ATTACHMENT E
ESTIMATED PROJECT SCHEDULE
ID
Task
Mode
Task Name Duration Start Finish
1 Palm Springs Airport Schedule 95 days Mon 6/1/26 Fri 10/9/26 2 Contract Executed 0 days Mon 6/1/26 Mon 6/1/26
3 Contract Executed 0 days Mon 6/1/26 Mon 6/1/26
4 Submittals 10 days Mon 6/1/26 Fri 6/12/26
5 Submit Lane Hardware 5 days Mon 6/1/26 Fri 6/5/26
6 Design plans for permitting 5 days Mon 6/1/26 Fri 6/5/26 7 As-builts 5 days Mon 6/1/26 Fri 6/5/26
8 Architecture/Construction plans 5 days Mon 6/1/26 Fri 6/5/26 9 Submittal for server and network design5 days Mon 6/1/26 Fri 6/5/26 10 Detailed schedule 5 days Mon 6/8/26 Fri 6/12/26
11 Receive and acceptance 5 days Mon 6/8/26 Fri 6/12/26 12 Submittal for training manual 5 days Mon 6/8/26 Fri 6/12/26 13 Submittal of Lane Acceptance Test 1 day Mon 6/8/26 Mon 6/8/26 14 Hardware Production 40 days Mon 6/8/26 Fri 7/31/26
15 Production Equipment 8 wks Mon 6/8/26 Fri 7/31/26
16 Equipment Manufacturing 8 wks Mon 6/8/26 Fri 7/31/26 17 Order third party equipment 17 days Mon 6/8/26 Tue 6/30/26 18 Civil Work 30 days Wed 7/1/26 Tue 8/11/26
19 Civil and Electrical Upgrades 30 days Wed 7/1/26 Tue 8/11/26 20 Pre install/Pre config 26 days Mon 8/3/26 Mon 9/7/26 21 Offsite Configuration 15 days Mon 8/3/26 Fri 8/21/26 22 Offsite testing 10 days Mon 8/24/26 Fri 9/4/26
23 Ready to deploy 1 day Mon 9/7/26 Mon 9/7/26
24 Software Upgrade 2 days Mon 8/24/26 Tue 8/25/26
25 Software upgrade 2 days Mon 8/24/26 Tue 8/25/26
26 Installation phase (7 Entry, 4 Exit) 24 days Tue 9/8/26 Fri 10/9/26 27 Site ready for install 2 days Tue 9/8/26 Wed 9/9/26
28 Field Coordination 2 days Thu 9/10/26 Fri 9/11/26
29 Install start 0 days Fri 9/11/26 Fri 9/11/26
30 2 Entry, 1 Exit 5 days Mon 9/14/26 Fri 9/18/26
31 Prep for mounting equipment 1 day Mon 9/14/26 Mon 9/14/26 6/1
6/1
9/11
M J J A S O N D
Half 1, 2026 Half 2, 2026
ID
Task
Mode
Task Name Duration Start Finish Predecessors
32 Install new equipment 3 days Tue 9/15/26 Thu 9/17/26 31 33 Lane Acceptance Test (LAT) 1 day Fri 9/18/26 Fri 9/18/26 32 34 2 Entry, 1 Cashier Booth with column 5 days Mon 9/21/26 Fri 9/25/26 35 Prep for mounting equipment 1 day Mon 9/21/26 Mon 9/21/2633 36 Install new equipment 3 days Tue 9/22/26 Thu 9/24/26 35 37 Lane Acceptance Test (LAT) 1 day Fri 9/25/26 Fri 9/25/26 36 38 2 Entry, 1 Exit, 1 cashier station 5 days Mon 9/28/26 Fri 10/2/26 39 Prep for mounting equipment 1 day Mon 9/28/26 Mon 9/28/2637 40 Install new equipment 3 days Tue 9/29/26 Thu 10/1/26 39 41 Lane Acceptance Test (LAT) 1 day Fri 10/2/26 Fri 10/2/26 40 42 1 Entry, 1 Exit 5 days Mon 10/5/26 Fri 10/9/26
43 Prep for mounting equipment 1 day Mon 10/5/26 Mon 10/5/2641 44 Install new equipment 3 days Tue 10/6/26 Thu 10/8/26 43 45 Lane Acceptance Test (LAT) 1 day Fri 10/9/26 Fri 10/9/26 44 46 Contract closeout 0 days Fri 10/2/26 Fri 10/2/26
47 Project closeout 0 days Fri 10/2/26 Fri 10/2/26 41
48 Final Acceptance 0 days Fri 10/2/26 Fri 10/2/26 41
49 Training for managers/ supervisors 1 day Mon 9/21/26 Mon 9/21/26 50 Training for supervisors 1 day Mon 9/21/26 Mon 9/21/2633 51 Training for system adminstrators 1 day Mon 9/21/26 Mon 9/21/2633 52 Training for accounting and audit 1 day Mon 9/21/26 Mon 9/21/2633 53 Training on equipment 1 day Mon 9/21/26 Mon 9/21/2633 10/2
10/2
10/2
M J J A S O N D
Half 1, 2026 Half 2, 2026