VICTORIA PARK RESTROOM REPLACEMENT -1- 00 52 13 – CONTRACT FOR CONSTRUCTION
00 52 13 – CONTRACT FOR CONSTRUCTION
This Contract for Construction (“Contract”), No. ________ is made and entered into this 1 8th day of May 2026, by and between the City of Palm Springs, with its principal place of business at 3200 E. Tahquitz Canyon Way Palm Springs, California 92262, sometimes hereinafter called the “City” and Global Builders, Inc., sometimes hereinafter called “Contractor.”
WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these presents do covenant and agree with each other as follows:
ARTICLE 1. SCOPE OF WORK.
The Contractor shall perform all Work within the time stipulated in the Contract, and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5, below, for the following Project:
Victoria Park Restroom Replacement, City Project 18-06
Contractor is an independent contractor and not an agent of the C ity. The Contractor and its surety shall be liable to the City for any damages arising as a result of the Contractor’s failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION.
Time is of the essence in the performance of the Work. The Work shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents within 130 Working Days from the commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.
ARTICLE 3. CONTRACT PRICE.
The City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of Four Hundred Ninety-Five Thousand Nine Hundred Seventy-Six Dollars and Zero Cents ($495,976.00). Payment shall be made as set forth in the General Conditions. The City will pay to Contractor compensation based upon the prices set forth in the Bid Schedule.
ARTICLE 4. LIQUIDATED DAMAGES.
Contractor acknowledges that the City will sustain actual damages for each and every Day completion of the Project is delayed beyond the Contract Time. Because of the nature of the Project, it would be impracticable or extremely difficult to determine the City ’s actual damages. Accordingly, in accordance with Government Code section 53069.85, it is agreed that the Contractor will pay the City the sum of $500.00 for each and every calendar day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as liquidated damages and not as a penalty or forfeiture. This Article does not exclude recovery of other damages specified in the Contract Documents. Liquidated damages may be deducted from progress payments due Contractor, Project retention or may be collected directly from Contractor, or from Contractor's surety. These provisions for liquidated damages shall not prevent the City, in case of Contractor's default, from terminating the Contractor.
ARTICLE 5. COMPONENT PARTS OF THE CONTRACT.
The “Contract Documents” include the following:
VICTORIA PARK RESTROOM REPLACEMENT -2- 00 52 13 – CONTRACT FOR CONSTRUCTION
• Notice Inviting Bids
• Instructions to Bidders
• Bid Forms
• Bid
• Bid Schedule
• Bid Security
• Designation of Subcontractors
• Information Required of Bidders
• Non-Collusion Declaration Form
• Iran Contracting Act Certification
• Public Works Contractor DIR Registration Certification • Executive Order N-22 Certification
• Fleet Compliance Certification
• Performance Bond
• Payment (Labor and Materials) Bond
• Community Workforce Agreement
• Contract for Construction
• General Conditions
• Special Conditions
• Specifications
• Addenda
• Construction Plans and Drawings
• Standard Specifications for PW Construction “Greenbook”, latest edition, Except Sections 1-9 • Applicable Local Agency Standards and Specifications, as last revised • Reference Specifications
• Approved and fully executed Change Orders
• Permits
• Any other documents contained in or incorporated into the Contract The Contractor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. In the event of conflict, the various Contract Documents will be given effect in the order set forth in the General Conditions. This Contract shall supersede any prior agreement of the parties.
ARTICLE 6. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE.
Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Work.
ARTICLE 7. INDEMNIFICATION.
Contractor shall provide indemnification and defense as set forth in the General Conditions.
ARTICLE 8. PREVAILING WAGES.
Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates shall be made available at the City or may be obtained online at http://www.dir.ca.gov and which must be posted at the job site.
VICTORIA PARK RESTROOM REPLACEMENT -3- 00 52 13 – CONTRACT FOR CONSTRUCTION
ARTICLE 9. FALSE CLAIMS.
Contractor acknowledges that if a false claim is submitted to the City, it may be considered fraud and Contractor may be subject to criminal prosecution. Contractor acknowledges that the False Claims Act, California Government Code sections 12650, et seq., provides for civil penalties where a person knowingly submits a false claim to a public entity. These provisions include within their scope false claims made with deliberate ignorance of the false information or in reckless disregard of the truth or falsity of the information.
In the event the City seeks to recover penalties pursuant to the False Claims Act, it is entitled to recover its litigation costs, including attorneys’ fees. Contractor hereby acknowledges that the filing of a false claim may the Contractor to an administrative debarment proceeding wherein Contractor may be prevented from further bidding on public contracts for a period of up to five (5) years.
ARTICLE 10. CONFLICT OF INTEREST
Contractor acknowledges that no officer or employee of the City has or shall have any direct or indirect financial interest in this Agreement, nor shall Contractor enter into any agreement of any kind with any such officer or employee during the term of this Contract and for one (1) year thereafter. Contractor warrants that Contractor has not paid or given, and will not pay or give, any third party any money or other consideration in exchange for obtaining this Contract.
ARTICLE 11. COVENANT AGAINST DISCRIMINATION.
Contractor shall not discriminate against any employee or applicant for employment because of actual or perceived race, religion, color, sex, age, marital status, ancestry, national origin ( i.e., place of origin, immigration status, cultural or linguistic characteristics, or ethnicity), sexual orientation, gender identity, gender expression, physical or mental disability, or medical condition (each a “prohibited basis”).
Contractor shall ensure that applicants are employed, and that employees are treated during their employment, without regard to any prohibited basis. As a condition precedent to City’s lawful capacity to enter this Contract, and in executing this Contract, Contractor certifies that its actions and omissions hereunder shall not incorporate any discrimination arising from or related to any prohibited basis in any Contractor activity, including but not limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship; and further, that Contractor is in full compliance with the provisions of Palm Springs Municipal Code Section 7.05.02, including without limitation the provision of benefits, relating to non-discrimination in city contracting.
ARTICLE 12. COMMUNITY WORKFORCE AGREEMENT: INTENTIONALLY OMITTED
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
VICTORIA PARK RESTROOM REPLACEMENT -4- 00 52 13 – CONTRACT FOR CONSTRUCTION
SIGNATURE PAGE TO AGREEMENT BY AND BETWEEN THE CITY OF PALM SPRINGS AND GLOBAL BUILDERS, INC.
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on the day and year above written.
CONTRACTOR:
By Date
Signature
By
Date
Signature
CITY OF PALM SPRINGS:
APPROVED BY CITY COUNCIL: Date: Item No.
APPROVED AS TO FORM: ATTEST:
By
By
City Attorney City Clerk
APPROVED:
By Date
City Manager – up to $150,000
Deputy/Assistant City Manager – up to $50,000
Director – up to $25,000
Manager – up to $5,000
VICTORIA PARK RESTROOM REPLACEMENT -5- 00 52 13 – CONTRACT FOR CONSTRUCTION
EXHIBIT “A”
COMMUNITY WORKFORCE AGREEMENT
INTENTIONALLY OMITTED
VICTORIA PARK RESTROOM REPLACEMENT -6- 00 52 13 – CONTRACT FOR CONSTRUCTION
EXHIBIT “B”
LETTER OF ASSENT
INTENTIONALLY OMITTED
END OF CONTRACT FOR CONSTRUCTION
VICTORIA PARK RESTROOM REPLACEMENT -7- 00 61 13 – BOND FORMS
00 61 13 – BOND FORMS
PERFORMANCE BOND
KNOW ALL PERSONS BY THESE PRESENTS:
THAT WHEREAS, the City of Palm Springs, with its principal place of business at 3200 E. Tahquitz Canyon Way Palm Springs, California 92262, (hereinafter referred to as the “City”) has awarded to Global Builders, Inc., (hereinafter referred to as the “C ontractor”) an agreement for Contract No ._________, (hereinafter referred to as the “Project”);
WHEREAS, the work to be performed by the Contractor is more particularly set forth in the C ontract Documents for the Project dated May 18, 2026, (hereinafter referred to as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof and to furnish a bond for the faithful performance of said Contract Documents.
NOW, THEREFORE, we, the undersigned Contractor and
________________________________________________ as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held and firmly bound unto the City in the sum of Four Hundred Ninety-Five Thousand Nine Hundred Seventy-Six Dollars and Zero Cents, ($495,976.00), said sum being not less than one hundred percent (100%) of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor , his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations including the one (1) year guarantee of all materials and workmanship; and shall indemnify and save harmless the City , its officials, officers, employees, and authorized volunteers , as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees including reasonable attorney’s fees, incurred by the City in enforcing such obligation.
As a condition precedent to the satisfactory completion of the C ontract Documents, unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of one (1) year after the acceptance of the work by the City, during which time if Contractor shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage resulting from or caused by defective materials or faulty workmanship. The obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations under the Contract, law or equity, including, but not limited to, California Code of Civil Procedure Section 337.15.
Whenever Contractor shall be, and is declared by the City to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents , or shall promptly, at the City’s option:
i. Take over and complete the Project in accordance with all terms and conditions in the Contract Documents; or
VICTORIA PARK RESTROOM REPLACEMENT -8- 00 61 13 – BOND FORMS
ii. Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a Contract between such bidder, the Surety and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
iii. Permit the City to complete the Project in any manner consistent with California law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.
Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.
Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the City, when declaring the Contractor in default, notifies Surety of the City’s objection to Contractor’s further participation in the completion of the Project.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]
VICTORIA PARK RESTROOM REPLACEMENT -9- 00 61 13 – BOND FORMS
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20___.
(Corporate Seal)
Contractor/ Principal
By
Title
(Corporate Seal)
Surety
By
Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title
The rate of premium on this bond is ____________ per thousand. The total amount of premium charges is $_______________________________.
(The above must be filled in by corporate attorney.)
THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety) ___________________________________________ ___________________________________________
___________________________________________
(Name and Address of Agent or ___________________________________________ Representative for service of ___________________________________________ process in California, if different ___________________________________________ from above)
(Telephone number of Surety ___________________________________________ and Agent or Representative for
service of process in California)
VICTORIA PARK RESTROOM REPLACEMENT -10- 00 61 13 – BOND FORMS
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally
appeared , who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal.
VICTORIA PARK RESTROOM REPLACEMENT -11- 00 61 13 – BOND FORMS
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally
appeared , who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of Attorney to local representatives of the bonding company must also be attached.
END OF PERFORMANCE BOND
VICTORIA PARK RESTROOM REPLACEMENT 12 PLANS AND DRAWINGS 55575.18165\44345389.2
PAYMENT BOND (LABOR AND MATERIALS).
KNOW ALL MEN BY THESE PRESENTS:
THAT WHEREAS, the City of Palm Springs , with its principal place of business at 3200 E.
Tahquitz Canyon Way Palm Springs, California 92262, (hereinafter designated as the “City”), has awarded to Global Builders, Inc. , (hereinafter designated as the “Principal”) an agreement for Contract No._________, (hereinafter referred to as the “Project”); WHEREAS, the work to be performed by the Principal is more particularly set forth in the Contract Documents for the Project dated May 18, 2026, (hereinafter referred to as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.
NOW THEREFORE, we, the Principal and __________________________, as Surety, are held and firmly bound unto the City in the penal sum of Found Hundred Ninety-Five Thousand Nine Hundred Seventy-Six Dollars and Zero Cents ($495,976.00) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Civil Code section 9100, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Revenue and Taxation Code Section 18663, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, i ncluding reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.
This bond shall inure to the benefit of any of the persons named in Civil Code Section 9100 so as to give a right of action to such persons or their assigns in any suit brought upon this bond.
It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of paym ent or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted VICTORIA PARK RESTROOM REPLACEMENT 13 PLANS AND DRAWINGS 55575.18165\44345389.2
rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or the City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Civil Code Section 9100, and has not been paid the full amount of his claim.
The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract to be performed thereunder, shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of Contract, including but not limited to, the provisions of Sections 2819 and 2845 of the California Civil Code.
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20__.
(Corporate Seal)
Contractor/ Principal
By
Title
(Corporate Seal)
Surety
By
Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title
VICTORIA PARK RESTROOM REPLACEMENT 14 PLANS AND DRAWINGS 55575.18165\44345389.2
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally
appeared , who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal.
VICTORIA PARK RESTROOM REPLACEMENT 15 PLANS AND DRAWINGS 55575.18165\44345389.2
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally
appeared , who proved to me on the basis of satisfactory
evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.
WITNESS my hand and official seal.
Signature of Notary Public
OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s) Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:
Signer is representing:
Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of-Attorney to local representatives of the bonding company must also be attached.
END OF PAYMENT BON