Attachment D - 2022 Multifamily New Construction Cost-Effectiveness Study and MF

Palo Alto City Council
June 3, 2024

Document
Attachment D - 2022 Multifamily New Construction Cost-Effectiveness Study and MF
Meeting
June 3, 2024
Body
Palo Alto City Council
Original file
5.2 MB
Text extracted from the city's file for reading and search. Open the original on cityofpaloalto.primegov.com. That file is the official record.

Prepared by:

Frontier Energy, Inc
Misti Bruceri & Associates, LLC

Prepared for:

Kelly Cunningham, Codes and Standards Program, Pacific Gas and Electric Last modified: 2023/06/20
Revision: 1.1
2022 Cost-Effectiveness Study:

Multifamily New Construction

Cost-Effectiveness Analysis: Multifamily New Construction

Legal Notice
This report was prepared by Pacific Gas and Electric Company and funded by the California utility customers under the auspices of the California Public Utilities Commission.

Copyright 2022 , Pacific Gas and Electric Company. All rights reserved, except that this document may be used, copied, and distributed without modification.

Neither PG&E nor any of its employees makes any warranty, express or implied; or assumes any legal liability or responsibility for the accuracy, completeness or usefulness of any data, information, method, product, policy or process disclose d in this document; or represents that its use will not infringe any privately -owned rights including, but not limited to, patents, trademarks or copyrights.

Acronym List
2023 PV$ – Present value costs in 2023
ACH50 – Air Changes per Hour at 50 pascals pressure differential ACM – Alternative Calculation Method
ADU – Accessory Dwelling Unit
AFUE – Annual Fuel Utilization Efficiency
B/C – Lifecycle Benefit-to-Cost Ratio
BEopt – Building Energy Optimization Tool
BSC – Building Standards Commission
CA IOUs – California Investor-Owned Utilities
CASE – Codes and Standards Enhancement
CBECC-Res – Computer program developed by the California Energy Commission for use in demonstrating compliance with the California Residential Building Energy Efficiency Standards CFI – California Flexible Installation
CFM – Cubic Feet per Minute
CO2 – Carbon Dioxide
CPAU – City of Palo Alto Utilities
CPUC – California Public Utilities Commission
CZ – California Climate Zone
DHW – Domestic Hot Water
DOE – Department of Energy
DWHR – Drain Water Heat Recovery
EDR – Energy Design Rating
EER – Energy Efficiency Ratio
EF – Energy Factor
GHG – Greenhouse Gas

Cost-Effectiveness Analysis: Multifamily New Construction

HERS Rater – Home Energy Rating System Rater
HPA – High Performance Attic
HPWH – Heat Pump Water Heater
HSPF – Heating Seasonal Performance Factor
HVAC – Heating, Ventilation, and Air Conditioning
IECC – International Energy Conservation Code
IOU – Investor Owned Utility
kBtu – kilo-British thermal unit
kWh – Kilowatt Hour
LBNL – Lawrence Berkeley National Laboratory
LCC – Lifecycle Cost
LLAHU – Low Leakage Air Handler Unit
VLLDCS – Verified Low Leakage Ducts in Conditioned Space MF – Multifamily
NEEA – Northwest Energy Efficiency Alliance
NEM – Net Energy Metering
NPV – Net Present Value
NREL – National Renewable Energy Laboratory
PG&E – Pacific Gas and Electric Company
POU – Publicly-Owned-Utilities
PV – Photovoltaic
SCE – Southern California Edison
SDG&E – San Diego Gas and Electric
SEER – Seasonal Energy Efficiency Ratio
SF – Single Family
SMUD – Sacramento Municipal Utility District
SoCalGas – Southern California Gas Company
TDV – Time Dependent Valuation
Therm – Unit for quantity of heat that equals 100,000 British thermal units Title 24 – Title 24, Part 6
TOU – Time-Of-Use
UEF – Uniform Energy Factor
ZNE – Zero-net Energy

Cost-Effectiveness Analysis: Multifamily New Construction

Summary of Revisions
Date Description Reference (page or section)
2/28/2022 Original Release N/A
6/20/2023 Minor revisions to content; no change to results 2, 3, 32, 33

Cost-Effectiveness Analysis: Multifamily New Construction

TABLE OF CONTENTS
Executive Summary .......................................................................................................................................................... 1 1 Introduction ................................................................................................................................................................ 4 2 Methodology and Assumptions ............................................................................................................................... 5

2.1 Analysis for Reach Codes ..................................................................................................................................................... 5

2.1.1 Modeling ....................................................................................................................................................................... 5

2.1.2 Cost-Effectiveness ........................................................................................................................................................ 5

2.1.3 Utility Rates ................................................................................................................................................................... 6

2.2 2022 T24 Compliance Metrics .............................................................................................................................................. 8

2.3 Greenhouse Gas Emissions ................................................................................................................................................. 8 3 Prototypes, Measure Packages, and Costs ............................................................................................................ 9

3.2 Measure Definitions and Costs ........................................................................................................................................... 11

3.2.1 Efficiency, Solar PV, and Batteries ............................................................................................................................. 11

3.2.2 All-Electric ................................................................................................................................................................... 15

3.3 Measure Packages ............................................................................................................................................................. 18 4 Results ...................................................................................................................................................................... 20

4.1 All-Electric Prescriptive Code .............................................................................................................................................. 20

4.2 All-Electric Plus PV ............................................................................................................................................................. 23

4.3 Mixed Fuel Efficiency .......................................................................................................................................................... 25

4.4 Mixed Fuel Plus PV (Plus Battery for the 3-Story Prototype) .............................................................................................. 26

4.5 CARE Rate Comparison ..................................................................................................................................................... 29

4.6 Greenhouse Gas Reductions .............................................................................................................................................. 30 5 Summary .................................................................................................................................................................. 32 6 References ............................................................................................................................................................... 34 7 Appendices .............................................................................................................................................................. 36

7.1 Map of California Climate Zones ......................................................................................................................................... 36

7.2 Utility Rate Schedules ......................................................................................................................................................... 37

7.2.1 Pacific Gas & Electric .................................................................................................................................................. 38

7.2.2 Southern California Edison ......................................................................................................................................... 43

7.2.3 Southern California Gas .............................................................................................................................................. 46

7.2.4 San Diego Gas & Electric............................................................................................................................................ 48

7.2.5 City of Palo Alto Utilities .............................................................................................................................................. 53

7.2.6 Sacramento Municipal Utilities District (Electric Only) ................................................................................................. 55

7.2.7 Fuel Escalation Assumptions ...................................................................................................................................... 57

7.3 Cost Details......................................................................................................................................................................... 58

7.4 PG&E Gas Infrastructure Cost Memo ................................................................................................................................. 59

7.5 Central Heat Pump Water Heater Comparison ................................................................................................................... 62

7.6 Summary of Measures by Package .................................................................................................................................... 63

Cost-Effectiveness Analysis: Multifamily New Construction

LIST OF TABLES
Table ES-1. Summary of Efficiency TDV Compliance Margins and Cost-Effectiveness ....................................................................... 3 Table 1. Utility Tariffs Used Based on Climate Zone ............................................................................................................................ 8 Table 2. Prototype Characteristics ........................................................................................................................................................ 9 Table 3. Base Case Characteristics of the Prototypes ........................................................................................................................ 10 Table 4. Base Package PV Capacities (kW-DC) ................................................................................................................................ 10 Table 5. Incremental Cost Assumptions ............................................................................................................................................. 13 Table 6. Heat Pump Water Heater Incremental System Costs (Present Value (2023$)) .................................................................... 16 Table 7. Heat Pump Space Heater Costs per Dwelling Unit (Present Value (2023$) ......................................................................... 16 Table 8. Lifetime of Water Heating & Space Conditioning Equipment Measures ............................................................................... 17 Table 9. IOU Natural Gas Infrastructure Cost Savings for All-Electric Building................................................................................... 18 Table 10. Multifamily IOU Total Natural Gas Infrastructure Costs ...................................................................................................... 18 Table 11. Multifamily CPAU Total Natural Gas Infrastructure Costs ................................................................................................... 18 Table 12. 3-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric Prescriptive Code ......................................................... 21 Table 13. 5-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric Prescriptive Code ......................................................... 22 Table 14. 3-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric 100% PV ...................................................................... 23 Table 15. 5-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric 100% PV ...................................................................... 24 Table 16. 3-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency ..................................................................... 25 Table 17. 5-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency ..................................................................... 26 Table 18. 3-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency + PV + Battery ............................................. 27 Table 19. 5-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency + PV ............................................................ 28 Table 20. On-Bill IOU Cost-Effectiveness Comparison with CARE Tariffs, Results per Dwelling Unit: All-Electric Prescriptive Code 29 Table 21. On-Bill IOU Cost-Effectiveness Comparison with CARE Tariffs, Results per Dwelling Unit: Mixed Fuel Packages ........... 29 Table 22. Summary of Efficiency TDV Compliance Margins and Cost-Effectiveness ......................................................................... 33 Table 23. PG&E Baseline Territory by Climate Zone .......................................................................................................................... 38 Table 24. PG&E Monthly Gas Rate ($/therm) ..................................................................................................................................... 38 Table 25. PG&E Monthly CARE (GL-1) Gas Rate ($/therm)............................................................................................................... 39 Table 26: SCE Baseline Territory by Climate Zone ............................................................................................................................ 43 Table 27. SoCalGas Baseline Territory by Climate Zone ................................................................................................................... 46 Table 28. SoCalGas Monthly Gas Rate ($/therm) .............................................................................................................................. 46 Table 29. SDG&E Baseline Territory by Climate Zone ....................................................................................................................... 48 Cost-Effectiveness Analysis: Multifamily New Construction

Table 30. SDG&E Monthly Gas Rate ($/therm) .................................................................................................................................. 48 Table 31. CPAU Monthly Gas Rate ($/therm) ..................................................................................................................................... 53 Table 32: Real Utility Rate Escalation Rate Assumptions ................................................................................................................... 57 Table 33. Heat Pump Water Heater First Costs per Building (Present Value (2023$)) ....................................................................... 58 Table 34. Heat Pump Space Heater First Costs per Dwelling Unit (Present Value (2023$) ............................................................... 58 Table 35. 5-Story Cost-Effectiveness: All-Electric Prescriptive Code with R-134a Heat Pump Water Heater .................................... 62 Table 36. Mixed Fuel Efficiency Package Measures .......................................................................................................................... 63 Table 37. Upgrade Package PV Capacities (kW-DC) ......................................................................................................................... 64

LIST OF FIGURES
Figure 1. 3-Story greenhouse gas reductions (metric tons) per dwelling unit ..................................................................................... 31 Figure 2. 5-Story greenhouse gas savings (metric tons) per dwelling unit .......................................................................................... 31 Figure 3. Map of California climate zones. .......................................................................................................................................... 36

Cost-Effectiveness Analysis: Multifamily New Construction Executive Summary
1 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Executive Summary
The California Codes and Standards (C&S) Reach Codes program provides technical support to local governments considering adopting a local ordinance (reach code) intended to support meeting local and/or statewide energy efficiency and greenhouse gas (GHG) reduction goals. The program facilitates adoption and implementation of the code when requested by local jurisdictions by providing resources such as cost-effectiveness studies, model language, sample findings, and other supporting documentation.

This report documents cost-effective combinations of measures that exceed the minimum state requirements, the 2022 Building Energy Efficiency Standards (Title 24, Part 6 or Energy Code), effective January 1, 2023, for newly constructed multifamily buildings. The analysis considers low-rise and mid-rise multifamily building types and evaluates mixed fuel and all-electric package options in all sixteen California climate zones (CZs) Packages include a code compliant electrification package and a mixed fuel efficiency package, as well as the addition of above-code on-site solar photovoltaic (PV) capacity and battery energy storage. The 2022 Energy Code established electric heat pumps as the prescriptive baseline for space heating in most climate zones. As a result, this analysis primarily focuses on the electrification of central water heating. Space heating electrification was also evaluated where the prescriptive heat pump baseline didn’t apply: In Climate Zone 16 for multifamily buildings three habitable stories or fewer, and Climate Zones 1 and 16 for multifamily buildings greater than three habitable stories.

This analysis used two different metrics to assess the cost-effectiveness of the proposed upgrades. Both methodologies require estimating and quantifying the incremental costs and energy savings associated with each energy efficiency measure over a 30-year analysis period. On-Bill cost-effectiveness is a customer-based lifecycle cost (LCC) approach that values energy based upon estimated site energy usage and customer utility bill savings using today’s electricity and natural gas utility tariffs. Time Dependent Valuation (TDV) is the California Energy Commission’s LCC methodology, which is intended to capture the long-term projected cost of energy including costs for providing energy during peak periods of demand, carbon emissions, grid transmission and distribution impacts. This is the methodology used by the Energy Commission in evaluating cost-effectiveness for efficiency measures in Title 24, Part

6. Two multifamily prototypes were evaluated in this study. A 3-story loaded corridor and a 5-story mixed use prototype, which combined are estimated to represent 91 percent of new multifamily construction in California.

The following summarizes key results from the study:
• The Reach Codes Team found all-electric new construction to be feasible and cost-effective based on the California Energy Commission’s Time Dependent Valuation (TDV) metric in all cases. In many cases all- electric prescriptive code construction results in an increase in utility costs and is not cost-effective On-Bill.

Some exceptions include the SMUD and CPAU territories where lower electricity rates relative to gas rates result in lower overall utility bills.
• All-electric packages have lower GHG emissions than mixed fuel packages in all cases, due to the clean power sources currently available from California’s power providers. • The 2022 Energy Code’s new source energy metric combined with the heat pump space heating baseline in most climate zones encourages all-electric construction. While the code does not include an electric baseline for water heating, the penalty for central electric water heating observed in the performance approach in past code cycles has been removed and a credit is provided for well-designed central heat pump water heaters in most cases.
• Electrification combined with increased PV capacity results in utility cost savings and was found to be On-Bill cost-effective in all cases.
• The results in this study are based on today’s net energy metering (NEM 2.0) rules and do not account for recently approved changes to the NEM tariff (referred to as the net billing tariff). The net billing tariff decreases the value of PV to the consumer as compared to NEM 2.0. As a result, the cost-effectiveness of the packages that include above-code PV capacity is expected to be less under the net billing tariff. Conversely, the net Cost-Effectiveness Analysis: Multifamily New Construction Executive Summary
2 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

billing tariff is expected to increase On-Bill cost-effectiveness of the all-electric prescriptive code scenario. An all-electric home has better on-site utilization of generated electricity from PV than a mixed fuel home with a similar sized PV system, and as a result exports less electricity to the grid. Since the net -billing tariff values exports less than under NEM 2.0, the relative impact on annual utility costs to the mixed fuel baseline is greater.
• This analysis does justify a modest reach based on either efficiency TDV or source energy for all-electric buildings. However, this may be challenging for some projects given the recent changes to which the industry must adapt, including the efficiency updates and multifamily restructuring in the 2022 Title 24, Part 6 code.

While project compliance margins using a CO2 refrigerant heat pump water heating system are high, the Reach Code Team found lower compliance margins using other heat pump water heater system designs.

Focusing on supporting projects to electrify water heating is expected to support the market shift towards more central heat pump water heaters.
• For jurisdictions interested in a reach code that allows for mixed fuel buildings, a mixed fuel efficiency and PV package (and battery for the 3-story prototype) was found to be cost-effective based on TDV in all cases and cost-effective On-Bill in most climate zones. This path, referred to as “Electric-Preferred”, allows for mixed fuel buildings but requires a higher building performance than for all-electric buildings. The efficiency measures evaluated in this study did not provide significant compliance benefit. As a result, the Reach Codes Team recommends establishing a compliance margin target based on source energy or total TDV. This would allow for PV and battery above minimum code requirements to be used to meet the target. • Jurisdictions interested in increasing affordable multifamily housing should know that applying the CARE rates has the overall impact of increasing utility cost savings for an all-electric building in most climate zones compared to a code compliant mixed fuel building, improving On-Bill cost-effectiveness.

Table ES-1 summarizes results for each prototype and depicts the efficiency TDV compliance margins achieved for each climate zone and package. All results presented in the table have a positive compliance margin (greater than zero percent). Cells highlighted in green depict cases with a positive compliance margin and cost-effective results using both On-Bill and TDV approaches. Cells highlighted in yellow depict cases with a positive compliance margin and cost- effective results using either the On-Bill or TDV approach. Cells not highlighted depict cases with a positive compliance margin but that were not cost-effective using either the On-Bill or TDV approach.

Cost-Effectiveness Analysis: Multifamily New Construction Executive Summary
3 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table ES-1. Summary of Efficiency TDV Compliance Margins and Cost-Effectiveness Climate
Zone
Electric
/Gas Utility
3-Story 5-Story
All-Electric
Prescriptive
Code
All-
Electric
+ PV
Mixed
Fuel
Efficiency
Mixed
Fuel
Efficiency
+ PV +
Battery
All-Electric
Prescriptive
Code
All-
Electric
+ PV
Mixed
Fuel
Efficiency
Mixed
Fuel
Efficiency
+ PV
CZ01 PGE 26% 26% 1% 1% 14% 14% 0% 0%
CZ02 PGE 20% 20% 1% 1% 9% 9% 1% 1%
CZ03 PGE 21% 21% 1% 1% 11% 11% 0% 0%
CZ04 PGE 18% 18% 1% 1% 9% 9% 1% 1%
CZ04 CPAU 18% 18% 1% 1% 9% 9% 1% 1%
CZ05 PGE 23% 23% 1% 1% 12% 12% 0% 0%
CZ05 PGE/SCG 23% 23% 1% 1% 12% 12% 0% 0%
CZ06 SCE/SCG 18% 18% 1% 1% 9% 9% 0% 0%
CZ07 SDGE 20% 20% 0% 0% 11% 11% 0% 0%
CZ08 SCE/SCG 13% 13% 1% 1% 8% 8% 1% 1%
CZ09 SCE 13% 13% 1% 1% 7% 7% 1% 1%
CZ10 SCE/SCG 14% 14% 3% 3% 7% 7% 2% 2%
CZ10 SDGE 14% 14% 3% 3% 7% 7% 2% 2%
CZ11 PGE 14% 14% 3% 3% 8% 8% 2% 2%
CZ12 PGE 17% 17% 2% 2% 9% 9% 2% 2%
CZ12 SMUD/PGE 17% 17% 2% 2% 9% 9% 2% 2%
CZ13 PGE 13% 13% 4% 4% 7% 7% 2% 2%
CZ14 SCE/SCG 13% 13% 3% 3% 6% 6% 2% 2%
CZ14 SDGE 13% 13% 3% 3% 6% 6% 2% 2%
CZ15 SCE/SCG 5% 5% 5% 5% 3% 3% 3% 3%
CZ16 PG&E 24% 24% 5% 5% 9% 9% 2% 2%

Local jurisdictions may also adopt ordinances that amend different Parts of the California Building Standards Code or may elect to amend other state or municipal codes. The decision regarding which code to amend will determine the specific requirements that must be followed for an ordinance to be legally enforceable. Reach codes that amend Part 6 of the CA Building Code and require energy performance (including PV and storage) beyond state code minimums must demonstrate that the proposed changes are cost-effective and obtain approval from the Energy Commission prior to filing with the BSC.

Model ordinance language and other resources are posted on the C&S Reach Codes Program website at LocalEnergyCodes.com. Local jurisdictions that are considering adopting an ordinance may contact the program for further technical support at [email protected].

Cost-Effectiveness Analysis: Multifamily New Construction Introduction
4 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

1 Introduction
This report documents cost-effective combinations of measures that exceed the minimum state requirements, the 2022 Building Energy Efficiency Standards, effective January 1, 2023, for newly constructed multifamily buildings. This report was developed in coordination with the California Statewide Investor-Owned Utilities (CA IOUs) Codes and Standards Program, key consultants, and engaged cities—collectively known as the Reach Codes Team. The CA IOU Codes and Standards Program is comprised of IOUs representatives from Pacific Gas and Electric (PG&E), Southern California Edison (SCE) and San Diego Gas and Electric (SDG&E) and two Publicly-Owned-Utilities (POUs) – Sacramento Municipal Utility District (SMUD) and City of Palo Alto Utilities (CPAU), The analysis considers low-rise and mid-rise multifamily building types and evaluates mixed fuel and all-electric package options in all sixteen California climate zones (CZs)1 Packages include combinations of efficiency measures, on-site renewable energy, and battery energy storage.

The California Building Energy Efficiency Standards Title 24, Part 6 (Energy Code) (California Energy Commission, 2022a) is maintained and updated every three years by two state agencies: the California Energy Commission (Energy Commission) and the Building Standards Commission (BSC). In addition to enforcing the code, local jurisdictions have the authority to adopt local energy efficiency ordinances—or reach codes—that exceed the minimum standards defined by Title 24 (as established by Public Resources Code Section 25402.1(h)2 and Section 10- 106 of the Building Energy Efficiency Standards (California Energy Commission, 2022a)). Local jurisdictions must demonstrate that the requirements of the proposed ordinance are cost-effective and do not result in buildings consuming more energy than is permitted by Title 24. In addition, the jurisdiction must obtain approval from the Energy Commission and file the ordinance with the BSC for the ordinance to be legally enforceable.

The Department of Energy (DOE) sets minimum efficiency standards for equipment and appliances that are federally regulated under the National Appliance Energy Conservation Act, including heating, cooling, and water heating equipment (E-CFR, 2020). Since state and local governments are prohibited from adopting higher minimum efficiencies than the federal standards require, the focus of this study is to identify and evaluate cost-effective packages that do not include high efficiency heating, cooling, and water heating equipment. High efficiency appliances are often the easiest and most affordable measures to increase energy performance. While federal preemption limits reach code mandatory requirements for covered appliances, in practice, builders may install any package of compliant measures to achieve the performance requirements.

1 See Appendix 7.1 Map of California Climate Zones for a graphical depiction of climate zone locations.

Cost-Effectiveness Analysis: Multifamily New Construction Methodology and Assumptions
5 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

2 Methodology and Assumptions

2.1 Analysis for Reach Codes
This section describes the approach to calculating cost-effectiveness including benefits, costs, metrics, and utility rate selection.

2.1.1 Modeling
The Reach Codes Team performed energy simulations using software approved for 2022 Title 24 Code compliance analysis, CBECC 2022.2.0.

Using the 2022 baseline as the starting point, prospective energy efficiency measures were identified and modeled to determine the projected site energy (therm and kWh) and compliance impacts. Annual utility costs were calculated using hourly data output from CBECC, and electricity and natural gas tariffs for each of the investor -owned utilities (IOUs).

This analysis focused on residential apartments only (a prior study and report analyzed the cost-effectiveness of above code packages for nonresidential buildings (Statewide Reach Codes Team, 2022b). The Statewide Reach Codes Team selected measures for evaluation based on the single family 2022 reach code analysis (Statewide Reach Codes Team, 2022a) and the multifamily 2019 reach code analysis [ (Statewide Reach Codes Team, 2020), (Statewide Reach Codes Team, 2021)] as well as experience with and outreach to architects, builders, and engineers.

2.1.2 Cost-Effectiveness

2.1.2.1 Benefits
This analysis used two different metrics to assess the cost-effectiveness of the proposed upgrades. Both methodologies require estimating and quantifying the incremental costs and energy savings associated with each energy efficiency measure. The main difference between the methodologies is the manner in which they value energy and thus the cost savings of reduced or avoided energy use:

Utility Bill Impacts (On-Bill): This customer-based lifecycle cost (LCC) approach values energy based upon estimated site energy usage and customer utility bill savings using the latest electricity and natural gas utility tariffs available at the time of writing this report. Total savings are estimated over a 30-year duration and include discounting of future utility costs and energy cost inflation.

Time Dependent Valuation (TDV): This reflects the Energy Commission’s current LCC methodology, which is intended to capture the total value or cost of energy use over 30 years. This method accounts for long-term projected costs, such as the cost of providing energy during peak periods of demand, costs for carbon emissions, and grid transmission and distribution impacts. This metric values energy use differently depending on the fuel source (natural gas, electricity, and propane), time of day, and season. Electricity used (or saved) during peak periods has a much higher value than electricity used (or saved) during off-peak periods due to the less inefficient energy generation sources providing peak electricity (Horii, Cutter, Kapur, Arent, & Conotyannis, 2014). This is the methodology used by the Energy Commission in evaluating cost-effectiveness for efficiency measures in the 2022 Energy Code.

2.1.2.2 Costs
The Reach Codes Team assessed the incremental costs of the measures and packages over a 30-year lifecycle.

Incremental costs represent the equipment, installation, replacements, and maintenance costs of the proposed measure relative to the 2022 Energy Code minimum requirements or standard industry practices. Present value of replacement cost is included for measures with lifetimes less than the evaluation period.

2.1.2.3 Metrics
Cost-effectiveness is presented using net present value (NPV) and benefit-to-cost (B/C) ratio metrics.

NPV: The lifetime NPV is reported as a cost-effectiveness metric, Equation 1 demonstrates how this is calculated. If the NPV of a measure or package is positive, it is considered cost-effective. A negative values represent net costs.

Cost-Effectiveness Analysis: Multifamily New Construction Methodology and Assumptions
6 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

B/C Ratio: This is the ratio of the present value (PV) of all benefits to the present value of all costs over 30 years (PV benefits divided by PV costs). The criteria benchmark for cost-effectiveness is a B/C ratio greater than one. A value of one indicates the NPV of the savings over the life of the measure is equivalent to the NPV of the lifetime incremental cost of that measure. A value greater than one represents a positive return on investment. The B/C ratio is calculated according to Equation 2.

Equation 1
𝑁𝑁𝑁𝑁𝑁𝑁 = 𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑏𝑏𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙 − 𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑐𝑐𝑜𝑜𝑐𝑐𝑙𝑙 Equation 2
𝐵𝐵𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙 − 𝑙𝑙𝑜𝑜 − 𝐶𝐶𝑜𝑜𝑐𝑐𝑙𝑙 𝑅𝑅𝑅𝑅𝑙𝑙𝑙𝑙𝑜𝑜 = 𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑏𝑏𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙 𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑐𝑐𝑜𝑜𝑐𝑐𝑙𝑙
Improving the efficiency of a project often requires an initial incremental investment. In most cases the benefit is represented by annual On-Bill utility or TDV savings, and the cost is represented by incremental first cost and replacement costs. Some packages result in initial construction cost savings (negative incremental cost), and either energy cost savings (positive benefits), or increased energy costs (negative benefits). I n cases where both construction costs and energy-related savings are negative, the construction cost savings are treated as the ‘benefit’ while the increased energy costs are the ‘cost.’ In cases where a measure or package is cost-effective immediately (i.e., upfront construction cost savings and lifetime energy cost savings), B/C ratio cost-effectiveness is represented by “>1”.

The lifetime costs or benefits are calculated according to Equation 3.

Equation 3
𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑐𝑐𝑜𝑜𝑐𝑐𝑙𝑙 𝑜𝑜𝑜𝑜 𝑏𝑏𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙 = � (𝐴𝐴𝑏𝑏𝑏𝑏𝐴𝐴𝑅𝑅𝑙𝑙 𝑐𝑐𝑜𝑜𝑐𝑐𝑙𝑙 𝑜𝑜𝑜𝑜 𝑏𝑏𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙)𝑡𝑡 (1 + 𝑜𝑜)𝑡𝑡
𝑛𝑛
𝑡𝑡=0

Where:
• n = analysis term in years
• r = discount rate
The following summarizes the assumptions applied in this analysis to both methodologies. • Analysis term of 30 years
• Real discount rate of three percent
TDV is a normalized monetary format and there is a unique procedure for calculating the present value benefit of TDV energy savings. The present value of the energy cost savings in dollars is calculated by multiplying the TDV savings (reported by the CBECC simulation software) by a NPV factor developed by the Energy Commission (see E3’s 2022 TDV report for details (Energy + Environmental Economics, 2020)). The 30-year residential NPV factor is $0.173/kTDV for the 2022 Energy Code.

Equation 4
𝑇𝑇𝑇𝑇𝑁𝑁 𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑏𝑏𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑙𝑙𝑙𝑙 = 𝑇𝑇𝑇𝑇𝑁𝑁 𝑙𝑙𝑏𝑏𝑙𝑙𝑜𝑜𝑒𝑒𝑒𝑒 𝑐𝑐𝑅𝑅𝑠𝑠𝑙𝑙𝑏𝑏𝑒𝑒𝑐𝑐 ∗ 𝑁𝑁𝑁𝑁𝑁𝑁 𝑜𝑜𝑅𝑅𝑐𝑐𝑙𝑙𝑜𝑜𝑜𝑜

2.1.3 Utility Rates
In coordination with the CA IOU rate team (comprised of representatives from PG&E, SCE , SDG&E, SMUD, and CPAU), the Reach Codes Team determined appropriate utility rates for each climate zone in order to calculate utility costs and determine On-Bill cost-effectiveness for the proposed measures and packages. The utility tariffs, summarized in Table 1, were determined based on the most prevalent active rate in each territory. Utility rates were applied to each climate zone based on the predominant IOU serving the population of eac h zone, with a few climate zones evaluated multiple times under different utility scenarios. Climate Zones 10 and 14 were evaluated with both Cost-Effectiveness Analysis: Multifamily New Construction Methodology and Assumptions
7 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

SCE for electricity and Southern California Gas Company (SoCalGas) for gas and SDG&E tariffs for both electricity and gas since each utility has customers within these climate zones. Climate Zone 5 is evaluated under both PG&E and SoCalGas natural gas rates. Two POU or municipal utility rates were also evaluated: SMUD in Climate Zone 12 and CPAU in Climate Zone 4.

For the IOUs in-unit gas was evaluated under the G1 rate and central gas for water heating was evaluated under the relevant master metered gas tariff, GM. Electricity use for central water heating was evaluated using the residential TOU rates. The water heating utility bill was calculated separately from the in-unit electricity bill. Photovoltaic (PV) and battery energy storage benefits were applied according to virtual net energy metering (VNEM) rules.2 PV was first assigned to the central water heating meter to offset 100 percent of the electricity use. The remaining PV and all of the battery impacts were then split evenly across the apartment meters. The same approach was applied for CPAU and SMUD using the rates described in Table 1.

The multifamily prototypes used in this analysis include common area spaces that serve the residents (lobby, leasing office, corridors, etc.). Most of the energy use for these spaces could not be separated from that for the dwelling units within the CBECC model. As a result, average per dwelling unit hourly energy use was calculated to include both the dwelling unit and common space energy use.

First-year utility costs were calculated using hourly electricity and natural gas output from CBECC and applying the utility tariffs summarized in Table 1. Annual costs were also estimated for customers eligible for the CARE tariff discounts on both electricity and natural gas bills. The CARE tariff was only applied to the in-unit apartment meters.

Appendix 7.2 Utility Rate Schedules includes details of each utility tariff.

For cases with PV generation, the approved NEM 2.0 tariffs were applied along with minimum daily use billing and mandatory non-bypassable charges. In December the California Public Utilities Commission (CPUC) issued a decision adopting a net billing tariff (NBT) as a successor to NEM 2.0 that will go into effect April of 2023 3 Given the recent
timing of this decision there was not time to incorporate these changes into this analysis . The Reach Codes Team conducted a limited sensitivity analysis on the impacts of NBT relative to NEM 2.0 on utility bills. It was found that utility costs will increase for all homes with PV systems; however, the increase was less for an all-electric building compared to a mixed fuel building with a similarly sized PV system. As a result of better onsite utilization of PV generation and thus fewer exports to the grid, the Reach Codes Team expects the cost-effectiveness for the electrification scenarios for the all-electric home evaluated in this report to improve under NBT. Conversely, cost-effectiveness of increasing PV capacity is expected to be reduced under NBT.

2 PG&E: https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_SCHEDS_NEM2V.pdf SDG&E: https://tariff.sdge.com/tm2/pdf/tariffs/ELEC_ELEC-SCHEDS_NEM-V-ST.pdf SCE:
https://edisonintl.sharepoint.com/teams/Public/TM2/Shared%20Documents/Forms/AllItems.aspx?ga=1&id=%2Fteams %2FPublic%2FTM2%2FShared%20Documents%2FPublic%2FRegulatory%2FTariff%2DSCE%20Tariff%20Books%2F Electric%2FSchedules%2FOther%20Rates%2FELECTRIC%5FSCHEDULES%5FNEM%2DV%2DST%2Epdf&parent= %2Fteams%2FPublic%2FTM2%2FShared%20Documents%2FPublic%2FRegulatory%2FTariff%2DSCE%20Tariff%20 Books%2FElectric%2FSchedules%2FOther%20Rates
3 https://www.cpuc.ca.gov/nemrevisit
Cost-Effectiveness Analysis: Multifamily New Construction Methodology and Assumptions
8 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 1. Utility Tariffs Used Based on Climate Zone
Climate Zones Electric / Gas Utility Electricity Natural Gas IOUs
1-5,11-13,16 PG&E / PG&E E-TOU Option C G1 (in-unit) & GM (central water heating)1
5 PG&E / SoCalGas E-TOU Option C GM
6, 8-10, 14, 15 SCE / SoCalGas TOU-D Option 4-9 GM
7, 10, 14 SDG&E / SDG&E TOU-DR-1 GM
POUs
4 CPAU / CPAU E-1 (in-unit) & E-2 (central
water heating) G-2
12 SMUD / PG&E R-TOD, RT02 (in-unit) &
RSMM (central water heating) GM
1G1 rate applied to gas use within the apartment units, which only occurs in Climate Zones 1 and 16, see Section 3 for details. GM rate applied to gas use for central water heating.

Utility rates are assumed to escalate over time according to the assumptions from the CPUC 2021 En Banc hearings on utility costs through 2030 (California Public Utilities Commission, 2021a). Escalation rates through the remainder of the 30-year evaluation period are based on the escalation rate assumptions within the 2022 TDV factors. See Appendix 7.2.7 Fuel Escalation Assumptions for details.

2.2 2022 T24 Compliance Metrics
2022 Title 24, Part 6 Section 170.1 defines the energy budget of the building based on source energy and TDV energy for space-conditioning, indoor lighting, mechanical ventilation, PV and battery storage systems, service water heating and covered process loads. In 2022, the Energy Commission introduced the new compliance metric of source energy, which differs by fuel source (as does TDV) and is a reasonable proxy for greenhouse gas emissions. Additionally, for multifamily buildings four habitable stories and higher prescriptive requirements for PV and battery systems were also introduced. This led to the need to differentiate an efficiency compliance metric, which ensured that the building met minimum efficiency standards, and a total energy compliance metric which incorporated the PV and battery standards.

In order to be compliant with the building code a building needs to comply with all three compliance metrics described below:
• Efficiency TDV. Efficiency TDV accounts for all regulated end-uses but does not include the impacts of PV and battery storage.
• Total TDV. Total TDV includes regulated end-uses and accounts for PV and battery storage contributions. • Source Energy. Source energy is based on fuel used for power generation and distribution.

2.3 Greenhouse Gas Emissions
The analysis reports the greenhouse gas (GHG) emission estimates based on assumptions within CBECC. There are 8,760 hourly multipliers accounting for time dependent energy use and carbon based on source emissions, including renewable portfolio standard projections. There are two series of multipliers—one for Northern California climate zones, and another for Southern California climate zones. 4 GHG emissions are reported as average annual metric tons of CO2 equivalent over the 30-year building lifetime.

4 CBECC multipliers are the same for CZs 1-5 and 11-13 (Northern California), while there is another set of multipliers for CZs 6-10 and 14-16 (Southern California).

Cost-Effectiveness Analysis: Multifamily New Construction Prototypes, Measure Packages, and Costs
9 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

3 Prototypes, Measure Packages, and Costs
This section describes the prototypes, measures, costs, and the scope of analysis drawing from previous reach code research where appropriate.

3.1 Prototype Characteristics
The Energy Commission defines building prototypes which it uses to evaluate the cost-effectiveness of proposed changes to Title 24 requirements. There are 4 multifamily prototypes used in code development: a 2-story garden style, a 3-story loaded corridor, a 5-story mixed use and a 10-story mixed use. Based on work completed for the 2022 Title 24 code development, the 3-story and the 5-story represent 33 percent and 58 percent, respectively, of new multifamily construction in California. As a result, these two prototypes are used in this analysis. Additional details on all four prototypes can be found in the Multifamily Prototypes Report (TRC, 2019).

Table 2 describes the basic characteristics of each prototype.

Table 2. Prototype Characteristics
Characteristic 3-Story Loaded
Corridor 5-Story Mixed Use
Conditioned Floor Area 39,372 ft2
113,100 ft2 total:
33,660 ft2 nonresidential
79,440 ft2 residential
Num. of Stories 3
6 Stories total:
1 story parking garage (below grade)
1 story of nonresidential space
4 stories of residential space
Num. of Bedrooms
(6) Studio
(12) 1-bed
(12) 2-bed
(6) 3-bed
(8) studios
(40) 1-bed units
(32) 2-bed units
(8) 3-bed units
Window-to-Wall Area Ratio 25% 25%
Wall Type Wood framed Wood frame over a first-floor concrete podium
Roof Type Flat roof Flat roof
Foundation Slab-on-grade Concrete podium with underground parking

The methodology used in the analyses for each of the prototypical building types begins with a design that precisely meets the minimum 2022 prescriptive requirements.5 Table 170.2-A and 170.2-B in the 2022 Standards (California Energy Commission, 2022a) list the prescriptive measures that determine the baseline design in each climate zone.

Other features are designed to meet, but not exceed, the minimum requirements and are consistent with the Standard Design in the ACM Reference Manual (California Energy Commission, 2022c). The analysis also assumed electric resistance cooking in the apartment units to reflect current market data. The 3-story building prototype includes a central laundry facility, and the 5-story assumes laundry in the units. Laundry equipment was assumed to be electric in all cases; electrification of laundry equipment was not addressed in this study. The nonresidential 2022 reach code analysis (Statewide Reach Codes Team, 2022b) did consider electrification of central laundry facilities within the small hotel prototype.

Table 3 describes characteristics as they were applied to the base case energy model in this analysis. In a shift from the 2019 Standards, the 2022 Standards define a prescriptive fuel source for space heating establishing an electric

5Due to planned software updates to how the prescriptive requirements are applied in the Standard Design and challenges for certain space types with sizing heating and cooling equipment the same in the Proposed Design as in the Standards, the results compliance margins for the base case models were not exactly zero percent..

Cost-Effectiveness Analysis: Multifamily New Construction Prototypes, Measure Packages, and Costs
10 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

heat pump baseline in all climate zones except 16 for multifamily buildings three habitable stories and fewer and 1 and 16 for multifamily buildings four habitable stories and greater.

Table 3. Base Case Characteristics of the Prototypes
Characteristic 3-Story Loaded Corridor 5-story Mixed Use Space
Heating/Cooling1
Individual split systems with ducts in
conditioned space
CZ 1-15: Heat pump
CZ 16: Natural gas furnace with air
conditioner
Individual split systems with ducts in
conditioned space
CZ2-15: Heat pump
CZ1, 16: Dual-fuel heat pump with
natural gas backup
Ventilation Individual balanced fans, continuously
operating
Individual balanced fans, continuously
operating
Water Heater1
Natural gas central boiler with solar
thermal sized to meet the prescriptive
requirements by climate zone.

Natural gas central boiler with solar
thermal sized to meet the prescriptive
requirements by climate zone.

Hot Water
Distribution Central recirculation Central recirculation Cooking Electric Electric
Clothes Drying Electric (central) Electric (in-unit)
PV System
Sized according to the prescriptive
requirements in Equation 170.2-C of the
2022 Title 24 Standards. Size differs by
climate zone ranging from 1.60 kW to

2.90 kW per dwelling unit, see Table 4.

Sized according to the prescriptive
requirements in Equation 170.2-D of the
2022 Title 24 Standards. Size differs by
climate zone ranging from 2.26 kW to

3.34 kW per dwelling unit, see Table 4.

Battery System None None
1 Equipment efficiencies are equal to minimum federal appliance efficiency standards.

Table 4 summarizes the PV capacities for the base case packages.

Table 4. Base Package PV Capacities (kW-DC)
Climate
Zone
Base Package
3-Story 5-Story
CZ01 2.00 2.26
CZ02 1.79 2.68
CZ03 1.70 2.26
CZ04 1.75 2.68
CZ05 1.60 2.26
CZ06 1.77 2.68
CZ07 1.67 2.68
CZ08 1.91 2.68
CZ09 1.92 2.68
CZ10 1.98 2.68
CZ11 2.21 2.68
CZ12 1.96 2.68
CZ13 2.33 2.68
CZ14 1.94 2.68
CZ15 2.90 3.34
CZ16 1.76 2.26
Cost-Effectiveness Analysis: Multifamily New Construction Prototypes, Measure Packages, and Costs
11 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

3.2 Measure Definitions and Costs
Measures evaluated in this study fall into two categories: those associated with general efficiency, onsite generation, and demand flexibility and those associated with building electrification. The Reach Codes Team selected measures based on cost-effectiveness as well as decades of experience with residential architects, builders, and engineers along with general knowledge of the relative consumer acceptance of many measures. This analysis focused on measures that impacted the residential dwelling units only.

The following sections describe the details and incremental cost assumptions for each of the measures. Incremental costs represent the equipment, installation, replacement, and maintenance costs of the proposed measures relative to the base case. Replacement costs are applied for roofs, mechanical equipment , PV inverters and battery systems over the 30-year evaluation period. Incremental maintenance costs are estimated for PV systems, but not any other measures. Costs were estimated to reflect costs to the building owner. All costs are provided as present value in 2023 (2023 PV$).

The Reach Codes Team obtained measure costs from distributors, contractors, literature review, and online sources such as Home Depot and RS Means. Contractor markups are incorporated. These are the Reach Codes Team best estimate of average costs statewide. Regional variation in costs is not accounted for, although it's recognized that local costs may differ. Cost increases due to recent high inflation rates and supply chain delays are not included.

3.2.1 Efficiency, Solar PV, and Batteries
The following are descriptions of each of the efficiency, PV, and battery measures evaluated under this analysis and applied in at least one of the packages presented in this report. Table 5 summarizes the incremental cost assumptions for each of these measures. These measures were evaluated for all climate zones but were ultimately adopted in a subset of climate zones based on cost-effectiveness outcomes.

Lower U-Factor Fenestration: Reduce window U-factor to 0.24. The prescriptive U-factor is 0.30 in all climate zones except Climate Zones 7 and 8 where it is 0.34. This measure is included in Climate Zone 16 only.

Cool Roof: Install a roofing product that’s rated by the Cool Roof Rating Council to have an aged solar reflect ance (ASR) equal to or greater than 0.70. Low-sloped roofs were assumed in all cases. The 2022 Title 24 specifies a prescriptive ASR of 0.63 for Climate Zones 9 through 11 and 13 through 15. This measure is included in Climate Zones 9 through 15.

Low Pressure Drop Ducts: Upgrade the duct distribution system to reduce external static pressure and meet a maximum fan efficacy of 0.35 Watts per cfm. This may involve upsizing ductwork, reducing the total effective length of ducts, and/or selecting low pressure drop components such as filters. Fan watt draw must be verified by a HERS rater according to the procedures outlined in the 2022 Reference Appendices RA3.3 (California Energy Commission, 2022b). This measure is included in Climate Zones 1 and 10 through 16.

Verified Low Leakage Ducts in Conditioned Space: Seal the ducts to achieve a measured leakage no greater than 25 cfm leakage to outside. This may be verified using a guarded blower door test to isolate leakage to outside.

Alternatively, this can also be satisfied by demonstrating that total leakage is not greater than 25 cfm. Ducts are assumed to already be located in conditioned space in the baseline. This measure is included in all climate zones.

Solar PV: Installation of on-site PV is required in the 2022 residential code unless an exception is met. The PV sizing methodology in each package was developed to offset annual building electricity use and avoid oversizing which would violate net energy metering (NEM) rules.6 In all cases, PV is evaluated in CBECC according to the California Flexible Installation (CFI) assumptions. This measure is included in all climate zones.

Battery Energy Storage: A battery system was evaluated in CBECC-Res with control type set to “Time-of-Use” and with default efficiencies of 95% for both charging and discharging. This control option assumes the battery system will

6 NEM rules apply to the IOU territories only.

Cost-Effectiveness Analysis: Multifamily New Construction Prototypes, Measure Packages, and Costs
12 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

charge or discharge based on a utility tariff time-of use signal. To qualify, the battery system must meet the requirements outlined in the 2022 Reference Appendices JA12.2.3.2 (California Energy Commission, 2022b). This measure is included in all climate zones but only for the 3-story prototype. A 100kWh battery was applied following the battery sizing requirements for multifamily buildings more than three habitable stories per Equation 170.2- E of the 2022 Energy Code.

Cost-Effectiveness Analysis: Multifamily New Construction Prototypes, Measure Packages, and Costs
13 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 5. Incremental Cost Assumptions
Measure
Performance
Level
Incremental Cost per
Dwelling Unit
(2023 PV$)
Source & Notes 3-Story 5-Story
Non-Preempted Measures
Window U-factor 0.24 vs 0.30 $536 $489 $4.23/ft2 of window area based on analysis conducted for the 2019 and 2022 Title 24 cycles (Statewide CASE Team, 2018).

Low-Sloped Cool
Roof Aged Solar
Reflectance

0.63 vs 0.10 $314 $222
$0.525/ft2 of roof area first incremental cost based on the 2022 Residential Additions and Alterations CASE Report (Statewide CASE Team, 2020b).Total costs assume present value of replacement at year 15.

0.70 vs 0.63 $24 $17
$0.04/ft2 of roof area first incremental cost based on the 2022 Nonresidential High Performance Envelope CASE Report (Statewide CASE Team, 2020a). Costs assume a blended average across roofing product types. Total costs assume present value of replacement at year 15.

Low Pressure
Drop Ducts

0.35 vs 0.45
W/cfm $44 $44
Costs assume half-hour labor per multifamily dwelling unit. Labor rate of $88 per hour is from 2022 RS Means for sheet metal workers and includes a weighted average City Cost Index for labor for California.

Verified Low
Leakage Ducts in
Conditioned
Space
≤25 cfm leakage
to outside $132 $132
Costs assume half-hour labor per multifamily dwelling unit and a $100 HERS Rater fee.

Labor rate of $88 per hour is from 2022 RS Means for sheet metal workers and includes a weighted average City Cost Index for labor for California. Ducts are already assumed to be located in conditioned space and the incremental costs reflect additional sealing and testing only.

PV + Battery
PV System
First Cost $1.47/W $1.47/W
First costs from LBNL’s Tracking the Sun 2022 costs (Barbose, Darghouth, O'Shaughnessy, & Forrester, 2022) and represent median costs in California in 2021 of $2.10/WDC for nonresidential greater than 100kWDC systems. The first cost was reduced by the solar energy Investment Tax Credit (ITC) of 30%.1 Costs are presented as the average of 2023, 2024, and 2025.

Inverter replacement cost of $0.14/WDC present value includes replacements at year 11 at $0.15/WDC (nominal) and at year 21 at $0.12/WDC (nominal) per the 2019 PV CASE Report (California Energy Commission, 2017).

System maintenance costs of $0.31/WDC present value assume $0.02/WDC (nominal) annually per the 2019 PV CASE Report (California Energy Commission, 2017).

Inverter
replacement $0.14/W $0.14/W
Maintenance $0.31/W $0.31/W
Cost-Effectiveness Analysis: Multifamily New Construction Prototypes, Measure Packages, and Costs
14 localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Measure
Performance
Level
Incremental Cost per
Dwelling Unit
(2023 PV$)
Source & Notes 3-Story 5-Story
Battery
First cost $700/kWh n/a
First cost of $1,000/kWh from LBNL’s Tracking the Sun 2022 costs (Barbose, Darghouth, O'Shaughnessy, & Forrester, 2022) for residential systems > 30kWh. The report derived costs from California’s Self-Generation Incentive Program (SGIP) residential participant cost data. First cost is reduced by the solar energy ITC of 30%.1 No SGIP incentives are included.

Costs are assumed to remain consistent at $1,000/kWh through 2025 and then reduced by 7% annually based on SDG&E’s Behind-the-Meter Battery Market Study (E-Source companies, 2020) over a 10 year period. Replacement is assumed at years 10 and 20. At year 10 the replacement cost is based on the average of expected 2033, 2034, and 2035 costs after applying the ITC for a future value cost of $435. Replacement cost at year 20 is based on a future value cost of $484 and does not include any ITC reduction.

Replacement
cost $564/kWh n/a
1As part of the Inflation Reduction Act in August 2022 the Section 25D Investment Tax Credit was extended and raised to 30% through 2032 with a step-down to 26% in 2033 and 22% in 2034. It’s assumed that the ITC is not renewed and is 0% starting in 2035. https://www.irs.gov/pub/taxpros/fs-2022-40.pdf.

Cost-Effectiveness Analysis: Single Family New Construction 15 Prototypes, Measure Packages, and Costs

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

3.2.2 All-Electric
This analysis compared a code compliant mixed fuel prototype, which uses natural gas for water heating only in most climate zones, with a code compliant all-electric prototype. In these cases, the relative costs between natural gas and electric appliances and natural gas infrastructure and the associated infrastructure costs for not providing natural gas to the building were included.

To estimate costs the Reach Codes Team leveraged costs from the 2022 Multifamily All -Electric CASE Report (Statewide CASE Team, 2020c) and the 2019 reach code multifamily cost-effectiveness studies ( (Statewide Reach Codes Team, 2020), (Statewide Reach Codes Team, 2021)), and online equipment research. Present value replacement costs are included in the total lifetime incremental costs.

3.2.2.1 Water Heating
Federal regulations establish minimum efficiency requirements for heat pump water heaters with rated storage volume less than 120 gallons. While some heat pump water heaters falling into this regulated category can be used in a central water heater design, they are not required and therefore this measure does not trigger federal preemption and heat pump equipment of any efficiency level may be used for this analysis to justify the basis of a reach code .

For the central heat pump water heating system in the 3-story prototype the system design was based on the 2022 All- Electric Multifamily CASE Report (Statewide CASE Team, 2020c) and used CO2 refrigerant based heat pump water heaters (four Sanden GS3-45HPA-US units), 525 gallons of storage, and a 250 gallon electric resistance swing tank.

The 2022 CASE work based the 5-story system design on Colmac R-134a refrigerant heat pump water heaters. While this is an acceptable design, R-134a or R-410a refrigerant heat pump water heaters were found to be less cost- effective for the prototypes evaluated in this analysis due to higher incremental costs and lower overall performance relative to CO2 refrigerant products. As such, the Reach Codes Team evaluated a CO2 refrigerant system for the 5- story prototype for this analysis. As part of the 2025 Energy Code update cycle, designs for both multifamily prototypes are being reexamined using CO2 refrigerant heat pump water heaters. While full design and cost information was not yet available for this analysis, preliminary design data was used to inform sizing of a Sanden system for this prototype.

The system used 10 heat pump water heaters (Sanden GS3-45HPA-US units), 800 gallons of storage, and a 200 gallon electric resistance swing tank.

Table 6 reports costs for the central heat pump water heating systems relative to a gas boiler system with solar thermal that meets the prescriptive requirements of 20% solar fraction in Climate Zones 1 through 9 and 35% solar fraction in Climate Zones 10 through 16. Costs include equipment and labor, gas piping within the building for the boiler system, and additional electrical service necessary for the heat pump system. Replacement costs are based on an effective useful life of 15 years for the water heaters and tanks, and 20 years for the solar thermal collectors. For the solar thermal systems, it’s also assumed that the glycol is replaced at years 9, 18 and 27. Additional details on cost assumptions are presented in Appendix 7.3 Cost Details.

Cost-Effectiveness Analysis: Single Family New Construction 16 Prototypes, Measure Packages, and Costs

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 6. Heat Pump Water Heater Incremental System Costs (Present Value (2023$)) Item
3-Story 5-Story
Source & Notes Central
Gas
Boiler
Central
Heat
Pump
Central
Gas
Boiler
Central
Heat
Pump
First Cost CZs 1-9 $173,772
$211,531
$279,163
$343,920
3-story costs directly from 2022
Multifamily All-Electric CASE
Report. 5-story costs estimated
based on component costs for
the 3-story from the CASE
report.

CZs 10-16 $182,810 $300,883
Replacement Cost CZs 1-9 $32,297
$44,263
$59,930
$110,659
CZs 10-16 $36,943 $69,361
Total Incremental
Cost
CZs 1-9
n/a
$49,725
n/a
$115,486
CZs 10-16 $36,041 $84,335
Incremental Cost
per Dwelling Unit
CZs 1-9 $1,381 $1,312
CZs 10-16 $1,001 $958

3.2.2.2 Space Heating
Table 7 presents the costs for heat pump space heater conversion from gas equipment. In most climate zones the baseline per the 2022 Energy Code is a heat pump space heater, so these costs are only applied in a couple of instances. For the 3-story prototype the baseline in Climate Zone 16 is a gas furnace and air conditioner. For the 5- story prototype the baseline in Climate Zones 1 and 16 is a dual fuel heat pump with a gas furnace as backup. Costs include equipment and labor, gas piping within the building for the boiler system, and additional electrical service necessary for the heat pump system. Most of the cost difference between the two systems is attributed to higher labor costs to install the gas system as a result of gas piping and venting. Additional details on cost assumptions are presented in Appendix 7.3 Cost Details.

Table 7. Heat Pump Space Heater Costs per Dwelling Unit (Present Value (2023$) Item
3-Story 5-Story
Source & Notes Furnace +
Split AC
Heat
Pump
Furnace +
Split HP
Heat
Pump
First Cost
$20,667 $16,776 $21,245 $16,597
Costs largely based on the 2022
Multifamily All-Electric CASE Report with
some updates to reflect online equipment
cost research and labor cost alignments.

Replacement Cost $8,059 $7,326 $9,052 $7,326 See lifetimes referenced in Table 8.

Residual value at the end of the 30-year
analysis period was accounted for to
represent the remaining life of any
equipment.

Residual Value ($1,591) $0 $0 $0
Total $27,135 $24,102 $30,296 $23,924
Incremental Cost ($3,032) ($6,373)

Equipment lifetimes applied in this analysis for the space conditioning measures are summarized in Table 8. The lifetime for the heat pump, furnace, and air conditioner are based on the Database for Energy Efficient Resources (DEER) (California Public Utilities Commission, 2021b). In DEER, heat pump and air conditioner measures are assigned an effective useful lifetime (EUL) of 15 years and a furnace an EUL of 20 years. The heating and cooling system components are typically replaced at the same time when one reaches the end of its life and the other is near Cost-Effectiveness Analysis: Single Family New Construction 17 Prototypes, Measure Packages, and Costs

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

it. Therefore, it is assumed that both the furnace and air conditioner are replaced at the same time at year 17.5, halfway between 15 and 20 years. For HVAC system costing, air-conditioning is included in all cases in both the base case and proposed models.

Table 8. Lifetime of Water Heating & Space Conditioning Equipment Measures Measure Lifetime
Gas Furnace 17.5
Air Conditioner 17.5
Heat Pump 15
Dual Fuel Heat Pump 15

3.2.2.3 Natural Gas Infrastructure
Eliminating natural gas to a building saves costs associated with connecting a service line from the street main to the building, piping distribution within the building, and monthly meter customer charges from the utility. This section focuses on the first item, not connecting gas service to the building. The latter two are captured in the appliance costs and the utility bill analysis. Cost savings for removing natural gas infrastructure to a multifamily building in IOU territory are presented in Table 9 and Table 10. These costs are applied as cost savings for the all-electric case when compared to the mixed fuel baseline.

These costs are project dependent and may be significantly impacted by such factors as utility territory, site characteristics, distance to the nearest natural gas main and main location, joint trenching, whether work is conducted by the utility or a private contractor, and number of dwelling units per development. All gas utilities participating in this study were solicited for cost information.

Service Extension: Service extension costs to the building were taken from a PG&E memo dated December 5, 2019 to Energy Commission staff (see Appendix 7.4 PG&E Gas Infrastructure Cost Memo for a copy of the memo). The estimated cost of $6,750 excludes costs for trenching and assumes nonresidential new construction within a developed area. For the 5-story building the cost is apportioned between the residential and nonresidential spaces in the building based on associated conditioned floor areas where 84 percent is residential. All of the spaces in the 3-story building are residential based.

Today, total costs are reduced to account for deductions per the Utility Gas Main Extensions rules. 7 These rules categorize distribution line extensions as “refundable” costs, which are offset or subsidized by all other ratepayers. The CPUC issued a Decision in September 2022 that eliminates the subsidies effective July 1, 2023 (California Public Utilities Commission, 2022). Since most of the development that will occur during the three-year 2022 code cycle (2023-2025) will not be subject to these deduction allowances they are not included in this analysis.

Meter: Cost per meter provided by PG&E of $3,600 for a commercial meter to serve the central water heating and $600 per multifamily dwelling unit. The $600 dwelling unit meter is only applied in Climate Zone 16 for the 3-story prototype and Climate Zones 1 and 16 for the 5-story prototypes where gas is used either for primary or backup space heating. Two scenarios are presented in the tables. One is the case with electric space heating, no in- unit gas and the only residential gas use is to serve the central water heating system. The other case represents the scenario where there is in-unit gas to service space heating.

7 PG&E Rule 15: https://www.pge.com/tariffs/assets/pdf/tariffbook/GAS_RULES_15.pdf.

SoCalGas Rule 20: https://www.socalgas.com/regulatory/tariffs/tm2/pdf/20.pdf.

SDG&E Rule 15: https://tariff.sdge.com/tm2/pdf/GAS_GAS-RULES_GRULE15.pdf.

Cost-Effectiveness Analysis: Single Family New Construction 18 Prototypes, Measure Packages, and Costs

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Natural Gas Plan Review: Total costs are based on TRC’s 2019 reach code analysis for Palo Alto (TRC, 2018 ) . The cost for the 5-story prototype is apportioned between the residential and nonresidential spaces in the building in the same way as was done for the service extension costs.

Table 9. IOU Natural Gas Infrastructure Cost Savings for All-Electric Building Item 3-Story 5-Story
Service Extension $6,750 $5,695
Meter
No In-Unit Gas
(Gas DHW only) $3,600 $3,600
In-Unit Gas $25,200 $56,400
Plan Review $2,316 $1,954
Table 10. Multifamily IOU Total Natural Gas Infrastructure Costs Prototype Scenario Total
Building
Per Dwelling
Unit
3-Story No In-Unit Gas $12,666 $352
In-Unit Gas $34,266 $952
5-Story No In-Unit Gas $11,248 $128
In-Unit Gas $64,048 $728

CPAU provides gas service to its customers and therefore separate costs were evaluated based on CPAU gas service connection fees.8 Table 11 presents the breakdown of gas infrastructure costs used in this analysis for CPAU. The same approach to apportioning the total building costs to the residential spaces as described in the IOU section was applied here for the service extension and plan review costs for the 5-story prototype. Meter costs were based on $1,772 for an 800 cubic foot per hour commercial meter for the central water heating system.

Table 11. Multifamily CPAU Total Natural Gas Infrastructure Costs Item 3-Story 5-Story
Service Extension $5,892 $4,971
Meter $1,772 $1,772
Plan Review $2,557 $2,157

3.3 Measure Packages
The Reach Codes Team evaluated three packages for mixed fuel homes and five packages for all-electric homes for each prototype and climate zone, as described below.

1. All-Electric Prescriptive Code: This package meets all the prescriptive requirements of the 2022 Energy Code.

2. All-Electric Prescriptive Code + PV: Using the code minimum package as a starting point, PV capacity was added to offset 100 percent of the estimated annual electricity use.

3. Mixed Fuel Efficiency Only: This package uses only efficiency measures that do not trigger federal preemption including envelope and duct distribution efficiency measures.

8 CPAU Schedule G-5 effective 09-01-2019: https://www.cityofpaloalto.org/files/assets/public/utilities/utilities- engineering/general-specifications/gas-service-connection-fees.pdf Cost-Effectiveness Analysis: Single Family New Construction 19 Prototypes, Measure Packages, and Costs

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

4. Mixed Fuel Efficiency + PV + Battery: Using the Efficiency Package as a starting point, PV capacity was added to offset 100 percent of the estimated annual electricity use. A battery system was also added. This package only applies to the 3-story prototype. The 5-story prototype includes a battery system in the baseline per the 2022 prescriptive requirements.

5. Mixed Fuel Efficiency + PV: Using the Efficiency Package as a starting point, PV capacity was added to offset 100 percent of the estimated annual electricity use. This package only applies to the 5-story prototype.

Cost-Effectiveness Analysis: Single Family New Construction 20 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

4 Results
Cost-effectiveness results are presented per prototype and measure packages described in Section 3.3. The TDV and On-Bill based cost-effectiveness results are presented in terms of B/C ratio and NPV. Energy savings, compliance margin, utility bill savings, and incremental costs are also shown.

In the following figures, green highlighting indicates that the case is cost-effective with a B/C ratio greater than or equal to 1 and a NPV greater than or equal to 0. Red highlighting indicates the case is not cost-effective.

Compliance margins are presented as percentages both for the efficiency TDV and the source energy metrics. A compliance margin that is equal to or greater than 0 indicates the case is code compliant.

4.1 All-Electric Prescriptive Code
Table 12 and Table 13 shows results for the multifamily all-electric prescriptive code case compared to the 2022 baseline. For both prototypes this scenario is cost-effective based on TDV in all climate zones. This scenario is only On-Bill cost-effective in a few climate zones. The 3-story all-electric case is cost-effective On-Bill in Climate Zones 1 through 3, 4 in CPAU territory, 12 in SMUD territory, and 16. The 5-story all-electric case is cost-effective On-Bill in Climate Zones 1, 4, 12 in SMUD territory, and 16.

In most cases there is a small net increase in utility cost in the first year.

There is an incremental cost for the central heat pump water heater ranging from $361 to $697 per dwelling unit.

The all-electric packages applied to the 3-story prototype in Climate Zone 16 and the 5-story prototype in Climate Zones 1 and 16 incorporate both gas to electric water heating and gas to electric space heating measures. In these cases, there are significant cost savings due to the avoided first costs of installing a gas furnace as compared to a heat pump. As a result, these cases are On-Bill cost-effective.

These results reflect a CO
2 refrigerant based central heat pump water heating system. The 5-story prototype was also evaluated with a R-134a refrigerant based central heat pump water heater and these results are shown in Appendix

7.5 Central Heat Pump Water Heater Comparison.

Cost-Effectiveness Analysis: Single Family New Construction 21 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 12. 3-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric Prescriptive Code

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 26% 15% -904 135 ($19) $1,676 $97 $429 3.9 $1,247 >1 $4,158 CZ02 PGE 20% 11% -801 115 ($30) $1,061 $697 $1,029 1.0 $32 9.9 $2,998 CZ03 PGE 21% 10% -789 115 ($26) $1,148 $697 $1,029 1.1 $119 9.9 $2,990 CZ04 PGE 18% 9% -759 109 ($31) $922 $697 $1,029 0.9 ($108) 9.2 $2,767 CZ04 CPAU 18% 9% -759 109 $233 $8,191 $765 $1,097 7.5 $7,094 7.7 $2,700 CZ05 PGE 23% 9% -789 112 ($30) $1,009 $697 $1,029 0.98 ($21) 9.3 $2,782 CZ05 PGE/SCG 23% 9% -789 112 ($79) ($515) $697 $1,029 0.0 ($1,545) 9.3 $2,782 CZ06 SCE/SCG 18% 7% -709 100 ($61) ($226) $697 $1,029 0.0 ($1,255) 8.6 $2,551 CZ07 SDGE 20% 8% -704 102 ($69) ($427) $697 $1,029 0.0 ($1,456) 9.1 $2,712 CZ08 SCE/SCG 13% 6% -689 96 ($61) ($302) $697 $1,029 0.0 ($1,331) 8.2 $2,432 CZ09 SCE 13% 5% -698 96 ($64) ($351) $697 $1,029 0.0 ($1,380) 8.0 $2,363 CZ10 SCE/SCG 14% 7% -701 83 ($88) ($1,109) $446 $649 0.0 ($1,758) >1 $1,959 CZ10 SDGE 14% 7% -701 83 ($112) ($1,803) $446 $649 0.0 ($2,452) >1 $1,959 CZ11 PGE 14% 10% -740 91 ($64) ($177) $446 $649 0.0 ($826) >1 $2,212 CZ12 PGE 17% 11% -755 94 ($62) ($70) $446 $649 0.0 ($719) >1 $2,297 CZ12 SMUD/PGE 17% 11% -755 94 $68 $2,942 $446 $649 4.5 $2,293 >1 $2,297 CZ13 PGE 13% 9% -717 86 ($65) ($291) $446 $649 0.0 ($940) >1 $2,050 CZ14 SCE/SCG 13% 7% -748 83 ($102) ($1,413) $446 $649 0.0 ($2,063) >1 $1,759 CZ14 SDGE 13% 7% -748 83 ($128) ($2,191) $446 $649 0.0 ($2,841) >1 $1,759 CZ15 SCE/SCG 5% 2% -607 64 ($89) ($1,403) $446 $649 0.0 ($2,053) >1 $1,305 CZ16 PG&E 24% 29% -1,928 185 ($178) ($1,066) ($4,045) ($2,983) 2.8 $1,917 >1 $4,352 Cost-Effectiveness Analysis: Single Family New Construction 22 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 13. 5-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric Prescriptive Code

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 14% 9% -1,146 147 ($49) $1,209 ($4,639) ($5,788) >1 $6,998 >1 $9,816 CZ02 PGE 9% 6% -888 120 ($45) $809 $608 $1,185 0.7 ($375) 3.0 $2,270 CZ03 PGE 11% 7% -874 120 ($46) $778 $608 $1,185 0.7 ($407) 3.1 $2,421 CZ04 PGE 9% 6% -824 113 $18 $2,130 $608 $1,185 1.8 $945 3.1 $2,393 CZ04 CPAU 9% 6% -824 113 $230 $8,205 $635 $1,211 6.8 $6,994 3.0 $2,367 CZ05 PGE 12% 6% -871 117 ($47) $706 $608 $1,185 0.6 ($479) 2.8 $2,065 CZ05 PGE/SCG 12% 6% -871 117 ($99) ($919) $608 $1,185 0.0 ($2,103) 2.8 $2,065 CZ06 SCE/SCG 9% 5% -739 104 ($10) $986 $608 $1,185 0.8 ($199) 2.9 $2,183 CZ07 SDGE 11% 6% -735 106 ($74) ($500) $608 $1,185 0.0 ($1,685) 2.9 $2,215 CZ08 SCE/SCG 8% 4% -710 100 ($79) ($644) $608 $1,185 0.0 ($1,829) 3.0 $2,259 CZ09 SCE 7% 4% -725 100 ($53) ($51) $608 $1,185 0.0 ($1,236) 3.0 $2,274 CZ10 SCE/SCG 7% 4% -729 84 ($111) ($1,615) $361 $831 0.0 ($2,445) 2.7 $1,374 CZ10 SDGE 7% 4% -729 84 ($137) ($2,404) $361 $831 0.0 ($3,234) 2.7 $1,374 CZ11 PGE 8% 5% -790 92 ($86) ($663) $361 $831 0.0 ($1,494) 3.1 $1,656 CZ12 PGE 9% 6% -809 96 ($83) ($527) $361 $831 0.0 ($1,358) 3.0 $1,620 CZ12 SMUD/PGE 9% 6% -809 96 $62 $2,831 $361 $831 3.4 $2,000 3.0 $1,620 CZ13 PGE 7% 5% -754 88 ($83) ($686) $361 $831 0.0 ($1,517) 3.0 $1,570 CZ14 SCE/SCG 6% 3% -803 84 ($131) ($2,085) $361 $831 0.0 ($2,916) 2.2 $928 CZ14 SDGE 6% 3% -803 84 ($165) ($3,106) $361 $831 0.0 ($3,937) 2.2 $928 CZ15 SCE/SCG 3% 1% -602 65 ($105) ($1,775) $361 $831 0.0 ($2,606) 1.9 $695 CZ16 PG&E 9% 11% -1,388 142 ($127) ($675) ($4,886) ($6,142) 9.1 $5,467 >1 $6,704 Cost-Effectiveness Analysis: Single Family New Construction 23 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

4.2 All-Electric Plus PV
Table 14 and Table 15 present cost-effectiveness results for the all-electric plus PV packages for the 3-story and 5-story prototypes, respectively. All cases are cost-effective both On-Bill and based on TDV.

Table 14. 3-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric 100% PV

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 26% 24% 2,127 135 $782 $20,242 $3,638 $5,034 4.0 $15,208 3.2 $9,448 CZ02 PGE 20% 20% 1,835 115 $653 $16,910 $3,294 $4,406 3.8 $12,504 3.3 $8,632 CZ03 PGE 21% 20% 1,711 115 $614 $15,998 $3,076 $4,123 3.9 $11,875 3.4 $8,209 CZ04 PGE 18% 18% 1,558 109 $559 $14,587 $2,841 $3,818 3.8 $10,770 3.6 $8,230 CZ04 CPAU 18% 18% 1,558 109 $489 $14,138 $2,909 $3,886 3.6 $10,253 3.6 $8,162 CZ05 PGE 23% 20% 1,604 112 $579 $15,137 $2,826 $3,798 4.0 $11,338 3.6 $8,026 CZ05 PGE/SCG 23% 20% 1,604 112 $531 $13,613 $2,826 $3,798 3.6 $9,814 3.6 $8,026 CZ06 SCE/SCG 18% 17% 1,207 100 $378 $9,795 $2,364 $3,197 3.1 $6,598 3.8 $7,092 CZ07 SDGE 20% 21% 1,528 102 $723 $19,318 $2,777 $3,734 5.2 $15,584 3.5 $7,623 CZ08 SCE/SCG 13% 17% 1,393 96 $426 $10,842 $2,569 $3,464 3.1 $7,378 3.9 $7,908 CZ09 SCE 13% 15% 1,204 96 $379 $9,756 $2,335 $3,160 3.1 $6,596 3.9 $7,158 CZ10 SCE/SCG 14% 18% 1,381 83 $404 $10,130 $2,237 $2,978 3.4 $7,152 4.1 $7,031 CZ10 SDGE 14% 18% 1,381 83 $621 $16,493 $2,237 $2,978 5.5 $13,514 4.1 $7,031 CZ11 PGE 14% 19% 1,843 91 $625 $15,782 $2,940 $3,893 4.1 $11,889 3.4 $7,748 CZ12 PGE 17% 19% 1,704 94 $579 $14,777 $2,756 $3,654 4.0 $11,124 3.6 $7,607 CZ12 SMUD/PGE 17% 19% 1,704 94 $399 $10,615 $2,756 $3,654 2.9 $6,961 3.6 $7,607 CZ13 PGE 13% 17% 1,572 86 $544 $13,822 $2,567 $3,408 4.1 $10,415 3.6 $7,148 CZ14 SCE/SCG 13% 18% 1,572 83 $449 $11,152 $2,300 $3,060 3.6 $8,092 4.2 $7,668 CZ14 SDGE 13% 18% 1,572 83 $688 $18,158 $2,300 $3,060 5.9 $15,098 4.2 $7,668 CZ15 SCE/SCG 5% 11% 1,163 64 $330 $8,164 $1,966 $2,626 3.1 $5,539 3.9 $5,567 CZ16 PG&E 24% 38% 1,371 185 $700 $19,307 ($1,064) $894 21.6 $18,412 58.9 $11,596 Cost-Effectiveness Analysis: Single Family New Construction 24 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 15. 5-Story Cost-Effectiveness Results per Dwelling Unit: All-Electric 100% PV

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 14% 21% 1,437 147 $629 $16,919 ($1,574) ($1,803) >1 $18,721 >1 $18,222 CZ02 PGE 9% 14% 428 120 $262 $7,918 $1,930 $2,904 2.7 $5,015 4.0 $8,679 CZ03 PGE 11% 16% 682 120 $327 $9,417 $2,121 $3,152 3.0 $6,265 4.0 $9,285 CZ04 PGE 9% 13% 92 113 $207 $6,524 $1,476 $2,313 2.8 $4,211 4.1 $7,054 CZ04 CPAU 9% 13% 92 113 $337 $10,667 $1,502 $2,340 4.6 $8,327 4.0 $7,027 CZ05 PGE 12% 16% 451 117 $259 $7,806 $1,815 $2,754 2.8 $5,052 4.0 $8,096 CZ05 PGE/SCG 12% 16% 451 117 $207 $6,182 $1,815 $2,754 2.2 $3,427 4.0 $8,096 CZ06 SCE/SCG 9% 12% -163 104 $98 $3,449 $1,127 $1,859 1.9 $1,590 3.8 $5,035 CZ07 SDGE 11% 15% 74 106 $192 $6,131 $1,387 $2,198 2.8 $3,934 3.9 $6,204 CZ08 SCE/SCG 8% 14% 265 100 $154 $4,666 $1,516 $2,365 2.0 $2,301 4.0 $7,053 CZ09 SCE 7% 12% 60 100 $122 $3,930 $1,307 $2,093 1.9 $1,837 3.7 $5,636 CZ10 SCE/SCG 7% 13% 289 84 $131 $3,912 $1,266 $2,007 1.9 $1,905 3.9 $5,749 CZ10 SDGE 7% 13% 289 84 $238 $6,951 $1,266 $2,007 3.5 $4,945 3.9 $5,749 CZ11 PGE 8% 17% 1,091 92 $417 $10,990 $2,226 $3,256 3.4 $7,734 4.2 $10,472 CZ12 PGE 9% 16% 594 96 $263 $7,487 $1,712 $2,587 2.9 $4,901 4.3 $8,544 CZ12 SMUD/PGE 9% 16% 594 96 $260 $7,419 $1,712 $2,587 2.9 $4,889 4.3 $8,544 CZ13 PGE 7% 17% 1,036 88 $398 $10,479 $2,064 $3,045 3.4 $7,434 4.2 $9,715 CZ14 SCE/SCG 6% 11% 182 84 $102 $3,250 $1,170 $1,883 1.7 $1,368 4.0 $5,515 CZ14 SDGE 6% 11% 182 84 $194 $5,858 $1,170 $1,883 3.1 $3,975 4.0 $5,515 CZ15 SCE/SCG 3% 10% 387 65 $153 $4,119 $1,238 $1,971 2.1 $2,148 3.6 $4,998 CZ16 PG&E 9% 23% 1,007 142 $501 $13,864 ($2,682) ($3,275) >1 $17,139 >1 $16,140 Cost-Effectiveness Analysis: Single Family New Construction 25 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

4.3 Mixed Fuel Efficiency
Table 16 and Table 17 show results for the Mixed Fuel Efficiency packages. The packages are cost-effective based on at least one of the two metrics in Climate Zones 1, 2, 4, and 8 through 16 for the 3-story prototype and in Climate Zones 2, 4, 6, and 8 through 15 for the 5-story prototype. In all cases the NPV values, whether negative or positive, are small. The compliance impacts are also small.

A summary of measures included in each package is provided in Appendix 7.6 Summary of Measures by Package.

Table 16. 3-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 1% 1% 41 0 $12 $273 $176 $176 1.6 $98 1.2 $38 CZ02 PGE 1% 0% 24 0 $7 $162 $132 $132 1.2 $30 1.5 $62 CZ03 PGE 1% 0% 17 0 $5 $111 $132 $132 0.8 ($21) 0.8 ($27) CZ04 PGE 1% 0% 21 0 $6 $141 $132 $132 1.1 $9 1.3 $46 CZ04 CPAU 1% 0% 21 0 $3 $74 $132 $132 0.6 ($58) 1.3 $46 CZ05 PGE 1% 0% 19 0 $5 $123 $132 $132 0.9 ($9) 0.8 ($32) CZ05 PGE/SCG 1% 0% 19 0 $5 $123 $132 $132 0.9 ($9) 0.8 ($32) CZ06 SCE/SCG 1% 0% 9 0 $2 $56 $132 $132 0.4 ($75) 0.7 ($44) CZ07 SDGE 0% 0% 7 0 $3 $72 $132 $132 0.5 ($60) 0.4 ($81) CZ08 SCE/SCG 1% 0% 20 0 $6 $140 $132 $132 1.1 $9 1.5 $59 CZ09 SCE 1% 0% 28 0 $8 $192 $146 $156 1.2 $36 1.6 $88 CZ10 SCE/SCG 3% 1% 65 0 $20 $447 $190 $199 2.2 $247 2.4 $277 CZ10 SDGE 3% 1% 65 0 $27 $683 $190 $199 3.4 $484 2.4 $277 CZ11 PGE 3% 1% 91 0 $30 $699 $190 $199 3.5 $499 3.5 $489 CZ12 PGE 2% 0% 98 0 $33 $766 $381 $514 1.5 $252 1.5 $273 CZ12 SMUD/PGE 2% 0% 98 0 $17 $396 $381 $514 0.8 ($118) 1.5 $273 CZ13 PGE 4% 1% 99 0 $33 $765 $190 $199 3.8 $566 3.9 $574 CZ14 SCE/SCG 3% 1% 88 0 $26 $585 $190 $199 2.9 $385 3.1 $427 CZ14 SDGE 3% 1% 88 0 $36 $886 $190 $199 4.4 $686 3.1 $427 CZ15 SCE/SCG 5% 2% 182 0 $54 $1,226 $190 $199 6.1 $1,026 5.8 $957 CZ16 PG&E 5% 4% 16 12 $34 $1,012 $712 $712 1.4 $300 1.3 $184 Cost-Effectiveness Analysis: Single Family New Construction 26 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 17. 5-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency

4.4 Mixed Fuel Plus PV (Plus Battery for the 3-Story Prototype) Table 18 presents the Mixed Fuel Efficiency + PV + Battery package for the 3-story prototype. The battery system is a 100kWh battery. This scenario is cost- effective for all climate zones and under both metrics except for On-Bill in Climate Zone 4 in CPAU territory. Table 19 presents the Mixed Fuel Efficiency + PV package for the 5-story prototype. This package is cost-effective under TDV in all climate zones and cost-effective On-Bill everywhere except in Climate Zones 6 and 7. In the cases where it is not cost-effective, it is very close to being so with small negative NPV. In Climate Zone 6 in the 5-story prototype there is no upgrade to the PV system capacity as the prescriptive PV system already offset all of the estimated electricity use.

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 0% 0% 5 0 $2 $39 $176 $176 0.2 ($137) 0.2 ($136) CZ02 PGE 1% 0% 11 0 $2 $38 $132 $132 0.3 ($94) 1.9 $118 CZ03 PGE 0% 0% 7 0 $2 $46 $132 $132 0.3 ($86) 0.8 ($23) CZ04 PGE 1% 0% 12 0 $2 $40 $132 $132 0.3 ($92) 1.9 $114 CZ04 CPAU 1% 0% 12 0 $2 $39 $132 $132 0.3 ($93) 1.9 $114 CZ05 PGE 0% 0% 6 0 $1 $17 $132 $132 0.1 ($114) 0.4 ($73) CZ05 PGE/SCG 0% 0% 6 0 $1 $17 $132 $132 0.1 ($114) 0.4 ($73) CZ06 SCE/SCG 0% 0% 12 0 $2 $51 $132 $132 0.4 ($81) 1.4 $49 CZ07 SDGE 0% 0% 10 0 $0 $0 $132 $132 0.0 ($132) 0.9 ($7) CZ08 SCE/SCG 1% 0% 24 0 $8 $184 $132 $132 1.4 $53 2.2 $152 CZ09 SCE 1% 0% 28 0 $4 $96 $142 $149 0.6 ($52) 2.1 $163 CZ10 SCE/SCG 2% 1% 66 0 $21 $491 $186 $192 2.6 $298 3.2 $425 CZ10 SDGE 2% 1% 66 0 $30 $751 $186 $192 3.9 $558 3.2 $425 CZ11 PGE 2% 1% 83 0 $29 $665 $186 $192 3.5 $473 4.2 $621 CZ12 PGE 2% 0% 84 0 $29 $681 $321 $414 1.6 $267 2.3 $546 CZ12 SMUD/PGE 2% 0% 84 0 $16 $372 $321 $414 0.9 ($42) 2.3 $546 CZ13 PGE 2% 1% 95 0 $33 $765 $186 $192 4.0 $573 4.9 $742 CZ14 SCE/SCG 2% 1% 75 0 $11 $246 $186 $192 1.3 $54 3.9 $561 CZ14 SDGE 2% 1% 75 0 $34 $847 $186 $192 4.4 $654 3.9 $561 CZ15 SCE/SCG 3% 2% 172 0 $55 $1,257 $186 $192 6.5 $1,065 7.3 $1,212 CZ16 PG&E 2% 2% 40 4 $23 $616 $665 $665 0.9 ($49) 0.999 ($0) Cost-Effectiveness Analysis: Single Family New Construction 27 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 18. 3-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency + PV + Battery

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 1% 16% 2,068 0 $543 $12,588 $4,603 $6,917 1.8 $5,671 1.5 $3,724 CZ02 PGE 1% 16% 1,757 0 $462 $10,718 $3,881 $5,990 1.8 $4,728 1.6 $3,820 CZ03 PGE 1% 17% 1,624 0 $423 $9,797 $3,700 $5,754 1.7 $4,043 1.5 $3,157 CZ04 PGE 1% 17% 1,476 0 $383 $8,878 $3,518 $5,518 1.6 $3,360 1.6 $3,067 CZ04 CPAU 1% 17% 1,476 0 $171 $3,967 $3,518 $5,518 0.7 ($1,551) 1.6 $3,067 CZ05 PGE 1% 18% 1,520 0 $393 $9,107 $3,503 $5,498 1.7 $3,609 1.6 $3,526 CZ05 PGE/SCG 1% 18% 1,520 0 $393 $9,107 $3,503 $5,498 1.7 $3,609 1.6 $3,526 CZ06 SCE/SCG 1% 18% 1,112 0 $336 $7,677 $3,127 $5,009 1.5 $2,668 1.4 $1,917 CZ07 SDGE 0% 20% 1,431 0 $550 $13,713 $3,498 $5,493 2.5 $8,220 1.6 $3,159 CZ08 SCE/SCG 1% 18% 1,311 0 $413 $9,427 $3,328 $5,270 1.8 $4,156 1.4 $2,277 CZ09 SCE 1% 17% 1,129 0 $367 $8,375 $3,129 $5,017 1.7 $3,359 1.4 $1,937 CZ10 SCE/SCG 3% 19% 1,342 0 $420 $9,584 $3,321 $5,254 1.8 $4,331 1.5 $2,588 CZ10 SDGE 3% 19% 1,342 0 $533 $13,303 $3,321 $5,254 2.5 $8,049 1.5 $2,588 CZ11 PGE 3% 17% 1,833 0 $500 $11,587 $3,914 $6,025 1.9 $5,562 1.6 $3,852 CZ12 PGE 2% 17% 1,701 0 $442 $10,239 $3,926 $6,105 1.7 $4,133 1.6 $3,583 CZ12 SMUD/PGE 2% 17% 1,701 0 $285 $6,609 $3,926 $6,105 1.1 $503 1.6 $3,583 CZ13 PGE 4% 17% 1,568 0 $431 $9,983 $3,594 $5,609 1.8 $4,374 1.7 $3,944 CZ14 SCE/SCG 3% 19% 1,556 0 $477 $10,886 $3,388 $5,341 2.0 $5,545 1.6 $3,434 CZ14 SDGE 3% 19% 1,556 0 $607 $15,155 $3,388 $5,341 2.8 $9,815 1.6 $3,434 CZ15 SCE/SCG 5% 19% 1,241 0 $421 $9,616 $3,136 $5,013 1.9 $4,603 1.6 $3,076 CZ16 PG&E 5% 17% 1,286 12 $357 $8,508 $3,894 $5,833 1.5 $2,674 1.6 $3,219 Cost-Effectiveness Analysis: Single Family New Construction 28 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 19. 5-Story Cost-Effectiveness Results per Dwelling Unit: Mixed Fuel Efficiency + PV

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 0% 5% 1,446 0 $341 $7,917 $1,889 $2,403 3.3 $5,514 3.0 $4,757 CZ02 PGE 1% 2% 444 0 $55 $1,275 $567 $697 1.8 $578 4.4 $2,365 CZ03 PGE 0% 4% 693 0 $119 $2,766 $801 $1,002 2.8 $1,764 4.4 $3,423 CZ04 PGE 1% 1% 112 0 $14 $324 $226 $254 1.3 $69 3.5 $632 CZ04 CPAU 1% 1% 112 0 $13 $307 $226 $254 1.2 $53 3.5 $632 CZ05 PGE 0% 3% 464 0 $56 $1,310 $550 $676 1.9 $634 4.2 $2,165 CZ05 PGE/SCG 0% 3% 464 0 $56 $1,310 $550 $676 1.9 $634 4.2 $2,165 CZ06 SCE/SCG 0% 0% 12 0 $2 $51 $132 $132 0.4 ($81) 1.4 $49 CZ07 SDGE 0% 1% 95 0 $0 $0 $212 $237 0.0 ($237) 2.8 $423 CZ08 SCE/SCG 1% 3% 299 0 $42 $968 $388 $465 2.1 $504 4.3 $1,527 CZ09 SCE 1% 1% 99 0 $12 $284 $204 $230 1.2 $54 3.0 $465 CZ10 SCE/SCG 2% 3% 364 0 $57 $1,296 $450 $536 2.4 $759 4.2 $1,720 CZ10 SDGE 2% 3% 364 0 $103 $2,566 $450 $536 4.8 $2,030 4.2 $1,720 CZ11 PGE 2% 7% 1,178 0 $281 $6,521 $1,276 $1,610 4.1 $4,911 4.8 $6,162 CZ12 PGE 2% 4% 683 0 $120 $2,791 $898 $1,164 2.4 $1,627 4.2 $3,716 CZ12 SMUD/PGE 2% 4% 683 0 $102 $2,362 $898 $1,164 2.0 $1,198 4.2 $3,716 CZ13 PGE 2% 7% 1,137 0 $274 $6,347 $1,179 $1,484 4.3 $4,863 4.8 $5,599 CZ14 SCE/SCG 2% 2% 266 0 $33 $748 $342 $395 1.9 $353 4.7 $1,447 CZ14 SDGE 2% 2% 266 0 $62 $1,554 $342 $395 3.9 $1,158 4.7 $1,447 CZ15 SCE/SCG 3% 5% 567 0 $125 $2,851 $535 $646 4.4 $2,204 5.6 $2,994 CZ16 PG&E 2% 6% 1,051 4 $237 $5,569 $1,601 $1,883 3.0 $3,686 3.1 $4,011 Cost-Effectiveness Analysis: Single Family New Construction 29 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

4.5 CARE Rate Comparison
Table 20 presents a comparison of On-Bill cost-effectiveness results for CARE tariffs relative to standard tariffs for the all-electric prescriptive code case. The CARE rates apply to the apartment meters only and don’t impact the central water heating utility costs. Applying the CARE rates lowers both electric and gas utility bills for the consumer and the net impact for an all-electric building in most climate zones is lower overall bills and improved cost -effectiveness relative to the standard tariffs. Although not presented here, the all-electric + PV packages are all still On-Bill cost- effective using the CARE tariffs.

Table 20. On-Bill IOU Cost-Effectiveness Comparison with CARE Tariffs, Results per Dwelling Unit: All-Electric Prescriptive Code
Climate
Zone
Electric
/Gas Utility
3-Story 5-Story
Standard CARE Standard CARE
B/C Ratio NPV B/C Ratio NPV B/C Ratio NPV B/C Ratio NPV CZ01 PGE 3.9 $1,247 9.5 $3,637 >1 $6,998 >1 $10,045
CZ02 PGE 1.0 $32 3.1 $2,139 0.7 ($375) 2.5 $1,831
CZ03 PGE 1.1 $119 3.1 $2,187 0.7 ($407) 2.6 $1,901
CZ04 PGE 0.9 ($108) 2.8 $1,884 1.8 $945 2.9 $2,218
CZ05 PGE 0.98 ($21) 3.0 $2,041 0.6 ($479) 2.5 $1,773
CZ05 PGE/SCG 0.0 ($1,545) 1.5 $517 0.0 ($2,103) 1.1 $148 CZ06 SCE/SCG 0.0 ($1,255) 0.9 ($57) 0.8 ($199) 2.1 $1,349 CZ07 SDGE 0.0 ($1,456) 1.8 $856 0.0 ($1,685) 1.3 $343
CZ08 SCE/SCG 0.0 ($1,331) 0.8 ($165) 0.0 ($1,829) 1.2 $271 CZ09 SCE 0.0 ($1,380) 0.8 ($204) 0.0 ($1,236) 1.6 $750
CZ10 SCE/SCG 0.0 ($1,758) 0.1 ($574) 0.0 ($2,445) 0.5 ($447) CZ10 SDGE 0.0 ($2,452) 0.8 ($162) 0.0 ($3,234) 0.0 ($1,590) CZ11 PGE 0.0 ($826) 2.7 $1,119 0.0 ($1,494) 1.7 $616
CZ12 PGE 0.0 ($719) 2.9 $1,263 0.0 ($1,358) 2.0 $793
CZ13 PGE 0.0 ($940) 2.4 $936 0.0 ($1,517) 1.6 $491
CZ14 SCE/SCG 0.0 ($2,063) 0.0 ($803) 0.0 ($2,916) 0.3 ($613) CZ14 SDGE 0.0 ($2,841) 0.0 ($3,407) 0.0 ($3,937) 1.1 $61 CZ15 SCE/SCG 0.0 ($2,053) 0.0 ($1,036) 0.0 ($2,606) 0.0 ($1,452) CZ16 PG&E 2.8 $1,917 >1 $5,527 9.1 $5,467 >1 $8,557

Error! Not a valid bookmark self-reference. presents the comparison for the mixed fuel efficiency and PV packages.

Generally, the opposite trend occurs here for the mixed fuel packages where the CARE rate lowers utility cost savings and the benefit-to-cost ratios decline.

Cost-Effectiveness Analysis: Single Family New Construction 30 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 21. On-Bill IOU Cost-Effectiveness Comparison with CARE Tariffs, Results per Dwelling Unit: Mixed Fuel Packages
Climate
Zone
Electric
/Gas Utility
3-Story (Efficiency + PV + Battery) 5-Story (Efficiency + PV) Standard CARE Standard CARE
B/C Ratio NPV B/C Ratio NPV B/C Ratio NPV B/C Ratio NPV CZ01 PGE 1.8 $5,671 1.2 $1,113 3.3 $5,514 2.2 $2,765 CZ02 PGE 1.8 $4,728 1.2 $907 1.8 $578 1.5 $337
CZ03 PGE 1.7 $4,043 1.1 $579 2.8 $1,764 2.0 $1,028
CZ04 PGE 1.6 $3,360 1.0 $259 1.3 $69 0.8 ($44)
CZ05 PGE 1.7 $3,609 1.1 $414 1.9 $634 1.7 $442
CZ05 PGE/SCG 1.7 $3,609 1.1 $414 1.9 $634 1.7 $442
CZ06 SCE/SCG 1.5 $2,668 0.9 ($515) 0.4 ($81) 0.3 ($92) CZ07 SDGE 2.5 $8,220 1.7 $4,106 0.0 ($237) 0.0 ($237) CZ08 SCE/SCG 1.8 $4,156 1.1 $446 2.1 $504 1.3 $137
CZ09 SCE 1.7 $3,359 0.99 ($26) 1.2 $54 0.9 ($28)
CZ10 SCE/SCG 1.8 $4,331 1.1 $577 2.4 $759 1.3 $180
CZ10 SDGE 2.5 $8,049 1.8 $4,180 4.8 $2,030 0.0 ($536) CZ11 PGE 1.9 $5,562 1.2 $1,435 4.1 $4,911 2.7 $2,744 CZ12 PGE 1.7 $4,133 1.1 $517 2.4 $1,627 1.8 $905
CZ13 PGE 1.8 $4,374 1.2 $883 4.3 $4,863 2.9 $2,777
CZ14 SCE/SCG 2.0 $5,545 1.3 $1,395 1.9 $353 1.3 $136 CZ14 SDGE 2.8 $9,815 1.4 $2,292 3.9 $1,158 0.0 ($395) CZ15 SCE/SCG 1.9 $4,603 1.2 $887 4.4 $2,204 1.9 $586 CZ16 PG&E 1.5 $2,674 0.97 ($162) 3.0 $3,686 2.0 $1,908

4.6 Greenhouse Gas Reductions
Figure 1 and Figure 2 compare greenhouse gas reductions across all the packages for the multifamily 3-story and 5- story prototypes, respectively. Savings represent average annual savings per dwelling unit over the 30-year lifetime of the analysis. Electrification of gas uses represents the greatest greenhouse gas reductions , followed by PV.

Greenhouse gas reductions are greatest for the all-electric + PV package.

Cost-Effectiveness Analysis: Single Family New Construction 31 Results

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Figure 1. 3-Story greenhouse gas reductions (metric tons) per dwelling unit

Figure 2. 5-Story greenhouse gas savings (metric tons) per dwelling unit

0.0 0.1

0.2 0.3

0.4 0.5

0.6 0.7

0.8 0.9

1.0 CZ01 CZ02 CZ03 CZ04 CZ05 CZ06 CZ07 CZ08 CZ09 CZ10 CZ11 CZ12 CZ13 CZ14 CZ15 CZ16 Greenhouse Gas Reduc�ons (metric tons )
Mixed Fuel Efficiency
Mixed Fuel Efficiency + PV + Ba�ery
All-Electric Code Minimum
All-Electric + PV

0.0 0.1

0.2 0.3

0.4 0.5

0.6 0.7

0.8 0.9

1.0 CZ01 CZ02 CZ03 CZ04 CZ05 CZ06 CZ07 CZ08 CZ09 CZ10 CZ11 CZ12 CZ13 CZ14 CZ15 CZ16 Greenhouse Gas Reduc�ons (metric tons ) Mixed Fuel Efficiency Mixed Fuel Efficiency + PV
All-Electric Code Minimum
All-Electric + PV
Cost-Effectiveness Analysis: Single Family New Construction 32 Summary

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

5 Summary
The Reach Codes Team identified packages of electrification and energy efficiency measures as well as packages combining these measures with solar PV generation and battery storage, simulated them using building modeling software, and gathered costs to determine the cost-effectiveness of multiple scenarios. The Reach Codes Team coordinated with multiple utilities, cities, and building community experts to develop a set of assumptions considered reasonable in the current market. Changing assumptions, such as the period of analysis, measure selection, cost assumptions, energy escalation rates, or utility tariffs are likely to change results.

Table 22 summarizes results for each prototype and depicts the efficiency TDV compliance margins achieved for each climate zone and package. Because local reach codes must both exceed the Energy Commission performance budget (i.e., have a positive compliance margin) and be cost-effective, the Reach Codes Team highlighted cells meeting these two requirements to help clarify the upper boundary for potential reach code policies . All results presented in this study have a positive compliance margin.
• Cells highlighted in green depict cases with a positive compliance margin and cost-effective results using both On-Bill and TDV approaches.
• Cells highlighted in yellow depict cases with a positive compliance margin and cost-effective results using either the On-Bill or TDV approach.
• Cells not highlighted depict cases with a positive compliance margin but that were not cost-effective using either the On-Bill or TDV approach.

Following are key takeaways and recommendations from the analysis. • The Reach Codes Team found all-electric new construction to be feasible and cost-effective based on the California Energy Commission’s Time Dependent Valuation (TDV) metric in all cases. In many cases all - electric prescriptive code construction results in an increase in utility costs and is not cost -effective On-Bill.

Some exceptions include the SMUD and CPAU territories where lower electricity rates relative to gas rates result in lower overall utility bills.
• All-electric packages have lower GHG emissions than mixed fuel packages in all cases, due to the clean power sources currently available from California’s power providers. • The 2022 Energy Code’s new source energy metric combined with the heat pump space heating baseline in most climate zones encourages all-electric construction. While the code does not include an electric baseline for water heating, the penalty for central electric water heating observed in the performance approach in past code cycles has been removed and a credit is provided for well-designed central heat pump water heaters in most cases.
• Electrification combined with increased PV capacity results in utility cost savings and was found to be On- Bill cost-effective in all cases.
• The results in this study are based on today’s net energy metering (NEM 2.0) rules and do not account for recently approved changes to the NEM tariff (referred to as the net billing tariff). The net billing tariff decreases the value of PV to the consumer as compared to NEM 2.0. As a result, the cost-effectiveness of the packages that include above-code PV capacity is expected to be less under the net billing tariff. Conversely, the net billing tariff is expected to increase On-Bill cost-effectiveness of the all-electric prescriptive code scenario. An all-electric home has better on-site utilization of generated electricity from PV than a mixed fuel home with a similar sized PV system, and as a result exports less electricity to the grid. Since the net -billing tariff values exports less than under NEM 2.0, the relative impact on annual utility costs to the mixed fuel baseline is greater.
• This analysis does justify requiring a modest reach based on either efficiency TDV or source energy for all- electric buildings. However, this may be challenging for some projects given the recent changes to which the industry must adapt, including the efficiency updates and multifamily restructuring in the 2022 Title 24, Part 6 code. While project compliance margins using a CO
2 refrigerant heat pump water heating system are high, the Reach Code Team found lower compliance margins using other heat pump water heater system designs.

Cost-Effectiveness Analysis: Single Family New Construction 33 Summary

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Focusing on supporting projects to electrify water heating is expected to support the market shift towards more central heat pump water heaters.
• For jurisdictions interested in a reach code that allows for mixed fuel buildings, a mixed fuel efficiency and PV package (and battery for the 3-story prototype) was found to be cost-effective based on TDV in all cases and cost-effective On-Bill in most climate zones. This path, referred to as “Electric-Preferred”, allows for mixed fuel buildings but requires a higher building performance than for all-electric buildings. The efficiency measures evaluated in this study did not provide significant compliance benefit. As a result, the Reach Codes Team recommends establishing a compliance margin target based on source energy or total TDV. This would allow for PV and battery above minimum code requirements to be used to meet the target. • Jurisdictions interested in increasing affordable multifamily housing should know that applying the CARE rates has the overall impact of increasing utility cost savings for an all-electric building in most climate zones compared to a code compliant mixed fuel building, improving On-Bill cost-effectiveness.

Local jurisdictions may also adopt ordinances that amend different parts of the California Building Standards Code or may elect to amend other state or municipal codes. The decision regarding which code to amend will determine the specific requirements that must be followed for an ordinance to be legally enforceable. Reach codes that amend Part 6 of the California Building Code and require energy performance beyond state code minimums must demonstrate the proposed changes are cost-effective and obtain approval from the Energy Commission.

Table 22. Summary of Efficiency TDV Compliance Margins and Cost-Effectiveness Climate
Zone
Electric
/Gas Utility
3-Story 5-Story
All-Electric
Prescriptive
Code
All-
Electric
+ PV
Mixed
Fuel
Efficiency
Mixed
Fuel
Efficiency
+ PV +
Battery
All-Electric
Prescriptive
Code
All-
Electric
+ PV
Mixed
Fuel
Efficiency
Mixed
Fuel
Efficiency
+ PV
CZ01 PGE 26% 26% 1% 1% 14% 14% 0% 0%
CZ02 PGE 20% 20% 1% 1% 9% 9% 1% 1%
CZ03 PGE 21% 21% 1% 1% 11% 11% 0% 0%
CZ04 PGE 18% 18% 1% 1% 9% 9% 1% 1%
CZ04 CPAU 18% 18% 1% 1% 9% 9% 1% 1%
CZ05 PGE 23% 23% 1% 1% 12% 12% 0% 0%
CZ05 PGE/SCG 23% 23% 1% 1% 12% 12% 0% 0%
CZ06 SCE/SCG 18% 18% 1% 1% 9% 9% 0% 0%
CZ07 SDGE 20% 20% 0% 0% 11% 11% 0% 0%
CZ08 SCE/SCG 13% 13% 1% 1% 8% 8% 1% 1%
CZ09 SCE 13% 13% 1% 1% 7% 7% 1% 1%
CZ10 SCE/SCG 14% 14% 3% 3% 7% 7% 2% 2%
CZ10 SDGE 14% 14% 3% 3% 7% 7% 2% 2%
CZ11 PGE 14% 14% 3% 3% 8% 8% 2% 2%
CZ12 PGE 17% 17% 2% 2% 9% 9% 2% 2%
CZ12 SMUD/PGE 17% 17% 2% 2% 9% 9% 2% 2%
CZ13 PGE 13% 13% 4% 4% 7% 7% 2% 2%
CZ14 SCE/SCG 13% 13% 3% 3% 6% 6% 2% 2%
CZ14 SDGE 13% 13% 3% 3% 6% 6% 2% 2%
CZ15 SCE/SCG 5% 5% 5% 5% 3% 3% 3% 3%
CZ16 PG&E 24% 24% 5% 5% 9% 9% 2% 2%

Cost-Effectiveness Analysis: Single Family New Construction 34 References

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

6 References
Barbose, G., Darghouth, N., O'Shaughnessy, E., & Forrester, S. (2022, October). Tracking the Sun. Pricing and Design Trends for Distributed Photovoltaic Systems in the United States 2022 Edition. Retrieved from https://emp.lbl.gov/tracking-the-sun
California Energy Commission. (2017). Rooftop Solar PV System. Measure number: 2019-Res-PV-D Prepared by Energy and Environmental Economics, Inc. Retrieved from https://efiling.energy.ca.gov/getdocument.aspx?tn=221366 California Energy Commission. (2022a). 2022 Building Energy Efficiency Standards for Residential and Nonresidential Buildings. CEC-400-2022-010-CMF. Retrieved from https://www.energy.ca.gov/sites/default/files/2022- 12/CEC-400-2022-010_CMF.pdf
California Energy Commission. (2022b). 2022 Reference Appendices for the 202 Building Energy Efficiency Standards.

CEC-400-2022-010-AP. Retrieved from https://www.energy.ca.gov/sites/default/files/2022-08/CEC-400- 2022-010-AP.pdf
California Energy Commission. (2022c, Feb). 2022 Single-Family Residential Alternative Calculation Method Reference Manual. CEC-400-2022-008-CMF-REV. Retrieved from https://www.energy.ca.gov/publications/2022/2022- single-family-residential-alternative-calculation-method-reference-manual California Public Utilities Commission. (2021a). Utility Costs and Affordability of the Grid of the Future: An Evaluation of Electric Costs, Rates, and Equity Issues Pursuant to P.U. Code Section 913.1. Retrieved from https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/office-of-governmental-affairs- division/reports/2021/senate-bill-695-report-2021-and-en-banc-whitepaper_final_04302021.pdf California Public Utilities Commission. (2021b). Database for Energy-Efficient resources (DEER2021 Update). Retrieved April 13, 2021, from http://www.deeresources.com/index.php/deer-versions/deer2021 California Public Utilities Commission. (2022). Proposed Decision Rulemaking 19-01-011: PHASE III DECISION ELIMINATING GAS LINE EXTENSION ALLOWANCES. Retrieved from https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M496/K876/496876177.PDF E-CFR. (2020). https://www.ecfr.gov/cgi-
bin/retrieveECFR?gp=&SID=8de751f141aaa1c1c9833b36156faf67&mc=true&n=pt10.3.431&r=PART&ty=HTM L#se10.3.431_197. Retrieved from Electronic Code of Federal Regulations: https://www.ecfr.gov/cgi- bin/retrieveECFR?gp=&SID=8de751f141aaa1c1c9833b36156faf67&mc=true&n=pt10.3.431&r=PART&ty=HTM L#se10.3.431_197
Energy + Environmental Economics. (2020). Time Dependent Valuation of Energy for Developing Building Efficiency Standards: 2022 Time Dependent Valuation (TDV) and Source Energy Metric Data Sources and Inputs.

E-Source companies. (2020). Behind-the-Meter Battery Market Study. Prepared for San Diego Gas & Electric.

Retrieved from https://www.etcc-ca.com/reports/behind-meter-battery-market-study?dl=1582149166 Horii, B., Cutter, E., Kapur, N., Arent, J., & Conotyannis, D. (2014). Time Dependent Valuation of Energy for Developing Building Energy Efficiency Standards.

Statewide CASE Team. (2018). Energy Savings Potential and Cost-Effectiveness Analysis of High Efficiency Windows in California. Prepared by Frontier Energy. Retrieved from https://www.etcc-ca.com/reports/energy-savings- potential-and-cost-effectiveness-analysis-high-efficiency-windows-california Statewide CASE Team. (2020a). Nonresidential High Performance Envelope Codes and Standards Enhancement (CASE) Initiative 2022 California Energy Code. Prepared by Energy Solutions. Retrieved from https://title24stakeholders.com/wp-content/uploads/2020/10/2020-T24-NR-HP-Envelope-Final-CASE- Report.pdf
Statewide CASE Team. (2020b). Residential Energy Savings and Process Improvements for Additions and Alterations Codes and Standards Enhancement (CASE) Initiative 2022 California Energy Code. Prepared by Frontier Cost-Effectiveness Analysis: Single Family New Construction 35 References

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Energy. Retrieved from https://title24stakeholders.com/wp-content/uploads/2020/08/SF-Additions-and- Alterations_Final_-CASE-Report_Statewide-CASE-Team.pdf
Statewide CASE Team. (2020c). Multifamily All-Electric Codes and Standards Enhancement (CASE) Initiative 2022 California Energy Code. Prepared by TRC.

Statewide Reach Codes Team. (2020). 2019 Mid-Rise New Construction Reach Code Cost-Effectiveness Study.

Prepared by Frontier Energy, Misti Bruceri & Associates, and EnergySoft. Retrieved from https://localenergycodes.com/download/492/file_path/fieldList/2019%20Mid-rise%20NC%20Cost- Eff%20Report.pdf
Statewide Reach Codes Team. (2021). 2019 Cost-Effectiveness Study: 2020 Analysis of High-Rise Residential New Construction. Prepared by Frontier Energy and Misti Bruceri & Associates. Retrieved from https://www.localenergycodes.com/download/737/file_path/fieldList/2019%20High-Rise%20NC-Cost- Eff%20Report-2021-02-22.pdf
Statewide Reach Codes Team. (2022a). 2022 Cost-Effectiveness Study: Single Family new Construction. Prepared by Frontier Energy and Misti Bruceri & Associates. Retrieved from California Energy Codes & Standards:
https://localenergycodes.com/content/resources
Statewide Reach Codes Team. (2022b). Nonresidential New Construction Reach Code Cost-effectiveness Study.

Prepared by Avani Goyal, Farhad Farahmand, TRC Companies. Retrieved from California Energy Codes & Standards: https://localenergycodes.com/content/resources TRC. (2018 ). 2019 Title 24 Energy Reach Code Cost-Effectiveness Analysis Draft. City of Palo Alto. Retrieved from https://cityofpaloalto.org/civicax/filebank/documents/66742 TRC. (2019). Multifamily Prototypes. Prepared for Southern California Edison. Retrieved from https://title24stakeholders.com/wp-content/uploads/2019/06/SCE- MFModeling_MultifamilyPrototypesReport_2019-06-07_clean.pdf

Cost-Effectiveness Analysis: Single Family New Construction 36 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7 Appendices

7.1 Map of California Climate Zones
Climate zone geographical boundaries are depicted in Figure 3. The map in Figure 3 along with a zip-code search directory is available at: https://ww2.energy.ca.gov/maps/renewable/building_climate_zones.html Figure 3. Map of California climate zones.

Cost-Effectiveness Analysis: Single Family New Construction 37 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2 Utility Rate Schedules
The Reach Codes Team used the CA IOU and POU rate tariffs detailed below to determine the On-Bill savings for each package. The California Climate Credit was applied for both electricity and natural gas service for the IOUs using the 2022 credits shows below.9 The credits were applied to reduce the total calculated annual bill, including any fixed fees or minimum bill amounts.

Electricity rates reflect the most recent approved tariffs. Monthly gas rates were estimated based on the latest available gas rate (December 2022) and a curve to reflect how natural gas prices fluctuate with seasonal supply and demand.

The seasonal curve was estimated from monthly residential tariffs between 2012 and 202 2 (between 2020 and 2022 for CPAU). 12-month curves were created from monthly gas rates for each of the eleven years (three years for CPAU).

These annual curves were then averaged to arrive at an average normalized annual curve. This was conducted separately for baseline and excess energy rates. Costs used in this analysis were then derived by establishing the most recent baseline and excess rate from the latest tariff as a reference point (December 2022), and then using the normalized curve to estimate the cost for the remaining months relative to the reference point rate.

9 https://www.cpuc.ca.gov/industries-and-topics/natural-gas/greenhouse-gas-cap-and-trade-program/california-climate- credit

Cost-Effectiveness Analysis: Single Family New Construction 38 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.1 Pacific Gas & Electric
The following pages provide details on the PG&E electricity and natural gas tariffs applied in this study. Error! Reference source not found. describes the baseline territories that were assumed for each climate zone. A net surplus compensation rate of $0.0474/ kWh was applied to any net annual electricity generation based on a one-year average of the rates between November 2021 and October 2022.

Table 23. PG&E Baseline Territory by Climate Zone
Climate
Zone
Baseline
Territory
CZ01 V
CZ02 X
CZ03 T
CZ04 X
CZ05 T
CZ11 R
CZ12 S
CZ13 R
CZ16 Y

The PG&E monthly gas rate in $/therm was applied on a monthly basis according to the rates shown in Error! Reference source not found.. These are applied to both the G-1 and GM rates. These rates are based on applying a normalization curve to the December 2022 tariff based on eleven years of historical gas data. See the beginning of Section Error! Reference source not found. Error! Reference source not found. for further details. The corresponding CARE rates are shown in Error! Reference source not found. and reflect the 20 percent discount per the GL-1 tariff. The GM master metered wather heating baseline quantity of 0.43 therms per dwelling unit per day in all baseline territories and in both seasons was applied to the centrally metered gas water heating.

Table 24. PG&E Monthly Gas Rate ($/therm)
Month Total Charge
Baseline Excess
January $2.20579 $2.66008
February $2.24291 $2.69637
March $2.11750 $2.58278
April $2.08101 $2.55500
May $2.08062 $2.55844
June $2.09104 $2.56928
July $2.10404 $2.58189
August $2.15162 $2.63251
September $2.18718 $2.67910
October $2.23153 $2.71934
November $2.32121 $2.79158
December $2.34123 $2.80922

Cost-Effectiveness Analysis: Single Family New Construction 39 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 25. PG&E Monthly CARE (GL-1) Gas Rate ($/therm)
Month Total CARE Charge
Baseline Excess
January $1.76463 $2.12806
February $1.79433 $2.15710
March $1.69400 $2.06622
April $1.66480 $2.04400
May $1.66449 $2.04675
June $1.67283 $2.05543
July $1.68323 $2.06551
August $1.72129 $2.10601
September $1.74974 $2.14328
October $1.78523 $2.17547
November $1.85697 $2.23327
December $1.87298 $2.24738

Cost-Effectiveness Analysis: Single Family New Construction 40 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 41 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 42 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 43 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.2 Southern California Edison
The following pages provide details on are the SCE electricity tariffs applied in this study. Error! Reference source not found. describes the baseline territories that were assumed for each climate zone. A net surplus compensation rate of $ 0.04361/ kWh was applied to any net annual electricity generation based on a on e-year average of the rates between November 2021 and October 2022
Table 26: SCE Baseline Territory by Climate Zone
Climate
Zone
Baseline
Territory
CZ06 6
CZ08 8
CZ09 9
CZ10 10
CZ14 14
CZ15 15

Cost-Effectiveness Analysis: Single Family New Construction 44 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 45 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 46 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.3 Southern California Gas
Following are the SoCalGas natural gas tariffs applied in this study. Error! Reference source not found. describes the baseline territories that were assumed for each climate zone.

Table 27. SoCalGas Baseline Territory by Climate Zone
Climate
Zone
Baseline
Territory
CZ05 2
CZ06 1
CZ08 1
CZ09 1
CZ10 1
CZ14 2
CZ15 1

The SoCalGas monthly gas rate in $/therm was applied on a monthly basis according to the rates shown in Error! Reference source not found.. These rates are based on applying a normalization curve to the December 2022 tariff based on eleven years of historical gas data. See the beginning of Section Error! Reference source not found.

Error! Reference source not found. for further details. Long-term historical natural gas rate data was only available for SoCalGas’ procurement charges.10 The baseline and excess transmission charges were found to be consistent over the course of a year and applied for the entire year based on 2022 rates. CARE rates reflect the 20 percent discount per the GR tariff.

Table 28. SoCalGas Monthly Gas Rate ($/therm)
Month Procurement
Charge
Transportation Charge Total Charge
Baseline Excess Baseline Excess
January $0.90581 $0.82487 $1.23877 $1.73068 $2.14458
February $0.83669 $0.82487 $1.23877 $1.66156 $1.84967
March $0.80596 $0.82487 $1.23877 $1.63083 $1.82938
April $0.71941 $0.82487 $1.23877 $1.54428 $1.75890
May $0.77049 $0.82487 $1.23877 $1.59536 $1.78548
June $0.86253 $0.82487 $1.23877 $1.68740 $1.83337
July $0.87687 $0.82487 $1.23877 $1.70174 $1.86833
August $0.95391 $0.82487 $1.23877 $1.77878 $1.91089
September $0.85896 $0.82487 $1.23877 $1.68383 $1.83611
October $0.84147 $0.82487 $1.23877 $1.66634 $1.84936
November $0.89018 $0.82487 $1.23877 $1.71505 $1.88836
December $1.05329 $0.82487 $1.23877 $1.87816 $1.98294

10 The SoCalGas procurement and transmission charges were obtained from the following site:
https://www.socalgas.com/for-your-business/energy-market-services/gas-prices Cost-Effectiveness Analysis: Single Family New Construction 47 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 48 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.4 San Diego Gas & Electric
Following are the SDG&E electricity and natural gas tariffs applied in this study. Error! Reference source not found. describes the baseline territories that were assumed for each climate zone. A net surplus compensation rate of $0.04174 / kWh was applied to any net annual electricity generation based on a one- year average of the rates between January 2022 and December 2022.

Table 29. SDG&E Baseline Territory by Climate Zone
Climate
Zone
Baseline
Territory
CZ07 Coastal
CZ10 Inland
CZ14 Mountain

The SDG&E monthly gas rate in $/therm was applied on a monthly basis according to the rates shown in Error! Reference source not found.. These rates are based on applying a normalization curve to the December 2022 tariff based on eleven years of historical gas data. See the beginning of Section Error! Reference source not found.

Error! Reference source not found. for further details. CARE rates reflect the 20 percent discount per the G-CARE tariff.

Table 30. SDG&E Monthly Gas Rate ($/therm)
Month Total Charge
Baseline Excess
January $2.33762 $2.34748
February $2.26751 $2.28440
March $2.25119 $2.27016
April $2.20192 $2.22744
May $2.24252 $2.26403
June $2.31819 $2.33060
July $2.32406 $2.33630
August $2.37527 $2.38090
September $2.33542 $2.34971
October $2.30366 $2.32151
November $2.31722 $2.33381
December $2.45653 $2.73517

Cost-Effectiveness Analysis: Single Family New Construction 49 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 50 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 51 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 52 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 53 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.5 City of Palo Alto Utilities
Following are the CPAU electricity and natural gas tariffs applied in this study. The CPAU monthly gas rate in $/therm was applied on a monthly basis according to the rates shown in Error! Reference source not found.. These rates are based on applying a normalization curve to the December 2022 tariff based on three years of historical gas data. See the beginning of Section Error! Reference source not found. Error! Reference source not found. for further details. The monthly service charge applied was $106.90 per month per the December 2022 G-2 tariff.

Table 31. CPAU Monthly Gas Rate ($/therm)
Month G2
Volumetric
Totals
January $1.80964
February $1.67009
March $1.68480
April $1.68698
May $1.78478
June $1.88288
July $1.88355
August $2.06943
September $2.06798
October $2.08553
November $2.09681
December $2.45700

Cost-Effectiveness Analysis: Single Family New Construction 54 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 55 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.6 Sacramento Municipal Utilities District (Electric Only) Following are the SMUD electricity tariffs applied in this study. The rates effective January 2023 were used.

Cost-Effectiveness Analysis: Single Family New Construction 56 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 57 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.2.7 Fuel Escalation Assumptions
The average annual escalation rates in Error! Reference source not found. were used in this study. These are based on assumptions from the CPUC 2021 En Banc hearings on utility costs through 2030 (California Public Utilities Commission, 2021a). Escalation rates through the remainder of the 30-year evaluation period are based on the escalation rate assumptions within the 2022 TDV factors. No data was available to estimate electricity escalation rates for CPAU and SMUD, therefore electricity escalation rates for PG&E and statewide natural gas escal ation rates were applied.

Table 32: Real Utility Rate Escalation Rate Assumptions

Statewide Natural
Gas Residential
Average Rate
(%/year, real)
Electric Residential Average Rate
(%/year, real)

PG&E SCE SDG&E
2023 4.6% 1.8% 1.6% 2.8%
2024 4.6% 1.8% 1.6% 2.8%
2025 4.6% 1.8% 1.6% 2.8%
2026 4.6% 1.8% 1.6% 2.8%
2027 4.6% 1.8% 1.6% 2.8%
2028 4.6% 1.8% 1.6% 2.8%
2029 4.6% 1.8% 1.6% 2.8%
2030 4.6% 1.8% 1.6% 2.8%
2031 2.0% 0.6% 0.6% 0.6%
2032 2.4% 0.6% 0.6% 0.6%
2033 2.1% 0.6% 0.6% 0.6%
2034 1.9% 0.6% 0.6% 0.6%
2035 1.9% 0.6% 0.6% 0.6%
2036 1.8% 0.6% 0.6% 0.6%
2037 1.7% 0.6% 0.6% 0.6%
2038 1.6% 0.6% 0.6% 0.6%
2039 2.1% 0.6% 0.6% 0.6%
2040 1.6% 0.6% 0.6% 0.6%
2041 2.2% 0.6% 0.6% 0.6%
2042 2.2% 0.6% 0.6% 0.6%
2043 2.3% 0.6% 0.6% 0.6%
2044 2.4% 0.6% 0.6% 0.6%
2045 2.5% 0.6% 0.6% 0.6%
2046 1.5% 0.6% 0.6% 0.6%
2047 1.3% 0.6% 0.6% 0.6%
2048 1.6% 0.6% 0.6% 0.6%
2049 1.3% 0.6% 0.6% 0.6%
2050 1.5% 0.6% 0.6% 0.6%
2051 1.8% 0.6% 0.6% 0.6%
2052 1.8% 0.6% 0.6% 0.6%
Cost-Effectiveness Analysis: Single Family New Construction 58 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.3 Cost Details
Table 33 presents additional detail on the first cost assumptions for the central water heating systems. For the 5- story prototype costs are provided both for a CO2 refrigerant Sanden-based and R-134a refrigerant Colmac-based heat pump water heater designs. The results presented in the main body of this report are based on the Sanden design. A sensitivity analysis was also conducted for a Colmac design (see Appendix 7.5 Central Heat Pump Water Heater Comparison) and the cost comparison is presented here. All costs are based on data from the 2022 Multifamily All- Electric CASE Report (Statewide CASE Team, 2020c).

Table 33. Heat Pump Water Heater First Costs per Building (Present Value (2023$)) Item
3-Story (36-units) 5-Story (88-units)
Gas
Boiler
(CZs 1-9)
Gas Boiler
(CZs 10-16)
Heat
Pump
Gas
Boiler
(CZs 1-9)
Gas Boiler
(CZs 10-16)
Heat
Pump
(Sanden)
Heat
Pump
(Colmac)
Water Heating
Equipment $87,602 $87,602 $140,907 $135,146 $135,146 $244,742 $319,485 Solar Thermal
Collector $39,800 $46,888 n/a $74,740 $91,776 n/a n/a
Gas Piping $8,890 $8,890 n/a $9,065 $9,065 n/a n/a
Electrical Circuits n/a n/a $25,000 n/a n/a $25,000 $25,000 Overhead & Markup $37,480 $39,430 $45,624 $60,212 $64,896 $74,179 $94,733 Total $173,772 $182,810 $211,531 $279,163 $300,883 $343,920 $439,218

Table 34 presents additional detail on the first cost assumptions for the space hating systems.

Table 34. Heat Pump Space Heater First Costs per Dwelling Unit (Present Value (2023$) Item
3-Story 5-Story
Source & Notes Furnace +
Split AC
Heat
Pump
Furnace +
Split HP
Heat
Pump
Dwelling Unit HVAC
$5,651 $5,460 $6,109 $5,460
Gas system costs based on 2022
Multifamily All-Electric CASE Report.

Heat pump costs based on online
equipment research indicating a 2-ton
HP is $191 less than a furnace/AC of
the same size.

Refrigerant Piping $563 $563 $423 $423
2022 Multifamily All-Electric CASE
Report. Gas Piping $92 $0 $227 $0
Electrical Circuits $0 $150 $0 $150
Labor
$9,904 $6,985 $9,904 $6,985
Based on the 2022 Multifamily All-
Electric CASE Report with
adjustments to align with updated
equipment costs.

Overhead & Markup $4,457 $3,618 $4,582 $3,579 Based on a 27% markup Total $20,667 $16,776 $21,245 $16,597
Incremental Cost ($3,891) ($4,647)

Cost-Effectiveness Analysis: Single Family New Construction 59 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.4 PG&E Gas Infrastructure Cost Memo

Cost-Effectiveness Analysis: Single Family New Construction 60 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 61 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Cost-Effectiveness Analysis: Single Family New Construction 62 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.5 Central Heat Pump Water Heater Comparison
Table 35 presents energy and cost-effectiveness results for a R-134a refrigerant based system design using a Colmac central heat pump water heater in the 5- story prototype. This was only found to be cost-effective based on at least one of the two metrics in Climate Zones 1, 4 in CPAU territory, and 16.

Table 35. 5-Story Cost-Effectiveness: All-Electric Prescriptive Code with R-134a Heat Pump Water Heater

Climate
Zone
Electric
/Gas Utility
Efficiency
TDV
Comp
Margin
Source
Comp
Margin
Annual
Elec
Savings
(kWh)
Annual
Gas
Savings
(therms)
Utility Cost
Savings Incremental Cost On-Bill TDV
First
Year
Lifecycle
(2022$)
First
Year
Lifecycle
(2022$)
B/C
Ratio NPV B/C
Ratio NPV
CZ01 PGE 6% 6% -1,496 147 ($155) ($1,240) ($3,556) ($4,223) 3.4 $2,984 >1 $5,870 CZ02 PGE 4% 2% -1,197 120 ($145) ($1,513) $1,691 $2,749 0.0 ($4,262) 0.5 ($1,287) CZ03 PGE 6% 3% -1,166 120 ($138) ($1,360) $1,691 $2,749 0.0 ($4,109) 0.8 ($523) CZ04 PGE 4% 2% -1,116 113 ($76) ($49) $1,691 $2,749 0.0 ($2,798) 0.7 ($949) CZ04 CPAU 4% 2% -1,116 113 $185 $7,144 $1,718 $2,776 2.6 $4,368 0.6 ($976) CZ05 PGE 5% 2% -1,161 117 ($137) ($1,391) $1,691 $2,749 0.0 ($4,140) 0.5 ($1,412) CZ05 PGE/SCG 5% 2% -1,161 117 ($189) ($3,016) $1,691 $2,749 0.0 ($5,765) 0.5 ($1,412) CZ06 SCE/SCG 4% 1% -1,000 104 ($92) ($879) $1,691 $2,749 0.0 ($3,628) 0.6 ($1,013) CZ07 SDGE 5% 2% -996 106 ($183) ($3,216) $1,691 $2,749 0.0 ($5,965) 0.7 ($936) CZ08 SCE/SCG 3% 1% -948 100 ($156) ($2,413) $1,691 $2,749 0.0 ($5,162) 0.7 ($695) CZ09 SCE 3% 0% -966 100 ($132) ($1,863) $1,691 $2,749 0.0 ($4,612) 0.7 ($738) CZ10 SCE/SCG 3% 1% -962 84 ($188) ($3,375) $1,444 $2,395 0.0 ($5,770) 0.3 ($1,596) CZ10 SDGE 3% 1% -962 84 ($239) ($4,959) $1,444 $2,395 0.0 ($7,354) 0.3 ($1,596) CZ11 PGE 4% 3% -1,029 92 ($165) ($2,487) $1,444 $2,395 0.0 ($4,882) 0.4 ($1,367) CZ12 PGE 4% 3% -1,081 96 ($172) ($2,591) $1,444 $2,395 0.0 ($4,986) 0.3 ($1,667) CZ12 SMUD/PGE 4% 3% -1,081 96 $26 $1,988 $1,444 $2,395 0.8 ($407) 0.3 ($1,667) CZ13 PGE 3% 2% -976 88 ($156) ($2,361) $1,444 $2,395 0.0 ($4,756) 0.4 ($1,452) CZ14 SCE/SCG 2% -1% -1,045 84 ($210) ($3,880) $1,444 $2,395 0.0 ($6,275) 0.1 ($2,056) CZ14 SDGE 2% -1% -1,045 84 ($270) ($5,725) $1,444 $2,395 0.0 ($8,120) 0.1 ($2,056) CZ15 SCE/SCG 2% -1% -718 65 ($146) ($2,713) $1,444 $2,395 0.0 ($5,108) 0.3 ($1,564) CZ16 PG&E -5% 6% -1,913 142 ($276) ($4,142) ($3,803) ($4,577) 1.1 $435 1.2 $746 Cost-Effectiveness Analysis: Single Family New Construction 63 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

7.6 Summary of Measures by Package
Table 36 provides the details of the measures in each of the efficiency package by climate zone. The measures are the same for the 3-story and 5-story prototypes. Table 37 presents the PV capacities per dwelling unit in the upgrade packages. In Climate Zone 6 for the mixed fuel case in the 5-story prototype there is no upgrade to the PV system capacity as the prescriptive PV system already offset all of the estimated electricity use.

Table 36. Mixed Fuel Efficiency Package Measures
Climate
Zone

0.70 Roof
Solar
Reflectance

0.24 U-Factor
Windows

0.35 W/cfm
Verified Low
Leakage Ducts in
Conditioned
Space
1 X X
2 X
3 X
4 X
5 X
6 X
7 X
8 X
9 X X
10 X X X
11 X X X
12 X X X
13 X X X
14 X X X
15 X X X
16 X X X

Cost-Effectiveness Analysis: Single Family New Construction 64 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Table 37. Upgrade Package PV Capacities (kW-DC)
Climate
Zone
All-Electric + PV Mixed Fuel + PV
3-Story 5-Story 3-Story 5-Story
CZ01 4.41 4.35 3.69 3.43
CZ02 3.56 3.58 3.02 2.98
CZ03 3.31 3.29 2.80 2.72
CZ04 3.21 3.27 2.73 2.75
CZ05 3.04 3.08 2.57 2.55
CZ06 2.91 3.04 2.49 2.68
CZ07 3.09 3.21 2.64 2.74
CZ08 3.18 3.30 2.76 2.86
CZ09 3.04 3.16 2.63 2.73
CZ10 3.20 3.30 2.79 2.86
CZ11 3.90 3.95 3.42 3.43
CZ12 3.53 3.60 3.05 3.08
CZ13 3.77 3.84 3.32 3.36
CZ14 3.20 3.23 2.79 2.79
CZ15 3.93 3.94 3.58 3.58
CZ16 3.79 3.76 2.60 2.90

Cost-Effectiveness Analysis: Single Family New Construction 65 Appendices

localenergycodes.com California Energy Codes & Standards | A statewide utility program 2023-06-20

Get In Touch
The adoption of reach codes can differentiate jurisdictions as efficiency leaders and help accelerate the adoption of new equipment, technologies, code compliance, and energy savings strategies.

As part of the Statewide Codes & Standards Program, the Reach Codes Subprogram is a resource available to any local jurisdiction located throughout the state of California.

Our experts develop robust toolkits as well as provide specific technical assistance to local jurisdictions (cities and counties) considering adopting energy reach codes. These include cost-effectiveness research and analysis, model ordinance language and other code development and implementation tools, and specific technical assistance throughout the code adoption process.

If you are interested in finding out more about local energy reach codes, the Reach Codes Team stands ready to assist jurisdictions at any stage of a reach code project.

Visit LocalEnergyCodes.com to
access our resources and sign up
for newsletters

Contact [email protected]
for no-charge assistance from expert
Reach Code advisors

Follow us on Twitter

← All documents from this meeting