ATTACHMENT A
Semiannual Update on the Status of Capital Improvement Program Projects

Capital Improvement Fund CIP Projects
• Buildings and Facili�es Projects
• Parks and Open Space Projects
• Streets and Sidewalks Projects
• Traffic and Transporta�on Projects
Enterprise Fund CIP Projects
• Airport Projects
• Electric Projects
• Fiber Op�cs Projects
• Gas Projects
• Stormwater Management Projects
• Wastewater Collec�on Projects
• Wastewater Treatment Projects
• Water Projects
List of Completed Project
Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 1 of 13
One‐Time Projects
Animal Shelter
Renovation
(PE‐19002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $2,921,108    $6,181,882  Public Works  Design  Fall 2027 Project  Status:   A  new  five‐year  agreement  with  Pets  in  Need  (PIN)  was  approved  by  Council  in  March  2024.

Discussions with PIN and City staff regarding capital projects started in late 2024, with a scope of work to be finalized with  PIN  in  early  2025.  Tentative  schedule  shows  design  complete  by  summer  2026  and  for  construction  to  start afterwards.

Baylands
Boardwalk
Piling Repair
(PE‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $182,854    $1,140,076  Public Works  Completed  Fall 2024 Project  Status:   This  project  repaired  damage  caused  by  aquatic  borers  to  The  Lucy  Evans  Baylands  Interpretive Center’s boardwalk pilings. The project received permits from the San Francisco Bay Regional Water Quality Control Board, Bay Conservation and Development Commission, United States Fish and Wildlife Services, and United States Army Corps of Engineers. The project was issued to bid in April 2024 and Council approved a construction contract in June 2024. Project construction began in early September and was completed by October 2024. The project will remain open until later fall 2025 after a one‐year monitoring report is submitted to the permitting agencies.

California
Avenue Parking
District Parking
Improvements
(PF‐25000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $110,102  Public Works  Design  Fall 2025
Project Status:  This project provides funding for parking improvements in the California Avenue parking district such as  parking  lot  resurfacing,  striping  and  signing;  parking  structure  painting  or  staining;  electrical  system  upgrades needed  to  support  improved  lighting  security,  parking,  fountains  and/or  other  systems;  and  replacement  or rehabilitation of parking lot signs.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $ 0  $ 137,628  Community Services  Pre‐Design  Summer 2025 Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 2 of 13
Children’s
Theater Facility
Upgrade/Repair
(AC‐28002)
Project  Status:   This  project  will  upgrade  and  repair  the  Children’s  Theatre  Facility,  including  backstage  work  and storage  areas,  classrooms,  performance  stages,  restrooms  and  public  spaces.  Phase  1  will  focus  on  procuring  a consultant to conduct a facility needs assessment and provide cost estimates.

City Facilities
Assessment and
Record Plan
Management
System
(PE‐20002)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $288,961  $333,134   Public Works   Completed  Fall 2024 Project Status: The Kitchell Report in 2008 summarized the last City‐wide facility condition assessment.  A new facility condition  assessment  is  warranted  per  the  City’s  APWA  reaccreditation  requirements.   All  City  facilities  will  be assessed  to  bring  current  the  “catch‐up”  and  “keep  up”  costs.   In  addition,  an  electrification  assessment  will  be included to help the City reach its sustainability goals for 2030.  Council awarded the contract in April 2022. All City facilities  have  been  assessed  for  the  Condition  and  Electrification  assessments.   A  detailed  list  of  buildings  for electrification is being analyzed to determine prioritization for replacements. The data has been updated into the City’s Infrastructure  Management  System  to  provide  long  range  capital  planning  based  on  the  results  of  the  FCA.  The Electronic Records Management System, originally included in this project, is being implemented through TE‐13004 utilizing Laserfiche as the sole repository for Public Works Engineering. The project reached completion in fall 2024.

City Hall Space
Planning
(PE‐19000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $52,615    $700,343  Public Works  Design  Fall 2026
Project Status:   This project involves space planning to determine future workgroup space needs and programming for the City Hall office building focused on the Police Department areas that will be vacated once the new Public Safety Building is complete and the City Hall Office Tower. The city completed solicitations for a qualified architectural firm to perform the space needs assessment for the two city facilities.  A contract is anticipated to be awarded in February 2025, with work to begin by spring 2025.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $2,710,140  Police Department  Design  Summer 2029
Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 3 of 13
City Radio
Replacement
Program
(PD‐25000)
Project Status: Two‐way commercial radios are used by many Departments in the City of Palo Alto. The City operates approximately 772 radios across 9 workgroups, including Police, Fire, Office of Emergency Services (OES), Community Services Park Rangers, Public Works, Utilities, Development Center, and Information Technology. This project will be used to replace the original digital radios.

Civic Center
Electrical
Upgrade & EV
Charger
Installation
(PE‐17010)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $656,289    $2,176,935   Public Works  Design  Winter 2027 Project Status: This project has installed EV chargers in existing downtown garages and will replace the aging Civic Center electrical switchgear and motor control centers.   EV charger construction at the Civic Center, Bryant Street garage and Webster Street garage was completed in December 2021. A contract was awarded in June 2021 for the design of the Civic Center switchgear replacement and is currently at the 90 percent design stage. Lead times on switch gear are now taking 18 months, so the project completion date has been extended. The structural analysis design of the  switchgear  area  and  its  permit  set  will  be  completed  in  April  2025.  Recent  plan  check  comments  required  a redesign to accommodate fire code updates and provided some cost savings benefit.

Civic Center Fire
Life Safety
Upgrades
(PE‐18016)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $904,269    $1,117,335  Public Works  Construction  Winter 2026 Project Status:   This project will assess, update, and replace the Civic Center fire alarm system and the emergency responder radio communication system (ERRCS).  The fire life safety system is approaching the end of its useful life.

The fire alarm panel and associated equipment need an upgrade to meet current code requirements.  The award of a design‐build contract was approved by Council in June 2021. Construction in the main tower areas is nearly complete.

The  ground  floor  and  the  garage  levels  have  been  completed.  The  project  completion  date  for  the  fire  alarm installation has been extended to winter 2025 due to ongoing testing issues. The ERRCS study will be conducted upon the completion of the planning and design for 275 Forest Avenue.

Civic Center  Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 4 of 13
Waterproofing
Study and
Repairs
(PE‐15020)
$798,460    $1,830,089  Public Works  Design  Fall 2026 Project Status: This project includes a condition assessment of the Civic Center Plaza deck structural system.  In 2016, RDH Building Science, Inc. determined that the expansion joint on the plaza could be repaired and that replacing the waterproof coatings on the inside of the plaza perimeter planter boxes was needed.  Repair of the waterproofing joint in front of City Hall was completed in winter 2023. Further study of the water intrusion into the garage was performed by a consultant in summer 2024; a design contract for repair of the planter boxes and garage water damage is expected in summer 2025.

Cubberley Gym
HVAC
Replacement
(CB‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $826,113  Public Works  Pre‐Design  Spring 2026
Project Status: The existing heating system in Cubberley Gyms A & B is original to the building, which was constructed in the mid‐1950s. The system is currently not functioning because multiple leaks have developed in the steel hot water piping, which is in the walls and under the floor. These leaks contributed (in addition to a domestic water main supply leak)  to  significant  water  damage  in  the  walls,  floors,  and  crawl  spaces  of  the  gyms.  Asbestos  and  mold  were remediated from the under‐floor crawl space.  All the old heating units and piping were removed from the ceilings in both gyms. The next step is to hire a consultant to create design drawings for a new heating system. This project has been  put  on  hold  due  to  the  City’s  pending  purchase  of  the  remaining  Cubberley  buildings  and  then  ultimately rebuilding a new Cubberley Community Center.

Fire Station 4
Replacement
(PE‐18004)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,860,907    $ 15,434,655  Public Works  Design  Winter 2026 Project Status: This project will replace Fire Station #4 at the corner of Middlefield Road and East Meadow Drive. The design consultant completed design development and received Planning approval for the project in November 2023.

A construction management contract was awarded in December 2023. The project has been submitted for building permit review, and the architect is preparing resubmittal. Pre‐qualification of bidders was completed in November Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 5 of 13
2024,  and  solicitation  for  construction  is  anticipated  for  spring  2025  with  construction  to  follow  in  summer  2025.

Construction of the temporary station will start in winter 2025.

Fire Training
Facility
Replacement
(FD‐24000)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $459    $55,293  Public Works  Pre‐Design  Summer 2026
Project Status: This project will identify an appropriate site and construct a new fire training facility in Palo Alto. This will  be  the  first  City‐owned  and  City‐maintained  permanent  fire  training  facility,  and  it  will  allow  training  to  be conducted within City limits and therefore reduce the downtime associated with the need for staff to travel for training and when responding to calls.

Homekey
Facilities
(PE‐24005)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $2,218,979    $4,944,710  Public Works  Construction  Spring 2025 Project Status: This project involves relocating the City of Palo Alto (City) GreenWaste facility from its current site on one portion of 1237 San Antonio Road to the rear portion of the same site as a result of adding the Homekey Palo Alto interim housing shelter. Homekey Palo Alto will be operated by LifeMoves who will provide intensive, customized case management  for  clients  including  counseling,  employment  and  housing  search  services  with  the  goal  of  paving  a dignified path to self‐sufficiency. The project is currently in construction.  The site work, utility infrastructure, building foundations,  and  energization  for  the  incoming  modular  units  has  been  completed.  Setting  and  finishing  of  the modular  units  will  soon  be  underway,  along  with  the  interior  completion  of  the  conventional  framed  community building and site landscaping.  Construction is anticipated to be completed in spring 2025.

JMZ Renovation
(AC‐18001)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $4,172,284   $5,020,310  Community Services  Construction  Summer 2025 Project Status: This project provides for the temporary relocation of the Junior Museum and Zoo and the construction of  a  new  facility  and  exhibits.  The  California  Dinosaur  Garden  exhibit,  which  is  partially  funded  by  a  reimbursable federal grant, was opened with a special ribbon cutting ceremony in October 2023.  Funds associated with the grant Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 6 of 13
are expended against the project until reimbursements are made.  Reimbursement has been submitted and expected in  the  first  quarter  of  FY  2025.  A  portion  of  the  project  was  extended  through  FY  2025  to  complete  the  list  of remediations, and equipment not purchased in FY 2024 due to staffing shortages. Completion is expected in July 2025.

Library
Automated
Material
Handling
(LB‐21000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $205,811   $1,898,292  Public Works  Construction  Fall 2028 Project Status:  This project will provide the design and construction of three new Automated Material Handling (AMH) Systems  for  the  Children’s,  Mitchell  Park  and  Rinconada  Libraries.  AMH  systems  efficiently  sort  returned  library materials based on the Radio Frequency Identification Devices (RFID) on the materials. For the Children’s Library, the building  permit  has  been  issued.  The  construction  contract  was  awarded  in  November  2024,  and  construction  at Children’s Library will begin in February 2025. Construction is anticipated to be complete by summer 2025.

Lucie Stern
Community
Theatre
Mechanical
Equipment
Replacement
(PE‐24002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $28,548    $2,443,408  Public Works  Pre‐Design  Winter 2027 Project Status:  This project will upgrade and replace the Heating Ventilation and Air Conditioning (HVAC) system at the Lucie Stern Community Theatre. As a first step, the project will include a detailed feasibility study to determine if natural  gas‐powered  equipment  in  the  facility  can  be  electrified  per  the  recommended  results  of  the  City‐wide electrification assessment. An RFP for design services is currently being compiled.

Lucie Stern
Community
Theatre Fire
Curtain
(AC‐24001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $241,374  Community Services  Pre‐Design  Fall 2026 Project Status: This project will replace the fire curtain and its associated rigging at the Lucie Stern Community Theatre.

The fire curtain work will be coordinated with the Theatrical and House Lighting System Replacement Project (PE‐ 24003).

Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 7 of 13
Lucie Stern
Community
Theatre Stage
Rigging System
Refurbishment
(AC‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $116,113  Community Services  Construction  Winter 2025 Project Status: This project will refurbish the most heavily used components of the stage rigging system at the Lucie Stern  Community  Theatre.  The  construction  contract  was  approved  by  City  Council  on  June  3,  2024.  Work  was scheduled to start in July 2024, but parts needed for the installation were delayed. Anticipated construction is now early 2025.

Lucie Stern
Community
Theatre
Theatrical
and House
Lighting System
Replacement
(PE‐24003)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $21,177   $333,210  Public Works  Design  Winter 2027
Project Status: This project will upgrade and replace lighting systems at the Lucie Stern Community Theatre for stage work areas, the performance stage, and audience areas. The bridging documents for the new system are complete and an RFP for a Design Build Entity will be submitted for bidding. The timing of this project will coincide with the Community Theatre Mechanical Equipment Replacement (PE‐24002).

Mitchell Park
Library Repair
(PE‐24006)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $15,083   $266,540  Public Works  Design  Fall 2025
Project Status: This project will repair the damage caused by a vehicular accident in January 2023. A vehicle ran into the north wall of the Mitchell Park Library near the center of the building. The car impacted an area of the stone cladding on cold‐formed steel studs, causing the cladding to fall from the wall and the wall to bulge into the building’s interior.  Architectural  and  structural  surveys  and  reports  were  completed.  The  stone  cladding  wall  will  require replacement, but the structural steel frame was not damaged. The design contract  was completed in October 2024.

Design documents are on track to be completed in spring 2025.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 8 of 13
Municipal
Service Center
Lighting,
Mechanical,
and Electrical
Improvements
(PF‐16006)
$1,195,776   $8,850,720  Public Works  Design  Winter 2027 Project  Status:  This  project  replaces  original  mechanical,  electrical,  and  lighting  systems  installed  in  1966.  It  also includes design and construction for office renovations for the Zero Waste group.  The electrical design is complete and the planning permit was approved in spring 2024. However, additional stakeholder review is needed to ensure the scope aligns with anticipated future capacity requirements.

New Downtown
Parking Garage
(PE‐15007)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,440,311  $17,300,000  Public Works  Design  Summer 2027 Project Status: In December 2021, Council directed staff to look at the feasibility of partnering with a private entity to develop new parking using downtown in‐lieu parking fees in conjunction with housing or other uses, including the use of  City  surface  lots  or  privately  held  parcels.  A  Request  for  Information  was  issued  in  December  2022  and  staff reviewed proposals and held interviews in May 2023. Council gave directions to staff in December 2023 to advance the project in conjunction with advancement of affordable housing in the Downtown area. In December 2024, the City executed  a  contract  with  Watry  Design,  Inc.  to  provide  for  design,  environmental  review,  and  construction administration services for the New Downtown Parking Garage. Concept designs will be presented to City Council in spring 2025.

New Public
Safety Building
(PE‐15001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $113,275,793   $ 123,500,000  Public Works  Construction  Spring 2025 Project Status: This project will provide a new, modern Public Safety Building (PSB) that will meet essential services standards and the current and future needs of the public safety departments.  The PSB and new garage in the California Avenue  business  district  are  now  an  integrated  project  and  both  are  part  of  the  2014  Council  Infrastructure  Plan.

Construction on the PSB started in March 2021 and will continue into spring 2025. The Tier 4 emergency generator has completed source testing. Punch list and department inspections are in progress. The project is expected to obtain temporary certificate of occupancy in early 2025.

Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 9 of 13
Palo Alto Art
Center
Ceramics
Equipment
(AC‐28003)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0   $181,367  Community Services  Design  Summer 2026
Project Status: This project renews and replaces ceramics program equipment, upgrades facility Wi‐Fi and electrical infrastructure, and waterproofs outdoor kiln sheds.  The majority of the Art Center’s existing ceramics equipment was obtained during the renovation of the Art Center in 2011 and 2012.  These pieces of equipment are showing signs of aging, necessitating facility updates.

Performing Arts
Venues Seat
Replacement
(AC‐18000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $663,022   $1,281,909  Public Works  Construction  Summer 2025 Project Status:  This project will replace all the seats in the Community and Children’s Theatres.  Staff hired a consultant to design the seat replacements and ADA upgrades for the Children’s Theatre portion of the project.  The Children’s Theatre seats replacement was completed in November 2022.  A contract for the design of the Community Theatre was issued in June 2023.  Council approved a construction contract on April 22, 2024, with project completion expected in fall 2024. The installation of the ADA upgrades and auditorium seats are complete with additional companion seats arriving in February. Painting of the auditorium will be completed in the summer 2025.

Rinconada Pool
Family
Changing Room
(PE‐24004)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $34,922    $1,397,698  Public Works  Design  Winter 2026 Project Status:  The project will construct a gender‐neutral restroom and family changing facility that is compliant with the Americans with Disabilities Act (ADA) at the Rinconada Pool. The facility will include two separate rooms, each consisting of a toilet, sink, shower, and child/adult changing station. The facility will provide community members who have special needs, and individuals who require privacy, an accessible space for changing and personal hygiene. Design of the family changing rooms started in December 2024.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $6,927,119   $11,367,366  Public Works  Construction  Winter 2024 Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 10 of 13
Roth Building
Rehabilitation
Phase 1
(PF‐23001)
Project Status: This project provides funding for Phase 1 of the rehabilitation and build‐out of the Roth Building facility.

Phase  I  will  make  the  building  suitable  for  occupancy,  also  known  as  a  “warm  shell.  Phase  II  of  the  rehabilitation includes the interior build‐out of the museum and exhibits, readying the facility to welcome visitors, and will be funded by  the  Palo  Alto  History  Museum  (PAHM).  A  Tenant  Work  Letter  was  approved  by  Council  in  April  2023  and construction is underway including underground utilities, roof, demolition, and abatement. Phase I of this project will be substantially completed in February 2025.

Recurring Projects
Americans
With
Disabilities Act
Compliance
(PF‐93009)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0  $880,820  Public Works  N/A  Recurring
Project  Status:   This  project  provides  accessibility  upgrades  to  City  facilities  and  equipment.  It  includes  continued funding  for  improvements  such  as  path  of  travel,  restrooms,  drinking  fountains,  and  counters.  An  updated  ADA Transition Plan was adopted by Council in June 2021. Staff is waiting to solicit new software that will allow staff to identify and log new barriers, track grievances from the public, and update the ADA Transition Plan Report.

Building
Systems
Improvements
(PF‐01003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $77,759  $1,366,177  Public Works  N/A  Recurring
Project  Status:   This  project  provides  electrical,  mechanical,  plumbing,  structural,  and  security  upgrades  for  City facilities. The UCC Emergency Generator Replacement project is currently in permitting. Once permitting is approved, the project will be go out to bid in spring 2025. The City Hall Cooling Tower Overhaul project contract was signed in December 2024.  The material lead time is 12 to 14 weeks, pushing back construction until spring 2025.

Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 11 of 13
City Facility
Parking Lot
Maintenance
(PE‐09003)

Prior Year Actuals   Current Year Budget  Implementing Department  Project Phase  Project Completion $0  $567,564  Public Works   N/A   Recurring
Project  Status:   This  project  repairs,  resurfaces,  or  reconstructs  parking  lots  and  walkways  at  various  City  facilities, including  restriping  and  signage.  The  Cubberley  Community  Center  restriping  and  base‐failure  repair  work  was completed in fall 2024.

Cubberley
Repairs
(CB‐17001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $309,506  $746,556  Public Works  N/A  Recurring
Project Status:   This project is for general maintenance needs of the Cubberley campus. Gym B completed floor sanding, game line repainting, and refinishing in July 2024.  One third of the hardwood flooring and subflooring has been restored in Gym A due to water damage.  All repair work on Gyms A & B have been completed and the facilities are ready to rent out.

Cubberley
Roof
Replacements
(CB‐16002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $27,039  $1,224,164  Public Works  N/A  Recurring
Project Status: This project replaces existing roofs at Cubberley Community Center. The Pavilion Roofing project was canceled due to the City’s pending purchase of the remaining Cubberley buildings and then ultimately rebuilding a new Cubberley Community Center.

Electric
Charger
Infrastructure
Installation
(PF‐23000)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $63,243  $ 122,453  Public Works  N/A  Recurring
Project Status: This project designs and installs electric vehicle chargers at various City facilities. The primary use of the electric vehicle chargers will be for City fleet vehicles. The City Hall Level C EV Charger project to install six new chargers on Level C of the parking garage is complete.

Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 12 of 13
Electrification
of City
Facilities
(PE‐24001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $ 204,162  $1,358,531  Public Works  Pre‐Design  Fall 2030 Project Status: This project will evaluate feasibility, prepare designs, and implement construction for the electrification of fossil fuel consuming building systems in coordination with the Building Systems Improvements project (PF‐01003).

The City Facility Electrification assessment report will act as a workplan to implement the electrification of City facilities.

An RFP for an on‐call task order consultant for all City facilities requiring electrification will be issued in summer 2025.

Facilities will be electrified in order by priorities set by the Electrification Assessment to facilitate reaching the S/CAP goals.  Funding  is  also  included  for  the  HVAC  electrification  upgrade  at  the  445  Bryant  Street  property.   Mechanical design for the replacement of seven package units and one exhaust fan is 90% complete.  Expect 100% design by early January 2025.

Facility
Interior
Finishes
Replacement
(PF‐02022)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $83,323  $615,564  Public Works  N/A  Recurring
Project  Status:  This  project  improves  the  interior  finishes  of  City  facilities,  including  flooring,  walls,  cabinets,  paint, lighting,  ceiling  tiles,  soundproofing,  and  fixed  office  furniture,  doors,  windows,  and  associated  fire/life  safety, mechanical, electrical and plumbing code compliance requirements. New carpet has been selected for the Children’s Library with work scheduled for spring 2025.

Fire
Equipment
Replacement
(FD‐25000)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0  $113,405  Fire Department  N/A  Recurring
Project Status: This project funds ongoing replacement of Fire and Emergency Medical Services (EMS) equipment used for training, medical response, and technical rescue in all emergency situations.

Police Video
Recording
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $ 10,751  $ 203,503  Police Department  N/A  Recurring
Buildings and Facilities Projects          Status as of December 2024 Buildings and Facilities Projects – Page 13 of 13
Systems
Replacement
(PD‐20000)
Project Status: This project maintains the Palo Alto Police Department video recording systems used to record events in the field with up to five in‐car cameras as well as body‐worn cameras (BWC).  In FY 2024, the City solicited for a new vendor to include the in‐car and BWC systems and newly added fixed interrogation systems in the PSB. A vendor was selected, and City Council approved a Purchase Order. Materials have been shipped, and the transition is in process.

Full  implementation  is  expected  to  be  completed  on  or  around  the  end  of  FY  2025.  The  CIP  will  remain  open  to coordinate with the vehicle replacement cycle.

Roofing
Replacement
(PF‐00006)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $447,681  $1,316,825  Public Works  N/A  Recurring
Project Status: This project replaces existing roofs at City facilities that have outlived their useful lifespans.  The Animal Shelter roof recoat has been delayed due to roof modifications required for the proposed kennel remodel. Permits for the Phase 2 of the Lucie Stern Community Center roof replacement project have been completed. This project will go out to bid in early 2025 with construction to start in summer 2025.

University
Avenue
Parking
Improvements
(PF‐14003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0  $171,116  Public Works  N/A  Recurring
Project  Status:  This  project  maintains  parking  lots  and  parking  structures  within  the  University  Avenue  Downtown Business Parking District. There is no work planned for parking improvements in the first half of FY 2025.

Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 1 of 9
One‐Time Projects
Baylands
Comprehensive
Conservation
Plan
(PG‐17000)

Prior Years Actuals     Total Project Budget  Implementing Department  Project Phase  Project Completion $386,401  $438,413  Community Services  Design  Summer 2026 Project  Status:  This  project  provides  funding  for  a  conservation  plan  that  will  examine  native  vegetation,  wildlife habitat resources, and wildlife‐appropriate public access for the entire Baylands, including Byxbee Park. This plan will provide information to successfully manage wildlife habitat and provide  trails or other recreation amenities; provide a design overlay for appropriate types and locations of public art in the Baylands; and design interpretive messaging throughout the Baylands. The plan seeks to optimize opportunities for low‐impact recreation ensuring that these are compatible with the Baylands Master Plan direction for passive use of the nature preserve. The Conservation Plan will also provide input for the Byxbee Park Completion project. The Parks and Recreation Commission has created an Ad Hoc Committee to work with staff on this project. Staff and the Ad Hoc Committee have been  reviewing the draft plan and identifying gaps and highlighting where updates are required.

Baylands
Interpretive
Signage
Program
(OS‐24001)
Prior Years Actuals     Total Project Budget  Implementing Department  Project Phase  Project Completion $  $178,366  Community Services  Construction  Spring 2025 Project Status: This project was originally planned for 2018‐2021 but was delayed due to project priorities involved with the moving of the Junior Museum & Zoo to Cubberley Community Center and construction of the newly rebuilt Junior  Museum  &  Zoo.  The  project  will  install  interpretive  signage  and  exhibits  on  two  miles  of  trails  and  on  the boardwalk at the Palo Alto Baylands. Construction is anticipated to be complete by spring 2025.

Boulware Park
Improvements
(PE‐17005)
Prior Years Actuals     Total Project Budget  Implementing Department  Project Phase  Project Completion $2,937,729   $5,782,383  Public Works  Construction  Spring 2025 Project Status: This park renovation project was initially planned in FY 2018 but was postponed due to project priorities and potential purchase of the adjacent AT&T lot located at 3350 Birch Street. In fall 2019, the lot was purchased by the City.  A  Park  Improvement  Ordinance  for  the  improvements  was  adopted  by  the  City  Council  in  October  2021.  A Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 2 of 9
construction contract was awarded in June 2023, and the project construction began in August 2023. Current site work is 85% complete. The project is anticipated to be completed by spring 2025

Byxbee Park
Completion
(PE‐18006)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $368,192  $3,699,189  Public Works  Pre‐Design  Summer 2028 Project Status: This project allows for the remaining improvements to Byxbee Park that follow the completion of the landfill  capping  work.  The  Baylands  Comprehensive  Conservation  Plan  (BCCP),  which  is  currently  undergoing  CEQA analysis, will include recommendations on the scope of the Byxbee Park project. The BCCP and the conceptual plan for Byxbee Park need additional outreach and review which is anticipated to continue through fiscal year 2026.  The project has been moved to FY 2027 pending completion of the BCCP.

Cameron Park
Improvements
(PG‐14002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $205,627  $538,898  Community Services  Completed  Fall 2024 Project Status: This project upgraded and renovated safety and accessibility features at Cameron Park with a primary focus on the park playground improvements. The Cameron Park Improvements Project was completed in November 2024.

Cubberley Field
Restroom
(CB‐17002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $776,349  $1,452,876  Public Works  Construction  Spring 2025 Project Status: This project will install a new restroom in the sports field area of the Cubberley Community Center. In June  2023,  Council  approved  a  purchase  order  with  the  Public  Restroom  Company  for  a  four‐stall  prefabricated restroom  building.  Council  awarded  a  construction  contract  for  site  work  in  September  2024.  The  prefabricated restroom  building  was  installed  in  December  2024.  The  sewer  pump  station  and  remaining  site  utilities  work  are anticipated to be completed by spring 2025.

Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 3 of 9
El Camino Park
Turf
Replacement
(PG‐24000)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $ 40,000  $931,121  Community Services  Design  Summer 2026 Project Status: This project has been paused and City Council has provided direction to use a portion of this CIP funding to  complete  a  comprehensive  study  comparing  synthetic  turf  fields  to  natural  grass  fields.  The  study  will  assess environmental and health impacts, field utilization capacity, and capital and operating costs required for both types of fields. Once complete, the study will enable staff to provide recommendations to City Council for replacement.

Eucalyptus Tree
Removal
(PG‐25002)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $  $110,102  Community Services     Construction  Fall 2025 Project Status: This Hazardous Fuel Abatement project  identified eucalyptus trees from the City of Palo Alto’s open space preserves for removal. During Phase 1 of this CIP, 36 Eucalyptus trees were removed within Esther Clark Park to reduce hazardous fuels adjacent to homes in the Palo Alto Wildland Urban Interface. Foothills Nature Preserve and Arastradero Preserve are to be evaluated for further Eucalyptus tree removals pending available resources.

Foothills Nature
Preserve
Boronda Lake
Dock
Replacement
(OS‐18000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $278,470  Public Works  Design  Summer 2026
Project Status: This project is a refurbishment of the existing dock. The dock was originally built in 1965 and was last refurbished in 2010 with repairs to the wood decking. The current condition of the dock has declined and now requires a complete replacement with new decking, ramp, floats, and pilings. Design for the Foothills Nature Preserve Boronda Lake Dock renovation is currently in progress.

Foothills Nature
Preserve Dam
Seepage
Investigation
and Repairs
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $42,170  $112,716  Public Works  Design  Spring 2025
Project Status: This project will study the location of historic seepage from the Foothills Nature Preserve Dam at the sharp bend in the road on the face of the dam and will locate and investigate the pipe and trench backfill material. The source  of  the  seepage  is  suspected  to  be  the  trench  backfill  around  the  pipe  that  returns  shallow  groundwater  to Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 4 of 9
(PE‐20000)  Boronda Lake.  Staff continue to monitor and investigate the seepage per the Department of Water Resources Division of Safety of Dams (DSOD) inspections and recommendations. Staff completed camera inspections of the underdrain pipes  to  identify  potential  obstructions  and  leakage  issues.  Per  the  DSOD  recommendations,  the  City’s  consultant completed a field assessment in fall 2024 identifying location of a seepage weir on the downstream side of the Foothill Nature  Preserve  Dam.  The  weir  is  anticipated  to  be  installed  by  early  2025  which  will  allow  the  City  to  collect quantitative measurements of the seepage flow and inform the seepage trends and needs for a long‐term solution as necessary.

Foothills Nature
Preserve
Improvements
(PE‐21000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $246,859  $3,710,577  Public Works  Design  Summer 2028 Project Status: This project has repaired the bridge to Sunfish Island, and will complete the design and permitting to replace the footbridge in Los Trancos Valley, replace the grade control structures along Buckeye Creek, provide new split rail fencing to protect sensitive areas, new pedestrian pathways to keep park visitors safe while walking along the park road, and improvements to some of the existing parking areas to make them safer and more efficient. Council awarded  a  professional  services  contract  for  additional  outreach,  detailed  design  and  bid  package  preparation  for pathways, fencing and parking improvements in spring 2024. Preliminary renderings have been prepared, and staff anticipate outreach and preliminary design in early 2025. The replacement of the footbridge in Los Trancos Valley and the grade control structures along Buckeye Creek have been moved to FY 2027 and FY 2028 due to staffing constraints.

Golf Course Net
and Artificial
Turf
Replacement
(PG‐18000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $925,056  Community Services  Pre‐Design  Summer 2027 Project Status: This project will remove and replace the golf course driving range netting and synthetic turf. This project has been delayed due to the assessment of  additional ball retention needs throughout the golf course and the ongoing development of a potential long‐term partnership with the First Tee of Silicon Valley for driving range and practice facility improvements.

Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 5 of 9
Heritage Park
Site Amenities
Replacement
(PG‐21000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $143,134  Community Services  Construction  Summer 2025 Project Status: The project will replace select walkways and all of the site amenities in Heritage Park including benches, picnic tables, trash receptacles, playground arbor, bicycle racks and drinking fountain. In the first half of FY 2025, staff conducted a site assessment to ascertain the full extent of site furnishings to be replaced, with replacement targeted in summer 2025.

Ramos Park
Improvements
(PG‐14000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $279,354  $682,057  Community Services  Construction  Spring 2025 Project  Status:    This  project  replaces  the  playground  equipment  at  Ramos  Park.  Council  awarded  a  cooperative agreement with Ross Recreation in June 2024 to replace and install the playground equipment for Ramos Park. Work is anticipated to be completed by spring 2025.

Rinconada Park
Improvements
(PE‐08001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $5,447,216  $10,176,310  Public Works  Construction  Fall 2027 Project Status: This project provides upgrades to safety, site amenities, playground facilities, a new restroom, irrigation, drainage,  and  ADA  accessibility  improvements  at  Rinconada  Park.  These  improvements  were  identified  in  the Rinconada Long Range Plan (LRP).  Phase 1 park improvements to the western half of the park were completed in spring 2022. A new park restroom was installed and opened to the public in summer 2024. Funding was approved by Council in FY 2025 for City to complete structural and electric design for replacement of a storage unit (purchased by Palo Alto Tennis Club (PATC) at Rinconada Park. The design and a Memorandum of Understanding between City and PATC are in progress. Staff anticipate submitting a building permit application for the storage unit upon completion of design work by early 2025.  According to the LRP, future improvement phases will include improvements to the eastern half of the park by FY 2028 including pathway improvements, ADA upgrades, planting, irrigation, lighting, and site furnishings.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 6 of 9
Robles Park
Improvements
(PE‐18015)
$161,765  $742,055  Public Works  Design  Fall 2025
Project Status: This project will replace playground equipment. Community meetings were held in September 2023 and March 2024 to obtain community input. An online community survey regarding the play equipment is currently underway and will end in January of 2025. If the proposed playground equipment is supported by the community, a cooperative agreement with Ross Recreation will be processed.  Due to fabrication lead times, it is anticipated the new playground equipment will be installed in fall 2025.

Stanford Palo
Alto Community
Playing
Fields Turf
Replacement
(PG‐26000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $  $2,707,547  Community Services  Design  Summer 2025
Project Status: The project provides funding for the replacement of synthetic turf at the Stanford Palo Alto Community Playing Fields. The Stanford Palo Alto Community Playing Fields accommodate year‐round play, including additional evening play with some temporary lighting. Since the turf was installed in 2016, it has been in high demand and is used by youth and adult leagues as well as walk‐on play. Synthetic turf has a typical lifespan of approximately eight to ten years with each year of use contributing to gradual wear and tear resulting in loss of pile height, turf fiber, and infill.

The design was completed in fall 2024, and construction is scheduled to begin in spring 2025 through an approved sole source contract.

Recurring Projects
Art in Public
Spaces
(AC‐86017)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $189,175   $1,823,508  Community Services  N/A  Recurring Project Status: This project provides the ongoing temporary and permanent artworks throughout the City of Palo Alto. Two new artworks were installed at the Public Safety Building, and one more will be installed in early 2025, a new mural was painted at Cubberley, artwork was installed at Boulware Park, and artwork is under development for Fire Stations 4 and 5, and for three murals downtown. Twenty utility box projects were painted throughout the City Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 7 of 9
during fall 2024. Other projects in process include the ongoing King Artist‐in‐Residence with artist Alma Landeta, including the development of temporary artwork for King Plaza, and preparations for the 2025 Code: ART festival.

Athletic Courts
Resurfacing
(PG‐06001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $22,294  $194,499  Community Services  N/A  Recurring
Project Status: This project repairs and resurfaces athletic courts in various Palo Alto parks. The reconfiguration and resurfacing of the Greer Park basketball courts is scheduled to begin construction in spring 2025.

Benches, Signage,
Walkways,
Perimeter
Landscaping
(PG‐06003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $513,204  $325,544  Community Services  N/A  Recurring
Project Status: This project restores and replaces existing benches, signage, fencing, walkways, and landscaping at various City facilities. The refurbishing of the wooden picnic tables at Rinconada Park was completed in summer 2024. In November 2024 a design consultant was hired for the design of the Lytton Plaza fountain grate. Lytton Plaza design is scheduled for completion in winter 2024 and construction of the fountain grate is estimated for spring 2025.

Dog Park
Installation and
Renovation
(PG‐18001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $30,278  $0  Community Services  N/A  Recurring
Project Status: This project enables the construction of dog parks at various City parks and facilities for constructing new or renovating existing dog parks. A new dog park will be added with the Boulware Park expansion project for which construction started in summer 2023. Council approved a Park Improvement Ordinance in September 2022 for the expansion of the Mitchell Park Dog Park. Mitchell Dog Park installation and expansion began in fall 2024 and was completed in April2025.

Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $22,075   $269,457  Public Works  N/A  Recurring
Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 8 of 9
Off‐Road Pathway
Resurfacing and
Repair
(OS‐09001)
Project  Status:  This  project  repairs,  resurfaces,  or  replaces   pathways  as  needed  within  the  City  of  Palo  Alto.

Pathways are chosen based on safety inspections, condition, and usage. Open Space pathways are currently under review for repair.

Open Space Lakes
and Pond
Maintenance
(OS‐00002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $27,900   $78,037  Community Services  N/A  Recurring
Project Status: This project rehabilitates lakes and ponds in open space nature preserves to protect wildlife habitat and recreational safety and to meet State Division of Safety of Dams requirements. A new three‐year contract was awarded in July 2024 for the removal of aquatic vegetation in Boronda Lake.

Open Space Trails
and Amenities
(OS‐00001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $360,820   $296,701  Community Services  N/A  Recurring Project Status: This project restores unpaved trails, fences, picnic areas, and campgrounds at Foothills, Baylands, and Pearson‐Arastradero Nature Preserves. Work performed in summer 2024 included approximately 60 acres of firebreak  maintenance and  fire  road  mowing. A  new  five‐year  maintenance  contract  was  awarded  in  November 2024. Work performed in December 2024 included the reconstruction of a degraded levee in the Baylands Nature Preserve, and maintenance of 25 miles of trailside vegetation in the Foothills Nature Preserve.

Parks and Open
Space Emergency
Repairs
(PG‐09002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $192,025  $335,109  Community Services  N/A  Recurring
Project Status: This project replaces or repairs playgrounds, play yard surfaces, wooden structures, park amenities, and play equipment in the event of storms, fire, vandalism, or structural failure. In fall 2024, GMAX impact safety testing was conducted on four artificial turf sports fields located at Cubberley Community Center, El Camino Park, and Stanford Palo Alto Community Playing Fields to ensure safety compliance and evaluate surface performance. In fall  2024,  replacement  of  two  water  meters  on  California  Avenue  were  completed.  In  December  2024,  fencing Parks and Open Space Projects           Status as of December 2024

Parks and Open Space Projects – Page 9 of 9
repairs  were  completed  at  El  Camino  Park  and  repairs  to  the  permeable  parking  lot  pavers  are  scheduled  for completion in January 2025.

Park Restroom
Installation
(PG‐19000)
Prior Years Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $485,995  $693,359  Community Services  N/A  Recurring
Project Status: This project installs new restrooms at City parks that currently do not have restroom facilities. City Council approved a Park Improvement Ordinance for Ramos Park. In April 2023, Council approved a purchase order with the Public Restroom Company for a two‐stall prefabricated restroom building at Ramos Park. Staff completed design  and  obtained  a  building  permit  for  site  work  and  restroom.  On  December  18,  2023,  Council  awarded  a construction  contract  for  the  restroom  site  work.  In  summer  2024  the  Ramos  Park  restroom  construction  was completed and opened to the public.

Streets and Sidewalks Projects           Status as of December 2024

Streets and Sidewalks Projects – Page 1 of 5

One‐Time Projects
California Avenue
District Gateway
Signs
(PE‐17004)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $26,943  $162,783  Public Works  Design  Fall 2025
Project  Status:  This  project  includes  the  design  and  replacement  of  two  existing  gateway  signs  for  the  California Avenue business district. Initial public outreach was completed in winter 2021. The California Avenue District Gateway Signs project is in the next phase of improvements following the California Avenue Streetscape update and near‐term improvements. The signage plan, including district gateway signs, will be discussed with the Architectural Review Board in Spring 2025 and presented to City Council for approval later in 2025.

Newell Road
San
Francisquito
Creek Bridge
Replacement
(PE‐12011)

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $3,957,812   $23,456,670  Public Works  Design  Fall 2026 Project Status: This project removes and replaces the Newell Road bridge over San Francisquito Creek with a clear span to allow the channel to convey up to the natural capacity of the San Francisquito Creek, approximately 7,500 cubic feet per second, and to improve safety for vehicular, bicycle, and pedestrian traffic. The project is being closely coordinated with the City of East Palo Alto, Valley Water, and San Francisquito Creek Joint Powers Authority (SFCJPA).

In the second half of FY 2024, staff acquired the eight easements needed to complete the project, obtain a permit from Regional Water Quality Control Board and a draft permit from California Department of Fish and Wildlife along with encroachment permits from East Palo Alto and Santa Clara Valley Water District. Staff and consultants worked with PG&E, Comcast, AT&T, City of East Palo Alto Water and City of Palo Alto Utilities on the Utility Relocation letters needed for Caltrans’ review and approval. The right‐of‐way acquisition and permitting was completed in September 2024. The request for Caltrans to authorize the start of the construction phase with the construction funding that was previously approved is still under review. Once approval is received from Caltrans staff will solicit bids for construction in spring 2025.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $8,799  $274,309  Public Works  Design  Fall 2025
Streets and Sidewalks Projects           Status as of December 2024

Streets and Sidewalks Projects – Page 2 of 5

Streetlights
Condition
Assessment
(PE‐13014)
Project Status: This project will assess the condition of the City’s streetlight system. The assessment will include an inventory of the entire lighting system, including age and condition of conduit, wiring, streetlight poles, foundations, luminaires,  and  lighting  coverage.  The  project  will  also  determine  the  inspection,  maintenance,  repair,  and rehabilitation necessary to prolong the life of the City’s streetlight system. This project has not started due to staffing constraints.

Recurring Projects
City Bridge
Improvements
(PE‐20001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $200,258  $1,704,161  Public Works  N/A  Recurring
Project Status: This project includes bridge inspections, maintenance, repair, and an improvement program over the next  five  years.  This  program  will  include  on‐going  inspections  to  report  physical  changes  to  the  structures, recommendations for work to be done, and additional information to meet functional and structural standards in accordance  with  industry  standards.  Staff  hired  an  on‐call  structural  engineering  firm  to  assist  with  the  bridge inspection and repair program. Staff completed design and bidding for repairs of seven bridges identified for repairs in winter 2023. A construction contract was awarded by the Council in March 2024. Bridge construction repair work began in September 2024 and was completed in December 2024. Staff will continue recurring inspections and repairs of City bridge structures as needed.

Curb and Gutter
Repairs
(PO‐12001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $1,519  $114,506  Public Works  N/A  Recurring
Project Status: This project repairs curbs and gutters uplifted by tree roots. Funding for FY 2023 was carried over into FY  2024  for  a  larger  curb  and  gutter  repairs  project  focusing  on  the  City’s  Sidewalk  Districts  1  &  2  that  includes Streets and Sidewalks Projects           Status as of December 2024

Streets and Sidewalks Projects – Page 3 of 5

Downtown North and University South neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middlefield Road) in addition to addressing hot spot locations from 311 requests. Approximately 2,136 linear feet of curbs  and  gutters  are  included  in  the  FY  2024  Sidewalk  Repair  ADA  Improvement  Project.  Council  approved  the construction contract on June 10, 2024.  Construction of curb and gutter repairs began in September 2024, prioritizing locations with CDBG funding, with the construction work estimated to be completed by February 2025.

San Francisquito
Creek Joint
Powers
Authority
Ongoing Creek
Projects
(PE‐22000)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $108,514   $220,205  Public Works  N/A  Recurring
Project Status: This project provides funding for studies and completion of the design for the San Francisquito Creek Joint Powers Authority (JPA) upstream project including channel widening and Continuing Authority Program Section 205 (CAP 205) study.   In FY 2024, the JPA awarded a contract with WRA Environmental Consultants to analyze the creek  hydraulics  and  the  improvement  alternatives  that  could  reduce  flooding.  The  Master  Service  Agreement includes  the  design  and  implementation  of  Reach  2  project  elements.  WRA  completed  their  initial  field  survey, developed  a  preliminary  list  of  improvement  alternatives  and  provided  the  initial  presentation  to  the  public  in November. Their efforts will be driven based on public feedback and direction from the SFCJPA Board. A preferred alternative will be determined in 2025.

Sidewalk Repairs
(PO‐89003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $1,265,080   $ 1,445,415  Public Works  N/A  Recurring
Project Status: This project repairs and replaces broken and uplifted sidewalks. The program completed all twenty‐ three sidewalk districts in 2017, a 30‐year (1986–2017) sidewalk repair district cycle. Council approved a sidewalk assessment contract in November 2017 to evaluate the sidewalk program and assess potential improvements to the current district‐based program. Funding for FY 2023 has been carried over into FY 2024 for a larger sidewalk project.

The FY 2024 Sidewalk Repair ADA Improvement Project will focus on sidewalk repairs (PO‐89003) and curb and gutter repairs (PO‐12001) in the Downtown Professorville neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middlefield Road). Council approved the construction contract on June 10, 2024. The project aims to replace Streets and Sidewalks Projects           Status as of December 2024

Streets and Sidewalks Projects – Page 4 of 5

approximately 23,199 square feet of concrete sidewalk, 4,309 square feet of driveways, install 86 new curb ramps, and retrofit 33 existing curb ramps with truncated domes to conform to the Americans with Disabilities Act (ADA).

Sidewalk repairs included in this project are estimated for completion in February 2025.

Sign Reflectivity
Upgrade
(PO‐11000)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $6,692   $ 55,052  Public Works  N/A  Recurring
Project Status: This project includes the annual inventorying, upgrading and maintaining of all traffic signs.  A list of signs not meeting the minimum requirement is derived from MUTCD approved Nighttime Visual Inspection surveys.

Staff will continue to work on replacing the 405 signs identified for replacement from the FY 2024 survey.   Due to continuing staffing constraints, nighttime reflectivity surveys are not planned for FY 2025.

Streetlight
Improvements
(PO‐05054)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $210,264  $399,481  Public Works  N/A  Recurring
Project Status:  This project replaces streetlights, including poles, pole foundations, luminaires and wiring as needed to restore or improve street lighting.   In the second half of FY 2024, there were four knockdown locations with six completed repairs and eleven are still in progress to be completed in FY 2025.

Street
Maintenance
(PE‐86070)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $3,892,921  $5,531,353  Public Works  N/A  Recurring
Project Status: Street Maintenance Projects include the annual resurfacing, micro‐seal, crack seal, and reconstruction of various city streets in support of the Council’s goal of achieving a citywide average pavement condition index (PCI) score of 85, representing very good or excellent conditions. The FY 2024 Street Resurfacing Project will replace 10,149 square feet of sidewalk, 3,371 square feet of driveway, 2,280 linear feet of curb and gutter, construct 37 new ADA curb ramps, and will place 9,844 tons of asphalt concrete overlay, 36 blue markers, 384 thermoplastic legends, and 39,615 LF of thermoplastic striping on the streets of Palo Alto. The FY 2024 Street Resurfacing Project is completed except  for  the  resurfacing  of  University  Avenue  due  to  an  existing  Gas  Main  Replacement  Project  still  under Streets and Sidewalks Projects           Status as of December 2024

Streets and Sidewalks Projects – Page 5 of 5

construction.  University  Avenue  will  be  resurfaced  in  spring  2025  once  the  Gas  Main  Replacement  Project  is completed.  The  FY  2024  Street  Preventive  Maintenance  Project  was  completed  in  October  2024.  The  FY  2024 Preventive  Maintenance  Project  micro‐surfaced  14.23  lane‐miles  of  streets,  replaced  19,200  LF  of  thermoplastic striping, installed 85 thermoplastic legends, and updated 77 blue markers. Together, both the Street Resurfacing and Preventive Maintenance Projects will maintain and improve the City’s Pavement Condition Index (PCI) beyond its average of 84 and will address many streets whose PCI scores fall below the City’s minimum goal of 60.

Thermoplastic
Lane Marking
and Striping
(PO‐11001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0  137,628  Public Works  N/A  Recurring
Project Status: This project maintains thermoplastic markings on roadways. Thermoplastic lane marking and striping are  incorporated  into  annual  Pavement  Preventive  Maintenance  Projects.  The  FY  2024  Streets  Preventive Maintenance Project (PE‐86070) was completed in October 2024 and installed 12,400 LF of thermoplastic striping and 33 thermoplastic legends.

Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 1 of 8
One‐Time Projects
California Avenue
Streetscape
Update
(PL‐23000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $84,054   $560,583  City Manager’s Office  Design  Spring 2025 Project Status: The project provides funding for interim changes to the street and for necessary CEQA analysis for  the  future  configuration  of  the  street.  Interim  changes  to  the  street  will  take  place  in  early  2025.  CEQA analysis will be brought forward to the Planning and Transportation Commission and City Council in spring 2025.

Charleston
Road/Alma Street
Railroad Crossing
Safety
Improvements
(PL‐25002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $1,298,512  Office of Transportation  Design  Fall 2027 Project  Status:  The  California  Department  of  Transportation,  in  cooperation  with  the  Peninsula  Corridor  Joint Power Board (JPB) and the City of Palo Alto, proposed a railroad crossing improvement project at Charleston Road and Alma Street to enhance traffic safety. This crossing was identified for possible funding of hazard elimination and  safety  improvements  through  Section  130  funds.  The  Section  130  program  is  a  federal‐funded  program, administered  at  the  state  level,  for  the  elimination  of  hazards  at  at‐grade  highway‐rail  crossings.  Section  130 funding will reimburse the actual and direct costs of the design and construction of the improvements. This project is  separate  and  independent  from  the  on‐going  rail  grade  separation  projects  and  addresses  more  immediate safety  concerns  at  this  crossing.  The  railroad  crossing  at  Alma  Street  and  Charleston  Road  experiences  a  large volume of pedestrian and bicycle traffic during the morning and afternoon school commute hours. JPB and the City will be responsible for the construction of the improvements within each respective agency’s right of way.

Churchill Avenue
Enhanced
Bikeway
(PL‐14000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $418,211    $4,914,801  Public Works  Design  Winter 2026 Project Status: This project includes planning, design and construction of a shared‐use path along the north side of Churchill Avenue between the existing shared‐use path at Castilleja Avenue and the Stanford Perimeter Trail.  It also  includes  intersection  improvements  at  Churchill  Avenue  and  El  Camino  Real,  which  will  include  a  new dedicated westbound right‐turn lane. PAUSD approved the easements required for the project in August 2023.

Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 2 of 8
Staff has worked with Caltrans for re‐issuance of the encroachment permit and received approval in June 2024.

The  construction  contract  was  approved  by  Council  on  December  9,  2024.  The  project  is  anticipated  to  be completed by winter 2026.

Churchill Avenue
Rail Grade
Separation and
Safety
Improvements
Main
(PL‐24001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $21,018   $198,542,138  Office of Transportation  Design  Spring 2029 Project  Status:  This  project  provides  for  the  planning,  design,  and  construction  of  the  grade  separation  at  the existing at‐grade crossing on Churchill Avenue in the Caltrain Rail Corridor. The project will provide improvements to accommodate bicycles, pedestrians, and vehicular movement at the crossing. After reviewing various studies and  refinements  to  the  alternatives,  the  Rail  Committee  recommended  proceeding  with  a  Partial  Underpass Alternative with Bicycle and Pedestrian crossing at Seale Avenue. On June 10, 2024, the City Council selected the Churchill Underpass with Ped/bike crossing at Seale Avenue. The funding agreement with the Federal Railroad Administration was approved by City Council on June 17,  2024. Staff  collaborated with Caltrain and the  Valley Transportation Agency to develop a cooperative agreement for the Preliminary Engineering and Environmental Documentation phase and funding from Measure B Grade Separation funds. This cooperative agreement between the City, Caltrain, and VTA was approved by the City Council on December 9, 2024. The City is also working with State  representatives  to  preserve  the  CalSTA,  Transit,  and  Intercity  Capital  Program  funding  awarded  for  the project, which is currently being reconsidered for reduction in the Governor’s budget.

Churchill Avenue
Alma Street
Railroad Crossing
Safety
Improvements
(PL‐20000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,804,194  $9,243,271  Public Works  Construction  Spring 2025 Project Status: This project is a railroad crossing improvement project to enhance safety at the intersection of Churchill Avenue and Alma Street. The design includes traffic signal modifications, street lighting improvements, roadway resurfacing, sidewalk realignment, drainage improvements, utility relocations, signage, and striping.  Staff is coordinating with Caltrain, Caltrans, and California Public Utilities Commission (CPUC). CPUC approved General Order 88‐B for the project in November 2022 and authorized the City to move forward with construction.  Council Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 3 of 8
approved the construction contract in June 2023 and construction started in summer 2023. Procurement issues and construction constraints from Caltrain will push out project completion through spring 2025.

Downtown
Automated
Parking
Guidance
Systems, Access
Controls &
Revenue
(PL‐15002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,658,417   $5,197,827  Public Works  Construction  Spring 2025 Project Status:  This project includes design and installation of new downtown parking guidance systems, access controls, and revenue collection equipment that will be coordinated with both the Downtown Parking Wayfinding, PL‐15004  project  and  the  2016  Downtown  Parking  Management.  Staff  contracted  with  Dixon  Resources  for additional management support in design and procurement for the system installation in the Downtown garages on  University  Avenue.  Building  permits  for  the  garage  interior  work  were  approved  in  June  2024  for  all  four garages. The High Street Parking Garage (Lot R) and Bryant Street Parking Garage (Lot S/L) passed final inspections in early December 2024. The Webster/Cowper Parking Garage (Lot J) interior work is in progress and expected to be complete in February 2025. Construction will then move the Civic Center Garage. Plans for the exterior digital matrix signs are under review with Planning.

Meadow
Drive/Charleston
Road Rail Grade
Separation and
Safety
Improvements
(PL‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $42,055   $401,639,254   Office of Transportation  Design  Spring 2028 Project Status:   This project provides for the planning, design, and construction of the grade separations at the existing at grade crossings on Meadow Drive and Charleston Road in the Caltrain Rail Corridor. The project will provide  improvements  to  accommodate  bicycles,  pedestrians,  and  vehicular  movement  at  the  crossings.  After reviewing various studies and refinements to the alternatives, the Rail Committee recommended proceeding to advance two alternatives, the Hybrid and Underpass Alternatives, into the early phase of Preliminary Engineering and Environmental Documentation. The committee also recommended refining these alternatives to reduce right‐ of‐way impacts and improve bicycle and pedestrian facilities. The City Council after reviewing directed staff to advance  these  alternatives  into  Preliminary  Engineering  and  Environmental  phase  at  Council  Meetings  in  June 2024. The funding agreement with the Federal Railroad Administration was approved by City Council on June 17, Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 4 of 8
2024. Staff collaborated with Caltrain and the Valley Transportation Agency to develop a cooperative agreement for  the  Preliminary  Engineering  and  Environmental  Documentation  phase  and  funding  from  Measure  B  Grade Separation  funds.  This  cooperative  agreement  between  the  City,  Caltrain,  and  VTA  was  approved  by  the  City Council on December 9, 2024. The City is also working with State representatives to preserve the CalSTA, Transit, and Intercity Capital Program funding awarded for the project, which is currently being reconsidered for reduction in the Governor’s budget.

Parking
Management and
System
Implementation
(PL‐16002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $292,811   $627,247  Office of Transportation  Procurement  Spring 2025 Project Status:  This project provides funding for the design and installation of the Comprehensive Parking Permit and Citation Management System. The all‐inclusive system is a tool staff will utilize in the management of parking permits for eight parking permit programs and associated on and off‐street parking citations. An RFP to solicit another vendor was issued the last week of June 2024. Interviews for the final three candidates were completed in December 2024.

Quarry Road
Improvements
and Transit
Center Access
(PL‐16000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,282,050  $1,682,068  Office of Transportation  Design  Fall 2026 Project Status:  This project provides funding for the planning, design, and construction of bicycle and pedestrian improvements along Quarry Road between El Camino Real and Welch Road, including, but not limited to, upgraded bicycle lanes and crosswalks, innovative intersection treatments for bicyclists, and improved access to transit stops.

Railroad Grade
Separation and
Safety
Improvements
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $4,501,430   $11,735,179  Office of Transportation  Pre‐Design  Fall 2025 Project Status: This project is a community‐based process to advance the railroad grade crossing circulation study and context sensitive solutions study envisioned by the City Council for the Palo Alto Avenue crossing. It will also Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 5 of 8
(PL‐17001)  fund the preparation of a Project Study Report and environmental analysis that will be required for the City to realize its goals of advancing grade separations. The project will perform preliminary engineering design, conduct project related studies, and prepare environmental documents for the improvements. This project is currently on hold  while  the  City  is  considering  quiet  zone  implementation  for  interim  conditions,  and  staff  will  initiate  the conceptual plan development for grade separation at this crossing in 2025.

Traffic
Intersection
Accessibility
Improvement
Project
(PL‐25001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $  $550,512  Office of Transportation  Design  Summer 2025 Project Status: This project will provide traffic intersection accessibility improvements at four identified locations across the City to enhance traffic congestion relief efforts. These modifications may include the addition of new crosswalks and curb ramps; accessible pedestrian system (APS) push buttons; updating existing 8” traffic signal indication heads to 12”; video detection for improved operations; and implementation of Automated Traffic Signal Performance Measures (ATSPM) for ongoing data collection and operational/safety analysis. Funding for this  project  will  be  provided  by  2016  Measure  B  Local  Streets  and  Roads  (LSR)  grant  funds.  Since  the  City’s pavement  condition  index  (PCI)  is  above  70,  the  City  is  eligible  to  use  this  funding  for  traffic  congestion  relief projects.

University Ave
Streetscape
Update
(PE‐21004)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $461,353  $1,625,909  Public Works  Design  Summer 2027 Project Status: This project includes a study to reconfigure University Avenue between Alma Street and Middlefield Road to adapt the public realm to maximize pedestrian and bicycle use, reduce congestion, and enhance the retail environment/economic activity, while maintaining two‐way vehicular access, parking opportunities, delivery and loading zones, ride share spaces, and other amenities including performance space. Council awarded a professional services contract for CSW/Stuber‐Stroeh Engineering in February 2022. The project uses a phased approach with Phase  1  consisting  of  public  outreach,  conceptual  design,  preliminary  environmental  studies,  and  financial assessment.  Staff  presented  an  alternatives  analysis  and  a  preferred  streetscape  concept  plan  to  Council  on Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 6 of 8
December 18, 2023. Council did not approve the plan and directed staff to identify additional concept alternatives for Council discussion. Staff conducted additional outreach to the Retail Committee, Stakeholder Working Group, and received input from Council on June 3, 2024. On December 9, 2024, Council approved staff’s recommended preferred concept plan. Staff will seek Council approval for a consultant contract amendment in early 2025 for Phase 2 services, including preliminary design, environmental review, and Engineer’s Report for an Assessment District.

Recurring Projects
Bicycle and
Pedestrian
Transportation
Plan
Implementation
(PL‐04010)

Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $211,611   $14,400,000  Office of Transportation  N/A  Recurring Project Status: This project funds the Bicycle and Pedestrian Transportation Plan Update effort, which kicked off in fall 2023 and is scheduled to be completed by fall 2025. This project also includes the implementation of various individual bicycle and pedestrian projects, such as the design and construction of bicycle boulevards, enhanced bikeways, shared‐paths, bicycle parking, pedestrian improvements, and quick‐build implementation of the City’s existing 2012 Bicycle and Pedestrian Transportation Plan.

Parking District
Implementation
(PL‐15003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0  $180,457  Office of Transportation  N/A  Recurring
Project Status: This project introduces additional parking permit programs throughout the City. One aspect of this project is to update City Council‐approved Residential Preferential Parking (RPP) ordinance language to establish uniform and streamlined procedures and processes to implement RPP districts through the process outlined in Municipal Code 10.50.

Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 7 of 8
Safe Routes
to School
(PL‐00026)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $77,525   $610,103  Office of Transportation  N/A  Recurring Project Status: This project enables the City’s Safe Routes to School program, including school commute planning, encouragement activities, and capital improvements along local and collector streets that may be impacted by school commute activities. The capital improvements include traffic calming devices, enhanced crosswalks, and improved signage along suggested safe routes to school. The community engagement and planning process for the construction of the South Palo Alto Bikeways project began in FY 2021.  The project will implement buffered or protected bike lanes on East Meadow Drive from Alma Way to Fabian Way, Fabian Way from East Meadow Drive to East Charleston Road, and widen and repave the Waverley Avenue Bike Path between East Meadow Drive and Charleston Road. Staff was notified of the award of a “Safe Streets for All” grant in spring 2024 to pilot the South Palo Alto Bikeways concept plans on East Meadow Drive and Fabian Way. In FY 2024, this project funded education  to  improve  school  access  and  safety.  In  addition,  this  project  supported  a  secondary  school  needs assessment to identify middle and high school education and encouragement programs and to query the Safe Routes  Partnership  for  the  resources  to  support  these  programs.  This  project  will  support  the  demonstration project local match and pre‐grant activities in FY 2025.

Traffic Signal
and Intelligent
Transportation
Systems
(PL‐05030)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $223,813  $994,336  Office of Transportation  N/A  Recurring Project  Status:  This  project  includes  design  and  construction  of  traffic  signals,  traffic  signal  communications networks, detection, and data projects for transportation use, and maintenance of the City’s traffic signal central management  system. The  project  includes  the  replacement  of  traffic  signal  controllers  and  cabinets,  video detection systems, accessible pedestrian buttons, and related field equipment. Design for traffic signal safety and operational  improvements  at  the  intersection  of  San  Antonio  Road  and  Charleston  Road  is  nearing  100% completion. Staff is finalizing the plans and will be preparing bid documents for construction to be released in fall 2024, with construction anticipated to begin in spring 2025. Staff is in the process of updating the Centralized Traffic Management system servers to improve operational functions and system security. An IFB for the Quarry Traffic and Transportation Projects  Status as of December 2024

Traffic and Transportation Projects – Page 8 of 8
Road  Traffic  Signal  and  Intelligent  Transportation  System  upgrade  project  is  anticipated  for  spring/summer 2025. Staff continually provide traffic signal modifications, installations, and upgrades throughout the City.

Transportation
and Parking
Improvements
(PL‐12000)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $309,114  $442,611  Office of Transportation  N/A  Recurring Project  Status:   This  project  implements  miscellaneous  parking  and  transportation  related  improvements including neighborhood traffic calming, neighborhood traffic studies, minor striping and signs installation, and parking improvements. This project also funds the development of grant proposals used to procure funding for future  projects.  For  the  traffic  calming  project  in  the  Crescent  Park  neighborhood,  City  Council  approved proceeding with the design of permanent improvements in November 2023. Staff has procured the services of the  consultant  to  design  improvements  and  conduct  community  outreach.  In  addition,  staff  initiated  an Engineering and Traffic Survey to select roadway segments to study prevailing speeds and review traffic conditions in  order  to  establish  and/or  certify  posted  speed  limits.  Staff  is  also  working  on  the  quiet  zone  project  for  all railroad crossings along the Caltrain corridor. A quiet zone study was performed for the Palo Alto Avenue and Alma  Street  crossing  in  collaboration  with  City  of  Menlo  Park  in  2022.  Staff  has  retained  the  services  of  the consultant to design final improvements at this crossing. The design plans are currently at 70% and are being reviewed by CPUC, Caltrain and FRA for feedback and comments that will be incorporated to develop final PS&E and procure necessary permits. In addition, staff procured the services of the consultant to conduct a study for evaluation of quiet zones at the other three crossings of Churchill Avenue, Meadow Drive, and Charleston Road.

The $200K Safe Streets for All (SS4A) Safety Action Plan is funded via this project but will be reimbursed up to $160K by a federal grant. The plan will target eliminating traffic deaths and life‐changing injuries on local streets.

Airport Projects   Status as of December 2024

Airport Projects – Page 1 of 2
One‐Time Projects
Airfield
Electrical
Improvements
(AP‐19001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0   $5,789,450  Public Works  Design  Summer 2030
Project Status: This project is for the design and construction of electrical improvements and installation of LED lighting at the airport runway and taxiway. This project has not received FAA funding and is currently on hold.

Airport Access
Road
Reconstruction
(AP‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0   $3,700,002  Public Works  Design  Summer 2027
Project Status: This project is for the design and reconstruction of the pavement on Embarcadero Way, which is the main access road for airport businesses and the Air Traffic Control Tower at the Airport. The Airport did not receive FAA funding for this project and the project is currently on hold.

Airport Layout
Plan
(AP‐21000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,179,551     $ 967,100  Public Works  Construction  Summer 2025 Project Status: This project provides updates to the Airport Layout Plan, also known as the Long‐Range Facilities and Sustainability Plan, including a narrative report and environmental study.  The Airport received funding for a Phase I portion of this project in fall 2020.  The airport conducted five public meetings for the project, and additional meetings  are  currently  being  planned  for  this  project.  Phase  I  is  approximately  95%  complete,  and  Phase  II  is approximately 75% complete. This project is currently on hold, and the completion date is unknown.

Airport Parking
Lot Electric
Vehicle
Charger
Installation
(AP‐24001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0   $28,993  Public Works  Design  Summer 2026
Project Status: This project will install electric vehicle charging stations in the Airport customer parking lot. The Airport is currently unable to offer electric vehicle charging to its customers, but there is increasing demand for vehicle  charging  capability  from  Airport  tenants.  This  project  has  been  delayed  as  the  Airport  explores  further funding options.

Airport Projects   Status as of December 2024

Airport Projects – Page 2 of 2
Airport
Temporary
Office Buildings
(AP‐22001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $947   $431,005  Public Works  Procurement  Winter 2025 Project Status:   This project provides funding for the installation and Furniture, Fixtures, & Equipment (FF&E) of existing temporary modular buildings at the airport to provide adequate office space for airport staff as well as terminal space for the public. This project has been delayed while the Airport explores further funding options.

Airport Zero
Emission
Vehicle Fleet
Replacement
Program
(AP‐23000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $192,546   $377,696  Public Works  Completed  Summer 2024 Project Status:  The Airport vehicle fleet will be replaced by three zero emissions vehicles (ZEV), to be supported by three electric charging stations. The van is used for the transportation of airport guests and passengers and improves safety by minimizing foot traffic on the airport apron. The truck is used as a maintenance, first response, and operations vehicle. The ZEV fleet will include one passenger vehicle and two trucks. FAA funding was received in  fall  2023,  for  the  fleet  replacement.  The  Airport  received  delivery  of  a  new  electric  truck  in  fall  2024  which replaced both airport vehicles with electric vehicles.

Automated
Weather
Observation
System
(AWOS)
AP‐19000
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $43,677     $1,588,533  Public Works  Design  Summer 2025 Project Status: This project provides a new weather information system to be installed at the Palo Alto Airport.

The Airport has applied for FAA funding and is waiting for the grant agreement to start design. The Airport received a bid for the project and is submitting a grant application to the FAA. It is anticipated that funding for the project will be received in spring 2025.

Recurring Projects

2024‐2028 – Airport Capital Improvements Program Projects: There are no recurring projects scheduled at this time.

Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 1 of 8
One‐Time Projects
115 kV Electric
Intertie
(EL‐06001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $742,639   $ 1,364,625  Utilities  Pre‐Design  Summer 2027 Project Status: This project will perform a technical feasibility study to determine the general project requirements to establish a 115 kV electric intertie line and construct a 115/60 kV substation to connect the City's electric system directly to the 115 kV transmission line at an additional location.   Staff did not receive California Independent System  Operator’s  (CAISO)  commitment  to  support  this  interconnection.    Staff  has  retained  the  services  of  a consultant to evaluate the options available to the City. Staff submitted CPAU electric load forecast and proposal for an additional 115 kV transmission line in October 2024 to CAISO for review and acceptance. Staff expects a response from CAISO by June 2025.

Colorado
Distribution
Feeder Outlet
Replacement
(EL‐22002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $10,576  $400,000  Utilities  Construction  Fall 2025
Project Status: This project is for the installation of a new underground duct bank and cable at Colorado Substation.

The  installation  will  improve  reliability  for  all  Colorado  circuits.   The  design  was  completed  in  spring  2024  and construction will begin by summer 2025. Council approved the contract in April 2024 and an order for the material has  been  issued.    The  construction  is  delayed  due  to  the  procurement  of  the  12  kV  pad‐mount  switches.  In addition, construction is being coordinated with the fiber hut installation which is expected to be installed by June 2025.

Colorado Power
Station
Equipment
Upgrades
(EL‐19001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $4,468,548   $11,293,873  Utilities  Design  Fall 2027
Project Status: This project is for the upgrades to equipment at the Colorado Power substation. In FY 2022 staff completed  the  evaluation  of  existing  equipment  and  will  proceed  with  replacing  the  COP‐3  115  kV/60  kV transformer bank and the 115 kV breaker.   Engineering is continuing to work on the design RFPs and construction IFBs for contract services to complete substation projects. The station’s service voltage transformers (SSVT1) was Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 2 of 8
purchased and installed. The 60 kV Bus 1 & 2 Potential Transformers (PT) have been purchased for their eventual replacement.

Colorado
Substation Site
Improvements
(EL‐19002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $275,777   $1,416,912  Utilities  Design  Fall 2025
Project Status: This project will make modifications to the substation driveways and fence to provide adequate ingress and egress for utility vehicles used for maintenance and repair. Staff has prepared an overall master plan for  Colorado  Substation  to  include  all  proposed  improvements.  Detailed  designs  for  lighting,  driveway,  fences, walls, and an improvement of oil containment have been prepared. The Planning Department approved the Utility engineering’s design in May 2024. Engineering staff are currently preparing the IFB for construction. Bid opening has been delayed until spring 2025 due to recent staff changes.

Foothills Rebuild
(Fire Mitigation)
(EL‐21001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $8,503,110   $14,999,581  Utilities  Construction  Fall 2025 Project Status: This project will rebuild the approximately 11 miles of overhead line in Foothills Park, as necessary to mitigate the possibility of wildfire due to overhead electric lines. This could include the utilization of more robust equipment  or  construction  practices,  rerouting  to  avoid  vegetation  and  improve  access  for  inspection  and maintenance, or converting the overhead lines to underground where feasible.  Two proposals were received for this project and both proposals were rejected because they did not provide an option to underground existing overhead electric lines. Substructure for Phases 1 and 2 are completed while Phase 3 substructure installation is currently in progress. Phase 4 construction is currently paused for an easement relocation from Mid‐Peninsula Open  Space.  Construction  will  resume  in  early  2025  when  the  easement  paperwork  is  completed.  Phase  5 substructure installation along Arastradero Road is currently in progress.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $350,153   $300,000,000  Utilities  Construction  Winter 2030 Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 3 of 8
Grid
Modernization
for Electrification
(EL‐24000)
Project Status:  This project will provide the City with an electric infrastructure adequate to support the City’s goal of 100% electrification and 80% carbon emissions reduction by the year 2030. To attain the 100% electrification scenario, the City must maximize use of electric energy and phase out carbon‐based end uses such as natural gas appliances  and  internal  combustion  vehicles.  The  electric  system  must  be  updated  to  meet  the  needs  of electrification, and older components in the distribution infrastructure must be replaced to mitigate chances of overloading  the  system.  Examples  of  assets  to  be  replaced  are  distribution  and  substation  transformers, primary/secondary distribution circuits. A Pilot area was designated and engineering staff in conjunction with a consultant have completed the distribution system design for the Pilot area, with a handful of power poles replaced and installed as initial construction efforts start to take shape. Starting in FY 2025, this project will incorporate and consolidate  the  scope  of  work  from  the  following  projects  into  one  CIP:  Coleridge  Cowper  Tennyson  4/12kV Conversion (EL‐14000), Hopkins Substation 4/12 kV Conversion (EL‐20000), Rebuild Underground District 15 (EL‐ 11003)  and  Rebuild  Underground  District  16  (EL‐13003).  Engineering  design  in  the  Pilot  area  is  complete  and construction  is  in  progress.   Fifty‐five  (73%)  poles  out  of  the  seventy‐five  targeted  for  replacement  have  been replaced  in  the  Grid  Modernization  Pilot  area,  with  the  remaining  twenty  poles  slated  for  replacement  by March 2025. Additionally, 428 (47%) of the 908 homes in the Pilot area are ready for electrification, with another 480 homes in line to be connected to the upgraded infrastructure by the end of April 2025.

Hanover
Substation
Improvement
(EL‐24001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $220,986   $15,000,000  Utilities  Completed  Fall 2024 Project Status: This project  installed two 12 kV 50 MVA transformers to replace two 4kV transformers that served 1501  Page  Mill  Road  and  make  all  substation  improvements  necessary  to  accommodate  the  installations.

Generally, three to four years are spent on a substation upgrade. Project construction is 100% complete and new Hanover substation transformers and switchgear have been successfully tested and commissioned and released to the Utility Operations group. Final project close out and settlement of the Public‐Private Partnership Contract between the City and Tesla remain.

Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 4 of 8
Inter‐Substation
Line Protection
Relay
(EL‐17005)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $371,146   $1,805,866  Utilities  Construction  Summer 2027 Project Status: This project replaces the existing HCB pilot wire relays with a new microprocessor line differential protective relay to protect the city’s 60 kV sub‐transmission line sections and equipment from damage due to faults  (i.e.  short  circuits)  on  the  60  kV  line  sections.  This  project  is  being  done  in  phases,  with  design  and construction happening concurrently on the different phases.  Construction of these improvements relies on work completed  by  other  projects  to  install  fiber  optic  connections.  Engineering  design  for  segments  Colorado substation to Adobe Creek substation, Park Boulevard substation to Quarry substation, and Maybell substation to Park Boulevard substation is in progress. A test plan is being written to prove the equipment will work as designed.

The Quarry to Park substation segment is delayed due to resources and is expected to be completed fall 2025. Park to Maybell segment is still in progress, fiber installation is complete, and completion is expected winter 2026. Staff has completed the testing and verification of a fiber optic transfer switch proof of concept project required to proceed with replacement of HCB relays at COP.

Rebuild
Underground
District 24
(EL‐10006)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,949,767  $2,240,451  Utilities  Design   Fall 2025
Project Status: This project rebuilds and replaces the underground electric system in Underground District 24, the area bounded by Lytton Avenue; Bryant Street; Forest Avenue; and Alma Street. The engineering design will be completed in spring 2025. Construction will follow in fall 2025.

Smart Grid
Technology
Installation
(EL‐11014)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $12,387,759   $19,430,985  Utilities  Construction  Spring 2025 Project Status: Council approved the Advanced Metering Infrastructure (AMI) with Sensus on October 18, 2021.

The project includes replacement of 30,000 electric meters and retrofit of 20,800 water and 24,200 gas meters with  radio  endpoints  to  transmit  meter  data  to  the  AMI  network.  The  proof‐of‐concept  phase  including  AMI Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 5 of 8
network installation, meter testing, and system integration will occur between January 2022 and August 2023. Full deployment is anticipated to run from September 2023 through April 2025.

Substation
Breaker
Replacement
(EL‐17002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $1,568,954   $7,312,009  Utilities  Pre‐Design  Summer 2028 Project Status: This project replaces high voltage circuit breakers that interconnect the nine electric substations and two power switching stations that are reaching the end of their useful life and are now underrated for their use.  This project is being done in phases, with design and construction happening concurrently on the different phases.  Staff completed the construction on the first phase and is working to procure a multi‐year contract with a contractor to complete the design and replacement of the remaining breakers. Staff is working on the design RFP and the construction IFB for contract services to complete substation projects. Lead times for circuit breakers are currently at around 18 months.

Substation
Physical Security
(EL‐16003)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $3,093,299   $7,397,072  Utilities  Construction  Winter 2025 Project  Status:  This  project  installs  facilities  providing  physical  protection  for  nine   electric  substations  from vandalism and intrusion. The installation for the first phase was completed for seven of the nine substations in December  2024.  The  bid  package  for  the  2nd  phase  and  final  two  substations  is  being  prepared  for solicitation. Construction is to be completed by summer 2026.

Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 6 of 8
Recurring Projects
Communications
System
Improvements
(EL‐89031)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $45,733  $100,000  Utilities  N/A  Recurring
Project  Status:  This  project  installs  high  frequency  coaxial  cable,  fiber  optic  cable,  and  related  equipment  to provide communications services for traffic signal coordination, telephone links, computer data transmission, and the  Electric Supervisory Control  and  Data  Acquisition  (SCADA)  system. This  project  is  funding  a  portion  of  the design phase of an expanded Utilities fiber optic network. The contract for design of this network was approved by Council in June 2020. Staff installed 48F FO Cable between Maybell MB and PBS Park Boulevard substations in Existing Aerial Innerduct for pilot wire relay protection.

Electric Customer
Connections
(EL‐89028)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $2,202,541   $2,700,000  Utilities  N/A  Recurring
Project Status: This project installs services, transformers, and meters for new customers; upgrading of existing services;  temporary  service  connections;  and  overhead  and  underground  extensions  for  new  or  existing customers. Projects are in many stages of design and construction to provide temporary and permanent power to residential and commercial customers in Palo Alto.

Electric System
Improvements
(EL‐98003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $1,567,547  $2,980,070  Utilities  N/A  Recurring
Project Status: This project consists of various projects that replace deteriorated facilities or install protective devices  that  improve  the  Electric  Distribution  System.  Projects  are  in  many  stages  of  development  to  replace transformers, replace poles, replace overhead wires, and install protective devices to improve service reliability.

Electric Utility
Geographic
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $68,397   $165,000  Utilities  N/A  Recurring
Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 7 of 8
Information
System
(EL‐02011)
Project  Status:  This  project  enhances  the  citywide  Geographical  Information  System  (GIS).  The  project  scope includes on‐going maintenance/technical support of the existing GIS system and implementation of the new GIS platform, ESRI.

SCADA System
Upgrades
(EL‐02010)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $136,591   $225,000  Utilities  N/A  Recurring
Project Status: This project upgrades the Supervisory Control and Data Acquisition (SCADA) system hardware.

Staff completed the upgrade of the servers used for monitoring the utility substations and equipment for 2024.

The next hardware and software upgrade is currently in progress at the factory and work will occur in winter 2025.

Substation
Facility
Improvements
(EL‐89044)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $29,240   $400,000  Utilities  N/A  Recurring
Project  Status:  This  project  makes  improvements  to  facilities  at  the  electric  substations  in  Palo  Alto.   Staff  is working  on  the  replacement  of  Remote  Terminal  Units  (RTU)  at  various  substations,  upgrading  gravel  and grounding, 60 kV air switches, and reconfiguring steel trusses and associated devices. Engineering is working on design  and  construction  for  contract  services  to  complete  substation  projects.  Staff  has  completed  the refurbishment  of  capacitor  cans  and  fuses  at  Adobe  Creek,  the  procurement  and  replacement  of  12kV  Alllis Chalmers circuit breakers at Hansen Way (7ea) and Hanover (9ea) as well as completed the installation of new Nexus meters at Hansen Way (22/23) and Colorado (20/21). The design of new Nexus meters at Hansen Way (20/21) is in progress.

Substation
Protection
Improvements
(EL‐89038)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $262,000   $300,000  Utilities  N/A  Recurring
Project  Status:  This  project  makes  improvements  to  equipment  used  at  electric  substations  to  protect  the substation equipment and circuits emanating from the substation from damage due to faults (i.e. short circuits) Electric Fund Projects  Status as of December 2024

Electric Fund Projects – Page 8 of 8
on the electric system. Staff issued a task order with Soudi Consultants to review and revise protection settings and training on the commissioning of Park Boulevard relay.

Underground
System Rebuild
(EL‐16001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0  $350,000  Utilities  N/A  Recurring
Project  Status:  This  project  replaces  underground  electric  equipment  in  areas  that  were  originally  installed underground, that are not part of an Underground District. Staff is working to identify areas where the age of the existing cables is a high priority for cable replacement. To date, this includes areas in the Stanford Research Park, Arastradero Road, and along East Bayshore Road. New areas have been identified, and progress has been made on  the  development  of  the  project.  Projects  are  in  many  stages  of  development  to  replace  underground transformers, cables, vaults, and to install protective devices to improve service reliability.

Wood Pole
Replacement
(EL‐19004)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $533,613   $750,000  Utilities  N/A  Recurring
Project Status: This project will fund the annual replacement of deteriorated wood power poles.  CPAU staff and contract  consultants  are  continuously  working  on  pole  replacement  designs  for  construction.  Replacement  of poles in the Grid Modernization Pilot area is the top priority.

Fiber Optics Fund Projects  Status as of December 2024

Fiber Optics Fund Projects – Page 1 of 2
One‐Time Projects
Fiber Optic
Network
System
Rebuild
(FO‐16000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $3,232,944   $29,789,313  Utilities  Design  December 2026 Project Status:  This project is for the System Capacity Improvement that rebuilds portions of the "dark" fiber optic network  around  Palo  Alto.  In  September  2022,  Council  approved  the  City’s  fiber  expansion  plan  including construction of a new fiber backbone and a phased buildout of a fiber‐to‐the‐premises network. The Fiber Optic Network System Rebuild CIP will be replaced with new Fiber Backbone and Fiber‐to‐the‐Premises (FTTP) CIPs in FY 2024.  Staff  has  hired  a  consultant  to  complete  the  Fiber  Backbone  and  FTTP  conceptual  design.  The  conceptual design has been completed the contract has been amended to complete the design and all provide documentation necessary for procurement of a construction contract. Staff is updating fiber databases and reviewing the current inventory of fiber strands in order to determine what sections of the Fiber Backbone should be upgraded first. Due to the Fiber to the Premises pilot and Wildfire Mitigation project in the Foothills, materials and resources have been reassigned from this project. Staff anticipates restarting this review phase of the new fiber backbone in July 2025 after the Foothills undergrounding, grid modernization pilot, and FTTP pilot are completed. As the FTTP pilot expands into Phase I, staff will be designing and constructing the new Fiber Backbone in phases and in alignment with Grid Modernization, with a tentative completion of the phase 1 Fiber Backbone by end of December 2026.

Fiber to the
Premises
(FTTP)
(FO‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $53,550   $ 20,000,000  Utilities  Design  Winter 2030
Project Status:   This project will build Fiber‐to‐the‐Premises (FTTP) to deliver broadband (high‐speed internet) for homes and businesses in the City of Palo Alto. As the City builds the FO‐16000 ‐ Fiber Optics Network ‐ System Rebuild Staff  has  divided  up  the  City  into  smaller  sections  for  a  phased  approach  of  the  Fiber‐to‐the‐Premises  project.

Furthermore, Staff has proceeded to combine the Phase 1 Fiber‐to‐the‐Premise design with a Grid Modernization Project covering the same area. Staff is capitalizing on inherent synergies between the two projects, as well as taking advantage of economies of scale deployment that can be realized as a result of combining the two projects. Staff has contracted with an Engineering firm to produce design drawings and specifications. The City is implementing a pilot Fiber Optics Fund Projects  Status as of December 2024

Fiber Optics Fund Projects – Page 2 of 2
during  Phase  1  of  the  FTTP  project  to  evaluate  various  new  technologies  and  to  assess  various  construction methodologies to closely align with Grid Modernization and inform on future phases of deployment. In conjunction with the grid modernization pilot, FTTP make‐ready work such as pole replacements and installation of messenger strands  is  being  performed.  The  remaining  FTTP  pilot  construction  including  fiber  lashing  and  fiber  distribution cabinets  is  scheduled  to  begin  in  February  2025  and  customers  in  the  pilot  area are  tentatively  scheduled  to  be served in July 2025.

Recurring Projects
Fiber Optics
Customer
Connections
(FO‐10000)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $18,434   $253,100  Utilities   N/A  Recurring
Project  Status:   This  project  enables  the  installation  of  fiber  optic  infrastructure  for  new  service  connections.

Projects are developed as needed to meet customer requests for leasing of fibers on the Dark Fiber system.  There have been seven new customer inquiries in the first half of FY 2025. The City is partnering with a non‐profit agency under a dark fiber licensing agreement to provide fiber broadband service to customers in the foothills area.

Fiber Optics
Network
System
Improvements
(FO‐10001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $36,608   $602,500  Utilities  N/A  Recurring
Project Status: This project improves the reliability within the fiber optic network system.    As part of the City’s wildfire mitigation plan, this project will add new fiber conduit and substructure in the foothills to support city infrastructure  and  improve  telecommunication  and  connectivity  in  the  open  space.  This  project  will  rebuild approximately 11 miles of overhead electric and fiber lines in Foothills Nature Preserve. Staff have completed the undergrounding  of  7,000  feet  of  fiber.  Staff  will  also  be  extending  the  fiber  backbone  from  Dahl  reservoir  to Montebello reservoir. The foothills project is scheduled to be completed by summer 2025.

Gas Fund Projects             Status as of December 2024

Gas Fund Projects – Page 1 of 3
One‐Time Projects
Gas Line
Repair at
Arastradero
Creek
(GS‐25001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $ 0  $1,000,000  Utilities  Design  Fall 2026
Project Status:  This project is for the design of the Arastradero Creek to address a creek bed erosion project that exposed an 8” natural gas pipeline and threatened the integrity of a 16” potable water pipeline and 16” sanitary sewer pipeline.

The project will address requirements outlined by the Water Board in the City emergency work permit to re‐bury the exposed 8” gas pipeline. The design is expected to finish by winter 2026, with construction beginning in summer 2026.

Gas Main
Replacement
Project 24
(GS‐14003)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $3,929,943   $11,409,309  Utilities  Construction  Spring 2025 Project  Status:  This  project  enables  the  design  and  construction  to  replace  approximately  20,100  linear  feet  (which represents 1.9% of the City's Gas distribution main system) of distribution main and 260 gas services constructed mainly of PVC on various streets within the University Park and Crescent Park neighborhoods. Release of the project for bidding has  been  delayed,  to  include  the  Town  &  Country  Village  scope.  This  project  was  split  into  GMR24A  and  GMR24B.

GMR24A  (Stanford  Shopping  Center)  was  completed  in  spring  2023.  GMR24B  construction  started  in  winter  2024,  is approximately 80% complete, and is anticipated  to be complete in spring 2025.

Gas Main
Replacement
Project 25
(GS‐15000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $15,525  $8,743,849  Utilities  Design  Fall 2026
Project Status: This Gas Main Replacement (GMR) project replaces approximately 26,000 linear feet (which represents

2.3% of the City’s Gas Distribution System) of leaking, inadequate sized, and structurally deficient gas mains and services located  on  various  streets  in  the  neighborhoods  of  Community  Center,  Leland  Manor,  Midtown,  and  Palo  Verde neighborhoods. Staff identified problematic mains and services by researching maintenance and leak histories, analyzing performance of the entire Gas Distribution System, and considering risk ratings of the Distribution Integrity Management Plan. A federal grant application was submitted in August 2023, and the City was awarded $16.5 million in grant funding for this project.  Staff is currently completing the Tier 2 Environmental documentation to meet federal grant requirements Gas Fund Projects             Status as of December 2024

Gas Fund Projects – Page 2 of 3
before it can be released through purchasing for construction bids. The Grant Agreement is anticipated to go before Council in January 2025.  The project is on track for construction to begin in summer 2025.

Recurring Projects
Gas
Distribution
System
Improvements
(GS‐11002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $484,530   $1,166,723  Utilities  N/A  Recurring
Project Status: This project enables Gas Distribution System improvements that include increasing distribution system capacity  for  load  growth,  replacing  deteriorated  capital  facilities,  reconfiguring  and  adding  and  improving  service reliability, and conducting research related to performance of the gas distribution system or its various components making general improvements to the system.   The City must continuously evaluate service reliability needs and make improvements to the system to maintain top level service to City customers and to minimize potential economic losses due to service interruptions. In the first half of FY 2025, City crews completed the replacement of various gas services and valves throughout the system and replaced leaking ten inch steel gas valves on the Waverley Street bridge crossing at Matadero Creek.

Gas
Equipment
and Tools
(GS‐13002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $80,226   $100,000  Utilities  N/A  Recurring
Project  Status:  This  project  purchases  polyethylene  (PE)  fusion  equipment  and  tools,  directional  boring/locating equipment and tools, and general shop equipment and tools. The equipment needs to be upgraded on an annual basis to safely operate and maintain a natural gas distribution system and to ensure operators’ safety and productivity. In the first half of FY 2025, no new equipment purchases were completed.

Gas Fund Projects             Status as of December 2024

Gas Fund Projects – Page 3 of 3
Gas Meters
and
Regulators
(GS‐80019)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $365,663   $688,545  Utilities  N/A  Recurring
Project Status: This project provides replacement of the existing gas meters and regulators annually. The coordination of gas meters and regulator replacements with gas meters identified to be replaced under the AMI contract, which is generally gas meters that are twenty‐five years or older. The gas meter replacement program ensures the accuracy of gas consumption measurement, reduces possible revenue loss due to under‐registered gas, and provides customers with accurate  monthly  bills.  Replacement  of  aged  gas  meters  and  regulators  is  on‐going.  The  next  major  replacement  of meters and regulators will be coordinated with Gas Main Replacement Project 25 (GS‐15000) and the Advanced Metering Infrastructure project.

Gas System,
Customer
Connections
(GS‐80017)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $584,034   $700,000  Utilities   N/A  Recurring
Project Status: This project enables the Gas Distribution System to be extended to provide gas service to new customers and  augment  service  to  customers  with  increased  natural gas  demands.  Improvements  include  new  mains,  services, valves, regulators, meters, and accessories in order to meet changes in existing customer service demands and respond to changes in gas service requirements due to new development or redevelopment. This project is funded partially from reimbursements by customers. City crews completed 22 gas service installations, 4 gas service relocations and 65 gas service demolitions in the first half of FY 2025.

Stormwater Management Projects           Status as of December 2024 Stormwater Management Projects ‐  Page 1 of 4
One‐Time Projects
Corporation
Way System
Upgrades and
Pump Station
(SD‐21000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $340,827   $4,146,554  Public Works  Design  Spring 2026 Project Status:   This project incorporates a design of a new small pump station with a 25 cubic feet per second capacity and upgrades 700 linear feet of pipe to 30‐inch diameter High Density Polyethylene pipe.   The existing system does not have the force needed to discharge storm flows into the Adobe Creek. Adding a pump station in advance of the outfall and upsizing the storm pipe will eliminate the routine flooding along East Bayshore Road and convey runoff from a 10‐year storm event. Staff secured an easement for the pump station from adjacent property owners. The consultant completed the design of the project in June 2024. Due to poor bid results combined with high construction costs, a third IFB is scheduled to be advertised in December 2024.

East Meadow
Drive System
Upgrades
(SD‐22000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $440,133   $663,551  Public Works  Completed  Summer 2024 Project Status: This project added approximately 404 linear feet of new 24‐inch high density polyethylene (HDPE) to be parallel to the existing 36‐inch pipe within East Meadow Drive to increase the capacity of the storm drain system.  This  project  includes  upsizing  manholes  based  on  new  pipes  and  reconnecting  laterals  from  private property  and  catch  basins.  A  construction  contract  was  awarded  in  October  2023,  and  construction  began  in November 2023. The project was completed in September 2024, after additional storm drain‐pipe replacement locations as part of the Storm Drain Rehab project (SD‐06101) were completed.

East Meadow
Circle
Connection to
Adobe Creek
Pump Station
(SD‐26000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $333,087   $634,016  Public Works  Completed  Summer 2024 Project  Status:   This  project  installed  approximately  506  linear  feet  of  15‐inch  pipe  and  manholes  along  East Meadow Circle. The upgraded line will eliminate flooding that occurs within East Meadow Circle when the water level within Barron Creek is higher than the flap‐gate, and flows are not able to drain into the creek. The new 15‐ inch HDPE line extension allows flows to drain away from Barron Creek and into Adobe Creek, where they can be pumped. The project also includes a small bioretention area to treat low flow runoff within East Meadow Circle Stormwater Management Projects           Status as of December 2024 Stormwater Management Projects ‐  Page 2 of 4
before discharging into either creek.  A construction contract was awarded in October 2023, and construction began in  November  2023.  The  project  was  completed  in  September  2024  following  additional  storm  drain‐pipe replacement locations as part of the Storm Drain Rehab project (SD‐06101).

Hamilton
Avenue System
Upgrades
(SD‐25000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $   $6,152,539  Public Works  Design   Summer 2026
Project Status:  This project adds approximately 3,700 linear feet of new 48‐inch high‐density polyethylene (HDPE) pipe and manholes on Hamilton Avenue to increase the capacity of the storm drain system. This project proposes to upsize the pipes to divert some flows away from Newell Road System and toward the 96‐inch line near Greer Road that would have otherwise drained towards Channing Avenue by adding storm pipe on a section of the 1500 block of Hamilton.  As a result of the December 31, 2022, flood event, the project includes upsizing the existing 12‐ inch line on Alester Drive for additional storage capacity. The design and project documents are underway. The project design is approximately 70% complete.

Trash Capture
Device
Installation
(SD‐22002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $762,720   $818,837  Public Works  Completed   Summer 2024 Project  Status:   This  project  involved  the  design  and  construction  of  a  large  trash  capture  device  (TCD)  to  be installed in the planting strip along Embarcadero Road located in front of the Palo Alto Baylands Golf Links parking lot. The TCD will be integrated into a 36‐inch storm pipe to capture trash as small as five millimeters from a section of the storm drain system prior to discharging to the San Francisco Bay. The 189‐acre drainage area treated by the TCD consists of 169 acres of commercial and office land use in the City’s jurisdiction and 20 acres in the California Department of Transportation (Caltrans) right‐of‐way. Caltrans provided funding for the project construction, while the City will take on the maintenance per an interagency agreement. Construction began in summer 2023 and was completed October 1, 2024.

Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $424,398   $2,881,017  Public Works  Design   Spring 2026 Stormwater Management Projects           Status as of December 2024 Stormwater Management Projects ‐  Page 3 of 4
West Bayshore
Road Pump
Station
(SD‐20000)
Project Status: This project incorporates the design and construction of a new small pump station with 15 cubic feet per second capacity.  Installing a new pump station will allow storm flows to be pumped into the Adobe Barron Creek confluence while adding a pump station in advance of the outfall would eliminate the routine flooding along West Bayshore Road and allow the system to convey runoff from a 10‐year storm event. Staff secured an easement for the pump station from adjacent property owners. The consultant completed the design of the project in June 2024. Due to poor bid results combined with high construction costs, a third IFB is scheduled to be advertised in December 2024.

West Bayshore
Road Trunk Line
Improvements
(SD‐23000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $44,554   $2,424,006  Public Works  Design  Spring 2026 Project Status: This project replaces approximately 1,400 linear feet of existing 15‐inch diameter pipe with 36‐inch High Density Polyethylene pipe.  These improvements along with the new West Bayshore Road Pump Station (SD‐ 20000) will eliminate the routine flooding along West Bayshore Road and allow the system to convey runoff from a  10‐year  storm  event.  Staff  secured  an  easement  for  the  pump  station  from  adjacent  property  owners.  The consultant  completed  the  design  of  the  project  in  June  2024.  Due  to  poor  bid  results  combined  with  high construction costs, a third IFB for the project is scheduled to be advertised in December 2024.

Recurring Projects
Green
Stormwater
Infrastructure
(SD‐22001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $77,092   $1,819,870  Public Works  N/A  Recurring
Project Status:  This project provides funding for Green Stormwater Infrastructure (GSI) projects and the integration of GSI features in the design and implementation of planned CIP projects supported by other funds. GSI mimics the natural  environment  to  slow,  spread,  infiltrate,  and  filter  pollutants  from  stormwater  runoff  through  native  or Stormwater Management Projects           Status as of December 2024 Stormwater Management Projects ‐  Page 4 of 4
engineered soils or other pervious material rather than discharging it directly into the storm drain system, creeks, and the Bay. Types of GSI include bioretention areas, flow‐through planters, tree wells, and pervious pavement to manage stormwater runoff.  The FY 2024 budget is allocated as a match to fund the balance of a GSI project partially funded by the U.S. Environmental Protection Agency (EPA) and for constructing a bioretention area as part of the East Meadow Circle Connection to Adobe Creek pump station project (SD‐26000) in spring 2024. SD‐26000 has been completed, while a request for proposals for the EPA‐funded project will be released in spring 2025.

Storm Drainage
System
Replacement
and
Rehabilitation
(SD‐06101)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $598,188   $1,650,239  Public Works  N/A  Recurring
Project  Status:  This  project  provides  for  annual  replacement  and  rehabilitation  to  maintain  the  integrity  of  the storm drain system, including deteriorated storm drain piping, manholes, and storm drain inlets. The rehabilitation includes replacement of broken corrugated metal pipe with High Density Polyethylene pipe. Based on recent pipe failures  that  occurred  in  early  2023,  storm  drain  pipes  at  seven  locations  (Forest  Avenue,  Embarcadero  Road, Fielding Drive, Middlefield Road, Newell Road, and Alexis Drive) were replaced as part of CIP projects SD‐22000 and SD‐26000. A construction contract was awarded in October 2023 and construction was completed in September 2024.

Wastewater Collection Fund Projects          Status as of December 2024

Wastewater Collection Fund Projects – Page 1 of 2
One‐Time Projects
Wastewater
Collection
System
Rehabilitation
Augmentation
Project 32
(WC‐20000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $3,000,000  Utilities  Construction  Summer 2026
Project Status:  This project designs and constructs high priority main and lateral replacements, which reduces inflow of rainfall and infiltration of groundwater into the collection system. The project will replace   approximately 5,200 linear feet (which represents 0.5 percent of the City’s Wastewater Collection System) for streets in the Middlefield Road, Webster Street, Santa Rita Avenue, and N. California Avenue neighborhoods. The project will be comprised of laterals identified in video inspection work or through maintenance records as deficient and in need of replacement.

Priority  will  be  given  to  areas  identified  by  Public  Works  as  targeted  work  zones  ensuring  coordination  between departments.

Recurring Projects
Sewer
Lateral/Manhole
Rehabilitation
and
Replacement
(WC‐99013)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $688,486   $875,500  Utilities  N/A  Recurring
Project Status: This project replaces defective sewer laterals, cleanouts, manholes, backwater devices, and equipment to support these activities to maintain the Wastewater Collection System, as well as to comply with the Sanitary Sewer Master Plan (SMP).  Information collected during routine annual maintenance activities is used to prioritize work. The continued work performed will also help to reduce both sewage blockage and the City's treatment expenses to treat rainwater or groundwater infiltration. A new three‐year construction contract was approved in FY 2023 to replace problematic sewer laterals. In the first half of FY 2025, two sewer lateral replacements were completed under this contract.

Wastewater Collection Fund Projects          Status as of December 2024

Wastewater Collection Fund Projects – Page 2 of 2
Sewer System,
Customer
Connections
(WC‐80020)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $386,388  $450,000  Utilities  N/A  Recurring
Project Status: This project installs sewer lateral connections and additions or extensions of existing mains to serve new  customers  and  to respond  to changes  in  sewer requirements  due  to  redevelopment.  Old existing  non‐plastic sewer laterals with condition deficiencies per Utilities Operations’ criteria are required to be replaced in accordance with the latest 2022 WGW Standards. In the first half of FY 2025, eleven new lateral connections were performed.

Wastewater
General
Equipment and
Tools
(WC‐13002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $44,679   $90,000  Utilities  N/A  Recurring
Project Status:    This project provides funds to procure new general equipment and new tools. In the first half of FY 2025, no new general equipment or tools was procured.

Wastewater
System
Improvements
(WC‐15002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $133,144   $200,000  Utilities  N/A  Recurring
Project Status: This project implements improvements to the Wastewater Collection System by increasing system capacity for growth, flow monitoring, hydraulic modeling and system analysis, load simulations, asset management analysis and assessment, system infiltration analysis, and sanitary sewer overflow monitoring and reduction. Part of this project funds the Sewer Master Plan Study, which is evaluating the City’s existing wastewater collection system, flows, and flow patterns to determine system capacity to meet current and future flows and recommend and prioritize capital  improvement  projects  where  needed.  The  consultant  contract  was  approved  in  November  2023  and  work began in December 2023. The project completed calibrating the collection system model in fall 2024 and is beginning to run the model to quantify existing system flows and buildout system flows. Project completion is anticipated in summer 2025.

Wastewater Treatment Fund Projects   Status as of December 2024

Wastewater Treatment Fund Projects – Page 1 of 4
One‐Time Projects
Local
Advanced
Water
Purification
System
(WQ‐19003)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $2,196,877   $ $67,138,041  Public Works  Design  Winter 2027 Project Status: This project enables the design and construction of an Advanced Water Purification Facility to further improve the quality of the tertiary‐treated recycled water by ultrafiltration followed by reverse osmosis to reduce the level of total dissolved solids. The water reuse partnership agreement with Valley Water and Mountain View provides $16 million in funding from Valley Water grant funding for a portion of the project costs and a State low‐interest loan for the design and construction phases. Mountain View agreed to pay the remainder of the capital costs associated with this project. The design is completed and staff issued an IFB in fall 2024. The project is in the process of receiving a building permit while financial agreements with funding agencies are being finalized. Construction is expected to start in spring 2025.

Headworks
Facility
Replacement
(WQ‐16002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $184,846   $55,820,790  Public Works  Pre‐Design  Fall 2032 Project Status: This project replaces the existing two outdated influent pump stations and their associated equipment and  ancillary  systems,  including  the  suction  and  discharge  piping  manifolds,  valves,  electrical  and  controls  system, screening  equipment,  grit  handling  equipment,  pumps,  flow  meters  and  yard  piping.  The  consultant  is  currently performing the preliminary design to finalize the design criteria. At the preliminary design conclusion, either the same or a different consultant will be selected to perform detailed design.

Horizontal
Levee Pilot
(WQ‐22001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $156,195   $754,625  Public Works  Design  Fall 2029
Project Status: This project consists of the design, permitting, and construction of a horizontal levee pilot system. The system will utilize treated wastewater to create a transitional brackish habitat on the Bayside of a future flood control levee located in the Palo Alto Baylands, adjacent to the Regional Water Quality Control Plant (RWQCP). Information and  data  collected  by  this  pilot  system  could  support  broader  implementation  of  horizontal  levees  as  green Wastewater Treatment Fund Projects   Status as of December 2024

Wastewater Treatment Fund Projects – Page 2 of 4
infrastructure components in larger flood control levee improvement projects within Palo Alto and beyond. The project completed design, CEQA review, conducted several stakeholder outreach events, created a project webpage, obtained all  construction  permits  from  resource  agencies,  received  a  recommendation  from  the  Parks  and  Recreation Commission, and obtained Council approval of the Park Improvement Ordinance as well as a Cooperative Agreement between project partners. The project is currently onboarding a construction management firm, preparing for required monitoring, and coordinating future community engagement activities including BioBlitz and King Tide Walks. The San Francisco Estuary Partnership/Association of Bay Area Governments will be posting the project for solicitation in early 2025.

Joint
Intercepting
Sewer
Rehabilitation
(Phase 1)
(WQ‐24000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $103,833   $12,590,181  Public Works  Construction  Summer 2025 Project Status: This project will rehabilitate 2,364 linear feet of the 60‐inch and 72‐inch diameter Joint Intercepting Sewer  (JIS)  trunk  line  leading  to  the  Regional  Water  Quality  Control  Plant  (RWQCP).  The  entire  trunk  sewer  line, constructed in 1972, is approximately 9,000 feet long consisting of thirteen manholes and three junction structures.

The JIS conveys raw wastewater mainly from the City of Mountain View, City of Los Altos, Los Altos Hills, and a portion of Palo Alto, which accounts for more than half of the RWQCP’s influent flows. A construction contract was awarded in winter 2024. Construction is 23% complete and is scheduled to be completed by summer 2025.

New
Laboratory
and
Environmental
Services
Building
(WQ‐14002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $363,705  $17,051,434  Public Works  Pre‐Design  Fall 2030 Project  Status:   This  project  was  originally  envisioned  to  replace  the  existing  plant  laboratory  and  environmental services offices.   Staff is currently revising space planning assumptions as the City and RWQCP are investigating the potential acquisition of a property adjoining the RWQCP and have put further design efforts on hold. The original design contract was terminated in March 2021. Solicitation for engaging a new consultant for detailed design will begin after advanced  planning  and  siting  analysis  are  completed  as  part  of  the  Long‐Range  Facilities  Plan  Update.

Wastewater Treatment Fund Projects   Status as of December 2024

Wastewater Treatment Fund Projects – Page 3 of 4
Recommendations from the Long Range Facilities Plan Update, anticipated to be completed in winter 2027, will help determine the direction the RWQCP will pursue to address this item.

Outfall Line
Construction
(WQ‐19000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $0  $18,237,754  Public Works  Design  Summer 2027
Project Status:  This project consists of the construction of a new parallel outfall pipe to convey final plant effluent to San Francisco Bay. A re‐design of the pipeline is needed to accommodate a potential future runway shift at Palo Alto Airport.  Staff  is  currently  working  with  the  Airport  staff  and  Federal  Aviation  Administration  (FAA)  to  gain  FAA concurrence for the pipeline construction and permanent easements on Airport property. The re‐design is anticipated to begin in 2025, moving immediately to construction upon design completion.

Secondary
Treatment
Upgrades
(WQ‐19001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $76,312,534   $193,322,311  Public Works  Construction  Summer 2028 Project  Status:  This  project  upgrades  the  Secondary  Treatment  process  at  the  RWQCP.  The  existing  Secondary Treatment process has two main components, the Fixed Film Reactors (FFR) and the Activated Sludge (AS) Process.

This project includes the reconstruction of the AS process, rehabilitation and reconfiguration of the AS Aeration Basins, the elimination of the FFRs, addition of denitrification capabilities, and replacement of equipment beyond its useful life.  Construction  began  in  winter  2023  with  the  completion  of  new  nitrification  denitrification  treatment  and retirement of the FFR’s is expected in 2028. Construction is still in progress with much of the underground support infrastructure in place. Reconfiguration of the first AS Aeration Basin is completed with the basin and is anticipated to be online in winter 2025.

Wastewater Treatment Fund Projects   Status as of December 2024

Wastewater Treatment Fund Projects – Page 4 of 4
Recurring Projects
Plant Master
Plan
(WQ‐10001)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $559,871   $442,061  Public Works  N/A  Recurring
Project Status: This project enables the ongoing program management support for major capital projects. Current tasks include  developing  scopes  of  work,  evaluating  consultant  proposals,  coordinating  project  management  activities, pursuing  State  low‐interest  loans  for  multiple  projects,  and  updating  partner  agreements.  The  consultant  provides support for the projects associated with the Long‐Range Facilities Plan (LRFP) update.

Plant Repair,
Retrofit and
Equipment
Replacement
(WQ‐19002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $5,804,943   $13,727,555  Public Works  N/A  Recurring
Project Status:  This project enables the assessment, repair, and retrofit of the RWQCP’s concrete and metal structures; the replacement of necessary equipment and ancillary facilities, including electrical equipment/systems, to maintain treatment  reliability  and  existing  infrastructure;  and  the  replacement  of  large  diameter  flow  meters  built  into  the wastewater treatment system on sewers, pipes, and water lines. Design of the 12 kV Electrical Loop Upgrade Project was completed in spring 2022. A construction contract for phase 1 was executed in winter 2023 and completed in fall 2024. A construction contract for Phase 2 was executed in fall 2024 and is scheduled to be completed by fall 2026.

Water Fund Projects              Status as of December 2024

Water Fund Projects – Page 1 of 5
One‐Time Projects
Water Main
Replacement
Project 29
(WS‐15002)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $3,888,047   $9,307,828  Utilities  Completed  Summer 2024 Project  Status:  This  project  funded  the  design  and  replacement  of  structurally  deficient  water  mains  and appurtenances. Mains are selected by researching the maintenance history of the system and identifying those that are undersized, corroded, and/or subject to breaks. The project scope includes approximately 7,500 linear feet (which represents 0.6 percent of the City’s Water Distribution System) of mains and services on various streets within  the  City,  including  areas  in  the  Evergreen  Park  and  Ventura  neighborhoods.  Construction  started  in November 2023 and was completed in September 2024.

Water Main
Replacement
Project 30
(WS‐16001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $5,371   $9,809,000  Utilities  Design  Spring 2026
Project Status: This project will fund the replacement of structurally deficient water mains and appurtenances in Fiscal Year 2026. Mains are selected by researching the maintenance history of the system and identifying those that are undersized, corroded, and subject to breaks. The project scope includes approximately 10,000 linear feet (which represents 0.8 percent of the City’s Water Distribution System) of mains and services on various streets within the City, including areas in Midtown/Midtown West, Palo Verde, and Green Meadow neighborhoods. The design is approximately 50% complete at the midpoint of FY 2025.

Water Recycling
Facilities
(WS‐07001)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $710,106  $852,674  Utilities  Pre‐Design   Fall 2027
Project Status: This project allows the City to hire a consultant to prepare a business plan, prepare preliminary design, and secure funding options for an expansion of the existing recycled water delivery system in the City. The expansion pipeline is one of several water reuse projects being considered in the Northwest County Recycled Water Strategic Plan. One Water Plan development is underway to evaluate alternative water supplies, define existing and future uncertainties and supply risks, and identify community needs and priorities. Funding contribution from Water Fund Projects              Status as of December 2024

Water Fund Projects – Page 2 of 5
the Water Fund to the Recycled Water project has ended and funding for Operations and Maintenance will be reviewed for budget cycle FY 2027.

Water Tank
Seismic Upgrade
and
Rehabilitation
(WS‐09000)
Prior Years Actuals  Total Project Budget  Implementing Department  Project Phase  Project Completion $9,944,241   $26,816,199  Utilities  Construction  Fall 2028 Project  Status:  This  project  for  Seismic  Water  System  Upgrades  includes  seismic  upgrades  at  the  Montebello, Mayfield,  Corte  Madera,  Park,  Boronda,  and  Dahl  Reservoirs  in  compliance  with  the  American  Society  of  Civil Engineers  (ASCE  7)  seismic  codes.  Mayfield  Reservoir  was  seismically  retrofitted  in  2011.  Seismic  upgrades  of Boronda and Montebello Reservoirs were completed in 2016 and 2018. The new concrete Corte Madera Reservoir was  completed  in  April  2022.  The  Park  Reservoir  and  Dahl  Reservoir  Tanks  are  scheduled  next  for  retrofit  or replacement. An Engineering and structural assessment of Park Reservoir was completed in spring 2023, and Dahl Reservoir will be assessed in 2025.

Recurring Projects
Water
Distribution
System
Improvements
(WS‐11003)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $161,813   $975,388  Utilities  N/A  Recurring
Project Status: This project enables improvements to water distribution system deliverability and reliability. Typical activities  include  installing  restraining  joints  at  critical  pipelines  and  bridge  crossings,  increasing  the  size  of inadequate  facilities,  system  leakage  surveys,  network  modeling,  and  fire  flow  studies  or  other  system improvements  as  required.  Continuous  evaluation  of  system  needs  and  making  required  improvements  is necessary to maintain adequate quantities of quality water, meeting local, state, and federal safe drinking water standards. The Pump Station Painting project to paint the five foothill pump stations was completed in May 2024.

Water Fund Projects              Status as of December 2024

Water Fund Projects – Page 3 of 5
Services for a full system leakage survey of the water distribution system will be solicited in 2025 and the work is expected to be completed by 2026.

Water, Gas,
Wastewater
Utility GIS Data
(WS‐02014)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $249,154   $578,800  Utilities  N/A  Recurring
Project Status: This project enables contracts related to Utilities GIS (Geographic Information System) needs.  AME database  is  heavily  utilized  by  Utilities  Engineering  staff  to  update  the  utility  information  in  GIS.   The  updated information  is  used  by  various  City  staff,  such  as  marking/locating  underground  utilities  to  comply  with  USA (Underground Service Alert) requirements; developing design drawings for pipeline replacement projects; verifying existing underground utilities during construction activities; creating customized utility map books for field crews and on‐call personnel to meet their specific needs.  Annual surveying contracts collect GPS points of existing above‐ ground utility features within CIP project areas. The data being collected continues to be used to correct the GIS database. Accurate utility data helps the design to select new pipe alignment to minimize construction conflicts and provides data for additional road feature linework to be corrected in the older GIS/AVEC database via ESRI.

Water General
Equipment/Tools
(WS‐13002)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $0.00   $100,000  Utilities  N/A  Recurring
Project Status: This project acquires new equipment and tools, the replacement of existing fusion equipment, and other associated tools. The fusion equipment is used to fuse together pipe joints in the City's water distribution system. Equipment and tools are required to be upgraded on an annual basis to maintain high quality standards for the installation of the City's water distribution mains, along with the associated service standards and worker safety and productivity measures. There were no purchases of equipment or tools in the first half of FY 2025.

Water Meters
(WS‐80015)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $2,801,577  $367,440  Utilities  N/A  Recurring
Water Fund Projects              Status as of December 2024

Water Fund Projects – Page 4 of 5
Project Status: This project enables the purchasing of meters for new customers, upgrading meters for current customers, installing meter bypasses, and replacing obsolete meters that are no longer repairable. This funding also allows for annual testing and calibration of selected meters to maintain meter accuracy and reliability. During the AMI implementation process, approximately 50% of the meters will be replaced, with a focus on meters more than twenty years old. Staff is currently testing large diameter meter sets. Staff continues to test additional larger diameter meters.

Water Service
and Hydrant
Replacement
(WS‐80014)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $152,163   $412,000  Utilities  N/A  Recurring
Project Status: This project replaces system control valves, deteriorated galvanized service lines, lead goosenecks, and fire hydrant valves and assemblies per the Fire Department’s flow testing, upgrades fire hydrants in main line replacement  project  areas,  replaces  damaged  fire  hydrants,  and  replaces  existing  undersized  or  deteriorated copper water services on an as needed basis. Staff has been working on an extensive valve audit and to date have operated and evaluated approximately 74% of the City’s 6,500 water valves. This project will be increasing work to replace inoperative and leaking valves identified during this audit process. This project will be increasing work to replace  inoperative  and  leaking  valves  identified  during  this  audit  process.  In  addition,  the  City  will  be  doing additional work to look for possible lead whips in our distribution system as we continue to comply with the new lead and copper rule revisions (LCRR).

Water System
Customer
Connections
(WS‐80013)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $1,187,207   $960,500  Utilities  N/A  Recurring
Project Status: This project allows for improvements that include new main extensions, valves, domestic services, meters on upgraded services, backflow devices, fire services, and fire hydrants. System extensions are required to provide  service  to  new  large  developments  and  to  serve  existing  customers  requesting  expanded  service  on Development Services projects. A total of 70 water services were installed in the first half of FY 2025.

Water Fund Projects              Status as of December 2024

Water Fund Projects – Page 5 of 5
Water System
Supply
Improvements
(WS‐11004)
Prior Year Actuals  Current Year Budget  Implementing Department  Project Phase  Project Completion $23,648   $4,133,706  Utilities  N/A  Recurring
Project Status: This project evaluates and improves the City’s water distribution system on an as‐needed basis. This project includes piping modifications, equipment replacements associated with water delivery, supervisory control software  upgrades,  system  modifications  for  water  system  quality  compliance,  conditional  assessment  of  the reliability  of  transmission  mains,  and  security  system  installations.  The  water  system  includes  the  connection facilities between the City’s and the San Francisco Public Utility Commission’s pipelines, emergency water wells within the City’s pumping stations, water reservoirs, and pipelines. Security cameras will also be added to various tanks,  pump  stations,  and  turnouts  as  part  of  the  Security  Cameras  project.  Two  new  generators  have  been purchased and will be deployed in FY 2025.

List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
AP‐23000
Airport Zero Emission
Vehicle Fleet Replacement
Program
This project provided the funding to replace existing support vehicles used by Airport staff with zero emission vehicles. The Airport received delivery of the final new electric truck in fall 2024 which replaced both airport vehicles with electric vehicles.

Procurement Airport Airport Summer 2024  $                377,696.00 PE‐24000 Baylands Boardwalk Piling
Repair
This project provided funding for the identification and implementation of a long‐term repair solution to damage caused by aquatic borers to the Lucy Evans Baylands Interpretive Center’s boardwalk pilings. The project received permits from the San Francisco Bay Regional Water Quality Control Board, Bay Conservation and Development Commission, United States Fish and Wildlife Services, and United States Army Corps of Engineers. Project construction was completed in October 2024.

Construction Buildings and
Facilities Public Works Fall 2024 276,461.00 $
PG‐14002 Cameron  Park Improvements
This project upgraded and renovated safety and accessibility features at Cameron Park with a primary focus on the park playground improvements. The Cameron Park Improvements Project were completed in November 2024.

Construction Parks and Open
Space
Community
Services Fall 2024  $                205,627.00
PE‐20002
City Facilities Assessment
and Record Plan
Management System
This project provided a complete Facility Condition Assessment (FCA)  to renew cost estimates of the deferred maintenance, planned maintenance, capital renewal and electrification costs of city facilities over the next 30 years.  A detailed list of buildings for electrification has been analyzed to determine prioritization to help meet SCAP goals. The data has been updated into the City of Palo Alto’s newly customized Infrastructure Management System to provide long range capital planning based on the results of the FCA.  The Record Plan Management System is being implemented through TE‐13004. The project reached completion in fall 2024.

Construction Buildings and
Facilities Public Works Fall 2024  $                333,134.00 SD‐22000 East Meadow Drive System
Upgrades
This project added 407 linear feet of new twenty‐four inch high density polyethylene (HDPE) to be parallel to the existing thirty‐six inch pipe within East Meadow Drive to increase the capacity of the storm drain system. This project included upsizing manholes based on new pipes and reconnecting laterals from private property and catch basins. Project was completed in September 2024.

Construction Stormwater
Management Public Works Summer 2024 636,405.00 $
SD‐26000
East Meadow Circle
Connection to Adobe Creek
Pump Station
This project installed 506 linear feet of fifteen‐inch pipe and manholes along East Meadow Circle.

The upgraded line will eliminate flooding that occurs within East Meadow Circle when the water level within Barron Creek is higher than the flap‐gate, and flows are not able to drain into the creek. The new fifteen‐inch HDPE line extension allows flows to drain away from Barron Creek and into Adobe Creek, where they can be pumped. The project also included a small bioretention area to treat low flow runoff within East Meadow Circle before discharging into either creek. The project was completed in September 2024.

Construction Stormwater
Management Public Works Summer 2024 634,016.00 $
SD‐22002 Trash Capture Device
Installation
This project included both the design and construction of a large trash capture device (TCD) installed in the planting strip along Embarcadero Road located in front of the Palo Alto Baylands Golf Links parking lot. The TCD was integrated into a thirty‐six inch storm pipe to capture trash as small as five millimeters from a section of the storm drain system prior to discharging to the San Francisco Bay. The 189‐acre drainage area treated by the TCD consists of 169 acres of commercial and office land use in the City’s jurisdiction and twenty acres in the California Department of Transportation (Caltrans) right‐of‐way. Construction was completed October 1, 2024.

Construction Stormwater
Management Public Works Fall 2024 818,837.00 $
December 2024
1 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
EL‐24001 Hanover Substation
Improvement
This project  installed two 12 kV 50 MVA transformers to replace two 4kV transformers that served 1501 Page Mill Road and make all substation improvements necessary to accommodate the installations. Project construction is 100% complete and new Hanover substation transformers and switchgear have been successfully tested and commissioned and released to the Utility Operations group. Final project close out and settlement of Public‐Private Partnership Contract between the City and Tesla still remain.

Construction Electric Utilities Fall 2024  $          15,000,000.00 WS‐15002 Water Main Replacement
Project 29
This project funded the design and replacement of structurally deficient water mains and appurtenances. Mains are selected by researching the maintenance history of the system and identifying those that are undersized, corroded, and/or subject to breaks. The project scope included approximately 7,500 linear feet (which represents 0.6 percent of the City’s Water Distribution System) of mains and services on various streets within the City, including areas in the Evergreen Park and Ventura neighborhoods. The project was completed in September 2024.

Construction Water Utilities Fall 2024 9,307,828.00$
OS‐24000 Baylands Nature Preserve
Entrance Gate
This project installed a new automated gate at the Baylands Nature Preserve main entrance. The existing gate was manually opened and closed by staff each day for public access. The scope of work included an electrical transformer, trenching, wiring, and gate automation equipment.  The project started  June 24, 2024 and reached substantial completion on June 30, 2024.

Construction Parks and Open
Space
Community
Services Spring 2024 132,701.00$
PE‐13011 Charleston Arastradero
Corridor Project
The Charleston Arastradero Corridor was reconfigured to provide new landscaped median islands, bulb outs, enhanced bike lanes, traffic signal improvements, and new street trees to complement the new lane configurations that were approved for permanent retention.  Phase 1 (Arastradero Road between Foothill Expressway to Clemo Avenue), Phase 2 (Charleston Road from Alma Street to Middlefield Road) and Phase 3 (Arastradero Road from Los Palos Avenue to El Camino Real, Charleston Road from El Camino Real to Alma Street and from Middlefield Road to San Antonio Road) have all been completed as of spring 2024.

Construction Traffic and
Transportation Public Works Spring 2024  $          20,788,951.00 WC‐19001
Wastewater Collection
System Rehabilitation
Augmentation Project 31
This project funded the design and construction of high priority main replacement work, which reduces inflow of rainfall and groundwater into the collection system. The project replaced approximately 11,000 linear feet (which represents 1.0 percent of the City's Wastewater Collection System) for El Camino Real from Page Mill Road to Cesano Court, and Page Mill Road from Ramos Way to Ash Street. The project wais comprised of mains identified in video inspection work or through maintenance records as structurally deficient and in need of replacement. The work was in Caltrans (El Camino Real) and the County of Santa Clara (Page Mill Road) right‐of‐way.  Construction was completed May 5, 2024.

Construction Wastewater
Collection Utilities Spring 2024 8,635,244.00$
WQ‐14003 Primary Sedimentation Tank
Rehabilitation
This project enabled the design and construction for new protective coatings on each of the four concrete primary sedimentation tanks, with replacement of worn rotating parts and mechanical and electrical equipment.  These tanks were installed in 1972 and the recoating project will will extend the concrete life for another thirty years.  Substantial completion was achieved on June 1, 2024.

Construction Wastewater
Treatment Public Works Spring 2024 20,449,644.00 $
WS‐07000 Water Regulation Station
Improvements
This project for Water Regulation Station Improvements included seismic upgrades, piping improvements and other various upgrades to increase the structural reliability of two of the City's turnouts with SFPUC.  Work under this project includes Seismic Upgrades of California Avenue and Page Mill Road Turnouts.  Structural evaluation for restraining the Page Mill turnout and piping was included in the design.   The construction  was completed in May 2024.

Construction Water Utilities Spring 2024 2,960,477.00$
June 2024
2 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
PE‐19001 Water, Gas, Wastewater
Office Remodel
This project incorporated renovations to the Utilities Water Gas Wastewater (WGW) office space at the Municipal Service Center (MSC).  The new work area includes a small reception area, a renovated kitchen and printer area, additional offices and cubicles, upgrades to the HVAC system, lighting improvements and fire life safety systems upgrade.  Construction was completed in April 2023.

Construction Buildings and
Facilities Public Works Spring 2023  $            1,234,354.00 FD‐22000 Extrication  Tool Replacement
This project provided funding for the replacement of all extrication tools for the Fire Department. Extrication tools, also known as "Jaws of Life", are used to rescue victims of car accidents and other emergencies where the victims are trapped in confined spaces.  Equipment was purchased in winter 2023 and the project is complete.

Procurement Buildings and
Facilities
Fire
Department Winter 2023 298,200.00 $
WS‐14001 Water Main Replacement
Project 28
This project has replaced approximately 18,600 linear feet (which represents 1.6% of the City's water distribution system) of mains and 265 services on various streets in the City, including areas in the Duveneck, St. Francis, Barron Park and Charleston Meadows neighborhoods.

Construction started in April 2022 and the project was substantially completed in spring 2023.

Construction Water Utilities Spring 2023 10,305,619.00 $ WC‐17001
Wastewater Collection
System Rehabilitation
Augmentation Project 30
This project included the design and construction of high priority mains with structural defects that could not be addressed with routine maintenance.  The wastewater mains on various streets in the City were replaced with approximately 10,000 linear feet of HDPE sanitary sewer mains and associated laterals in the Ventura, Charleston Meadows, Fair Meadow, and Palo Verde neighborhoods.   The project achieved substantial completion in April 2023.

Construction Wastewater
Collection Utilities Spring 2023 4,656,777.00 $
AP‐16000 Airport Apron
Reconstruction
This project included the design and reconstruction of the Palo Alto Airport apron.  The need to reconstruct the aircraft parking apron is critical to airport safety.  Construction Phase I was completed in November 2017.  Construction Phase II was completed in winter 2020.

Construction on Phase III reached substantial completion  in June 2023 Construction Airport Airport Spring 2023 41,563,570.00 $ PE‐21003
Magical Bridge Playground
Rubber and Synthetic Turf
Resurfacing
This project replace rubberized and synthetic turf surfacing in the playground and replace play equipment including swings, climbing net, and playhouse.  An IFB was issued in November 2021 and Council awarded a construction contract in spring 2022.  Installation of rubberized and synthetic surfacing, replacement of climbing nets and renovation of the playhouse took place in fall 2022. Project was completed in December 2022.

Construction Parks and Open
Space Public Works Fall 2022 857,380.00 $
June  2023
3 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
GS‐13001 Gas Main Replacement
Project 23
This project designed and constructed approximately 21,700 linear feet (which represents 1.9% of the City's Gas distribution main system) of distribution main and 320 gas services constructed mainly of PVC material on various streets within the Midtown, Evergreen Park, Ventura, College Terrace, Charleston Terrace, and Research Park neighborhoods.   Construction began in winter 2021and was completed in summer 2022
Construction Gas Utilities Summer 2022 7,951,858.00 $
FD‐21000 Automated External
Defibrillator Replacement
This project replaced the entire complement of Automated External Defibrillators (AEDs) throughout City facilities and emergency response vehicles, which currently totals 93 AEDs.  The RFP process was completed in fall 2021.  The new AEDs were purchased and deployed in summer 2022.

Procurement Buildings and
Facilities
Fire
Department Summer 2022  $                237,500.00
PF‐17000 Municipal Service Center A,
B, & C Roof Replacement
This project replaced the existing MSC roofs.  The existing asphalt and gravel roofs have reached the end of their useful life and needed to be replaced.  The new roofs will meet current cool roofing codes to optimize energy efficiency.   Construction was completed in November 2022.

Construction Buildings and
Facilities Public Works Fall 2022 2,013,475.00 $
EL‐16002 Capacitor  Bank Installation
This project installed capacitor banks at electric substations and on distribution lines to ensure Northern California Power Association Power Factor requirements are met.   Capacitor banks were installed at Hanover Avenue, Hansen Way, Maybell Avenue, and Park Boulevard Substations.    The project was substantially completed in June 2022 and will be commissioned and energized in summer 2022.

Construction Electric Utilities Spring 2022  $                  1,050,443 EL‐17007
Facility Relocation for
Caltrain Modernization
Project
The Utilities Department removed the overhead lines allowing for the installation of the Overhead Catenary System above the rails for the Caltrain Modernization.  This project was completed in spring 2022
Construction Electric Utilities Spring 2022  $                  3,055,472 PE‐08001 Rinconada Park
Improvement
This project upgraded safety, site amenities, playground facilities, a new restroom, irrigation, drainage, and ADA accessibility improvements at Rinconada Park.  These improvements were identified in the Rinconada Long Range Plan (LRP).  Phase 1 of construction started in August 2021 and construction was completed in spring 2022.

Construction Parks and Open
Space Public Works Spring 2022  $                  4,646,247 EL‐14005 Reconfigure  Quarry Feeders
This project reconfigured the distribution circuits to the substation transformer at Quarry Substation.  Design of QR 27 feeder replacement was completed in spring 2021. Construction was completed in December 2021 .

Construction Electric Utilities Fall 2021 792,034 $
AC‐18001 JMZ  Renovation
This project provided for the relocation of the Junior Museum and Zoo to Cubberley for two years while a new JMZ was being built, tenant improvements to the Cubberley Auditorium and then removal of tenant improvements post‐construction.  Construction of the new Junior Museum and Zoo started in June 2018 and was completed in late 2021. The new Junior Museum and Zoo was opened to the public on November 12, 2021.

Construction Buildings and
Facilities
Community
Services Fall 2021 2,927,870.00 $
December 2022 June 2022
4 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
PE‐18002
High and Bryant Street
Garages Waterproofing and
Repairs
This project included a systems analysis and repaired the water proofing system in the High Street and Bryant Street parking garages.  Water proofing repairs were completed in the High Street parking garage.   Additional funding was added and the contractor completed waterproofing repairs in the subterranean stairwells in the Bryant Street garage in fall 2021.

Construction Buildings and
Facilities Public Works Fall 2021 264,235.00 $
PE‐11011 Highway 101 Pedestrian
Bicycle Overpass Project
As part of the 2014 Council Infrastructure Plan, this project designed and constructed a new pedestrian bridge across Highway 101 at Adobe Creek. Council approved a contract with Granite Construction in November 2019.  Construction began in January 2020.  The project construction completed on November 20, 2021,  with a ribbon‐cutting ceremony and a community celebration.

Construction Traffic and
Transportation Public Works Fall 2021 22,889,453 $
EL‐12001 Underground District 46
Charleston
This project undergrounded the existing overhead utility systems in the area along the 400 block of West Charleston and El Camino Real.   Staff  completed  cable, equipment installation and 100% of customer service conversions. The construction for the final phase of the project to install two 60 foot tall steel poles and to reconductor the 60 kV sub‐transmission lines was completed in the fall 2021.

Construction Electric Utilities Fall 2021  $                  3,904,425 OS‐18001
Pearson Arastradero
Preserve Parking lot
Improvement
This project improved the Pearson Arastradero Preserve parking lot by improving the base rock surfacing, adding drainage, widening the entrance for safety, and new fencing.  This new improvement will allow the overflow parking area to be open year round.  The work was completed in May 2021.

Construction Parks and Open
Space
Community
Services Spring 2021  $                     170,300
CB‐16001 Cubberley Community
Center Master Plan
This project developed the master plan  for future use of the Cubberley Community Center site by the City and Palo Alto Unified School District. Study Buildings and Facilities
Community
Services Spring 2021  $                     926,792
CB‐19001 Cubberley Building
Management Systems
This project replaced the Building management System(BMS) controls for the pavilion, Theater, Wing I, and Gyms A and B boiler rooms at the Cubberley Community Center.  The project included the installation of control points for each building along with controllers, valve and damper actuators.

Construction Buildings and
Facilities Public Works Spring 2021  $                     350,000 FD‐14002 Fire Ringdown System
Replacement
This project replaced the current ring down system that provides an audible alert of calls in the fire stations.  Ongoing installations started in 2018 and were completed with Fire Station #3. Construction Buildings and Facilities Fire Departent Spring 2021  $                     400,144 PD‐14000 Internal Alarm System
Replacement
The project replaced the citywide internal alarm system.  The alarms at City Hall migrated to this new system in FY 2019, but was completed in early 2021. Construction Buildings and Facilities
Police
Department Winter 2021  $                        77,569 FD‐20001
Self Contained Breathing
Apparatus (SCBA) Air
Compressor Replacement
This project replaced the central air compressor that provides air for the self‐contained breathing apparatus (SCBA) tanks to ensure firefighter safety when entering environments with hazardous air quality.

Construction Buildings and
Facilities
Fire
Department Spring 2021  $                        94,500 December 2021 June 2021
5 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
AP‐20000 Airport Electrical
Improvements
This project replaced the outdated electrical panels for the Palo Alto Airport office rental spaces.

Construction was completed in January 2021. Construction Airport Public  Works Winter 2021  $                     146,466 PE‐18000 New California Avenue Area
Parking Garage
This project built the California Avenue Area Parking Garage, as part of the 2014 Council Infrastructure Plan.   The parking garage has 627 parking spaces with 2 basement levels and 4 above grade floors.  The garage features an automated parking space guidance system, EV charging stations, bicycle parking, and motorcycle parking. The garage was opened to the public on December 8, 2020.

Construction Buildings and
Facilities Public Works Fall 2020  $                50,119,976 PF‐14002 Fire  Station 1 Improvements
This project updated the individual sleeping quarters in the firehouse to address gender issues and privacy concerns.  Fire Station #1 was the only fire station in the City that did not have separate bedrooms to accommodate male and female firefighters.   This project was completed in fall 2020.

Construction Buildings and
Facilities Public Works Fall 2020  $                     187,064 GS‐18000 Gas ABS/Tenite Replacement
Project
This project replaced gas services laterals constructed of Acrylonitrile‐butadiene‐styrene (ABS) or Tenite material on various streets.  Council approved funding in June 2019.  The project replaced 104 ABS and Tenite gas services.  The WQCP ABS gas service is assigned to Utility Operations for replacement and the remaining five ABS gas services will be scheduled for replacement once the five‐year moratorium ends on those streets.  As of November 2020, this project is complete.

Construction Gas Utilities Fall 2020  $                  2,615,100 SD‐19000 Loma Verde Avenue Trunk
Line Improvements
This project replaced 1,750 linear feet of storm drain with 48‐inch diameter High Density Polyethylene (HDPE) pipe and associated catch basins, laterals and manholes.  In addition to underground work, additional street restoration and concrete work was completed. Work includes resurfacing one full lane on Loma Verde from the beginning to the end of the project limits, replacement of driveways, sidewalk, and 718 linear feet of curb and gutter.   The contract was awarded in June 2020, construction work began in August 2020,  and was completed in December 2020.

Construction Storm  Drain Utilities Fall 2020  $                  2,976,813 WS‐19000 Mayfield Reservoir Subgrade
and Venting Repair
This project is part of the City’s recent Seismic Upgrade and Emergency Water Supply and Storage Projects.  The reservoir was drained in 2012 for approximately two years to allow extensive seismic rehabilitation work to be performed and construction of a new pump station.

Subsequently hairline cracks were sealed in the reservoir.  A geotechnical consultant was hired to evaluate the tank foundation.  This study was completed and there were several options identified.  Staff has completed the design and construction of the vent screen replacement and crack sealing.

Construction Water Utilities Fall 2020  $                     600,000 EL‐11010
Underground District 47
Middlefield, Homer,
Webster, Addison
This project undergrounded the existing overhead distribution system in the area bounded by Middlefield Road, Homer Avenue, Webster Street, and Addison Avenue. Installation of substructures and utility electric system is completed.  Where possible, the overhead electric lines were removed and poles cut down to the level of the communication lines.

Construction Electric Utilities Fall 2020  $                  3,649,356 December 2020
6 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
WC‐16001
Wastewater Collection
System Rehabilitation
Augmentation Project 29
This project replaced of 8,972 linear feet of wastewater mains.  The sanitary sewer mains, laterals, and manholes to be rehabilitated or replaced in this project are located in the Charleston Meadows neighborhood.  Construction started in February 2020 and was suspended for almost 3 months due to COVID‐19 County’s Shelter‐in‐Place Order.  The project is complete as of December 2020.

Construction Wastewater
Collection Utilities Fall 2020  $                  4,434,839 PF‐18000 Parking Lot J Elevator
Modernization
This project modernized the existing elevators at parking Lot J.  The project involves upgrading the interior of the elevators, elevator control interface, call buttons, and meeting current ADA standards.  Construction started in April 2019.  Project is complete except for the State final inspection on the second car.  State is behind because of COVID, but the inspection should be done by the end of July 2020.

Construction Buildings and
Facilities Public Works Spring 2020  $                     781,324 PE‐15003 Fire  Station 3 Replacement
This project replaced the existing Fire Station at Embarcadero Road and Newell Road with a new structure that meets essential services standards and current program needs.   Construction completed in March 2020.

Construction Buildings and
Facilities Public Works Winter 2020  $                10,080,258 WS‐08001 Water Reservoir Coating
Improvements
This project included the recoating of four steel tanks. Work under this project was included in the Seismic Upgrade of four Steel Tanks and the three Turnout Projects. Once construction started, it was found that the Montebello Reservoir was in very poor condition. Due to escalating costs associated with roof replacement, staff decided to complete construction of the Montebello Reservoir and re‐evaluate the remaining three tanks for replacement.

Construction Water Utilities Spring 2020  $                  2,141,172 WS‐13001 Water Main Replacement ‐
Project 27
This project replaced approximately 9,600 linear feet of structurally deficient, aging, or corroded water mains and services along the mains on Sand Hill Road, Oak Creek Drive (5%) and Fulton Avenue.

Construction Water Utilities Spring 2020  $                  7,786,998 WC‐15001
Wastewater Collection
System Rehabilitation
Augmentation Project 28
This project enabled the design and construction of a high priority wastewater main and lateral replacement work to reduce inflow of rainfall and ground water into the collection system. The project replaced or rehabbed  a total of 7,655 linear feet of wastewater mains  located in the Leland Manor/Garland, Midtown West, and Lower Page Mill/Los Altos Hills areas of the City.

Construction Wastewater
Collection Utilities Spring 2020  $                  5,665,897 EL‐17003 VA Hospital ‐ Customer Load
Requirements
This project met the growing electric needs of the VA Hospital. Staff has had numerous discussions with VA Hospital on electric load growth at the hospital and anticipated needs from the utility. Much of the cost is reimbursed to the City by the VA Hospital. Staff has prepared preliminary designs for interim solutions and is awaiting additional information from VA to develop long range plans to meet their future needs.

Design Electric Utilities Spring 2020  $                        84,984 June 2020
7 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
EL‐04012 Utility Site Security
Improvements
This project added electronic security systems at utility sites to protect equipment at electric substations, water pumping plants, reservoirs, and gas stations from intrusion and vandalism.

Cameras and detection systems have been installed at nine electric substations, three water stations, and one natural gas station to monitor facilities.

Construction Electric Utilities Spring 2020  $                  1,644,681 EL‐11008 Rebuild Underground District
19 This project rebuilt and replaced the underground electric system in Underground District 19, the area bounded by Forest Avenue, Waverley Street, Addison Avenue, and Alma Street.  Construction Electric Utilities Spring 2020  $                     149,023 FD‐18000 Self Contained Breathing
Apparatus Replacement
This project replaced Self Contained Breathing Apparatus equipment (SCBA) used by firefighters when entering hazardous conditions when responding to fire and hazardous materials incidents.

The SCBA provides breathable air for firefighters when entering environments where the atmosphere is immediately dangerous to life or health.  The expected service life for SCBAs is 15 years.

Purchase Buildings and
Facilities
Fire
Department Spring 2020  $                     799,999
FD‐20000 Cardiac Monitor
Replacement
This project replaced the entire complement of twenty cardiac monitors in the Department.

Along with other tools needed for patient assessment and airway verification, cardiac monitors assess cardiac activity in patients and provide defibrillation and pacing.

Purchase Buildings and
Facilities
Fire
Department Spring 2020  $                     850,000
PL‐16001 Downtown Mobility and
Safety Improvements
This project included the construction of curb extensions and the installation of new pedestrian signal heads and traffic signal modifications in 2019 as part of the Upgrade Downtown project. Construction Traffic and Transportation
Office of
Transportation Fall 2019  $                  1,819,847
FD‐20002 Thermal Imaging Cameras
Replacement
This project replaced the Thermal Imaging Cameras (TICs) on all fire and response vehicles used to help identify the location of victims; assess the source of fires, smoke, and heat; to assist in creating a plan of action.

Purchase Buildings and
Facilities
Fire
Department Fall 2019  $                        99,000
WC‐11000
Wastewater Collection
System Rehabilitation
Augmentation Project 24
This project  addressed areas that were identified in Wastewater Capital Improvement Project 17 (Cleaning and Video Inspection of the Collection System) as needing rehabilitation. This project was combined with Project 25 and 26(WC‐12001; WC‐13001).

Construction Wastewater
Collection Utilities Fall 2019  $                  3,131,595 WC‐13001
Wastewater Collection
System Rehabilitation
Augmentation Project 26
This project was combined with Project 24 and 25(WC‐11001; WC‐12001). All new service laterals were installed from the new sewer main to the new sewer cleanouts located in the City’s right‐of‐way.

Construction Wastewater
Collection Utilities Fall 2019  $                  3,309,998 CB‐19000 Cubberley Track and Field
Replacement This project replaced the synthetic turf field, installed an all‐weather track and a fitness area. Construction Parks and Open Space Public Works Fall 2019  $                  1,851,708 PE‐14018 Baylands Boardwalk
Improvements  This project replaced the existing boardwalk with similar alignment and configuration.  Construction Buildings and Facilities Public Works Winter 2019 2,123,681 $
PE‐17009 City  Hall Floor 4 Remodel This project improved the Administrative Services Department offices on the fourth floor of City Hall. Construction Buildings and
Facilities Public Works Winter 2019 494,818 $
December 2019
8 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
PE‐14015
Lucie Stern Buildings
Mechanical and Electrical
Upgrades
This project replaced and upgraded the mechanical, electrical, and fire/life safety systems at Lucie Stern Children’s Theater, Lucie Stern Community Theater, and Lucie Stern Community Center.

Construction Buildings and
Facilities Public Works Spring 2019 6,142,607 $
PL‐16000 Quarry Road Improvements
and Transit Center Access
This project included planning, design and construction of bicycle and pedestrian improvements along Quarry Road. Construction Traffic and
Transportation
Planning and
Community
Environment
Spring 2019 5,148,378 $
EL‐17008 Utility Control Center
Upgrades This project upgraded the Utility Control Center working environment.  Construction Electric Utilities Winter 2019 499,997 $ GS‐12001 Gas Main Replacement
Project 22
This project replaced approximately 23,700 linear feet of gas mains and services along University Avenue and other streets in the Downtown North nieghborhood. Construction Gas Utilities Spring 2019 11,658,997 $ WC‐12001
Wastewater Collection
System Rehabilitation /
Augmentation Project 25
This project was combined with Project 24 and 26 (WC‐11001; WC‐13001) replacing 45,294 linear feet of sanitary sewer mains in university South, Professorville and Old palo Alto neigborhoods. Construction Wastewater Collection Utilities Spring 2019 3,211,998 $
WQ‐14001 Dewatering and Loadout
Facility
This project provides funding for the design and construction of the sludge dewatering facility and truck loadout to retire existing dewatering and sewage sludge incinerators.  Construction Wastewater Treatment Public Works Spring 2019 27,497,551 $
WS‐12001 Water Main Replacement –
Project 26
This project replaced approximately 11,000 linear feet of aging water mains and services which included water main replacement as part of the Upgrade Downtown Project. Construction Water Utilities Spring 2019 7,506,161 $ PE‐17009 City  Hall Floor 5 Remodel This project improved the Planning and Community Environment (PCE) Department offices on the fifth floor of City Hall.  Construction Buildings and Facilities Public Works Summer 2018 525,000 $
AC‐14001 Baylands Nature Interpretive
Center Exhibit Improvements
This project replaced worn out or non‐functioning exhibits at the Baylands Nature Interpretive Center. Construction Buildings and
Facilities
Community
Services Summer 2018 56,000 $
PE‐17000 Mitchell Park Adobe Creek
Bridge Replacement  This project replaced the existing bridge over Adobe Creek in Mitchell Park. Construction Parks and Open Space Public Works Summer 2018 250,000 $
PD‐14000 Internal Alarm System
Replacement
This project replaced the citywide system of panic alarms from various departments and the Council chambers. Construction Buildings and
Facilities Police Summer 2018 78,000 $
EL‐14004 Maybell 1&2 4/12kV
Conversion  This project converted circuits 1 & 2 at Maybell substation from 4kV to 12kV. Construction Electric Utilities Fall 2018 364,796 $ GS‐15001 Security at City Gas Receiving
Stations This project equiped the City’s four Gas Receiving Stations with video surveillance systems.  Construction Gas Utilities Summer 2018 150,000 $ SD‐13003
Matadero Creek Storm
Water Pump Station and
Trunk Line Improvements
This project upgraded the capacity to the Matadero Creek Storm Water Pump Station, which serves a low‐lying 1200‐acre area of southeastern Palo Alto.  Construction Storm  Drain Public  Works Summer 2018 6,685,317 $ June 2019 December 2018
9 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
AP‐16002 Wildlife Hazard Management
Plan
The Wildlife hazard Management Plan identified the specific actions the airport will take to mitigate the risk of wildlife strikes on or near the airport. Study Airport Public  Works Summer 2018 63,415 $ WC‐14001
Wastewater Collection
System Rehabilitation
Augmentation Project 27
This project replaced 16,859 linear feet of sanitary sewer mains of various sizes on various streets. Construction Wastewater
Collection Utilities Winter 2018 4,022,455 $
PG‐15000 Buckeye Creek Hydrology
Study
This project analyzed flooding conditions and recommended flood control structures and drainage and erosion control solutions for the creek located within Foothills Park.   Study Parks and Open Space Public Works Spring 2018 167,741 $
PE‐17004
CalTrain Corridor Video
Management System
Installation
This project replaced two existing gateway signs in the right‐of‐way for the California Avenue business district.  Construction Streets and
Sidewalks Public Works Spring   2018 1,550,000$
PF‐16003 Parking Lot Q Elevator
Modernization  This project modernized the existing elevator at Parking Lot Q. Construction Buildings and Facilities Public Works Fall 2017 170,608 $
PE‐13003 Parks, Trails, Open Space,
and Recreation Master Plan
This master plan provided guidance on the recreation and improvement needs for Palo Alto’s parks, trails, open space and recreational programs.   Study Parks and Open Space
Community
Services Fall  2017 627,057$
PE‐12003 Rinconada  Park Master Plan
This project developed a plan for short, medium and long range improvements to the regional park including the consideration of pathways, new restrooms and playgrounds, new landscaping, and revitalization of underutilized areas within the park.

Study Parks and Open
Space
Community
Services Fall 2017 541,355 $
PE‐13012 Structural Assessment of City
Bridges
The project developed an inventory of all City‐owned bridges and culvert structures, condition assessment, cost estimate for rehabilitation, and recommendation for future inspection frequencies, assessment and improvements.

Study Buildings and
Facilities Public Works Fall 2017 198,529 $
WC‐11000
Wastewater Collection
System Rehabilitation /
Augmentation Project 24
Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of various sizes, 779 sewer laterals, and 121 sewer manholes.

Construction Wastewater
Collection Utilities Fall 2017 3,119,806 $
WC‐13001
Wastewater Collection
System Rehabilitation /
Augmentation Project 26
Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of various sizes, 779 sewer laterals, and 121 sewer manholes.

Construction Wastewater
Collection Utilities Fall 2017 3,361,118 $
PG‐13003
Golf Reconfiguration and
Baylands Athletic Center
Improvements
This project completed the rehabilitation of the Palo Alto Municipal Golf Course, including  a new layout for the course, new prefabricated restroom, new water‐saving turf and irrigation system, and rebranded the course as the Baylands Golf Links.

Construction Parks and Open
Space Public Works Fall 2017 13,675,177 $
GS‐11000 Gas Main Replacement –
Project 21 This project combined with GWR 19B & GMR 20 and replaced ABS gas mains and services.   Construction Gas Utilities Winter 2017 2,364,937 $ June 2018 December 2017
10 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
WS‐11000 Water Main Replacement –
Project 25
This project provided installation of approximately 11,869 linear feet of new High Density Polyethylene (HDPE) water mains, 232 new HDPE water services, and 15 new fire hydrants within the City limits.

Construction Water Utilities Winter 2017 5,445,069 $
WS‐15004 Water  System Master Plan
The 2015 Water System Master Plan identified present capital improvements and replacement rates required to ensure optimal reliability levels of service to the existing distribution and transmission systems.

Study Water Utilities Spring 2017 500,000 $
WC‐10002
Wastewater Collection
System Rehabilitation /
Augmentation Project 23
Combined with Project 22 (WC‐09001).  This project replaced and/or rehabilitated approximately 33,497 linear feet of sanitary sewer mains of various sizes, 554 sewer laterals, and 102 sewer manholes.

Construction Wastewater
Collection Utilities Winter 2017 1,272,289 $
EL‐10009
Street Light System  Street
Light System Conversion
Project
This project converted HPS streetlights to LED and the conversion of approximately 4500 cobrahead streetlight fixtures.   Construction Electric Utilities Spring 2017 696,918 $ EL‐13006 Sand Hill / Quarry 12kV
InterTie  This project installed new wire to connect circuits QR‐24 and QR‐27 in the Sand Hill/Quarry area.  Construction Electric Utilities Winter 2017 208,648 $ EL‐15001 Electric Substation Battery
Replacement  This project replaced the batteries in all nine of the City's electric substations.  Construction Electric Utilities Winter 2017 400,000 $ PG‐13001
Stanford/Palo Alto Playing
Fields Soccer Turf
Replacement
This project replaced the synthetic turf at the Stanford/Palo Alto Playing Fields.  Construction Parks and Open Space
Community
Services Fall 2016 1,499,979 $
PG‐09003 Park Maintenance Shop
Remodel
This project renovated and remodeled the Parks maintenance shop for safety and efficienciency upgrades. Construction Parks and Open
Space
Community
Services Summer 2016 94,419 $
PE‐12017 City Hall First Floor
Renovations
This project installed new elevator control panels and replaced the gray‐painted panels inside the elevators. Construction Buildings and
Facilities Public Works Summer 2016 3,974,963 $
PE‐11012 Temporary  Main Library This project created a temporary main Library to be used while the new one was being constructed. Construction Buildings and
Facilities Public Works 156,254 $
PE‐15029 Baylands Nature Interpretive
Center Facility Improvement
The project replaced decking, railings, structural framing members, exterior wood flooring, and cabinetry, restroom reconfiguration, and provided Americans with Disabilities Act (ADA) improvements.

Construction Buildings and
Facilities Public Works Spring 2017 889,452 $
PE‐13008 Bowden  Park Improvements
This project improved the children’s playground and included park amenity upgrades such as new playground equipment, a new retaining wall, surfacing and pathway upgrades, planting restoration and irrigation renovations, and replaced of damaged wood benches and the playground perimeter fence.

Construction Parks and Open
Space
Community
Services Summer 2016 421,126 $
June 2017
11 List of Completed Projects
CIP # Project Name Project Description Project Type Fund Source Department Season Completed
Year
Completed
Total Project Budget
** CMR Date
PE‐13020 Byxbee  Park Trails  This project provided trail and site amenities over the remaining area of the landfill cap.   Construction Parks and Open Space Public Works Fall 2016 334,607 $
PE‐17002 City  Hall Floor 3 Remodel
This project improved the Utilities Department administrative offices on the third floor of City Hall. It included new carpet, wall reconfiguration, a kitchenette, cabinets, paint, soundproofing, office furniture, doors, and associated building systems.

Construction Buildings and
Facilities Public Works Spring 2017 440,000 $
PE‐14015
Lucie Stern Buildings
Mechanical and Electrical
Upgrades – Phase 1
This project replaced and upgraded the mechanical, electrical, and fire/life safety systems at Lucie Stern Children’s Theater, Lucie Stern Community Theater, and Lucie Stern Community Center.

Construction Buildings and
Facilities Public Works Summer 2016 3,247,248 $
PG‐12004 Sarah Wallis Park
Improvements
This project improved site amenities with new concrete pathways, replaced old furnishings, and upgraded landscape with drought tolerant species.  Construction Parks and Open Space
Community
Services Winter 2017 65,000 $
AP‐16003 Airport  Perimeter Fence
This project replaced the perimeter fencing and gates surrounding the Palo Alto Airport boundaries to prevent unauthorized access to the airport runway in accordance with Federal and State standards.

Construction Airport Public  Works Spring 2017 2,003,540 $ SD‐11101
Channing Avenue/Lincoln
Avenue Storm Drain
Improvements
This project installed of 5,800 linear feet of 36‐inch to 60‐inch diameter storm drain along Channing and Lincoln Avenues over three project phases to increase drainage system capacity.   Construction Storm  Drain Public  Works Winter 2016 7,676,275 $ GS‐14004 Gas Distribution System
Model
This project included the development, model installation, testing, documentation, and staff training of a natural gas distribution system model.   Study Gas Utilities Summer 2016 149,500 $ AC‐14000 Art Center Auditorium Audio,
Visual and Furnishings
This project replaced outdated audio visual equipment and furnishings following the auditorium’s use as a temporary library.   Construction Buildings and Facilities
Community
Services Winter 2016 150,000 $
PF‐15000 Rinconada  Pool Locker Room This project renovated the Rinconada Pool locker room including the changing area, restrooms, and showers in the women's and men's locker rooms.   Construction Buildings and Facilities Public Works Winter 2016 464,433 $
PE‐13016 El  Camino Park Restoration
This project installed new athletic fields, synthetic turf, field lighting, fencing, a new restroom, scorekeeper booth and storage buildings, an expanded parking lot, new bike and pedestrian pathways, landscaping, benches, and other amenities.

Construction Parks and Open
Space
Community
Services Fall 2015 5,611,122 $
434,107,677$              Notes: ** Final Project Actuals may be different from Total Project Budget amounts Grand Total December 2016