Item No. 10. Page 1 of 1

City Council
Supplemental Report
From: Brad Eggleston, Director Public Works/City Engineer Meeting Date: May 19, 2025
Item Number: 10
*Item Reordered to be Heard Under Consent Calendar
Report #:2505-4641
TITLE
Approval of Construction Contract No. C25193197 with Anderson Pacific Engineering Construction, Inc. in the Amount Not-to Exceed $47,282,100 for the Local Advanced Water Purification System project (WQ-19003); Authorization of Contract Contingency in an Amount Not-to-Exceed $4,728,210; and Approval of Amendment No. 2 to the First Amended and Restated Contract No. C059999 Between the City of Palo Alto and the City of Mountain View; CEQA Status - Addendum to the 2015 Environmental Impact Report for the Palo Alto Recycled Water Project (SCH 2011062037)

BACKGROUND
This report transmits Amendment No. 2 to the Recycled Water Supply Agreement, which was approved by the Mountain View City Council on May 13, 2025, as a late packet supplemental report to Staff Report #2503-4327 (Agenda Item 10).

ATTACHMENTS
Attachment A: Amendment No. 2 to the First Amended and Restated Contract No. C059999 Between the City of Palo Alto and the City of Mountain View.

APPROVED BY:

Brad Eggleston, Director Public Works/City Engineer