Attachment C
Steve Rados Inc. Change Order No. 9

Page 1 of 2 ends

CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER NO. 9
CP 20-25 & 21-07 WWTP Digester No. 2, Waste Gas Flare and Filtrate Pump Station

Contactor: Steve P. Rados, Inc. Date: June 29, 2026

CONTRACT CHANGE ORDER SUMMARY

MWH reviewed four costs from Steve P. Rados, Inc. covering various work modifications at the WWTP for work under the subject project. The Work included the remediation of a sinkhole, the replacement of a three- way valve to maintain operational functionality; relocation of a palm tree to accommodate the new gas flare installation; miscellaneous buried pipe alignment modifications to accommodate unidentified utilities encountered in the field; and gas flare pipe re-routing and modifications. All proposals were found to be contractually compliant with appropriate documentation, labor, equipment, materials, subcontractor support, and markups within allowable limits. No additional time is requested in this change order.

CONTRACT CHANGE ORDER COST

ID Description Qty Unit Cost
01 Cost proposal #08 involves pipe route and modifications and specific modifications to the flare, as well as the work was in accordance with directive WCD 03.
1 LS $23,840.30

02 Cost proposal #09
Misc. pipe Modifications to accommodate unidentified Utilities encountered in the field.
1 LS $158,179.67
03 Cost Proposal #10
Sinkhole remediation and replacement of the 3-way valve 1 LS $127,316.63 04 Cost Proposal # 11
Relocation of Palm due to proximity to the Flare.

1 LS $26,712.99
Total Lump Sum Change Order Amount: $336,049.59

CHANGES TO CONTRACT TIME

No time extension is requested.

SOURCE OF FUNDS

Sufficient funds are available in the Wastewater Capital Improvement Projects Fund.

Page 2 of 2 ends

SUMMARY OF COSTS

Original Contract Amount: $15,905,500.00

Construction Start Date: 07/21/2022
Previous Change Orders:

$1,710,581.94 Previous Agreed Completion Date: 01/10/2025 This Change Order Amount: $336,049.59 Working Days Added: 0 Revised Contract Amount: $18,836,367.49 Revised Completion: 07/31/2025

I have received a copy of this Change Order, and the above AGREED PRICES are acceptable.

Steve P. Rados, Inc.

Jason Riedel, Project Manager Date

City of Palm Springs

Recommended By:

Joel Montalvo, City Engineer Date

Approved By:

Scott C. Stiles, City Manager Date

Attest By:

Brenda Pree, City Clerk Date