DOWNTOWN PARKING STRUCTURE OPTION APPRAISAL
Disadvantage Advantage
Option 1a Waverley Residential (separate circulation)
Stall Count 274 (Net gain 163 stalls (minus existing and residential stalls)) Unit Count 15
• Lower residential unit count
and area than dogleg options
• Cost increase to residential
with required elevator and
second stair.
• Architectural challenge with
additional street facing shear
wall.
• Increased stall count over
dogleg options
• Good location for residential
units on street
• Could create landscaped city
space prior to residential
development phase. (may be
difficult to remove once used)
• Separation of parking and
residential uses allow clearer
definition of developments,
increased security.
• Separation of construction
contracts and ownership
• Residential floor height
flexibility since no connection
to garage floor requirements.
• More residential floor area than
other Waverley options.
• Preferred option by low income
housing developer.
Palo Alto Downtown Garage Page 2 of 6
Option Appraisal March 25 th , 2025
WDI 16138A
San Jose, CA | Long Beach, CA
watrydesign.com
Option 1b Waverley Residential (shared circulation)
Stall Count 274 (Net gain 1 68 stalls (minus existing and residential stalls)) Unit Count 15
• Less residential area than
option 1a
• Lower residential unit count
than dogleg option.
• More limited residential unit
types (no 3 bed option)
• Shared circulation may not
provide design quality and
safety at residential
connection.
• Requires residential floor
height to match garage.
• Code required separation of
building types at circulation
areas sacrifices residential
floor area and increase cost
prior to residential
development.
• Complication to construction
phasing and maintaining
garage use during process
• Increased stall count over
dogleg options
• Good location for residential
units on street
• Could create landscaped city
space prior to residential
development phase. (reduced
from option 1A)
Palo Alto Downtown Garage Page 3 of 6
Option Appraisal March 25 th , 2025
WDI 16138A
San Jose, CA | Long Beach, CA
watrydesign.com
Option 1c Waverley Residential (with podium shared circulation) Stall Count 278 (Net gain 1 67 stalls (minus existing and residential stalls)) Unit Count 15
• Less residential area than
option 1a
• Lower residential unit count
than dogleg option.
• More limited residential unit
types (no 3 bed option)
• Shared circulation may not
provide design quality and
safety at residential
connection.
• Requires residential floor
height to match garage.
• Code required separation of
building types at circulation
areas sacrifices residential
floor area and increase cost
prior to residential
development.
• Complication to construction
phasing and maintaining
garage use during process
• Forms difficult architecture at
Waverley podium until
residential development
proceeds.
• More complicated building
construction requiring
additional waterproofing at
podium.
• No landscaped green space
prior to residential unit
development
• Less clarity of ownership and
construction scope.
• Increased stall count over
dogleg options
• Good location for residential
units on street
• Slight increase in parking count
over other Waverely options
• Ground floor amenity space
built with garage.
Option 2 Non-Residential
Stall Count 329
Unit Count 0
• No residential program • Maximum parking count
available on site.
Palo Alto Downtown Garage Page 4 of 6
Option Appraisal March 25 th , 2025
WDI 16138A
San Jose, CA | Long Beach, CA
watrydesign.com
Option 3a Dogleg Residential (separate circulation)
Stall Count 209 (Net gain 73 stalls (minus existing and residential stalls)) Unit Count 25
• Location of residential units
at alley way and rear of adj.
buildings is not optimal living
conditions.
• Cost increase to residential
with required elevator and
second stair.
• Very reduced parking count.
• Complex construction process
behind other buildings.
• Compromised views and
access to light and air.
• Not preferred option of low
income house developer.
• Main entry off alley.
• Garage utility rooms
compromised.
• Interim commercial trash
area needs to be provided
• Larger residential area allows
more units and unit types than
Waverley options
• Separation of parking and
residential uses allows clearer
definition of developments and
better security
• Residential floor height
flexibility since no connection
to garage floor requirements
• Prior to residential build site
could be used for on grade
parking (approx. 25 stalls)
Palo Alto Downtown Garage Page 5 of 6
Option Appraisal March 25 th , 2025
WDI 16138A
San Jose, CA | Long Beach, CA
watrydesign.com
Option 3b Dogleg Residential (shared circulation)
Stall Count 209 (Net gain 83 stalls (minus existing and residential stalls)) Unit Count 25
• Location of residential units
at alley way and rear of adj.
buildings is not optimal living
conditions.
• Very reduced parking count.
• Complex construction process
behind other buildings.
• Compromised views and
access to light and air.
• Requires residential floor
height to match garage.
• Not preferred option of low
income house developer.
• Main entry off alley.
• Garage utility rooms
compromised.
• Code required separation of
building types at circulation
areas sacrifices residential
floor area and increase cost
prior to residential
development.
• Complication to construction
phasing and maintaining
garage use during process
• No landscaped green space
prior to residential unit
development
• Less clarity of ownership and
construction scope.
• Larger residential area allows
more units and unit types than
Waverley options
• Prior to residential build site
could be used for on grade
parking (approx. 25 stalls)
Palo Alto Downtown Garage Page 6 of 6
Option Appraisal March 25 th , 2025
WDI 16138A
San Jose, CA | Long Beach, CA
watrydesign.com
Option 3c Dogleg Residential (with podium separate circulation) Stall Count 21 6 (Net gain 85 stalls (minus existing and residential stalls)) Unit Count 25
• Location of residential units
at alley way and rear of adj.
buildings is not optimal living
conditions.
• Very reduced parking count.
• Complex construction process
behind other buildings.
• Compromised views and
access to light and air. Not
preferred option of low
income house developer.
• Main entry off alley.
• Garage utility rooms
compromised.
• Interim commercial trash
area needs to be provided
• Shared circulation may not
provide design quality and
safety at residential
connection.
• Code required separation of
building types at circulation
areas sacrifices residential
floor area and increase cost
prior to residential
development.
• Complication to construction
phasing and maintaining
garage use during process
and additional waterproofing
at podium.
• Less clarity of ownership and
construction scope.
• Larger residential area allows
more units and unit types than
Waverley options
• Separation of parking and
residential uses allows clearer
definition of developments and
better security
• Residential floor height
flexibility since no connection
to garage floor requirements
• Ground floor amenity spaces
and additional parking built
with garage.