Attachment B

CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER No. 01
CP 21-06, Wastewater Treatment Plant Various Demolitions

Contractor: Engineering Resources Inc. Date: July 6, 2026

CONTRACT CHANGE ORDER SUMMARY
The work was completed without performing several bid items because they were either unnecessary or replaced by approved alternatives, resulting in a credit of $273,733.74. This adjustment accounts for the unused portions of the Contractor’s Schedule updates, the adjusted quantity for grading and backfills, and the remaining balance of the allowance item, as well as the complete deletion of bid items for cutting and abandoning sewer lines, manhole removals, and the temporary sound wall and shoring and bracing not used.

CONTRACT CHANGE ORDER COST
ID Description Qty Unit Cost
COR 1 Unused portion of bid Item No 4- Schedule, monthly updates.

1 LS ($500.00)
COR 2 Deletion of Bid Item No. 08 - Cut and Abandon Sewer Lines (Diameter Greater Than or Equal to 16-inch) and Fill with Flowable Fill’. 1 LS ($36,210.00)
COR 3 Deletion of Bid Item No. 11. Remove Sewer Manhole. 1 LS ($3,000.00) COR 4 Credit for unused portion of Bid Item 30, Shoring and Bracing RFC No 33. ($50,000.00) COR 5 Deletion of Bid Item No. 31 ‘Temporary Sound Wall’ City Initiated. 1 LS ($45,600.00) COR 6 Bid Item no 32 Grading and backfill. $36/cu.yd. ~2,548.0 cu.yd. Not placed ~2,548.0 Cu.Yd ($91,730.52) COR 7 Bid item 35 (allowance) Remaining after June 2026 payment. 1 LS ($46,693.22)

Total Lump Sum Change Order Amount: ($ 273,733.74)

CHANGES TO CONTRACT TIME
No time extension is requested.

Summary of Costs
Original Contract Amount: $2,243,559.00 Construction Start Date: 11/17/2025 Previous Change Orders:

$ 0 Previous Agreed Completion Date: 06/04/2026
This Change Order Amount: $(273,733.74) Calendar Days Added: 0 Revised Contract Amount: $1,969,825.26 Revised Completion: 06/04/2026 have received a copy of this Change Order, and the above AGREED PRICES are acceptable to Contractor.

CONTRACTOR
Name and Tittle Date
City of Palm Springs

Recommended By:

Joel Montalvo, City Engineer Date

Approved By:

Scott Stiles, City Manager Date

Attest By:

Brenda Pree, City Clerk Date