to as “AB 1600 requirements”.

In Pacifica, fees are used to finance the acquisition, construction and improvement of public facilities needed as a result of this new development.

State law requires the City prepare and make available to the public the Report within 180 days of each fiscal year. The City Council must review the Report at a regularly scheduled public meeting not less than fifteen days after the information is made available to the public. A draft of this Report was filed with the City Clerk’s office and available for public review on December 18, 2024.

Respectfully submitted,
Yulia Carter
Assistant City Manager/Director of Finance

CITY OF PACIFICA
170 Santa Maria Avenue • Pacifica, California 94044-2506 www.cityofpacifica.org
MAYOR
Sue Beckmeyer

MAYOR PRO TEM
Mary Bier

COUNCIL
Christine Boles
Mayra Espinosa
Scenic Pacifica Greg Wright
Incorporated Nov. 22, 1957
2023/2024 Annual and Five-Year Impact Fee Report ii
4936-1109-8373 v3

CITY OF PACIFICA, CALIFORNIA

SUE BECKMEYER
Mayor

MARY BIER
Mayor Pro Tem

CHRISTINE BOLES

MAYRA ESPINOSA

GREG WRIGHT
Members of City Council

KEVIN WOODHOUSE
City Manager

MICHELLE MARCHETTA KENYON
City Attorney

OTHER ADMINISTRATIVE OFFICERS

YULIA CARTER

SAMANTHA UPDEGRAVE
Assistant City Manager/Director of Finance
Director of Community Development
MARIA SARASUA Police Chief
RON MYERS Fire Chief
JOHN MULLINS Interim Director of Public Works
SCOTT LESLIE Director of Parks, Beaches & Recreation
SARAH COFFEY City Clerk

OFFICIAL COMMISSIONS AND COMMITTEES

BEAUTIFICATION ADVISORY COMMITTEE

ECONOMIC DEVELOPMENT COMMITTEE

EMERGENCY PREPAREDNESS & SAFETY COMMISSION

OPEN SPACE AND PARKLAND ADVISORY COMMITTEE

PARKS, BEACHES AND RECREATION COMMISSION

PLANNING COMMISSION
2023/2024 Annual and Five-Year Impact Fee Report 1
4936-1109-8373 v3

INTRODUCTION

LEGAL REQUIREMENTS FOR DEVELOPMENT IMPACT FEE REPORTING In California, State legislation sets certain legal and procedural parameters for the charging of development impact fees. This legislation was passed as AB1600 by the California Legislature and is now codified as California Government Code Sections 66000 through 66008 (“Mitigation Fee Act”). This State law went into effect on January 1, 1989.

The Mitigation Fee Act imposes certain accounting and reporting requirements with respect to the fees collected.

The fees must be deposited in a special account to avoid commingling the fees with the City’s other revenues or funds. Interest on each development fee fund or account must be credited to that fund or account and used only for those purposes for which the fees were collected.

The Mitigation Fee Act also requires any local agency that imposes development impact fees to prepare a report containing annual findings, five-year findings, and capacity fee findings that provide specific information about those fees. This report serves both of those functions and has been prepared for the City of Pacifica for the fiscal year (FY) ended June 30, 2024 in accordance with the provisions of the California Government Code Sections 66006 (b), 66001 (d), and 66013 (d).

ANNUAL FINDINGS - CALIFORNIA GOVERNMENT CODE SECTION 66006(b) Pursuant to Government Code 66000 et seq. and specifically Government Code section 66006(b), the City is required to prepare annual findings regarding any fee imposed to provide for an improvement to be constructed to serve a development project, or which is a fee for public improvements within the meaning of subdivision (b) of Section 66000, and that is imposed by the local agency as a condition of approving the development project.

California Government Code Section 66006(b) requires local agencies that impose AB 1600 development impact fees on new development to make publicly available the information shown below for the most recent fiscal year. • A brief description of the type of fee in the account or fund (pages 4 to 7). • The amount of the fee (pages 8 to 12).
• The beginning and ending balance of the account or fund (pages 14 to 23). • The amount of the fees collected, and interest earned (pages 14 to 23). • An identification of each public improvement on which fees were expended and the amount of expenditures on each improvement, including the total percentage of the cost of the public improvement that was funded with fees (pages 14 to 23).
• An identification of an approximate date by which the construction of the public improvement will commence if the local agency determines that sufficient funds have been collected to complete financing on an incomplete public improvement and an identification of each public improvement identified in a previous report and whether construction began on the approximate date noted in the previous report (pages 14 to 23).
• A description of each interfund transfer or loan made from the account or fund, including the public improvement on which the transferred or loaned fees will be expended, and, in the case of an interfund loan, the date on which the loan will be repaid and the rate of interest that the account or fund will receive on the loan (page 2).
2023/2024 Annual and Five-Year Impact Fee Report 2
4936-1109-8373 v3
• The amount of refunds made due to sufficient funds being collected to complete financing on incomplete public improvements, and the amount of reallocation of funds made due to administrative costs of refunding unexpended revenues exceeding the amount to be refunded (page 2).

City Actions Regarding this Section:
• For the 2023-2024 fiscal year, the City did not provide any refunds of development fees. • For the 2023-2024 fiscal year, the City did not transfer or loan any development fees. • For the 2023-2024 fiscal year, the City reviewed the Annual Findings, and there are no actions to report.

FIVE-YEAR FINDINGS - CALIFORNIA GOVERNMENT CODE SECTION 66001(d) For all funds established for the collection and expenditure of development impact fees, California Government Code Section 66001(d) has additional requirements. For the fifth fiscal year following the first deposit into the fund and every five years thereafter, the local agency shall make all of the following findings with respect to that portion of the fund remaining unexpended, whether committed or uncommitted:
• Identify the purpose to which the fee is to be put (pages 4 to 7). • Demonstrate a reasonable relationship between the fee and purpose for which it is charged (pages 4 to 7).
• Identify all sources and amounts of funding anticipated to complete financing in incomplete improvements (pages 14 to 23).
• Designate the approximate dates on which the funding is expected to be deposited into the appropriate account or fund (pages 14 to 23).

City Actions Regarding this Section:
• For the 2023-2024 fiscal year, the City reviewed the 5-Year Findings, and there are no actions to report.

CAPACITY FEE FINDINGS – CALIFORNIA GOVERNMENT CODE SECTION California Government Code Section 66013 (d) requires that for each capacity fee fund or account established, the local agency shall make available to the public the following information for the fiscal year within 180 days after the last day of each fiscal year:
• A description of the fee (page 7).
• The beginning (July 1) and ending (June 30) balances of each fund for which, the fees were collected. • The amount of fee collected (pages 24-25).
• An identification of each public improvement on which fees were expended and the amounts expensed on each such improvement including the total percentage of the cost of the public improvement that was funded with the fees (pages 24-25).
• Each public improvement, either wholly or partially funded by fees, that was completed this past fiscal year (pages 24-25).
• Future public improvements funded, either wholly or partially, by fees (pages 24-25). 2023/2024 Annual and Five-Year Impact Fee Report 3
4936-1109-8373 v3
• Description of each interfund transfer or loan. The description of the interfund transfer shall identify the projects the transferred money is for. The description of the interfund loan shall include the date the loan will be repaid and the interest rate (page 2).

City Actions Regarding this Section:

For the 2023-2024 fiscal year, the City reviewed the Capacity Fee Findings, and there are no actions to report.

State law requires the City to prepare and make available to the public the above information within 180 days after the last day of each fiscal year. The City Council must review the Report at a regularly scheduled public meeting not less than fifteen days after the information is made available to the public. This report was filed with the City Clerk’s office and available for public review on December 18, 2024. 2023/2024 Annual and Five-Year Impact Fee Report 4
4936-1109-8373 v3

DESCRIPTION OF DEVELOPMENT IMPACT FEES, IDENTIFICATION OF PURPOSE OF FEES, AND

REASONABLE RELATIONSHIP BETWEEN FEE AND THE PURPOSE FOR WHICH IT IS CHARGED 66006(b)(1)(A), 66013(d)(1), and 66001(d)(1)(A) and (B) The City has ten (10) development impact fees.

1. Highway 1 Improvement Fund. Fees are imposed on private development projects pursuant to Pacifica Municipal Code (Traffic Impact Mitigation Improvement Fund for Highway One Improvements, Chapter 15, Title 8, as added by Ordinance No. 318-C.S.). The purpose of the Highway 1 impact mitigation fee is to defray the actual or estimated costs of constructing improvements to Highway One in the City from Westport Drive south to the southern City limits, which improvements will be required to accommodate the increased traffic flow in the area resulting from future development in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing traffic and street improvements to serve new development and the fee revenues will be used for the purpose of constructing traffic and street projects that will serve new development.

The fee amount collected is based on the traffic generated by the respective development, measured by the square footage of the new development, and the new development’s proportionate cost to construct the improvements required to serve the traffic generated by the new development. In addition, the traffic impact mitigation fee is imposed in two impacting areas. The primary impacting area is that area lying south of Sharp Park Road. The secondary impact area is that area lying north of Sharp Park Road. The fee is imposed on new residential, commercial, and retail development.

2. Street Improvement Fee. The City of Pacifica is responsible for maintaining over 90 centerline miles of street pavement. The City’s Street maintenance program has been chronically underfunded and as a result the City currently has one of the lowest pavement condition index (PCI) score in the bay area cities and faces a growing deficit in needed pavement maintenance and rehabilitation funding.

Utility Pavement Cut Recovery Fee (PMC Section 7-2.214). The Utility Pavement Cut Recovery Fee is imposed on private development projects pursuant to Pacifica Municipal Code (Utility Pavement Cut Recovery Fee, Section 214, Article 2, Chapter 2, Title 7). Excavations in paved streets owned and maintained by the City degrade and shorten the life of the surface of the streets, and this degradation increases the frequency and cost to the public of necessary resurfacing, maintenance and repair. These excavations cause degradation of the streets even where the excavations are refilled and repaired in conformity with applicable standards and requirements. It is appropriate that entities responsible for excavating into the City right-of-way bear the burden of the resulting cost of this degradation and shortened life of the surface rather than the taxpayers of the City. In addition, establishment of a Utility Pavement Cut Recovery Fee will create an incentive for utilities to coordinate excavations in the streets.

The purpose of this Utility Pavement Cut Recovery impact fee is to defray the actual or estimated cost of restoration and maintenance of City pavement related to the increased use and degradation of paved streets owned by the City resulting from pavement excavations for new development in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing traffic and street projects to serve new development and the fee revenues will be used for the purpose of constructing traffic and street projects that will serve new development.

The fee amount collected is based on the "Council-Approved Rate" contained in the most recently adopted Impact Fee Schedule. The fee is imposed on residential/commercial/retail development. 2023/2024 Annual and Five-Year Impact Fee Report 5
4936-1109-8373 v3
Construction Vehicle Impact Fee (PMC Title 8, Chapter 21). The Construction Vehicle Impact Fee is imposed on private development projects pursuant to Pacifica Municipal Code (Construction Vehicle Impact Fee, Chapter 21, Title 8). The purpose of the Construction Vehicle Impact fee is to defray the actual or estimated cost of restoring City streets to accommodate the increased use and deterioration resulting from heavy construction vehicles associated with future development in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing traffic and street projects to serve new development and the fee revenues will be used for the purpose of constructing traffic and street projects that will serve new development.

The fee amount collected is based on the deterioration of City streets caused by new development’s construction vehicles, measured by the square footage added by the new development, and the new development’s proportionate cost to restore the damaged City streets. The fee is imposed on all developments in the City that require a building permit and add new residential or nonresidential building square footage.

3. Manor Drive Improvement Fund. The Manor Drive/Palmetto Avenue/Oceana Boulevard Intersections Improvement Fees are imposed on private development projects pursuant to Pacifica Municipal Code (Traffic Impact Mitigation Fees for the Improvement of the Subject Intersection, Chapter 18, Title 8, as added by Ordinance No. 422-C.S.). The purpose of establishing traffic impact mitigation fees is to defray the actual costs of constructing improvements to the Manor Drive/Palmetto Avenue/Oceana Boulevard intersection, which improvements will be required to accommodate the increased traffic flow in the area resulting from future building activity in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing traffic and street improvements to serve new development and the fee revenues will be used for the purpose of constructing traffic and street projects that will serve new development.

The fee amount collected is based on the traffic generated by the respective development uses and the estimated cost to construct the required improvements. The traffic impact mitigation fee is imposed on the areas lying north of Paloma Avenue within the Pacifica City limits. The fee is imposed on new residential, commercial, and retail development.

4. Planned Local Drainage Fund. The Planned Drainage Facilities Fee is imposed on private development projects pursuant to Pacifica Municipal Code (Article 1, Chapter 4, Title 7, as added by Ordinance No. 333-C.S.). The purpose of the Local Drainage impact mitigation fee is to defray the actual or estimated cost of constructing planned drainage facilities for the removal of surface and storm drainage waters to accommodate the increased drainage needs resulting from future development in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing planned drainage facilities to serve new development and the fee revenues will be used for the purpose of constructing planned drainage facilities that will serve new development.

The fee amount collected is based on the required storm water drainage improvements generated by the respective development, measured by the location and acreage of the new development, and the new development’s proportionate cost to construct the improvements required to serve the increased use generated by the new development. The fee is imposed on new residential, commercial, and retail development.

5. General Capital Improvement Fund. The Capital Improvements Fees are imposed on private development projects pursuant to Pacifica Municipal Code (Capital Projects Fund, Article 2, Chapter 4, Title 7, as added by Ordinance No. 7-C.S.). The purpose of the General Capital Improvement impact 2023/2024 Annual and Five-Year Impact Fee Report 6
4936-1109-8373 v3
mitigation fee is to defray the actual or estimated cost of constructing new public safety facilities to accommodate the increased service needs resulting from future development in the City. The fee is used to develop capital programs and to provide for the capital outlays necessary to provide added services and facilities as a result of such new construction, and to safeguard life, limb, and the public health and safety. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing new public safety facilities to serve new development and the fee revenues will be used for the purpose of constructing new public safety facilities that will serve new development.

The fee amount collected is based on the estimated cost to construct the required capital improvements for new residential, commercial, and retail development, measured by the number of bedrooms or hotel or motel units or the permit valuation of the new development, and the new development’s proportionate costs to construct the improvements required to serve the increased use generated by the new development. It is to be used for the acquisition, construction, and improvement of major capital facilities of the City.

6. Housing In-Lieu Fee. For any residential development that is not located within the redevelopment project area, the developer may propose to pay the City an amount of money in lieu of providing a Below Market Rate (BMR) unit. The purpose of the Housing In-Lieu fee is to provide funding assistance for the provision of affordable housing in-lieu of the BMR unit required for new development in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of providing funding assistance for affordable housing to serve new development and the fee revenues will be used for the purpose of providing funding assistance for affordable housing that will serve new development.

The in-lieu fee amount collected shall be based on the estimated cost to provide the BMR unit and shall be set forth in a resolution adopted by the City Council. In-lieu payments shall be paid prior to occupancy of the first market rate unit to be developed within the residential development.

7. In-Lieu Parking Facilities Fee. The In-Lieu Parking Facilities Fee is imposed on private development projects in Rockaway Beach and Sharp Park areas. The purpose of the Rockaway Beach and Sharp Park In-Lieu Parking Fee is to provide additional public parking at West Rockaway Beach and West Sharp Park consistent with the goals of the Rockaway Beach and Sharp Park Specific Plan to encourage shared parking facilities and accommodate the increased demand for parking resulting from future development in the Rockaway Beach and Sharp Park areas. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of constructing additional public parking to serve new development and the fee revenues will be used for the purpose of constructing additional public parking that will serve new development.

The fee amount collected is based on the fee update study adopted by City Council Resolution No. 23- 2020 on April 27, 2020, and the approximate cost of constructing a parking space in an above grade parking structure.

8. Parks Facilities Impact Fee. The Park Facilities Impact Fee is imposed on private residential development projects pursuant to Pacifica Municipal Code (Park Facility Impact Fee Chapter 19, Title 8).

The purpose of the Parks Facilities impact fee is to defray the actual or estimated cost of constructing additional parks, recreational facilities, and open spaces to accommodate the increased needs resulting from future development in the City. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of 2023/2024 Annual and Five-Year Impact Fee Report 7
4936-1109-8373 v3
constructing additional parks, recreational facilities, and open spaces to serve new development and the fee revenues will be used for the purpose of constructing additional parks, recreational facilities, and open spaces that will serve new development.

The fee amount collected is based on the increase in use of parks, recreational facilities, and open spaces generated by the respective development, measured by the number of residents due to residential construction, and the new development’s proportionate cost to construct the required recreational facilities and purchase the needed land and open space.

9. Tree In-Lieu Fee. The City established the Tree Fund for the preservation of protected trees on public and private property and to promote the health, safety, and general welfare of the citizens of the City, while recognizing individual rights to develop, maintain, and enjoy private property. (Establishment of Tree Fund, Section 4-12-23, Chapter 12, Title 4). The Tree In-Lieu fee is an agreed upon restoration payment. The purpose of the Tree In-lieu fee is for payment of the full replacement value of a mature tree or trees in lieu thereof if on-site replacement is not feasible. There is a reasonable relationship between the amount of the fee and the purpose for which it is charged because the fee represents the City’s proportionate costs of replacing and restoring trees to serve new development and the fee revenues will be used for the purpose of replacing and restoring trees that will serve new development.

The City shall administer and use the Tree Fund for the following purposes: (1) Purchasing, planting, and maintaining trees within the City; (2) Acquiring, maintaining, and preserving trees within the City to remain in a naturalistic state in perpetuity; (3) Performing and maintaining a City-wide tree inventory; (4) Educating residents and developers on the preservation, care, maintenance, benefits and value of trees within the City of Pacifica; and (5) Supporting programs for the purpose of increasing the tree canopy within the City of Pacifica as approved by the Council.

To mitigate the adverse effects of tree removal, a tree removal permit shall include conditions that require relocation of tree(s) on-site as recommended by a certified arborist, and/or replacement planting of a minimum of two (2) replacement trees for every otherwise healthy tree removed and may be required to pay the replacement value of the mature protected tree minus the cost of the two (2) replacement trees or payment of the full replacement value of a mature tree or trees in lieu thereof if on-site replacement is not feasible. No applicant shall be required to expend more on the replacement trees than the appraised value of the trees for which a permit is required. The Director shall determine the replacement value of the trees utilizing the most recent edition of the Guide for Plant Appraisal by the Council of Tree and Landscape Appraisers.

10. Sewer Facility Construction Fund. The Planned Sanitary Sewer Facilities Fee is imposed on private development projects pursuant to Pacifica Municipal Code (Sewer Connection Charges, Chapter 11, Title 6). The purpose of the Sewer Facility capacity fee is to defray the actual or estimated cost of acquisition, construction, and operation of City sanitation and sewage facilities to accommodate the increased use of the facilities resulting from future development in the City. The sewer connection fees (PMC Section 6-

11.102 and 6-11.103) are designed to offset future costs for the replacement and expansion of the Wastewater Treatment Plant and related sewage collection facilities. The inflow and infiltration charges (PMC Section 6-11.104) reflect the contribution necessary to maintain the existing capacity of the collection system to serve new development by providing facilities to eliminate an equivalent volume of inflow and infiltration as the new flows contribute to the sewage system. The sewer tap fee (PMC Section 6-11.301) applies only if the City performs the tap and it reflects the actual cost of the service.

The fee amount collected is based on the required sanitary sewer improvements which are based on the proposed new projects generated by the respective uses and the estimated cost to construct the required improvements. The fee is imposed on new residential, commercial and retail development. 2023/2024 Annual and Five-Year Impact Fee Report 8
4936-1109-8373 v3

CURRENT IMPACT FEE SCHEDULES
66006(b)(1)(B)
Highway 1 Improvement Impact Fee
Table 1 Current Highway 1 Improvement Impact Fee
(a) Primary Impacting Area (as defined in Municipal Code Section 8-15.03) Fee
(1) Per new residential unit $6,563
(2) Per new second residential unit $3,174
(3) Per new commercial unit (per square foot of gross floor area) $2.64 (b) Secondary Impacting Area (as defined in Municipal Code Section 8-15.03) Fee
(1) Per new residential unit $2,192
(2) Per new second residential unit $1,116
(3) Per new commercial unit (per square foot of gross floor area) $0.84 Street Improvement Fee
Table 2 Current Street Improvement Fee
Utility Pavement Cut Fee
Functional Class Age Group
Cut Area (Percent Section Area)
<10% of Section Area ≥10% of Section Area
Arterials/Collector
s
<10 years $2.50 $4.00
≥10 years $1.50 $2.50
Residential
<10 years $1.50 $3.00
≥10 years $1.00 $2.50
Accessory Dwelling Units (ADU): Utility Pavement Cut Fee shall not be charged for any ADU that is under 750 square feet or an ADU of any size when the ADU is being constructed at the same time, under the same permit, as a new main residential unit or an expansion of the main unit that make payment of the fees as required.

Partial or Full Credit Utility Cut Fees for Developments with Pavement Improvements: A credit my be applied against the Utility Cut Fees for completing frontage roadway paving. 2023/2024 Annual and Five-Year Impact Fee Report 9
4936-1109-8373 v3
Reduced Utility Cut Fees Related to Sewer Lateral Repairs Not Requiring a Lateral Compliance Certificate: A minimal fee of $500 will be charged for pavement cuts fees related to fixing a sewer lateral not requiring a Sewer Lateral Compliance Certificate.

Construction Vehicle Impact Fee
Residential Unit /
Multi-Family Fee
Non-Residential
Unit Fee
Per Square Foot $1.25 / sq. ft. $1.19 / sq. ft.

Accessory Dwelling Units (ADU): Construction Vehicle Impact Fees shall not be charged for any ADU that is under 750 square feet or an ADU of any size when the ADU is being constructed at the same time, under the same permit, as a new main residential unit or an expansion of the main unit that make payment of the fees as required.

Manor Drive Improvement Impact Fee
Table 3 Current Manor Drive Improvement Impact Fee
(a) Primary Impacting Area (as defined in Municipal Code Chapter 18, Title 8) Fee
(1) Per daily trip generated. $479
Planned Local Drainage Impact Fee
Table 4 Current Planned Local Drainage Impact Fee
(a) Area Number (as defined in Municipal Code Section 7-4.101):

Area Number Watershed Title Fee per acre
1 Globe $0
2 Edgemar $7,124
3 Pacific Manor $6,934
4 Salada Beach $6,934
5 Brighton $8,276
6 Fairway Park $15,467
7 Vallemar $10,959
8 Rockaway Beach $20,413
9 Lower Linda Mar $0
10 Linda Mar $7,318
11 San Pedro Terrace $25,900
2023/2024 Annual and Five-Year Impact Fee Report 10
4936-1109-8373 v3
General Capital Improvement Impact Fee
Table 5 Current General Capital Improvement Impact Fee
(a) Primary Impacting Area (as defined in Municipal Code Article 2, Chapter 4, Title 7) Fee
(1) Per bedroom in a dwelling unit $329
(2) Per hotel or motel unit $164
(3) each other new structure (except accessory buildings and buildings or structures primarily used for Boys' or Girls' Clubs, Boy or Girl Scouts, or other nonprofit activities for which the Council may waive the fee). -1.7% of the
valuation
Housing In-Lieu Fee
Table 6 Current Housing In-Lieu Fee
(a) For a BMR Unit affordable to a Lower Income Household (Resolution No. 24-2007) Fee
Rental Unit: $205,416
For Sale Unit:

Detached Single Family: $561,910
Condominium/Townhouse: $356,910
(b) For a BMR Unit affordable to a Moderate Income Household (Resolution No. 24-2007) Fee
Rental Unit: $26,732
For Sale Unit:

Detached Single Family: $465,023
Condominium/Townhouse: $260,023
2023/2024 Annual and Five-Year Impact Fee Report 11
4936-1109-8373 v3
In-Lieu Parking Facilities Fee
Table 7 Current In-Lieu Parking Facilities Fee
On April 27, 2020 City Council approved the increase of the In-Lieu Parking Facilities Fee for the Rockaway Beach Specific Plan Area (a) Primary Impacting Area (as defined in Resolution No. 23-2020) Fee
(1) Fee per in-lieu parking space. $45,628
On May 11, 2020 City Council approved Resolution No. 25-2020 to establish the In-Lieu Parking Facilities Fee for the Sharp Park Specific Plan Area (a) Primary Impacting Area (as defined in Resolution No. 25-2020) Fee
(1) Fee per in-lieu parking space. $45,628
Parks Facilities Impact Fee
Table 8 Current Parks Facilities Impact Fee
(a) Primary Impacting Area (as defined in Municipal Code Chapter 19, Title 8) Park Facilities Impact Fee (Mitigation Fee Act)
Bedrooms Fee
Zero $9,614
One $11,274
Two $17,222
Three $20,888
Four $23,862
Five $27,597
Each after Five $3,735
Tree In-Lieu Fee
Table 9 Current Tree In-Lieu Fee
IN-LIEU TREE FEES (SEC. 4-12.04 (e))
Fee
Per Tree The appraised value of the tree(s) for which a tree removal permit is required.

The Director of the Department of Public Works shall determine the replacement value of the trees utilizing the most recent edition of the Guide for Plant Appraisal by the Council of Tree and Landscape Appraisers.
2023/2024 Annual and Five-Year Impact Fee Report 12
4936-1109-8373 v3
Sewer Facility Construction Impact Fee
Table 10 Current Sewer Facility Construction Impact Fee SEWER CONNECTION CHARGES (SEC. 6-11.102)
Residential or Commercial
Meter Size Cost/Meter size
1" $12,180

1.5" $24,361

2.0" $38,977

3.0" $73,082
4" $121,804
6" $243,607
8" $363,230
Accessory Dwelling Unit "ADU"
Cost per Drainage Fixture Unit "DFU" ** $641
SEWER TAP FEES (SEC. 6-11.301)
Cost per Sewer Tap $539
2023/2024 Annual and Five-Year Impact Fee Report 13
4936-1109-8373 v3

DEVELOPMENT IMPACT FEE REPORT

STATEMENT OF REVENUES, EXPENDITURES AND CHANGES IN FUND BALANCE 2023/2024 Annual and Five-Year Impact Fee Report 14
4936-1109-8373 v3
HIGHWAY 1 IMPROVEMENTS
Table 11 Highway 1 Improvements - Fund 12
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $21,566 $12,540
Interest $4,191 $9,536
Total Revenues $25,757 $22,076
EXPENDITURES [1] % From Fees % From Fees
Capital Improvements $0 0% $0 0%
Fee Administration [2] $20,889 100% $20,953 100%
Total Expenditures $20,889 $20,953

REVENUES OVER (UNDER)
EXPENDITURES $4,868 $1,123
Fund Balance, Beginning of the Year $148,265 $153,133
Fund Balance, End of Year $153,133 $154,256
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] Include staff time to manage Highway 1 projects, collection of fees, participating in the San Mateo County Congestion Management. [3] City is seeking grant funds to complete the project.

Proposed Future Projects Total Cost Impact Fees Grant Funds [3] % From Fees Commencement
Year
Pacifica State Beach Trail Rehabilitation Project $400,000 $200,000 $200,000 50% 2025 2023/2024 Annual and Five-Year Impact Fee Report 15
4936-1109-8373 v3

STREET IMPROVEMENT FEE
Table 12 Street Improvement Fund - Utility Pavement Cut Fee - Fund 13 Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $155,470 $159,158
Interest $4,375 $0
Total Revenues $159,845 $159,158
EXPENDITURES [1] % From Fees % From Fees
5 Year Pavement Resurfacing Plan [2] $0 0% $175,795 100% Total Expenditures $0 $175,795

REVENUES OVER (UNDER)
EXPENDITURES $159,845 ($16,637)
Fund Balance, Beginning of the Year $0 $159,845
Fund Balance, End of Year $159,845 $143,208
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] The 5 Year Pavement Resurfacing Plan was started FY 23-24 and completed in FY 24-25.

Proposed Future Projects Total Cost Impact Fees Gas Tax & Measure W % From Fees Commencement
Year
FY 2024-25 Pavement Resurfacing Project $2,200,000 $200,000 $2,000,000 9% 2025 2023/2024 Annual and Five-Year Impact Fee Report 16
4936-1109-8373 v3
Table 13 Street Improvement Fund - Construction Vehicle Impact Fee - Fund 13 Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $20,449 $2,648
Interest $575 $381
Total Revenues $21,024 $3,029
EXPENDITURES [1] % From Fees % From Fees
Capital Improvements $0 0% $0 0%
Total Expenditures $0 $0

REVENUES OVER (UNDER)
EXPENDITURES $21,024 $3,029
Fund Balance, Beginning of the Year $0 $21,024
Fund Balance, End of Year $21,024 $24,053
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees.

Proposed Future Projects Total Cost Impact Fees Gas Tax & Measure W % From Fees Commencement
Year
FY 2025-26 Pavement Resurfacing Project $2,000,000 $100,000 $1,900,000 5% 2025 2023/2024 Annual and Five-Year Impact Fee Report 17
4936-1109-8373 v3

MANOR DRIVE/PALMETTO AVENUE/OCEANA BOULEVARD INTERSECTIONS Table 14 Manor Drive/Palmetto Avenue/Oceana Boulevard - Fund 14 Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $21,566 $1,030
Interest $0 $0
Total Revenues $21,566 $1,030
EXPENDITURES [1] % From Fees % From Fees
Manor Drive Over-Crossing Improvement Project [2] [4] $635,822 5% $752,201 5% Total Expenditures $635,822 $752,201

REVENUES OVER (UNDER)
EXPENDITURES ($614,256) ($751,171)
Fund Balance, Beginning of the Year ($69,545) ($683,801) Fund Balance, End of Year ($683,801) ($1,434,972)
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] City Council adopted Resolution 82-2021 on 12/13/21 identifying the Manor Drive Over-Crossing Improvement Project to be funded by this fee. City will receive $2,700,000 in grant funds from San Mateo County Transportation Authority Measure W funds. Estimated construction year is 2030.
[3] City is seeking grant funds to complete the project. [4] In Fiscal Year 2023-2024, there were no delays in starting the current phase of the above mentioned projects.

Proposed Future Projects Total Cost [3] Impact Fees Grant Funds % From Fees Commencement Year
Manor Drive Over-Crossing Improvement
Project $17,000,000 $900,000 $16,100,000 5% On-going
2023/2024 Annual and Five-Year Impact Fee Report 18
4936-1109-8373 v3

PLANNED DRAINAGE FACILITIES FEES AND RESERVE FOR DRAINAGE FACILITY CONSTRUCTION FUNDS Table 15 Planned Drainage Facilities Fees/Reserve For Drainage Facility - Fund 19 Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $2,217 $0
Interest $2,456 $5,259
Total Revenues $4,673 $5,259
EXPENDITURES [1] % From Fees % From Fees
Storm Drainage Master Plan $0 0% $0 0%
Serra Outfall Project $0 0% $2,369 100%
Total Expenditures $0 $2,369

REVENUES OVER (UNDER)
EXPENDITURES $4,673 $2,890
Fund Balance, Beginning of the Year $85,070 $89,743
Fund Balance, End of Year $89,743 $92,633
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] City is seeking grant funds to complete the project. [3] The Serra Outfall Project was completed in FY 21-22. The ongoing project cost is for Environmental Inspections and Regional Water Board Permit Fees.

Proposed Future Projects Total Cost [2] Impact Fees Grant Funds % From Fees Commencement Year
Clarendon Road Drainage Improvements $1,240,000 $140,000 $1,100,000 11% 2028 2023/2024 Annual and Five-Year Impact Fee Report 19
4936-1109-8373 v3

CAPITAL PROJECTS FUNDS
Table 16 Capital Projects Fund - Fund 22
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $16,701 $12,105
Interest
Total Revenues $16,701 $12,105
EXPENDITURES [1] % From Fees % From Fees
Engineering Services $0 0% $0 0%
Work Order System $0 0% $0 0%
Various Bldg Repairs $0 0% $0 0%
PD Parking Light and Pathway $0 0% $0 0%
PW Office and Facility Assessment $0 0% $0 0%
Cubicles Community Center $0 0% $0 0%
Civic Center Conceptual Design $0 0% $0 0%
Total Expenditures $0 $0

REVENUES OVER (UNDER)
EXPENDITURES $16,701 [2] $12,105 [2]
Fund Balance, Beginning of the Year ($170,479) ($153,778) Fund Balance, End of Year ($153,778) ($141,673)
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers or refunds from funds that utilize development fees. [2] The $16,701 and $12,105 balance was used to repay the loan to complete the Cubicles Community Center project. Of all loan payments this FY, 100% was from this impact fee. The loan will be repaid by 2024 and with 0% interest rate on the loan.

Proposed Future Projects Total Cost Impact Fees Grant Funds % From Fees Commencement Year
None
2023/2024 Annual and Five-Year Impact Fee Report 20
4936-1109-8373 v3

HOUSING IN-LIEU FEE
Table 17 Housing In-Lieu Fee - Fund 24
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $0 $0
Interest $0 $0
Total Revenues $0 $0
EXPENDITURES [1] % From Fees % From Fees
Capital Improvements $0 0% $0 0%
Total Expenditures $0 $0

REVENUES OVER (UNDER)
EXPENDITURES $0 $0
Fund Balance, Beginning of the Year $0 $0
Fund Balance, End of Year $0 $0
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees.
[2] Housing In-Lieu Fee did not fund wholly or in part any projects this past FY. [3] In Fiscal Year 2023-2024, there were no delays in starting construction for the above mentioned projects.

Proposed Future Projects Total Cost Impact Fees Gas Tax & Measure W % From Fees Commencement
Year
None
2023/2024 Annual and Five-Year Impact Fee Report 21
4936-1109-8373 v3

IN-LIEU PARKING FACILITIES FEE
Table 18 In-Lieu Parking Facilities Fee - Fund 25
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $0 $0
Interest $3,268 $10,314
Total Revenues $3,268 $10,314
EXPENDITURES [1] % From Fees % From Fees
Capital Improvements $0 0% $0 0%
Total Expenditures $0 $0

REVENUES OVER (UNDER)
EXPENDITURES $3,268 $10,314
Fund Balance, Beginning of the Year $171,335 $174,603
Fund Balance, End of Year $174,603 $184,917
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] In-Lieu Parking Facilities Fee did not fund wholly or in part any projects this past FY. [3] In Fiscal Year 2023-2024, there were no delays in starting construction for the above mentioned projects.

Proposed Future Projects Total Cost Impact Fees Grant Funds % From Fees Commencement Year
Rockaway Beach Parking Structure $10,155,000 $10,155,000 $0 100% 2030 2023/2024 Annual and Five-Year Impact Fee Report 22
4936-1109-8373 v3

PARK FACILITIES IMPACT FEE
Table 19 Park Facilities Impact Fee - Fund 26
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $92,237 $142,833
Interest
Total Revenues $92,237 $142,833
EXPENDITURES [1] % From Fees % From Fees
Park Project FY21-22 [3] $0 0% $127,794 100%
Total Expenditures $0 $127,794

REVENUES OVER (UNDER)
EXPENDITURES $92,237 $15,039
Fund Balance, Beginning of the Year $197,643 $289,880
Fund Balance, End of Year $289,880 $304,919
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] City Council adopted a Resolution on 12/9/19 identifying the Playground Equipment Improvement Project for the unexpended fees. [3] The Park Project FY21-22 is on-going.
[4] In Fiscal Year 2023-2024, there were no delays in starting construction for the above mentioned projects.

Proposed Future Projects Total Cost Impact Fees Roy Davies Funds % From Fees Commencement
Year
Playground Equipment Improvement
(formerly Parks & Recreation Projects) [2] $2,430,000 $305,000 $2,125,000 13% On-going 2023/2024 Annual and Five-Year Impact Fee Report 23
4936-1109-8373 v3

TREE IN-LIEU FEE
Table 20 Tree In-Lieu Fee - Fund 29
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $0 $0
Interest $1,700 $0
Total Revenues $1,700 $0
EXPENDITURES [1] [2] % From Fees % From Fees
Tree Consultant Contractual Services $0 0% $0 0%
Total Expenditures $0 $0

REVENUES OVER (UNDER)
EXPENDITURES $1,700 $0
Fund Balance, Beginning of the Year $0 $1,700
Fund Balance, End of Year $1,700 $1,700
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers, loans or refunds from funds that utilize development fees. [2] Tree In-Lieu Fees did not fund wholly or in part any completed projects this past FY.

Proposed Future Projects Total Cost Impact Fees General Fund % From Fees Commencement Year
City of Pacifica Arbor Day Trees $2,000 $1,700 $300 85% 2025 2023/2024 Annual and Five-Year Impact Fee Report 24
4936-1109-8373 v3

SEWER CONNECTION CHARGES
Table 21 Sewer Connection Charges - Fund 34
Statement of Revenues, Expenditures and Changes in Fund Balance Ending June 30, 2024
Description FY 2022/23 FY 2023/24

REVENUES
Fees $63,282 $56,965
Interest $0 $475
Total Revenues $63,282 $57,440
EXPENDITURES [1] [3] % From Fees % From Fees
Pump Replacements $0 0% $0 0%
Scada & PLC System $0 0% $0 0%
WWTP Rate Study $0 0% $0 0%
Linda Mar Pump Station $0 0% $0 10%
Collection System $0 0% $0 0%
Rockaway Pump Station $0 0% $0 0%
Sewer System Master Plan $0 0% $0 0%
Sharp Park Pump Station $0 0% $0 0%
Equalization Basin Project $0 0% $0 0%
Lateral Grant Program $0 0% $0 0%
Sharp Park Bar Screen $0 0% $0 0%
Linda Mar Bar Screen $0 0% $0 0%
Linda Mar Jockey Pump $0 0% $0 10%
Pump Station Scada $0 0% $0 0%
Linda Mar Stormwater Pump $0 0% $0 0%
Digesters $0 0% $0 0%
San Pedro Creek TMDL $0 0% $0 0%
CCWRP Storage & Office $0 0% $0 0%
CCWRP Arc Flash $0 0% $0 0%
CCWRP Projects $0 0% $0 0%
CCWRP Ultra-Violet Disinfiction $0 0% $0 0%
CCWRP Photovoltaics Improvement $0 0% $0 0%
CCWRP Condition Assesment $0 0% $0 0%
CCWRP Environmental Compliance $0 0% $0 0%
CCWRP Repair & Replace $0 0% $0 0%
CCWRP Grit System $0 0% $0 0%
CCWRP Sand Filter $0 0% $0 0%
Anza Pump Station Repair $0 0% $0 10%
Total Expenditures $0 $0
2023/2024 Annual and Five-Year Impact Fee Report 25
4936-1109-8373 v3

REVENUES OVER (UNDER)
EXPENDITURES $63,282 $57,440 [2]
Fund Balance, Beginning of the Year ($569,319) ($506,037) Fund Balance, End of Year ($506,037) ($448,597)
[1] For the 2023-2024 fiscal year the City did not provide any interfund transfers or refunds from funds that utilize development fees. [2] The $57,440 balance was used to repay the loan to complete the Collection System Project. Of all loan payments this FY, 100% was from this impact fee. The loan will be repaid by 2024 and with 0% interest rate on the loan. [3] Sewer Connection Fees did not fund wholly or in part any completed projects this past FY.

Proposed Future Projects Total Cost Impact Fees Grant Funds % From Fees Commencement Year
None