Attachment B: Bid Summary
Project: PE ‐ 24000  Baylands Boardwalk Repair Project
IFB No.: 190876
IFB Issue Date: April 3, 2024
Bid Opening Date: May 1, 2024
Unit Price Total Item Price Unit Price Total Item Price 1 1 Lump Sum Mobilization and Demobilization $   40,000 40,000$                $  28,079  28,079 $ 2 1 Lump Sum Temporary Construction and Controls $   15,000 15,000$                $  50,000  50,000 $ 3 1 Lump Sum Water Quality and Spill Prevention $    5,000 5,000$                  $  17,000  17,000 $ 4 1,080 Linear Feet Remove and Reset 2x6 Bracing (Trans) $           20 21,600$                $         23  24,840 $ 5 1,080 Linear Feet Remove and Reset 2x6 Bracing (Long) $           20 21,600$                $         17  18,360 $ 6 105 Pound Furnish and install Miscellaneous Metal,
Galvanized
$           25 2,625$                  $         83  8,715 $ 7 135 Each Furnish and Install Fiber‐Reinforced Polymer System Post/Pile Encasement
$    2,600 351,000$             $    3,260  440,100 $
$           456,825   $           587,094
Alt 01 185 Linear Feet Remove and Reset 2x6 Bracing (Trans) $           20 3,700$                  $         24   $               4,440 Alt 02 155 Linear Feet Remove and Reset 2x6 Bracing (Long) $           20 3,100$                  $         17   $               2,635 Alt 03 15 Pound Furnish and install Miscellaneous Metal, Galvanized
$           25 375$    $         84   $               1,260 Alt 04 22 Each Furnish and Install Fiber‐Reinforced Polymer System Post/Pile Encasement
$    2,600 57,200$                $    3,270   $             71,940 64,375$              80,275$
521,200$            667,369$
28%
Total base plus bid alternates of the only bidder is 28% above the engineer's estimate.

Valentine CorporationEngineer's Estimate
Total (Base + Bid Alternate)
Bid Item Approx.

Quantity Unit Description
Total Base Bid (Items 01 to 07)
Base Bid ‐ Repair Priority 1, 2 & 3 Only
Bid Alternate ‐ Repair Priority 4
Total Bid Alternate (Alt 01 through 04)