Item No. 2. Page 1 of 1
9 1
3 0
City Council
Supplemental Report
From: Ed Shikada, City Manager
Meeting Date: January 12, 2026
Item Number: 2
Report #:2601-5804
TITLE
Supplemental Report - Review and Discuss 2025 Q4 Council Priorities & Objectives and format of the 2026 City Council Annual Retreat. CEQA Status – Not a project
ANALYSIS
This supplemental report adds an update that was inadvertently left out of Attachment B of the report.
The printed report for January 12, 2026, Item #2 did not include an update on Objective 3.2.1 (Partner with Santa Clara County Housing Authority to achieve construction timeline milestones for the Palo Alto Homekey project (which will provide transitional housing and services for unhoused residents)).
Objective 3.2.1 - Project Homekey
Status: Behind
December 2025 Update
Achievements:
Completion of all roofing and solar installation, as well as installation of all fencing for the Homekey project.
Roadblocks:
While there continue to be payment disputes (e.g., between contractors), there are no current critical path roadblocks.
Next Steps:
Continue construction of the elevated exterior walkway and support beams, maintaining progress to ensure overall completion remains on track for spring 2026.
APPROVED BY:
Ed Shikada, City Manager