Rev. 0
July 2024
Agreement 00 5200 - 1 Pacifica _____ Project
DOCUMENT 00 5200
AGREEMENT
THIS AGREEMENT, dated this [23] day of [March], 2026, by and between [Zara Construction, Inc.] whose place of business is located at [2343 Donner Pass Avenue, Sacramento, CA 95835] (Contractor), and CITY OF PACIFICA, a political subdivision of the State of California (Owner), acting under and by virtue of the authority vested in Owner by the laws of the State of California.
WHEREAS, Owner, by its Resolution No. [Insert Number] adopted on the [23] day of [March, 2026] awarded to Contractor the following Contract:
PACIFICA FY 2026-27 CONCRETE IMPROVEMENT PROJECT
at Various Streets within the Fairmont & Edgemar Neighborhoods NOW, THEREFORE, in consideration of the mutual covenants hereinafter set forth, Contractor and Owner agree as follows:
ARTICLE 1 SCOPE OF WORK OF THE CONTRACT
1.01 Work of the Contract
A. Contractor shall complete all Work specified in the Contract Documents, in accordance with the Specifications, Drawings, and all other terms and conditions of the Contract Documents (Work).
1.02 Price for Completion of the Work
A. Owner shall pay Contractor the following Contract Sum ($379,939.00) for completion of Work in accordance with Contract Documents as set forth in Contractor’s Bid, attached hereto.
B. The Contract Sum includes all allowances (if any).
C. The Contract Sum is all inclusive and includes all Work; all federal, state, and local taxes on materials and equipment, and labor furnished by Contractor, its subcontractors, subconsultants, architects, engineers, and" vendors or otherwise arising out of Contractor's performance of the Work, including any increases in any such taxes during the term of this Agreement; and any duties, fees, and royalties imposed with respect to any materials and equipment, labor or services. The taxes covered hereby include (but are not limited' to) occupational, sales, use, excise, unemployment, FICA, and income taxes, customs, duties, and any and all other taxes on any item or service that is part of the Work, whether such taxes are normally included in the price of such item or service or are normally stated separately. Notwithstanding the foregoing, each party shall bear such state or local inventory, real property, personal property or fixtures taxes as may be properly assessed against it by applicable taxing authorities.
COMMENCEMENT AND COMPLETION OF WORK
1.03 Commencement of Work
A. Contractor shall commence Work on the date established in the Notice to Proceed (Commencement Date).
B. Owner reserves the right to modify or alter the Commencement Date.
1.04 Completion of Work
Rev. 0
July 2024
Agreement 00 5200 - 2 Pacifica _____ Project
A. Contractor shall achieve Substantial Completion of the entire Work within 50 Days from the Commencement Date.
B. Contractor shall achieve Final Completion of the entire Work within 50 Days from the Commencement Date.
ARTICLE 2 PROJECT REPRESENTATIVES
2.01 Owner’s Project Manager
A. Owner has designated Rey Soriano, Assistant Engineer as its Project Manager to act as Owner’s Representative in all matters relating to the Contract Documents. If Project Manager is an employee of Owner, Project Manager is the beneficiary of all Contractor obligations to Owner including, without limitation, all releases and indemnities.
B. Project Manager shall have final authority over all matters pertaining to the Contract Documents and shall have sole authority to modify the Contract Documents on behalf of Owner, to accept work, and to make decisions or actions binding on Owner, and shall have sole signature authority on behalf of Owner.
C. Owner may assign all or part of the Project Manager’s rights, responsibilities and duties to a Construction Manager, or other Owner Representative.
2.02 Contractor’s Project Manager and Other Key Personnel A. Contractor has designated Gustavo Alvarez as its Project Manager to act as Contractor’s Representative in all matters relating to the Contract Documents.
B. Contractor has designated the following other Key Personnel for the Project:
Name Position
ARTICLE 3 LIQUIDATED DAMAGES FOR DELAY IN COMPLETION OF WORK
3.01 Liquidated Damage Amounts
A. As liquidated damages for delay Contractor shall pay Owner Three Thousand Six Hundred dollars ($3,600.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.
3.02 Scope of Liquidated Damages
A. Measures of liquidated damages shall apply cumulatively.
B. Limitations and stipulations regarding liquidated damages are set forth in Document 00 7200 (General Conditions).
ARTICLE 4 LIQUIDATED DAMAGES FOR UNAUTHORIZED CHANGES OF KEY PERSONNEL
4.01 Liquidated Damage Amounts
A. See Document 00 7200 (General Conditions) Paragraph 11.07.D for liquidated damages provisions pertaining to Key Personnel.
ARTICLE 5 CONTRACT DOCUMENTS
5.01 Contract Documents consist of the following documents, including all changes, Addenda, and Modifications thereto:
Document 00 1116 Notice Inviting Bids
Document 00 2100 Access, Indemnity and Release Agreement Document 00 2113 Instruction to Bidders
Rev. 0
July 2024
Agreement 00 5200 - 3 Pacifica _____ Project
Document 00 3132 Geotechnical Data and Existing Conditions Document 00 4113 Bid Form
Document 00 5100 Notice of Award
Document 00 5200 Agreement
Document 00 5500 Notice to Proceed
Document 00 6113.13 Construction Performance Bond
Document 00 6113.16 Construction Labor and Material Payment Bond Document 00 6290 Escrow Agreement for Security Deposits Document 00 6325 Substitution Request Form
Document 00 6530 Release of Claims
Document 00 6536 Guaranty
Document 00 7200 General Conditions
Document 00 7301 Supplemental General Conditions
Document 00 7316 Supplemental Conditions – Insurance and Indemnification
Document 00 7320 COVID Requirements
Document 00 7324 In-Use Off-Road Diesel-Fueled Fleets Regulation Document 00 7380 Apprenticeship Program
Document 01 0000 General Requirements
Attachment A FY26-27 Pacifica Concrete Improvements Project V2 Attachment B Technical Specifications 26-27 Concrete Improvements Attachment C CIP FY 26-27 Arborist Report
5.02 There are no Contract Documents other than those listed above. The Contract Documents may only be amended, modified or supplemented as provided in Document 00 7200 (General Conditions).
ARTICLE 6 MISCELLANEOUS
6.01 Terms and abbreviations used in this Agreement are defined in Document 00 7200 (General Conditions) and Section 01 4200 (References and Definitions) and will have the meaning indicated therein.
6.02 Contractor and Owner understand and agree that in no instance are the persons signing this Agreement for or on behalf of Owner or acting as an employee, agent, or representative of Owner, liable on this Agreement or any of the Contract Documents, or upon any warranty of authority, or otherwise. Contractor and Owner further understand and agree that liability of Owner is limited and confined to such liability as authorized or imposed by the Contract Documents or applicable law.
6.03 Pursuant to Labor Code Section 1771(a), Contractor represents that it and all of its Subcontractors are currently registered and qualified to perform public work pursuant to Labor Code Section 1725.5. Contractor covenants that any additional or substitute Subcontractors will be similarly registered and qualified.
6.04 In entering into a public works contract or a subcontract to supply goods, services or materials pursuant to a public works contract, Contractor or Subcontractor offers and agrees to assign to the awarding body all rights, title and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. § 15) or under the Cartwright Act (Chapter 2 (commencing with § 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time Owner tenders final payment to Contractor, without further acknowledgment by the parties.
6.05 Copies of the general prevailing rates of per diem wages for each craft, classification, or type of worker needed to execute the Contract, as determined by Director of the State of California Department of Industrial Relations, are on file at the Owner’s Engineering Division may be obtained from the California Department of Industrial Relations website [http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm] and are deemed included in the Rev. 0
July 2024
Agreement 00 5200 - 4 Pacifica _____ Project
Contract Documents, and shall be made available to any interested party on request. Pursuant to Labor Code Sections 1860 and 1861, in accordance with Labor Code Section 3700, every contractor will be required to secure the payment of compensation to Contractor’s employees.
Contractor represents that it is aware of the provisions of Labor Code Section 3700 that require every employer to be insured against liability for workers’ compensation or to undertake selfinsurance in accordance with the provisions of that Code, and Contractor shall comply with such provisions before commencing the performance of the Work of the Contract Documents.
6.06 This Agreement and the Contract Documents shall be deemed to have been entered into in the City of Pacifica, State of California, and governed in all respects by California law (excluding choice of law rules). The exclusive venue for all disputes or litigation hereunder shall be in the Superior Court for the County of San Mateo, California.
IN WITNESS WHEREOF the parties have executed this Agreement in quadruplicate the day and year first above written.
CITY OF PACIFICA:
By: ______________________________
Interim City Manager, Yulia Carter
CONTRACTOR:
Name: Zara Construction, Inc.
By: ______________________________
(Signature)
Its: President, Atif Zack Zahoor
Title (If Corporation: Chairman, President
or Vice President)
ATTEST:
By: ______________________________
City Clerk, Sarah Coffey
1099 INFORMATION:
Contractor Taxpayer I.D. No.: ________________
APPROVED AS TO FORM:
By: ____________________________
City Attorney, Michelle Marchetta Kenyon
[CITY TO CONFIRM PROPER SIGNATORIES]