Palo Alto Fiber Project and
Construction Alignment
with Electric Grid
Modernization
November 7, 2023
- 2
AGENDA
• Project(s) Recap
• Fiber Expansion Plan
• Fiber Backbone Expansion “Rebuild” Project
• Fiber-to-the-Premises (FTTP) Project
• Electrification
• Grid Modernization for Electrification Project
• Informational Updates
• Alignment of Fiber Expansion Plan and Grid Modernization • California Environmental Quality Act (CEQA) Initial Study • Joint Pole Ownership Coordination with AT&T
• Contract Amendments
• Other Updates
- 3
HOW DID WE GET HERE?
• What has Council Approved?
• Dec 19, 2022 Council Approved to
• Proceed with dark fiber backbone
expansion “rebuild”
• Build FTTP Phase 01 in multi-
phased approach without debt
financing
• Jun 19, 2023 Council Approved
• New Grid Modernization for Electrification project in FY24 Budget • New Fiber-to-the-Premises project in FY24 Budget
- 4
RECAP OF PROJECTS
FIBER BACKBONE REBUILD FIBER-TO-THE-PREMISES GRID MODERNIZATION Estimated cost $25.6M (FO-16000) Estimated cost for Phase 1 $20M; Citywide $102M (FO-24000)
Estimated cost $220M to $306M
(EL-24000)
Funded by Electric and Fiber funds Funded by Fiber Fund Funded by the Electric Fund; debt financing and/or grants
Supports the City’s fiber licensing
service and internal needs:
Improve fiber and electric
system reliability, security
and capacity
Enable more connectivity for
City departments
Internal communication
needs for SCADA, AMI, DA
and other critical
infrastructure
Supports the City’s high speed
broadband internet needs:
Provides City-owned
high-speed internet
service
Provides new capacity for
dark fiber licensing
Community investment in
its own broadband
network
Supports City’s S/CAP goals and
future demand
100% residential
electrification
Upgrade existing
substations,
replace transformers,
convert existing 4 kVa lines
to 12 kVa to increase
capacity and meet
future demand.
- 5
INFORMATIONAL UPDATES
Topics to address prior to construction
Pilot aligning fiber and grid modernization project to inform on • Pole make-ready and replacement
• Material lead time and warehousing
• Internal resources to implement and coordinate projects Initial Study for CEQA in progress to evaluate potential impacts • Identify physical, biological, social and economic factors • Provide mitigation efforts
Joint Pole Ownership Coordination with AT&T in progress • Approximately 5,550 poles shared with AT&T
• Upcoming replacements and coordination will overwhelm staff • Eliminated Northern California Joint Pole Association membership option Contract Amendments
• VIP Powerline – power and fiber construction
• MP Nexlevel– substructure and fiber construction
• Magellan/Entrust– power and fiber engineering design
- 6
Pilot Map Overlay with Phase 1 & Areas of Interest
Pilot Area Map to align Grid Modernization with FTTP
(1,224 customers and 409 poles)
Proposed Phase 1 FTTP Map (Additional 5,560
customers and 1,241 poles)
Areas of Interest Map based on Lower Construction
Cost, Higher Density, Less Competition, Higher
Customer Interest
- 7
Pilot Project Plan (draft outline subject to change)
Pre-construction
• Aerial Power Make Ready Engineering - Feb 2024
• Materials Ordering/Warehousing - Feb 2024
• CEQA Approval - Apr 2024
• Fiber Hut at Colorado Power Station - Oct 2024
Construction
• Power: Mar 2024 - Oct 2024
• Fiber: Jun 2024 - Feb 2025
Operations & Customer Outreach
• Operations Support Systems “OSS”
• Business Support Systems “BSS”
• Marketing/Event(s)
• Community Meeting(s)
- 8
Q&A