13 PROFESSIONAL SERVICES TASK ORDER
TASK ORDER FY25-4.31 Junior Museum and Zoo
Consultant shall perform the Services detailed below in accordance with all the terms and conditions of the Agreement referenced in Item 1A below. All exhibits referenced in Item 8 below are incorporated into this Task Order by this reference. The Consultant shall furnish the necessary facilities, professional, technical and supporting personnel required by this Task Order as described below.

CONTRACT NO. C21179340A
OR PURCHASE ORDER REQUISITION NO. (AS APPLICABLE)
1A. MASTER AGREEMENT NO. (MAY BE SAME AS CONTRACT / P.O. NO. ABOVE): C21179340A 1B. TASK ORDER NO.: FY25-4.31

2. CONSULTANT NAME: Baker Tilly Advisory Group, LP

3. PERIOD OF PERFORMANCE: START: January 1, 2025 COMPLETION: June 30, 2025

4. TOTAL TASK ORDER PRICE: $89,900

BALANCE REMAINING IN MASTER AGREEMENT/CONTRACT TBD

5. BUDGET CODE_______________ COST CENTER________________ COST ELEMENT______________ WBS/CIP__________ PHASE__________

6. CITY PROJECT MANAGER’S NAME & DEPARTMENT:

Lydia Kou, Chair of the City Council’s Policy and Services Committee

7. DESCRIPTION OF SCOPE OF SERVICES (Attachment A)
MUST INCLUDE:
 SERVICES AND DELIVERABLES TO BE PROVIDED
 SCHEDULE OF PERFORMANCE
 MAXIMUM COMPENSATION AMOUNT AND RATE SCHEDULE (as applicable)  REIMBURSABLE EXPENSES, if any (with “not to exceed” amount)

8. ATTACHMENTS: A: Task Order Scope of Services B (if any): N/A I hereby authorize the performance of the work
described in this Task Order.

APPROVED:

CITY OF PALO ALTO
BY:____________________________________
Name __________________________________
Title___________________________________
Date ___________________________________
I hereby acknowledge receipt and acceptance of
this Task Order and warrant that I have authority
to sign on behalf of Consultant.

APPROVED:

COMPANY NAME: Baker Tilly Advisory Group,
LP
BY:____________________________________
Name __________________________________
Title___________________________________
Date ___________________________________
Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 Kate Murdock
Manager/ City Auditor
12/23/2024
Council Member
Council Member Lydia Kou
12/25/2024
April 30, 2026
14 Attachment A

DESCRIPTION OF SCOPE OF SERVICES
Introduction
Attachment A, the Description of Scope of Services, contains the following four (4) elements:
 Services and Deliverables To Be Provided
 Schedule of Performance
 Maximum Compensation Amount and Rate Schedule (As Applicable)  Reimbursable Expenses, if any (With “Not To Exceed” Amount) Services & Deliverables
Baker Tilly’s approach to conducting an internal audit of the Junior Museum and Zoo involves three (3) primary steps:
 Step 1: Audit Planning
 Step 2: Fieldwork and Testing
 Step 3: Reporting
Step 1 – Audit Planning
This step consists of the tasks performed to adequately plan the work necessary to address the overall audit objective and to solidify mutual understanding of the audit scope, objectives, audit process, and timing between stakeholders and auditors. Tasks include:
 Gather information to understand the environment under review o Understand the environment under assessment
o Assess the City code, regulations, and other standards and expectations o Assess prior audit results, as applicable
o Assess additional documentation and conduct interviews as necessary  Assess the audit risk
 Prepare an audit planning memo and audit program
o Refine audit objectives and scope
o Identify the audit procedures to be performed and the evidence to be obtained and examined  Announce the initiation of the audit and kick-off meeting with key stakeholders o Discuss audit objectives, scope, audit process, timing, resources, and expectations o Discuss documentation and interview requests for the audit Step 2 – Fieldwork and Testing
The step involves executing the procedures in the audit program to gather information, interview individuals, and analyze the data and information to obtain sufficient evidence to address the audit objectives The preliminary audit objective is to determine if the City’s Junior Museum and Zoo is operating effectively and efficiently to fulfill the program’s mission. Procedures include, but are not limited to:
 Interviewing the appropriate individuals to gain an understanding of the organizational structure, processes, and controls related to the Junior Museum and Zoo  Analyze policies and procedures as well as the program mission and objectives to identify the criteria to be used for evaluation of control design and effectiveness  Compare processes and controls against best practices Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 15 Step 3 – Reporting
In Step 3, the project team will perform tasks necessary to finalize audit working papers, prepare and review a draft report with stakeholders, and submit a final report for management response. Tasks include:
 Developing findings, conclusions, and recommendations based on the supporting evidence gathered
 Validating findings with appropriate individuals and discuss the root cause of the identified findings
 Complete supervisory review of working papers and a draft audit report  Distribute a draft audit report and conduct a closing meeting with key stakeholders o Discuss the audit results, findings, conclusions, and recommendations o Discuss management responses
 Obtain written management responses and finalize a report  Review report with members of City Council and/or the appropriate Council Committee Deliverables:

The following deliverables will be prepared as part of this engagement:
 Audit Report
 Policy & Services Committee Audit Report Presentation Schedule of Performance
Anticipated Start Date: January 1, 2025
Anticipated End Date: June 30, 2025
Maximum Compensation Amount and Rate Schedule
The not-to-exceed maximum, inclusive of reimbursable expenses (as summarized below) for this Task is $89,900.

The not-to-exceed budget is based on an estimate of 500 total project hours, of which a minimum of 40 are estimated to be completed by the City Auditor.

Reimbursable Expenses
We plan to complete all work remote including all interviews and documentation review. However, during the planning and fieldwork phases of this audit, the City and Baker Tilly may mutually determine it will be beneficial to perform a portion of the work on-site. Given this possibility, Baker Tilly could incur expenses for this Task.

The not-to-exceed maximum for reimbursable expenses for this Task is $6,500.

The following summarizes anticipated reimbursable expenses:
 Round-trip Airfare – $2,000 (1 round trip flight x 2 auditors)  Ground transportation – $800 (car rental or Uber/taxi)  Hotel accommodation – $3,000 (2 rooms x 4 nights)
 Food & Incidentals – $2,100
Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 19 PROFESSIONAL SERVICES TASK ORDER
TASK ORDER FY25-4.33 Public Safety Staffing
Consultant shall perform the Services detailed below in accordance with all the terms and conditions of the Agreement referenced in Item 1A below. All exhibits referenced in Item 8 below are incorporated into this Task Order by this reference. The Consultant shall furnish the necessary facilities, professional, technical and supporting personnel required by this Task Order as described below.

CONTRACT NO. C21179340A
OR PURCHASE ORDER REQUISITION NO. (AS APPLICABLE)
1A. MASTER AGREEMENT NO. (MAY BE SAME AS CONTRACT / P.O. NO. ABOVE): C21179340A 1B. TASK ORDER NO.: FY25-4.33

2. CONSULTANT NAME: Baker Tilly Advisory Group, LP

3. PERIOD OF PERFORMANCE: START: January 1, 2025 COMPLETION: June 30, 2025

4. TOTAL TASK ORDER PRICE: $95,670

BALANCE REMAINING IN MASTER AGREEMENT/CONTRACT TBD

5. BUDGET CODE_______________ COST CENTER________________ COST ELEMENT______________ WBS/CIP__________ PHASE__________

6. CITY PROJECT MANAGER’S NAME & DEPARTMENT:

Lydia Kou, Chair of the City Council’s Policy and Services Committee

7. DESCRIPTION OF SCOPE OF SERVICES (Attachment A)
MUST INCLUDE:
 SERVICES AND DELIVERABLES TO BE PROVIDED
 SCHEDULE OF PERFORMANCE
 MAXIMUM COMPENSATION AMOUNT AND RATE SCHEDULE (as applicable)  REIMBURSABLE EXPENSES, if any (with “not to exceed” amount)

8. ATTACHMENTS: A: Task Order Scope of Services B (if any): N/A I hereby authorize the performance of the work
described in this Task Order.

APPROVED:

CITY OF PALO ALTO
BY:____________________________________
Name __________________________________
Title___________________________________
Date ___________________________________
I hereby acknowledge receipt and acceptance of
this Task Order and warrant that I have authority
to sign on behalf of Consultant.

APPROVED:

COMPANY NAME: Baker Tilly Advisory Group,
LP
BY:____________________________________
Name __________________________________
Title___________________________________
Date ___________________________________
Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 Manager/ City Auditor
Kate Murdock
12/23/2024
Council Member
Council Member Lydia Kou
12/25/2024
April 30, 2026
20 Attachment A

DESCRIPTION OF SCOPE OF SERVICES
Introduction
Attachment A, the Description of Scope of Services, contains the following four (4) elements:
 Services and Deliverables To Be Provided
 Schedule of Performance
 Maximum Compensation Amount and Rate Schedule (As Applicable)  Reimbursable Expenses, if any (With “Not To Exceed” Amount) Services & Deliverables
Baker Tilly’s approach to conducting an internal audit of Public Safety Staffing including Overtime three (3) primary steps:
 Step 1: Audit Planning
 Step 2: Fieldwork and Testing
 Step 3: Reporting
Step 1 – Audit Planning
This step consists of the tasks performed to adequately plan the work necessary to address the overall audit objective and to solidify mutual understanding of the audit scope, objectives, audit process, and timing between stakeholders and auditors. Tasks include:
 Gather information to understand the environment under review o Understand the environment under assessment
o Assess the City code, regulations, and other standards and expectations o Assess prior audit results, as applicable
o Assess additional documentation and conduct interviews as necessary  Assess the audit risk
 Prepare an audit planning memo and audit program
o Refine audit objectives and scope
o Identify the audit procedures to be performed and the evidence to be obtained and examined  Announce the initiation of the audit and kick-off meeting with key stakeholders o Discuss audit objectives, scope, audit process, timing, resources, and expectations o Discuss documentation and interview requests for the audit Step 2 – Fieldwork and Testing
The step involves executing the procedures in the audit program to gather information, interview individuals, and analyze the data and information to obtain sufficient evidence to address the audit objectives The preliminary audit objective is to determine if the Public Safety Departments (Fire and Police) are effectively and efficiently staffed including use of overtime:
 Interviewing the appropriate individuals to gain an understanding of the organizational structures, processes, and controls related to staffing and use of overtime including plans and systems used  Analyze policies and procedures related to Public Safety staffing to identify the criteria to be used for evaluation of control design and effectiveness
Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 21  Analyze Public Safety performance metrics to determine if staffing levels enable desired performance outcomes
 Compare performance processes and controls against best practices Step 3 – Reporting
In Step 3, the project team will perform tasks necessary to finalize audit working papers, prepare and review a draft report with stakeholders, and submit a final report for management response. Tasks include:
 Developing findings, conclusions, and recommendations based on the supporting evidence gathered
 Validating findings with appropriate individuals and discuss the root cause of the identified findings
 Complete supervisory review of working papers and a draft audit report  Distribute a draft audit report and conduct a closing meeting with key stakeholders o Discuss the audit results, findings, conclusions, and recommendations o Discuss management responses
 Obtain written management responses and finalize a report  Review report with members of City Council and/or the appropriate Council Committee Deliverables:

The following deliverables will be prepared as part of this engagement:
 Audit Report
 Policy & Services Committee Audit Report Presentation Schedule of Performance
Anticipated Start Date: January 1, 2025
Anticipated End Date: June 30, 2025
Maximum Compensation Amount and Rate Schedule
The not-to-exceed maximum, inclusive of reimbursable expenses (as summarized below) for this Task is $95,670.

The not-to-exceed budget is based on an estimate of 500 total project hours, of which a minimum of 50 are estimated to be completed by the City Auditor.

Reimbursable Expenses
We plan to complete all work remote including all interviews and documentation review. However, during the planning and fieldwork phases of this audit, the City and Baker Tilly may mutually determine it will be beneficial to perform a portion of the work on-site. Given this possibility, Baker Tilly could incur expenses for this Task.

The not-to-exceed maximum for reimbursable expenses for this Task is $6,500.

The following summarizes anticipated reimbursable expenses:
• Round-trip Airfare – $2,000 (1 round trip flight x 2 auditors) • Ground transportation – $800 (car rental or Uber/taxi) • Hotel accommodation – $3,000 (2 rooms x 4 nights)
• Food & Incidentals – $2,100
Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 22 PROFESSIONAL SERVICES TASK ORDER
TASK ORDER FY25-4.34 Follow-Up Audit Activities
Consultant shall perform the Services detailed below in accordance with all the terms and conditions of the Agreement referenced in Item 1A below. All exhibits referenced in Item 8 below are incorporated into this Task Order by this reference. The Consultant shall furnish the necessary facilities, professional, technical and supporting personnel required by this Task Order as described below.

CONTRACT NO. C21179340A
OR PURCHASE ORDER REQUISITION NO. (AS APPLICABLE)
1A. MASTER AGREEMENT NO. (MAY BE SAME AS CONTRACT / P.O. NO. ABOVE): C21179340A 1B. TASK ORDER NO.: FY25-4.34

2. CONSULTANT NAME: Baker Tilly Advisory Group, LP

3. PERIOD OF PERFORMANCE: START: January 1, 2025 COMPLETION: June 30, 2025

4. TOTAL TASK ORDER PRICE: $59,390

BALANCE REMAINING IN MASTER AGREEMENT/CONTRACT TBD

5. BUDGET CODE_______________ COST CENTER________________ COST ELEMENT______________ WBS/CIP__________ PHASE__________

6. CITY PROJECT MANAGER’S NAME & DEPARTMENT:

Lydia Kou, Chair of the City Council’s Policy and Services Committee

7. DESCRIPTION OF SCOPE OF SERVICES (Attachment A)
MUST INCLUDE:
 SERVICES AND DELIVERABLES TO BE PROVIDED
 SCHEDULE OF PERFORMANCE
 MAXIMUM COMPENSATION AMOUNT AND RATE SCHEDULE (as applicable)  REIMBURSABLE EXPENSES, if any (with “not to exceed” amount)

8. ATTACHMENTS: A: Task Order Scope of Services B (if any): N/A I hereby authorize the performance of the work
described in this Task Order.

APPROVED:

CITY OF PALO ALTO
BY:____________________________________
Name __________________________________
Title___________________________________
Date ___________________________________
I hereby acknowledge receipt and acceptance of
this Task Order and warrant that I have authority
to sign on behalf of Consultant.

APPROVED:

COMPANY NAME: Baker Tilly Advisory Group,
LP
BY:____________________________________
Name __________________________________
Title___________________________________
Date ___________________________________
Docusign Envelope ID: F60E09CC-400F-404E-8132-93318BE5ADE6 Kate Murdock
Manager/ City Auditor
12/23/2024
Council Member
12/25/2024
Council Member Lydia Kou
April 30, 2026
23 Attachment A

DESCRIPTION OF SCOPE OF SERVICES
Introduction
Attachment A, the Description of Scope of Services, contains the following four (4) elements:
 Services and Deliverables To Be Provided
 Schedule of Performance
 Maximum Compensation Amount and Rate Schedule (As Applicable)  Reimbursable Expenses, if any (With “Not To Exceed” Amount) Services & Deliverables
Baker Tilly will provide the following services in conducting Follow-Up Audit Activities::
 Track and monitor progress on all audit recommendations  Obtain sufficient evidence to support conclusions regarding the status of audit recommendations  Annually report on the status of recommendations
Deliverables:

The following deliverables will be prepared as part of this engagement:
 Annual Status of Audit Recommendations Report
 Policy & Services Committee Report Presentation
Schedule of Performance
Anticipated Start Date: January 1, 2025
Anticipated End Date: June 30, 2025
Maximum Compensation Amount and Rate Schedule
The not-to-exceed maximum, inclusive of reimbursable expenses (as summarized below) for this Task is $59,390.

The not-to-exceed budget is based on an estimate of 500 total project hours, of which a minimum of 40 are estimated to be completed by the City Auditor.