Attachment B
CITY OF PALM SPRINGS
FINAL BALANCING CONTRACT CHANGE ORDER NO. 1
CP 25-02, 2025 SLURRY SEAL
Contractor: American Asphalt South, Inc. Date: Aprill 22, 2026
CONTRACT CHANGE ORDER SUMMARY
This lump sum final balancing Change Order No. 1 is to address quantity changes throughout the project.
CONTRACT CHANGE ORDER COST
ID Description Qty Unit Cost
01 Field Allowance 1 LS -$250,000.00
02 Caltrans Double Permit 1 LS -$3,500.00
03 Crack Sealing and Crack Filling 1 LS -$1,190.68
Total Lump Sum Change Order Amount: -$254,690.68
CHANGES TO CONTRACT TIME:
No additional working days will be added to the Contract.
Summary of Costs:
Original Contract Amount: $1,855,006.45 Construction Start Date: 11/03/2025 Previous Change Orders: $0.00 Previous Agreed Completion Date: 02/17/2026 This Change Order Amount: -$254,690.68 Calendar Days Added: 0 Revised Contract Amount: $1,600,315.77 Revised Completion: No Change
I have received a copy of this Change Order and the above AGREED PRICES are acceptable to Contractor.
Company name
Enrique Rosales, Project Manager Date
City of Palm Springs
Recommended By:
Joel Montalvo, City Engineer Date
Approved By:
Scott Stiles, City Manager Date
Attest By:
Brenda Pree, City Clerk Date