Attachment B
CITY OF PALM SPRINGS
FINAL BALANCING CONTRACT CHANGE ORDER NO. 2
CP 25-01, 2025 Pavement Rehabilitation
Contractor: Matich Corporation Date: January 28, 2026
CONTRACT CHANGE ORDER SUMMARY
This lump sum final balancing Change Order No. 2 is to address quantity changes throughout the project.
CONTRACT CHANGE ORDER COST
ID Description Qty Unit Cost
01 Line items not fully used for project 1 LS -$221,573.97 Total Change Order Amount: -$221,573.97
CHANGES TO CONTRACT TIME
No additional working days will be added to the Contract. Due to a temporary suspension of work associated with the procurement of long-lead materials for the new pedestrian crossing systems, the remaining work is anticipated to be completed within one (1) working day following receipt of the final materials.
Summary of Costs
Original Contract Amount: $7,198,990.00 Construction Start Date: 05/06/2025 Previous Change Orders: $1,251,010.00 Previous Agreed Completion Date: 10/03/2025 This Change Order Amount: -$221,573.97 Working Days Added: 0 Revised Contract Amount: $ 8,228,426.03 Revised Completion Date: 12/19/2025
I have received a copy of this Change Order, and the above AGREED PRICES are acceptable to Contractor.
Matich Corporation
Brett Simon, Project Manager Date
City of Palm Springs
Recommended By:
Joel Montalvo, City Engineer Date
Approved By:
Scott Stiles, City Manager Date
Attest By:
Brenda Pree, City Clerk Date