ATTACHMENT A
Semiannual Update on the Status of Capital Improvement Program Projects
Capital Improvement Fund CIP Projects
• Buildings and Facilities Projects
• Parks and Open Space Projects
• Streets and Sidewalks Projects
• Traffic and Transportation Projects
Enterprise Fund CIP Projects
• Airport Projects
• Electric Projects
• Fiber Opcs Projects
• Gas Projects
• Stormwater Management Projects
• Wastewater Collection Projects
• Wastewater Treatment Projects
• Water Projects
Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 1 of 11
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 5 13 8 2 28
Recurring Projects 13
ONE-TIME PROJECTS
Animal Shelter RenovaƟon (PE-19002)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $$2,950,078 $5,915,405 Public Works Design Winter 2028
Project Status: A new five-year agreement with Pets in Need (PIN ) was approved by Council in March 2024.
Discussions with PIN and City sta ff regarding capital projects started in late 2024, with a scope of work finalized with PIN in May 2025. Sta ff are working on the RFP package to bring a consultant on board. The tenta Ɵve schedule shows that the design should be complete by fall 2027.
Children’s Theater Facility Upgrade and Repair (AC-28002) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $3,874 $137,628 Community Services Pre-Design Fall 2026 Project Status: This project will upgrade and repair the Child ren’s Theatre Facility, including backstage work and storage areas, classrooms, performance stages, restrooms and public spaces. Phase 1 will focus on procuring a consultant to conduct a facility needs assessment and provide cost esƟmates.
City Hall Space Planning (PE-19000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $85,525 $681,710 Public Works Design Fall 2026
Project Status: This project involves space planning to determine future workgroup space needs and programming for the City Hall o ffice building focused on the Police Department areas that will be vacated once the new Public Safety Building is complete and the City Hall O ffice Tower. The City has retained CJW Architects to conduct a space needs assessment for the vacated Police Department and the City Hall O ffice Tower, with a focus on post-pandemic, hybrid work. Data collec Ɵon and analysis for the Police Department space is currently underway, and a ques Ɵonnaire addressing post-pandemic, hybrid work needs for the City Hall Office Tower is in development.
Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 2 of 11
City Radio Replacement Program (PD-25000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $0 $2,739,500 Police Department Design Summer 2029
Project Status: Two-way commercial radios are used by many Departments in the City of Palo Alto. The City of Palo Alto operates approximately 772 radios across nine workgroups, including Police, Fire, O ffice of Emergency Services (OES), Community Services Park Rangers, Public Works, U ƟliƟes, Development Center, and Informa Ɵon Technology. This project will be used to replace the original digital radios.
Civic Center Electrical Upgrade & EV Charger InstallaƟon (PE-17010) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $759,159 $2,151,761 Public Works Design Winter 2027
Project Status: This project has installed EV chargers in exis Ɵng downtown garages and will replace the aging Civic Center electrical switchgear and motor control centers. EV charger construc Ɵon at the Civic Center, Bryant Street garage and Webster Street garage was completed in December 2021. A contract was awarded in June 2021 for the design of the Civic Center switchgear replacement and is currently at the 90 percent design stage. Lead Ɵmes on switch gear are now taking eighteen months, so the project comple Ɵon date has been extended. The structural analysis design of the switchgear area and its permit set is complete Recent plan check comments required a redesign to accommodate fire code updates and provided some cost savings benefit.
Civic Center Fire Life Safety Upgrade (PE-18016)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,046,227 $1,373,192 Public Works Construc Ɵon Winter 2026 Project Status: This project will assess, update, and replace the Civic Center fire alarm system and the Emergency Responder Radio CommunicaƟon System (ERRCS). The fire life safety system is approaching the end of its useful life.
The fire alarm panel and associated equipment need an upgrade to meet current code requirements. The award of a design-build contract was approved by Council in June 2021. Construc Ɵon is complete. The fire permit will be finalized as soon as the City receives as-built drawings from the contractor. The ERRCS study will be conducted upon the comple Ɵon of the planning and design for 275 Forest Avenue. Modi ficaƟons to the fire alarm system and fire suppression systems will also need re-evaluaƟon.
Civic Center Waterproofing Study and Repairs (PE-15020)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $798,592 $1,782,622 Public Works Design TBD
Project Status: This project includes performing a structural condi Ɵon assessment of the Civic Center. In 2016, RDH Building Science, Inc. determined that the expansion join t on the plaza could be repaired and that replacing the Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 3 of 11
waterproof coaƟngs on the inside of the plaza perimeter planter boxes was needed. Repair of the waterproofing joint in front of City Hall was completed in winter 2023. Further study of the water intrusion into the garage was performed by a consultant in summer 2024. This project has been placed on hold.
Cubberley Gym HVAC Replacement (CB-24000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $ 826,113 Public Works Pre-Design Spring 2026
The exisƟng heaƟng system in Cubberley Gyms A & B is original to the building, which was constructed in the mid- 1950s. The system is currently not func Ɵoning because mul Ɵple leaks have developed in the steel hot water piping, which is in the walls and under the floor. These leaks contributed (in addi Ɵon to a domes Ɵc water main supply leak) to significant water damage in the walls, floors, and crawl spaces of the gyms. Asbestos and mold were remediated from the under-floor crawl space. All the old hea Ɵng units and piping were removed from the ceilings in both gyms.
The next step is to hire a consultant to create design drawings for a new hea Ɵng system. This project has been put on hold due to the City’s pending purchase of the remaining Cubberley buildings and the subsequent rebuilding of a new Cubberley Community Center.
Fire StaƟon 4 Replacement (PE-18004)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $3,284,233 $ 19,972,811 Public Works Construc Ɵon Summer 2026 Project Status: This project will replace Fire StaƟon #4 at the corner of Middlefield Road and East Meadow Drive. The temporary Fire StaƟon #4 at the Cubberley Community Center is complete, and construc Ɵon of the new fire staƟon is currently underway. Beals Mar Ɵn, the project’s general contractor, has completed the deconstruc Ɵon phase and is preparing to begin underground u ƟliƟes and founda Ɵon work. Construc Ɵon is scheduled for comple Ɵon in summer 2026.
Fire Training Facility Replacement (FD-24000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $487 $50,458 Public Works Pre-Design Fall 2026
Project Status: This project will iden Ɵfy an appropriate site and construct a new fire training facility in Palo Alto. This will be the first City-owned and City-maintained permanent fire training facility, and it will allow training to be conducted within City limits and therefore reduce the down Ɵme associated with the need for sta ff t o t r a v e l f o r training and when responding to calls. Progress has not been made on this project due to staffing constraints.
Homekey FaciliƟes (PE-24005)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $2,256,042 $4,500,000 Public Works Construc Ɵon Spring 2026 Project Status: This project involves relocaƟng the City of Palo Alto (City) GreenWaste facility from its current site on Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 4 of 11
one porƟon of 1237 San Antonio Road to the rear por Ɵon of the same site as a resu lt of adding the Homekey Palo Alto interim housing shelter. Homekey Palo Alto will be operated by LifeMoves who will provide intensive, customized case management for clients including counseling, employment and housing search services with the goal of paving a dignified path to self-su fficiency. The project is nearing comple Ɵon, with major construc Ɵon milestones achieved.
The relocaƟon of the GreenWaste facility has been completed, an d all modular units at the Homekey site have been installed. Final connec Ɵons for the elevator, stairs and decking are currently underway. The plumbing, mechanical, electrical, and fire life safety are in the final stages of connecƟon, tesƟng, and commissioning. Interior finishes such as painƟng, flooring, and fixture installa Ɵon are also being completed within the modular units and the community building. Final site improvements, including landscaping and bioreten Ɵon areas, will be completed as construc Ɵon wraps up. Following final inspecƟons and closeout acƟviƟes, the project is expected to be complete by spring 2026.
JMZ RenovaƟon (AC-18001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $4,366,001 $4,927,730 Community Services Construc Ɵon Summer 2026 Project Status: This project funds remedia Ɵons and equipment purchases for the Junior Museum. In FY 2025 purchases of new equipment included washing machines and dryers for the educa Ɵon hub and zoo, a gate for guest services to protect delivered packages and lunches for school field trips, and new housing for rep Ɵles. A por Ɵon of the project was extended through FY 2026 to complete the list of remedia Ɵons and equipment not purchased in FY 2025 due to sta ffing shortages. The projects for FY 2026 include shade structures for the Fossil Dig exhibit, net replacement in the treehouse, and venƟlaƟon improvements. CompleƟon is expected in summer 2026.
Library Automated Material Handling (LB-21000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $480,829 $2,127,496 Public Works Construc Ɵon Fall 2028 Project Status: This project includes the design and construc Ɵon of three new Automated Material Handling (AMH) Systems for the Children’s, Mitchell Park and Rinconada Libraries. AMH systems e fficiently sort returned library materials based on the Radio Frequency IdenƟficaƟon Devices (RFID) on the materials. ConstrucƟon for the Children’s Library was completed in August 2025. The design and construc Ɵon of the AMH systems for Mitchell Park and Rinconada Libraries are scheduled for FY 2028 and FY 2029.
Library Furniture Replacements (LB-26001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $395,000 Library Design Summer 2029
Project Status: This project will replace broken and well-worn furniture in the public spaces of all five library branches. The current furniture is between ten and eighteen years old.
Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 5 of 11
Lucie Stern Community Theatre Mechanical Equipment Replacement (PE-24002) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $60,772 $2,450,496 Public Works Pre-Design Winter 2027
Project Status: This project will upgrade and replace the Hea Ɵng VenƟlaƟon and Air Condi Ɵoning (HVAC) system at the Lucie Stern Community Theatre. As a first step, the project will include a detailed feasibility study to determine if natural gas-powered equipment in the facility can be electri fied per the recommended results of the City-wide electrificaƟon assessment. An RFP for design services is currently being compiled.
Lucie Stern Community Theatre Fire Curtain (AC-24001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $220,205 Community Services Pre-Design Winter 2027
Project Status: This project will replace the fire curtain and its associated rigging at the Lucie Stern Community Theatre. The fire curtain work will be coordinated with the Theatrical and House LighƟng System Replacement Project (PE-24003).
Lucie Stern Community Theatre Stage Rigging System Refurbishment (AC-24000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $116,113 Community Services Completed Fall 2025
Project Status: This project refurbished the most heavily used co mponents of the stage rigging system at the Lucie Stern Community Theatre. The construc Ɵon contract was approved by Council on June 3, 2024. Work was scheduled to start in July 2024, but parts needed for the installa Ɵon were delayed. Work was completed in July 2025 with addiƟonal follow up work in October 2025 to complete the project.
Lucie Stern Community Theatre Theatrical and House LighƟng System Replacement (PE-24003) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $41,347 $333,210 Public Works Design Winter 2027
Project Status: This project will upgrade and replace ligh Ɵng systems at the Lucie Stern Community Theatre for stage work areas, the performance stage, and audience areas. The building documents for the new system are complete, and an RFP for a Design Build En Ɵty will be submi Ʃed for bidding. The Ɵming of this project will coincide with the Community Theatre Mechanical Equipmen t Replacement (PE-24002). A design build method of project delivery has been approved.
Mitchell Park Library Repair (PE-24006)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $61,386 $624,822 Public Works Design Fall 2026
Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 6 of 11
Project Status: This project will repair the damage caused by a ve hicular accident in January 2023. A vehicle ran into the north wall of the Mitchell Park Library near the center of the building. The car impacted an area of the stone cladding on cold-formed steel studs, causing the cladding to fall from the wall and the wall to bulge into the building’s interior. Architectural and structural surveys and reports were completed. The stone cladding wall will require replacement, but the structural steel frame was not damaged. The project was approved by the Building Department. The project received bids in March 2026. ConstrucƟon is expected to start by June 2026.
Mitchell Park Community Center Audio Visual Equipment (AC-26000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $340,000 Community Services Design Fall 2025
Project Status: This project will replace the built-in audio-visual equipment at the Mitchell Park Community Center because the equipment is either nonfuncƟoning or funcƟoning at a limited capacity.
Municipal Service Center LighƟng, Mechanical, and Electrical Improvements (PF-16006) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,223,795 $8,221,044 Public Works Design Winter 2027
Project Status: This project replaces original mechanical, electrical, and ligh Ɵng systems installed in 1966. It also includes design and construc Ɵon for o ffice renovaƟons for the Zero Waste group. The electrical design is complete, and the planning permit was approved in spring 2024. However, addi Ɵonal stakeholder review is needed to ensure the scope aligns with anƟcipated future capacity requirements.
New Downtown Parking Garage (PE-15007)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,669,257 $17,286,151 Public Works Design Fall 2027
Project Status: In December 2021, Council directed staff to look at the feasibility of partnering with a private en Ɵty to develop new parking using downtown in-lieu parking fees in conjuncƟon with housing or other uses, including the use of City surface lots or privately held parcels. A Request for Informa Ɵon was issued in December 2022 and sta ff reviewed proposals and held interviews in May 2023. Council gave direc Ɵons to sta ff in December 2023 to advance the project in conjunc Ɵon with advancement of a ffordable housing in the Downtown area. In December 2024, the City executed a contract with Watry Design, Inc. to provide for design, environmental review, and construc Ɵon administraƟon services for the New Downtown Parking Garage. Concept designs were presented to Council in April 2025. The Architectural Review Board reviewed the conceptual designs in December 2025.
New Public Safety Building (PE-15001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $122,812,614 $ 126,700,000 Public Works Completed Summer 2025 Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 7 of 11
Project Status : This project built a new, modern Public Safety Building (PSB) to meet current essential services standards and the future needs of the public safety depart ments. The PSB and new garage in the California Avenue business district are now an integrated project and bo th are part of the 2014 Council Infrastructure Plan.
Construction on the PSB started in March 2021 and will cont inue into spring 2025. The project obtained temporary certificate of occupancy at the end of May 2025. The first phase of staff moved into th e PSB in September 2025. The City held a grand opening ceremony in November 2025. Phase 2 of the PSB move-in is being finalized.
PAAC Auditorium Audio Visual Equipment and Facility Public Address System (AC-26001) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $191,000 Community Services Design Fall 2026
Project Status: This project will update the current audio-visual equipment in the Palo Alto Art Center auditorium, making it more func Ɵonal for facility rentals and City events. In addi Ɵon, the project includes funding for new chairs and a facility-wide Public Announcement System for co mmunity safety. The Art Center is currently coordina Ɵng the purchasing of replacement chairs for the space and mee Ɵng with vendors to secure es Ɵmates for the audio visual component of the project.
Palo Alto Art Center Ceramics Equipment (AC-28003)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $74,039 $170,879 Community Services Construc Ɵon Winter 2027 Project Status: This project renews and replaces ceramics program equipment, upgrades electrical infrastructure, and waterproofs outdoor kiln sheds. The majority of the Art Center’s exis Ɵng ceramics equipment was obtained during the renovaƟon of the Art Center in 2011 and 2012. These pieces of equipment show signs of aging, necessita Ɵng facility updates. The enƟre project has been completed, apart from the purchase of the gas kiln, which is currently in the bid process. The gas kiln’s anƟcipated arrival and installaƟon is in winter 2027.
Performing Arts Venues Seat Replacement (AC-18000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,215,428 $1,341,406 Public Works Construc Ɵon Winter 2026 Project Status: This project will replace all the seats in the Community and Children’s Theatres. Sta ff hired a consultant to design the seat replacements and ADA upgrades for the Children’s Theatre por Ɵon of the project. The Children’s Theatre seats replacement was completed in November 2022. A contract for the design of the Community Theatre was issued in June 2023. Council approved the construc Ɵon contract on April 22, 2024, and the ADA upgrades along with the installaƟon of auditorium seaƟng were completed in spring 2025. PainƟng of the auditorium has been completed. Ramp modificaƟons and conduit work are expected to be completed in winter 2026.
Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 8 of 11
Rinconada Pool Family Changing Room (PE-24004)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $88,395 $1,406,158 Public Works Design Fall 2027
Project Status: The project will construct a gender-neutral restroom and family changing facility that is compliant with the Americans with Disabili Ɵes Act (ADA) at the Rinconada Pool. The facility will include two separate rooms, each consis Ɵng of a toilet, sink, shower, and child/adult changing sta Ɵon. The facility will provide community members who have special needs and individuals who require privacy an accessible space for changing and personal hygiene. Design of the family changing rooms started in December 2024. However, due to addiƟons to project scope, staff started coordinaƟng with the consultant on revising the plans scheduled for January 2026.
Roth Building RehabilitaƟon Phase 1 (PF-23001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $11,032,176 $11,438,449 Public Works Construc Ɵon Summer 2025 Project Status: This project implements Phase I of the rehabilitaƟon and build-out of the Roth Building facility. Phase I will make the building suitable for occupancy, also known as a “warm shell. Phase II of the rehabilita Ɵon includes the interior build-out of the museum and exhibits, readying th e facility to welcome visitors, and will be funded by the Palo Alto History Museum (PAHM). A Tenant Work LeƩer was approved by Council in April 2023, and construc Ɵon is underway including underground u ƟliƟes, roof, demoli Ɵon, and abatement. Phase I of this project will be substanƟally completed in February 2025. The project was accepted as fully complete effecƟve June 12, 2025. Further meeƟngs are being held for comple Ɵon of construc Ɵon for the City archives’ loca Ɵon and ac ƟvaƟon of community spaces, i.e. consis Ɵng of a community room, boardroom, archives room, educa Ɵon resource room, and the park restroom. Access to these rooms as well as janitorial se rvices, maintenance and techno logy support are among the areas being planned and will be coordinated with the museum over the coming months.
RECURRING PROJECTS
Americans With DisabiliƟes Act Compliance (PF-93009)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $450,000 Public Works N/A Recurring
Project Status: This project provides accessibility upgrades to City faciliƟes and equipment. It includes conƟnued funding for improvements such as path of travel, restrooms, drinking fountains, and counters. An updated ADA Transi Ɵon Plan was adopted by Council in June 2021. Sta ff is waiƟng to solicit new so Ōware that will allow sta ff to idenƟfy and log new barriers, track grievances from the public, and update the ADA TransiƟon Plan Report.
Building Systems Improvements (PF-01003)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 9 of 11
$373,731 $1,052,725 Public Works N/A Recurring
Project Status: This project provides electrical, mechanical, plumbing, structural, and security upgrades for City facili Ɵes.
The permit process for Building and Fire has been completed for the UCC Emergency Generator Replacement project. An IFB for this project was put out for public bid, and a contractor has been selected. The construc Ɵon contract was approved by City Council. The contractor has ordered the equipment, and construc Ɵon is scheduled to start in fall 2026 because of the long lead Ɵme. Fire alarm systems were replaced at Lot R and Lot S/L.
California Avenue Parking District Parking Improvements (PF-25000) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $100,000 Public Works N/A Recurring
Project Status: This project will implement parking improvements in the California Avenue parking district such as parking lot resurfacing, striping and signing; parking structure pain Ɵng or staining; electrical system upgrades needed to support improved lighƟng security, parking, fountains and/or other systems; and replacement or rehabilitaƟon of parking lot signs.
Charging StaƟons Repair and Maintenance (PF-26001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $100,000 Public Works N/A Recurring
Project Status: This project implements the ongoing maintenance and replacement of eighty-nine public-use charging staƟons for electric vehicles (EVs) throughout the City. Three ChargePoint chargers were replaced in the 1 st half of FY 2026.
City Facility Parking Lot Maintenance (PE-09003)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $107,9170 $195,000 Public Works N/A Recurring
Project Status: This project repairs, resurfaces, or reconstructs parking lots and walkways at various City facili Ɵes, including restriping and signage. The Golf Course Service Parking Lot and Terman Center Parking Lot were completed as part of the FY 2025 Street Resurfacing Project this Fall. The Eleanor Pardee Garden center access will be repaired as part of the FY 2027 Street Resurfacing Project a nd the Gamble Garden Parking will be re paired as part of the FY 2028 Street Resurfacing Project.
Cubberley Repairs (CB-17001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $476,935 $ 650,000 Public Works N/A Recurring
Project Status: This project is for general maintenance needs of the Cubberley campus. No work occurred during 1st half of FY 2026.
Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 10 of 11
Cubberley Roof Replacements (CB-16002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $39,170 $ 303,375 Public Works N/A Recurring
Project Status: This project replaces exis Ɵng roofs at Cubberley Community Center. The Pavilion Roo fing project was canceled due to the City’s pending purchase of the remaining Cubberley buildings and then ul Ɵmately rebuilding a new Cubberley Community Center.
Electric Charger Infrastructure InstallaƟon (PF-23000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $56,737 $ 122,453 Public Works N/A Recurring
Project Status: This project designs and installs electric vehicle chargers at various City facili Ɵes. The primary use of the electric vehicle chargers will be for City fleet vehicles There were no new chargers installed in the 1st half of FY 2026.
ElectrificaƟon of City FaciliƟes (PE-24001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 153,642 $0 Public Works Pre-Design Fall 2030
Project Status: This project will evaluate feasibility, prepare designs, and implement construcƟon for the electrificaƟon of fossil fuel consuming building systems in coordina Ɵon with the Building Systems Improvements project (PF-01003).. The City evaluated the Facility Condi Ɵon Assessment reports to help iden Ɵfy five faciliƟes for iniƟal project implementaƟon:
the Golf Course Pro Shop/Restaurant, Ventura Community Center, Art Center, Downtown Library, and College Terrace Library. This e ffort will help inform electri ficaƟon delivery approaches, site-speci fic logis Ɵcal and construc Ɵon consideraƟons, and establish best pracƟces for large facility conversions. The Request for Proposal is in its final draŌ and anƟcipates release for early 2026. Funding is also included for the HVAC electri ficaƟon upgrade at the 445 Bryant Street property. The replacement of seven gas package units with seven new heat pump package units is complete.
Community Services has started running classes out of the facility now.
Facility Interior Finishes Replacement (PF-02022)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $275,123 $457,516 Public Works N/A Recurring
Project Status: This project improves the interior finishes of City facili Ɵes, including flooring, walls, cabinets, paint, lighƟng, ceiling Ɵles, soundproo fing, and fixed o ffice furniture, doors, windows, and associated fire/life safety, mechanical, electrical and plumbing code compliance requirements.
Fire Equipment Replacement (FD-25000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon Buildings and FaciliƟes Projects
Status as of December 2025
Buildings and FaciliƟes Projects Page 11 of 11
$9,647 $1,691,847 Fire Department N/A Recurring
Project Status: This project funds ongoing replacement of Fire and Emergency Medical Services (EMS) equipment used for training, medical response, and technical rescue in all emergency situaƟons.
Police Video Recording Systems Replacement (PD-20000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 170,644 $ 214,800 Police Department N/A Recurring
Project Status: This project maintains the Palo Alto Police Department video recording systems used to record events in the field with up to five in-car cameras as well as body-worn cameras (BWC). In FY 2024, the City solicited a new vendor to include the in-car and BWC systems and newly added fixed interrogaƟon systems in the Public Safety Building (PSB). A vendor was selected, and City Council approved a Purchase Order. Materials have been shipped, and the transi Ɵon is in process. Full implementaƟon is expected to be completed on or around the end of FY 2026. The CIP will remain open to coordinate with the vehicle replacement cycle.
Roofing Replacement (PF-00006)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $56,924 $380,018 Public Works N/A Recurring
Project Status: This project replaces exis Ɵng roofs at City facili Ɵes that have outlived their useful lifespans. The Animal Shelter roof recoat has been delayed due to roof modi ficaƟons required for the proposed kennel remodel. Permits for the Phase 2 of the Lucie Stern Community Theatre roof replacement project has been completed. An IFB for construcƟon was issued in spring 2025 with construc Ɵon expected to begin in summer 2025. The Lucie Stern Community Theatre roof replacement is now complete. A consultant has been hired to evaluate the structural integrity of the Baylands InterpreƟve Center roof and give roofing replacement recommendaƟons.
University Avenue Parking Improvements (PF-14003)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $44,512 $87,000 Public Works N/A Recurring
Project Status: This project maintains parking lots and parking structures within the University Avenue Downtown Business Parking District. Beginning in winter 2025, the Univer sity pedestrian underpass refu rbishment project will start construcƟon. Project includes repain Ɵng of the pedestrian tunnels and installa Ɵon of new ligh Ɵng fixtures; it is anƟcipated to complete construcƟon in spring 2026.
Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 1 of 9
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 4 6 7 2 19
Recurring Projects 9
ONE-TIME PROJECTS
Baylands Comprehensive ConservaƟon Plan (PG-17000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $386,401 $458,852 Community Services Design Winter 2027 Project Status: This project will implement a conserva Ɵon plan that will examine na Ɵve vegetaƟon, wildlife habitat resources, and wildlife-appropriate public access for the en Ɵre Baylands, including Byxbee Park. This plan will provide informaƟon to successfully manage wildlife habitat and provide trails or other recrea Ɵon ameniƟes; provide a design overlay for appropriate types and locaƟons of public art in the Baylands; and design interpre Ɵve messaging throughout the Baylands. The plan seeks to op Ɵmize opportuniƟes for low-impact recrea Ɵon ensuring that these are compaƟble with the Baylands Master Plan direc Ɵon for passive use of the nature preserve. The Conserva Ɵon Plan will also provide input for the Byxbee Park Comple Ɵon project. The Parks and Recrea Ɵon Commission has created an Ad Hoc Commi Ʃe e t o w o r k w i t h s t aff on this project. Sta ff and the Ad Hoc Commi Ʃee have been reviewing the draŌ plan and idenƟfying gaps and highlighƟng where updates are required.
Baylands Golf Links Sand Topdressing (PG-26001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 0 $66,000 Community Services Construc Ɵon Summer 2026 Project Status: This project provides sand-topdressing for the natural turf fairways and pu ƫng greens at the Baylands Golf Links golf course. The topdressing is an essen Ɵal applicaƟon of sand to improve growing condi Ɵons, drainage, and playability, specifically aŌer rain events and throughout the wet winter season. An applica Ɵon of sand has been applied as a top layer to promote new turf growth, allow for be Ʃer drainage, and provide a smoother playing surface. Addi Ɵonal sand may be applied upon return of warm weather in the summer during peak growth season.
Baylands Levee Repair for Public Safety Access (OS-09002) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $54,298 $342,298 Community Services Pre-Design Summer 2028 Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 2 of 9
Project Status: This project provides funding to restore the width and height of the earthen flood levee between Harbor Road near the Baylands Interpre Ɵve Center and the perimeter levee of the Airport to protect the interior areas, provide emergency and operaƟonal vehicle access, and o ffset the potenƟal for localized flooding and erosion to the trail. Pre-design work has begun; however, the majority of funding was pushed to FY 2028, following Finance CommiƩee acƟon on September 8, 2025.
Baylands InterpreƟve Signage Program (OS-24001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 117,962 $178,366 Community Services Construc Ɵon Fall 2025 Project Status: The grant-funded project will install interpre Ɵve signage and exhibits on two miles of trails and on the boardwalk at the Palo Alto Baylands. The fabrica Ɵon and installa Ɵon of 21 interpre Ɵve signs spread along two miles of trails in the Palo Alto Baylands and 41 interpre Ɵve signs on the 850-foot boardwalk was completed in October 2025In October 2024, the City received an announcement that the Grant performance period would end six months earlier than originally planned, on December 30, 2025, rather than June 2026. With the performance period constricted, the city was concerned that more Ɵme would be needed to ensure that the elements could be completed and so applied for an extension of the performa nce period. In October 2025, the City’s request for an extension to the grant performance period was approv ed. The remaining grant funds of $41,818 were released allowing scope to be completed in a new performance period that ends December 30, 2026.
Boulware Park Improvements (PE-17005)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $5,793,204 $6,107,473 Public Works Completed Fall 2025
Project Status: This park renova Ɵon project was ini Ɵally planned in FY 2018 but was postponed due to an increase in scope to incorporate the adjacent AT&T lot purchased by the City in 2019. A Park Improvement Ordinance for the improvements was adopted by the City Council in October 2021, and a construc Ɵon contract was awarded in summer 2023. The park opened to the public in spring 2025. All contract punch list items were completed in December 2025..
Byxbee Park CompleƟon (PE-18006)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $368,192 $3,199,189 Public Works Pre-Design Summer 2028 Project Status: This project allows for the remaining improvements to Byxbee Park that follow the compleƟon of the landfill capping work. The Baylands Comprehensive Conserva Ɵon Plan (BCCP), which is currently undergoing CEQA analysis, will include recommendaƟons on the scope of the Byxbee Park proj ect. The BCCP and the conceptual plan for Byxbee Park need addi Ɵonal outreach and review which is an Ɵcipated to conƟnue through FY 2027. The project has been moved to FY 2028 pending compleƟon of the BCCP .
Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 3 of 9
El Camino Park Turf Replacement (PG-24000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 41,620 $842,000 Community Services Design Fall 2026
Project Status: This project has been paused and Council has provided direc Ɵon to use a por Ɵon of this project’s funding to complete a comprehensive study comparing synthe Ɵc turf to natural grass with a case study focused on El Camino Park. The study is complete and was presented to Council in December 2025 and planned to be brought back again to Council in January 2026 for approval. The study assessed environmental and health impacts, field uƟlizaƟon capacity, and capital and opera Ɵng costs required for both types of fields. The study provides recommendaƟons to Council for replacement of turf at El Camino Park.
Eucalyptus Tree Removal (PG-25002)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 105,860 $410,102 Community Services Construc Ɵon Fall 2027 Project Status: This Hazardous Fuel Abatement project iden Ɵfied Eucalyptus trees from the City of Palo Alto’s open space preserves for removal. During Phase 1 of this CIP , 36 Eucalyptus trees were removed within Esther Clark Park to reduce hazardous fuels adjacent to homes in the Palo Alto Wildland Urban Interface. Foothills Nature Preserve and Arastradero Preserve are to be evaluated for further Eucalyptus tree removals. This project is being expanded through Fiscal Year 2027. Sta ff are working cross-departmentally to priori Ɵze Arastradero Preserve and Foothills Nature Preserve for phases 2 and 3. The majority of Phase 2 tree removals were completed in December 2025.
Foothills Nature Preserve Boronda Lake Dock Replacement (OS-18000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,675 $156,243 Public Works Design Summer 2026
Project Status: This project is a refurbishment of the exisƟng dock. The dock was originally built in 1965 and was last refurbished in 2010 with repairs to the wood decking. The current condi Ɵon of the dock has declined and now requires complete replacement with new decking, ramp, floats, and pilings. Materials for the dock have been ordered, and replacement work will begin in early 2026.
Foothills Nature Preserve Dam Seepage InvesƟgaƟon and Repairs (PE-20000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $118,549 $224,815 Public Works Construc Ɵon Summer 2026 Project Status: This project will study the locaƟon of historic seepage from the Foothills Nature Preserve Dam at the sharp bend in the road on the face of the dam and will locate and inves Ɵgate the pipe and trench back fill material.
The source of the seepage is suspected to be the trench back fill around the pipe that returns shallow groundwater to Boronda Lake. Sta ff con Ɵnue to monitor and inves Ɵgate the seepage of the Department of Water Resources Division of Safety of Dams (DSOD) inspec Ɵons and recommenda Ɵons. Sta ff completed camera inspec Ɵons of the Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 4 of 9
underdrain pipes to iden Ɵfy potenƟal obstrucƟons and leakage issues. Per the DSOD recommenda Ɵons, the City’s consultant installed a weir on the downstream side of the dam in spring 2025 which would allow the City to collect quanƟtaƟve measurements of the seepage flow and inform the seepage trends and needs for a long-term solu Ɵon The effecƟveness of the weir installed in spring 2025 for measuring seepage condiƟons conƟnues to be monitored.
Foothills Nature Preserve Improvements (PE-21000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $363,899 $3,421,243 Public Works Design Summer 2030
Project Status: This project has repaired the bridge to Sunfish Island, and will complete the design and permi ƫng to replace the footbridge in Los Trancos Valley, replace the grade control structures along Buckeye Creek, provide new split rail fencing to protect sensi Ɵve areas, provide new pedestrian pathways, signage, tra ffic control features to keep park visitors safe while walking along the park road, and add improvements to some of the exis Ɵng parking areas to make them safer and more e fficient. Council awarded a professional services contract for addi Ɵonal outreach, detailed design, and bid package prepara Ɵon for pathways, fencing, and parking improvements in spring 2024. In fall 2025, Council referred the project to the Parks and Recrea Ɵon Commission (PRC) for poten Ɵal scope reducƟons for the FY 2026 budget.. In fall 2025, sta ff obtained feedback from PRC on the reduced scope. The City’s consultant began detailed design and construc Ɵon documents per recommended reduced scope. Sta ff anƟcipates a Park Improvement Ordinance recommenda Ɵon in early 2026. The replacement of the footbridge in Los Trancos Valley and the grade control structures along Buckeye Creek have been moved to FY 2029 and FY 2030 due to staffing constraints.
Golf Course Net and ArƟficial Turf Replacement (PG-18000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $847,789 Community Services Pre-Design Fall 2028
Project Status: This project will remove and replace the golf course driving range ne ƫng and synthe Ɵc turf. This project has been delayed due to the assessment of addi Ɵonal ball retenƟon needs throughout the golf course. Sta ff has partnered with First Tee Silicon Valley on a short-term agreement and is currently developing a long-term agreement for driving range and pracƟce facility improvements. Concurrently, staff is finalizing a Second Deck Study that could impact the Ɵming and extent of replacement.
Heritage Park Site AmeniƟes Replacement (PG-21000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $37,275 $143,132 Community Services Construc Ɵon Summer 2025 Project Status: The project will replace select wa lkways and all of the site ameni Ɵes in Heritage Park including benches, picnic tables, trash receptacles, playground arbor, bicycle racks and drinking fountain. Improvements completed include replacement of retaining walls in the playground area and repairs to decomposed granite Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 5 of 9
pathways throughout the park. Further work throughout December 2025 included repairs to asphalt pathways, benches, and landscape improvements. Sta ff has met with stakeholders and plans to bid out the remaining fencing work to connect access from the playground to the Roth Building public restroom., Johnson Park RenovaƟon (PE-21002)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $2,050,000 Community Services Design Summer 2027
Project Status: This project renovates exis Ɵng park elements, including asphalt concrete and brick pathways, site furnishings, playground equipment and resurfacing, fencing, and improvements to irriga Ɵon and ligh Ɵng. Safety improvements associated with asphalt pathways repair s were addressed in fall 2025 as part of Public Works Engineering’s annual street resurfacing project.
Ramos Park Improvements (PG-14000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $646,631 $767,788 Community Services Construc Ɵon Winter 2027 Project Status: This project replaces the playground equipment at Ramos Park. Council awarded a coopera Ɵve agreement with Ross Recrea Ɵon in June 2024 to replace and install the playground equipment for Ramos Park.
Playground equipment was replaced in spring 2025. Funding has been added to this project for replacement of site ameniƟes and basketball court resurfacing repairs to occur in FY 2026-2027 and be completed by winter 2027
Rinconada Park Improvements (PE-08001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $5,761,775 $10,376,726 Public Works Construc Ɵon Fall 2030 Project Status: This project provides upgrades to safety, site ameni Ɵes, playground facili Ɵes, a new restroom, irrigaƟon, drainage, and ADA accessibility improvements at Rinconada Park. These improvements were iden Ɵfied in the Rinconada Long Range Plan (LRP). Phase 1 park improv ements to the western half of the park were completed in spring 2022. A new restroom was installed and opened to the public in summer 2024. Funding was approved by Council in FY 2025 to complete structural and electric desi gn for replacement of a storage unit (purchased by Palo Alto Tennis Club (PATC)) at Rinconada Park. The design has been completed and a Memorandum of Understanding between the City and PATC is in progress. Per PATC request, further work on the project has been paused. According to the LRP , future improvement phases will include improv ements to the eastern half of the park by FY 2030, including pathway improvements, ADA upgrades, planƟng, irrigaƟon, lighƟng, and site furnishings.
Robles Park Improvements (PE-18015)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $210,874 $1,073,351 Public Works Design Fall 2026
Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 6 of 9
Project Status: This project will replace playground equipment. Community mee Ɵngs were held in September 2023 and March 2024 to obtain community input. An online community survey regarding the play equipment was completed in January 2025. The project compleƟon has been extended to fall 2026 due to staffing constraints.
Stanford Palo Alto Community Playing Fields Turf Replacement (PG-26000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $36,504 $2,707,547 Community Services Completed Fall 2025 Project Status: The project will replace the synthe Ɵc turf at the Stanford Palo Alto Community Playing Fields. The Stanford Palo Alto Community Playing Fields accommodate year-round play, including addi Ɵonal evening play with some temporary lighƟng. Since the turf was installed in 2016, it has been in high demand and is used by youth and adult leagues as well as walk-on play. Synthe Ɵc turf has a typical lifespan of approximately eight to ten years with each year of use contribuƟng to gradual wear and tear resulƟng in loss of pile height, turf fiber, and infill. The design was completed in fall 2024, construc Ɵon began in summer 2025 through an approved sole source contract, and the turf replacement was completed in December 2025.
Werry Park Playground Improvements (PG-22000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $350,000 Community Services Pre-Design Summer 2028
Project Status: This project provides funding for the replacement and accessibility improvements of the exis Ɵng playground. The benches, tables, trash receptacles, bicycle rack and drinking fountain have reached the end of their useful life and need replacement as well. Perimeter landscaping will be replaced as part of this project.
RECURRING PROJECTS
Art in Public Spaces (AC-86017)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $269,649 $1,774,351 Community Services N/A Recurring
Project Status: This project provides the ongoing temporary and permanent artworks throughout the City of Palo Alto. ArƟst-in-Residence Aleo Landeta completed their residenc y and installed a temporary sculpture on King Plaza.
Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 7 of 9
ArƟst Kiana Honarmand has completed her community outreach and is developing her final report and artwork design for King Plaza. The final art piece was installed at the Public Safety Building, and artwork is under development for Fire Sta Ɵons 4 and 5, the downtown parking garage, and for three murals downtown as well as a series of temporary murals at the California Avenue garage. The 2025 Code: ART fes Ɵval drew approximately 25,000 people downtown over three evenings, and plans are unde rway for the next Code: ART in 2027. A new series of ArtLiŌ grant projects are planned for early 2026 to animate Cubberley campus and our commercial corridors with temporary public art.
AthleƟc Courts Resurfacing (PG-06001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $43,184 $315,190 Community Services N/A Recurring
Project Status: This project repairs and resurfaces athleƟc courts in various Palo Alto parks. The recon figuraƟon and resurfacing of the Greer Park basketball courts wwere co mpleted in July 2025. The Bike Safety Park (formerly referred to as the Traffic Garden located at Ventura Community Center) construc Ɵon was completed as part of the FY 2025 Street Resurfacing Project in summer 2025. Also, resurfacing of the basketball courts at Ventura Community Center was completed in fall 2025.
Benches, Signage, Walkways, Perimeter Landscaping (PG-06003) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $320,887 $212,198 Community Services N/A Recurring
Project Status: This project restores and replaces exis Ɵng benches, signage, fencing, walkways, and landscaping at various City faciliƟes. In June 2025, 13 replacement picnic benches were installed at Rinconada Pool. Design for 26 Park signs has been completed, and new signage has been installed at Boulware and Fred Eyerly Tower Well Park.
AddiƟonally, trailhead signage was installed at Pearson-Arastradero Preserve. Other Park ameniƟes replaced include tennis court windscreens at Weisshaar Park and drinking fountains at Mitchell Park. Lastly, Ly Ʃon Plaza fountain grate design was completed in May 2025, with installaƟon planned for 2026.
Dog Park InstallaƟon and RenovaƟon (PG-18001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $372,039 $150,000 Community Services N/A Recurring
Project Status: This project enables the construcƟon of dog parks at various City parks and facili Ɵes for construcƟng new or renova Ɵng exisƟng dog parks. A renovated Mitchell Park Dog Park was opened to the public in April 2025 which improved the dog park with separate areas for large and small dogs. A new dog park was built as part of the Boulware Park expansion project and opened to the public in May 2025.
Off-Road Pathway Resurfacing and Repair (OS-09001)
Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 8 of 9
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $133,000 Public Works N/A Recurring
Project Status: This project repairs, resurfaces, or replaces pathways as needed within the City of Palo Alto.
Pathways are chosen based on safety inspec Ɵons, condiƟon, and usage. Open Space pathways are currently under review for repair.
Open Space Lakes and Pond Maintenance (OS-00002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $27,798 $121,730 Community Services N/A Recurring
Project Status: This project rehabilitates lakes and ponds in open space nature preserves to protect wildlife habitat and recreaƟonal safety and to meet State Division of Safety of Dams requirements. A new three-year contract was awarded in July 2024 for the removal of aqua Ɵc vegetaƟon in Boronda Lake, which is conducted twice annually in the spring and fall.
Open Space Trails and AmeniƟes (OS-00001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $217,582 $300,673 Community Services N/A Recurring
Project Status: This project restores unpaved trails, fences, picn ic areas, and campgrounds at Foothills, Baylands, and Pearson-Arastradero Nature Preserves. A new five-year maintenance contract was awarded in November 2024.
Annual mowing of 60 acres of fire fuel break were completed in early Summer 2025, and 1.5 miles of trail tread repair was completed on Los Trancos Trail in fall 2025.
Parks and Open Space Emergency Repairs (PG-09002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 260,110 $356,561 Community Services N/A Recurring
Project Status: This project replaces or repairs playgrounds, play yard surfaces, wooden structures, park ameni Ɵes, and play equipment in the event of storms, fire, vandalism, or structural failure. In spring 2025, slide replacements were installed at Johnson and Juana Briones Parks. Repairs were done at the Magical Bridge playground including two saucer swings, wooden play elements, and rubber surfacing. The Mitchell Park splash pad also had rubber surfacing repairs performed. In December 2025, all the pa thway planks of the Briones pedestrian bridge were replaced with the recommenda Ɵon in the City-Wide Bridge Structural Assessment. Addi Ɵonally, the spinner play piece at the Magical Bridge playground was replaced. The Mitchell Park pickleball court entry gate was fixed to now swing inward instead of outward which was impeding the pedestrian path of travel.
Park Restroom InstallaƟon (PG-19000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon Parks, Open Space and Golf Projects
Status as of December 2025
Parks, Open Space and Golf Projects Page 9 of 9
$248,684 $753,898 Community Services N/A Recurring
Project Status: This project installs new restrooms at City parks that currently do not have restroom facili Ɵes. In summer 2024, the Ramos Park restroom construc Ɵon was completed and opened to the public. Sta ff is currently working on the replacement of the exis Ɵng two-stall restroom near the Magical Bridge Playground at Mitchell Park with a new four-stall prefabricated restroom building. The building was purchased in fall 2025. Contractor bidding is esƟmated to begin in spring and the restroom building delivery, and site construc Ɵon is esƟmated to be completed in summer 2026.
Streets and Sidewalk Projects
Status as of December 2025
Streets and Sidewalk Projects Page 1 of 4
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 0 3 0 0 3
Recurring Projects 9
ONE-TIME PROJECTS
California Avenue District Gateway Signs (PE-17004)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $26,943 $162,783 Public Works Design Fall 2026
Project Status: This project includes the design and replacement of two exis Ɵng gateway signs for the California Avenue business district. Ini Ɵal public outreach was completed in winter 2021. The California Avenue District Gateway Signs project is in the next phase of improvements following the California Avenue Streetscape update and near-term improvements. The signage plan includes a primary gateway sign at the intersec Ɵon of California Avenue and El Camino, along with a companion sign at the Birch Street exit ramp o ff of Oregon Expressway. This project will be discussed with the Architectural Review Board by the second quarter of 2026 and presented to City Council for approval later in 2026.
Newell Road/San Francisquito Creek Bridge Replacement (PE-12011) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 4,416,929 $23,456,670 Public Works Design Spring 2027 Project Status: This project removes and replaces the Newell Road bridge over San Francisquito Creek with a clear span to allow the channel to convey up to the natural capacity of the San Francisquito Creek, approximately 7,500 cubic feet per second, and to improve safety for vehicular, bicycle, and pedestrian traffic. The project is being closely coordinated with the City of East Palo Alto, Valley Water, and San Francisquito Creek Joint Powers Authority (SFCJPA). Granite ConstrucƟon was awarded the construcƟon contract on June 16, 2026. The No Ɵce to Proceed was issued in August and street tree removal was done in September. In addi Ɵon, AT&T, Comcast and PG&E completed the overhead power and fiber line relocaƟon in December 2025
Street Lights CondiƟon Assessment (PE-13014)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $8,799 $251,023 Public Works Design Fall 2027
Project Status: This project will assess the condi Ɵon of the City’s streetlight system. The assessment will include an Streets and Sidewalk Projects
Status as of December 2025
Streets and Sidewalk Projects Page 2 of 4
inventory of the enƟre lighƟng system, including age and condiƟon of conduit, wiring, streetlight poles, foundaƟons, luminaires, and ligh Ɵng coverage. The project will also determine the inspec Ɵon, maintenance, repair, and rehabilitaƟon necessary to prolong the life of the City’s streetlight system. This project has not started due to staffing constraints.
RECURRING PROJECTS
City Bridge Improvements (PE-20001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $749,852 $1,608,071 Public Works N/A Recurring
Project Status: This project includes recurring bridge inspec Ɵons, maintenance, repair, and an improvement program.. This program will include on-going inspec Ɵons to report physical changes to the structures, recommendaƟons for work to be done, and addi Ɵonal informaƟon to meet func Ɵonal and structural standards in accordance with industry standards. Sta ff completed structural and safety repa irs to seven bridges in 2024. Anon- call structural contract was awarded by Council in spring 2025 to con Ɵnue recurring inspec Ɵons and other as- needed structural assessments for Public Works projects. This CIP also provides funding for the San Francisquito Creek bank stabiliza Ɵon project under a memorandum of understanding between Caltrain, the City of Menlo Park and the City of Palo Alto.The bank stabiliza Ɵon project design was completed in fall 2025 and an IFBwas issued in December 2025. Caltrain an Ɵcipates awarding a construcƟon contract in spring 2026 with work scheduled to begin in summer 2026.
Curb and GuƩer Repairs (PO-12001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $278,905 $208,000 Public Works N/A Recurring
Project Status: This project repairs curbs and gu Ʃers upliŌed by tree roots. A FY 2026 repairs project resumes the City’s focus on improving Sidewalk Districts 1 & 2 that includes Downtown North and University South neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middle field Road), in addi Ɵon to addressing hot spot loca Ɵons from 311 requests. Approximately 2,977 linear feet of curbs and gu Ʃers are included in the FY 2026 Sidewalk, Curb & Gu Ʃer Repair Project. Council approved the construc Ɵon contract on October 20, 2025. Construc Ɵon of curb and gu Ʃer repairs began in December 1, 2025, priori Ɵzing loca Ɵons that require immediate ac Ɵon including a newly constructed valley gu Ʃer on Jacaranda Lane in Parking Lot 8. Contract compleƟon is set for June 15, 2026..
San Francisquito Creek Joint Powers Authority Ongoing Creek Projects (PE-22000) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $23,379 $553,492 Public Works N/A Recurring
Streets and Sidewalk Projects
Status as of December 2025
Streets and Sidewalk Projects Page 3 of 4
Project Status: This project will implement creek studies and the comple Ɵon of the design for the San Francisquito Creek Joint Powers Authority (JPA) upstream projects including channel widening and ConƟnuing Authority Program SecƟon 205 (CAP 205) study. In FY 2024, the JPA awarde d a contract with WRA Environmental Consultants to analyze the creek hydraulics and the improvement alterna Ɵves that could reduce flooding. The Master Service Agreement includes the design and implementa Ɵon of Reach 2 project elements. WRA completed their ini Ɵal field survey, developed a preliminary list of improvement alterna Ɵves and provided the ini Ɵal presentaƟon to the public in November. Their e fforts will be driven based on public feedback and direc Ɵon from the SFCJPA Board. Due to comments received from SFCJPA Board members and sta ff, the consultant’s scope had to be modified in 2025. This acƟon delayed the comple Ɵon of the Alterna Ɵve Evalua Ɵon Report that would have determined the preferred alternaƟve to advance.
Sidewalk Repairs (PO-89003)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $2,846,653 $ 1,402,000 Public Works N/A Recurring
Project Status: This project repairs and replaces broken and upli Ōed sidewalks. The program completed all twenty- three sidewalk districts in 2017, a 30-ye ar (1986–2017) sidewalk repair district cycle. Council a pproved a sidewalk assessment contract in November 2017 to evaluate the sidewalk program and assess potenƟal improvements to the current district-based program. The FY 2026 Sidewalk, Curb & Gu Ʃer Repair Project will focus on sidewalk repairs (PO-89003) and curb and gu Ʃer repairs (PO-12001) in Sidewalk Distri cts 1 & 2, which in clude the Downtown Professorville neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middle field Road). The FY 2026 repair project resumes improvement e fforts made in this area made by the FY 2024 Sidewalk Repair ADA Improvement Project. Council approved the construcƟon contract on October 20, 2025. The project aims to replace approximately 21,530 square feet of concrete sidewalk, 4, 615 square feet of driveways, and install 46 new curb ramps to conform to the Americans with DisabiliƟes Act (ADA). Contract compleƟon is set for June 15, 2026.
Sign ReflecƟvity Upgrade (PO-11000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $16,730 $ 128,000 Public Works N/A Recurring
Project Status: This project includes the annual inventorying, upgrading and maintaining of all tra ffic signs. A list of signs not mee Ɵng the minimum requirement is derived from Manual on Uniform Tra ffic Control Devices (MUTCD) approved Nighƫme Visual Inspec Ɵon surveys. Sta ff will con Ɵnue to work on replacing the 405 signs iden Ɵfied as replacement from the FY 2024 survey. Due to conƟnuing staffing constraints, nighƫme reflecƟvity surveys were not performed during FY 2025 and are not planned for FY 2026.
Street Lights Improvements (PO-05054)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $118,081 $408,422 Public Works N/A Recurring
Streets and Sidewalk Projects
Status as of December 2025
Streets and Sidewalk Projects Page 4 of 4
Project Status: This project replaces streetlights, including poles, pole foundaƟons, luminaires and wiring as needed to restore or improve street ligh Ɵng. In the second half of FY 2025, there were six knockdown loca Ɵons with nine completed repairs, and seven are sƟll in progress to be completed in FY 2026.
Street Maintenance (PE-86070)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $6,860,756 $5,437,687 Public Works N/A Recurring
Project Status : Street Maintenance Projects include the annual resurfacing, micro-seal, crack seal, and reconstrucƟon of various city streets in support of the Council’s goal of achieving a citywide average pavement condiƟon index (PCI) score of 85, represen Ɵng very good or excellent condi Ɵons. The FY 2024 Street Resurfacing Project is completed except for the California Avenue Street Improvements Project. The Project is in permi ƫng process with Caltrans. The FY 2025 Street Resurfacing Project construcƟon is completed except for the striping in the Caltrain right of way. Contractor is wai Ɵng for approval of the SWPPP plan and flagger available from Caltrain to perform the work. The FY 2025 Street PrevenƟve Maintenance Project was completed as of December 31, 2025.
ThermoplasƟc Lane Marking and Striping (PO-11001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $43,443 $328,000 Public Works N/A Recurring
Project Status: This project maintains thermoplasƟc markings on roadways. ThermoplasƟc lane marking and striping are incorporated into annual Pavement Preven Ɵve Maintenance Projects. The FY 2025 Streets Preven Ɵve Maintenance Project (PE-86070, PO-11001) was completed as of December 31, 2025.
Tree Grate AlternaƟves (PF-26000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $100,000 Public Works N/A Recurring
Project Status: This project implements the assessment and selec Ɵon of alternaƟve tree grate soluƟons to enhance tree root protec Ɵon and promote the long-term sustainability of the City’s urban forest. The scope includes evaluaƟng design alterna Ɵves, idenƟfying the most e ffecƟve solu Ɵons, and managing the replacement process to improve urban tree health and infrastructure resilience.
TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 1 of 8
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 1 7 4 1 13
Recurring Projects 5
ONE-TIME PROJECTS
California Avenue Streetscape Update (PL-23000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $278,523 $729,997 City Manager’s O ffice Design Spring 2026 Project Status: The project implements interim changes to the Ca lifornia Avenue Streetscape and for necessary CEQA analysis for the future con figuraƟon of the street. Temporary barriers were replaced with bollards, planters, colored paving and bike lane improvements, which were completed in summer 2025 with the excep Ɵon of paving the California Avenue/El Camino Real intersec Ɵon and the addi Ɵon of ADA parking spaces on Ash Street, which are anƟcipated to be complete in spring 2026. CEQA analysis was approved by Council in March 2025. Exis Ɵng parklet program is being adapted to permit pre-approved and customized parklets. A concept design is underway for the future implementaƟon of 2-way slow bike lanes with pedestrian safety improvements.
Charleston Road/Alma Street Railroad Crossing Safety Improvements (PL-25002) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $85,948 $1,214,305 O ffice of TransportaƟon Design Fall 2028 Project Status: The California Department of Transporta Ɵon, in coopera Ɵon with the Peninsula Corridor Joint Power Board (JPB) and the City of Palo Alto, proposed a railroad crossing improvement project at Charleston Road and Alma Street to enhance tra ffic safety. This crossing was iden Ɵfied for possible funding of hazard elimina Ɵon and safety improvements through SecƟon 130 funds. The Sec Ɵon 130 program is a federal-funded program, administered at the state level, for the elimina Ɵon of hazards at at-grade highway-rail crossings. Phase 1 of Sec Ɵon 130 funding will reimburse the actual and direct costs of the Preliminary Engineering phase of this project.
This project is separate and
independent from the on-going rail grade separa Ɵon projects and addresses more immediate safety concerns at this crossing. The railroad crossing at Alma Street and Charleston Road experiences a large volume of pedestrian and bicycle traffic during the morning and a Ōernoon school commute hours. JPB and the City will be responsible for the construcƟon of the improvements within each respecƟve agency’s right of way.
Churchill Avenue Enhanced Bikeway (PL-14000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 2 of 8
$564,143 $3,823,660 Public Works Construc Ɵon Spring 2026 Project Status: This project includes planning, design and construc Ɵon of a shared-use path along the north side of Churchill Avenue between the exis Ɵng shared-use path at Cas Ɵlleja Avenue and the Stanford Perimeter Trail. It also includes intersec Ɵon improvements at Churchill Avenue and El Camino Real, which will include a new dedicated westbound right-turn lane. PAUSD approved the easements required for the project in August 2023. Staff have worked with Caltrans for re-issuance of the encroachment pe rmit and received approval in June 2024. The construc Ɵon contract was approved by Council on December 9, 2024. Construc Ɵon is on hold through winter with major construcƟon acƟviƟes resuming in Summer2026. Bike pathway and intersec Ɵon work are anƟcipated to be completed during spring while the project should reach substanƟal compleƟon in late fall 2026.
Churchill Avenue Rail Grade SeparaƟon and Safety Improvements Main (PL-24001) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $118,034 $37,155,230 O ffice of TransportaƟon Design Spring 2028 Project Status: This project provides for the planning, design, and construc Ɵon of the grade separa Ɵon at the exis Ɵng at-grade crossing on Churchill Avenue in the Caltrain Rail Corridor. The project will provide improvements to accommodate bicycles, pedestrians, and vehicular movement at the crossing. A Ōer reviewing various studies and refinements to the alterna Ɵves, the Rail Commi Ʃee recommended proceeding with a Par Ɵal Underpass Alterna Ɵve with Bicycle and Pedestrian crossing at Seale Avenue. On June 10, 2024, the City Coun cil selected the Churchill Underpass with ped/bike crossing at Seale Avenue. The funding agreement with the Federal Railroad Administra Ɵon was approved by City Council on June 17, 2024. Sta ff collaborated with Caltrain and the Valley Transporta Ɵon Agency (VTA) to develop a coopera Ɵve agreement for the Preliminary Engineering and Environmental Documenta Ɵon phase and funding from Measure B Grade Separa Ɵon funds. This cooperaƟve agreement between the City, Caltrain, and VTA was approved by the City Council on December 9, 2024. Sta ff is working closely with Caltrain, VTA, and the Federal Railroad Administra Ɵon (FRA) to re fine the grade separa Ɵon alterna Ɵves. As part of this process, sta ff conducted community mee Ɵngs in September 2025 to present updated concepts and gather public input. Rail Commi Ʃee and City Council reviewed the updated alterna Ɵves in fall 2025 and selected the Alma Street Ramp alterna Ɵve for Bicycle and Pedestrian crossing at Seale Avenue as part of the Par Ɵal Underpass alterna Ɵve for Churchill Avenue Crossing.
Staff will work towards developing 15% design for Rail CommiƩee review in summer 2026.
Churchill Avenue Alma Street Railroad Crossing Safety Improvements (PL-20000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $2,575,381 $8,853,852 Public Works Completed Fall 2025
Project Status: This project is a railroad crossing improvement project to enhance safety at the intersecƟon of Churchill Avenue and Alma Street. The design includes tra ffic signal modi ficaƟons, street ligh Ɵng improvements, roadway resurfacing, sidewalk realignment, drainage improvements, u Ɵlity reloca Ɵons, signage, and striping. Sta ff is coordinaƟng with Caltrain, Caltrans, and California Public U ƟliƟes Commission (CPUC). CPUC approved General Order 88-B for the project in November 2022 and author ized the City to move forward with construc Ɵon. The construc Ɵon TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 3 of 8
contract was awarded and started in summer 2023 but was delayed due to prolonged procurement of the tra ffic controller cabinet, received in May 2025. Coordina Ɵon with Caltrain required a short and strict installa Ɵon window due to their electri ficaƟon and restric Ɵons on train shutdowns. A Ōer obtaining approval from Caltrain, the tra ffic system was switched over to new signals in June 2025. Comple Ɵon of the concrete pedestrian areas, repaving, and installaƟon of new striping occurred in early summer 2025. ConstrucƟon was completed in fall 2025.
Downtown Automated Parking Guidance Systems, Access Controls & Revenue (PL-15002) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $4,375,179 $5,197,827 Public Works Construc Ɵon Spring 2026 Project Status : This project includes design and installa Ɵon of new downtown parking guidance systems, access controls, and revenue collecƟon equipment that will be coordinated with both the Downtown Parking Way finding, PL- 15004 project and the 2016 Downtown Parking Management. Sta ff contracted with Dixon Resources for addi Ɵonal management support in design and procurement for the system installa Ɵon in the Downtown garages on University Avenue. The contractor completed tes Ɵng the interior infrastructure for all garages and found no major issues. The project received Planning approval for the exterior matrix signs in September 2025 and are now working with the consultant on applying for the building permits for sign fabricaƟon and installaƟon.
Meadow Drive/Charleston Road Rail Grade SeparaƟon and Safety Improvements (PL-24000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $224,204 $68,364,787 O ffice of TransportaƟon Design Spring 2028 Project Status: This project provides for the planning, design, and construc Ɵon of the grade separaƟons at the exisƟng at-grade crossings on Meadow Drive and Charleston Road in the Caltrain Rail Corridor. The project will provide improvements to accommodate bicycles, pedestrian s, and vehicular movement at the crossings. A Ōer reviewing various studies and re finements to the alterna Ɵves, the Rail Commi Ʃee recommended proceeding to advance two alternaƟves, the Hybrid and Underpass Alterna Ɵves, into the early phase of Preliminary Engineering and Environmental DocumentaƟon. The commi Ʃee also recommended re fining these alterna Ɵves to reduce right-of-way impacts and improve bicycle and pedestrian facili Ɵes. The City Council a Ōer reviewing directed staff to advance these alternaƟves into Preliminary Engineering and Environmental phase at Council Mee Ɵngs in June 2024. The funding agreement with the Federal Railroad AdministraƟon was approved by City Council on June 17, 2024. Sta ff collaborated with Caltrain and the Valley Transporta Ɵon Agency to develop a coopera Ɵve agreement for the Preliminary Engineering and Environmental Documenta Ɵon phase and funding from Measure B Grade Separa Ɵon funds. This cooperaƟve agreement between the City, Caltrain, and VTA was approved by the City Council on December 9, 2024.
City sta ff is working closely with Caltrain, VTA, and the Federal Railroad Administra Ɵon (FRA) to re fine the grade separaƟon alternaƟves. As part of this process, sta ff conducted community mee Ɵngs in September 2025 to present updated concepts and gather public input. Rail Commi Ʃee and City Council reviewed the updated alterna Ɵves in fall 2025 and selected the Hybrid alterna Ɵves for Meadow Drive crossing and Direct Ramp Underpass alterna Ɵve for Charleston Road. Staff will work towards developing 15% design for Rail CommiƩee review in summer 2026.
TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 4 of 8
Parking Management and System ImplementaƟon (PL-16002)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $433,182 $627,247 O ffice of TransportaƟon Construc Ɵon Summer 2026 Project Status: This project provides for the design and installa Ɵon of the Comprehensive Parking Permit and Cita Ɵon Management System. The all-inclusive system is a tool staff will uƟlize in the management of parking permits for eight parking permit programs and associated on and o ff-street parking cita Ɵons. A vendor has been selected and will be awarded by Council in fall 2025.
Quarry Road Improvements and Transit Center Access (PL-16000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,282,050 $2,554,268 O ffice of TransportaƟon Design Fall 2026 Project Status : This project implements the planning, design, and construc Ɵon of bicycle and pedestrian improvements along Quarry Road between El Camino Real and Welch Road, including, but not limited to, upgraded bicycle lanes and crosswalks, innova Ɵve intersecƟon treatments for bicyclists, and improved access to transit stops.
The required parkland un-dedica Ɵon for the Quarry Road Transit Connec Ɵon project was approved by the voters in November 2024. To begin design work, a cost-sharing agreement between Stanford and City was developed and approved by Council in November 2025, and design work has commenced.
Railroad Grade SeparaƟon and Safety Improvements (PL-17001) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $4,501,430 $10,994,119 O ffice of TransportaƟon Pre-Design TBD Project Status : This project involves development of conceptual alterna Ɵves and review through community-based processes to advance the railroad grade crossing for the Palo Alto Avenue crossing. It will also fund the prepara Ɵon of a Project Study Report and environmental analysis that will be required for the City to realize its goals of advancing grade separa Ɵons. The project will perform preliminary engineering design, conduct project related studies, and prepare environmental documents for the improvements. This project is currently on hold while the City is considering quiet zone implementa Ɵon for interim condi Ɵons, and sta ff will ini Ɵate the conceptual plan development for grade separaƟon at this crossing in 2026, depending upon the Rail CommiƩee and City Council direcƟon.
Ramona Street Streetscape Update (PE-26002)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $225,000 Public Works Design Winter 2026
Project Status: This project provides for the near-term streetscape improvements for the pedestrian-only por Ɵon of Ramona Street between Hamilton and University Avenues (approximately 200 feet of the street from the intersec Ɵon of Hamilton Avenue and Ramona Street). Forthcoming improvements include installa Ɵon of concrete bollards and meridian barriers to replace the orange barriers. These are expected to arrive in mid-January and be installed shortly TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 5 of 8
thereaŌer. Staff are making these improvements knowing we will take greater Ɵme in reviewing the streetscape design as recommended by the Commi Ʃee and will likely resume this work pending determina Ɵon of City Council priori Ɵes during the 2026 Council Retreat.
Traffic IntersecƟon Accessibility Improvement Project (PL-25001) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $550,512 O ffice of TransportaƟon Construc Ɵon Summer 2027 Project Status: This project will provide tra ffic intersec Ɵon accessibility improvements at four iden Ɵfied loca Ɵons across the City to enhance tra ffic conges Ɵon relief e fforts. These modi ficaƟons may include the addi Ɵon of new crosswalks and curb ramps; accessible pedestrian system (APS) push bu Ʃons; upda Ɵng exis Ɵng 8” tra ffic signal indicaƟon heads to 12”; video detec Ɵon for improved opera Ɵons; and implementa Ɵon of Automated Tra ffic Signal Performance Measures (ATSPM) for ongoing data collec Ɵon and opera Ɵonal/safety analysis. Funding for this project will be provided by 2016 Measure B Local Streets and Roads (LSR) grant funds. Since the City’s pavement condi Ɵon index (PCI) is above 70, the City is eligible to use this funding for tra ffic conges Ɵon relief projects. This project is currently upgrading traffic signal indicaƟon heads at three intersec Ɵons and APS bu Ʃons at five intersecƟons. Design for improvements is currently in progress at two addi Ɵonal intersecƟons with an Ɵcipated implementaƟon in lat e FY 2026 and FY 2027.
University Ave Streetscape Update (PE-21004)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $631,408 $3,388,810 Public Works Design Fall 2030
Project Status: This project includes a study to recon figure University Avenue between Alma Street and Middle field Road to adapt the public realm to maximize pedestrian and bicycle use, reduce conges Ɵon, and enhance the retail environment/economic ac Ɵvity, while maintaining two-way vehicular access, parking opportuni Ɵes, delivery and loading zones, ride share spaces, and other ameni Ɵes including performance space. Council awarded a professional services contract for CSW/Stuber-Stro eh Engineering in February 2022. The project uses a phased approach with Phase 1 consisƟng of public outreach, conceptual design, preliminary environmental studies, and financial assessment.
Staff presented an alterna Ɵves analysis and a preferred streetscape concept plan to Council on December 18, 2023.
Council did not approve the plan and directed sta ff to iden Ɵfy addiƟonal concept alterna Ɵves for Council discussion.
Staff conducted addi Ɵonal outreach to the Retail Commi Ʃee, Stakeholder Working Group, and received input from Council on June 3, 2024. On December 9, 2024, Council approved sta ff recommended preferred concept plan. In fall 2025, sta ff and its consultants re fined the streetscape concepts based on topographic survey data and began evaluaƟng cost reducƟon opƟons within the framework of the preferred concept plan. Sta ff will seek Council approval for a consultant contract amendment for Phase 2 services , including preliminary design, environmental review, and Engineer’s Report for an Assessment District once the alternaƟve cost evaluaƟon is complete
TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 6 of 8
RECURRING PROJECTS
Bicycle and Pedestrian TransportaƟon Plan ImplementaƟon (PL-04010) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 323,875 $2,814,186 O ffice of TransportaƟon N/A Recurring Project Status: This project implements the Bicycle and Pedestrian Transporta Ɵon Plan Update e ffort, which kicked off in fall 2023 and is scheduled to share a dra Ō plan by the end of 2025. This project also includes the implementaƟon of various individual bicycle and pedestrian projects, such as the design and construc Ɵon of bicycle boulevards, enhanced bikeways, shared-paths, bicycle parking, pedestrian improvements, and quick-build implementaƟon of the City’s exis Ɵng 2012 Bicycle and Pedestrian Transporta Ɵon Plan. This proj ect also funds the Embarcadero Road Improvements between Alma and Emerson. This project also funds the South Palo Alto Bike and Pedestrian Connec Ɵvity project, which is currently engaging with the community to select crossing loca Ɵons, conceptual designs, and bike/pedestrian network improvements for new grade-separated bicycle and pedestrian rail crossings in south Palo Alto. The City Council reviewed eight shortlisted alternaƟves and based on recommendaƟons from the Rail Commi Ʃee and Sta ff, selected Alterna Ɵve A (a crossing at El Dorado Avenue) as the preferred alternaƟve, eliminaƟng all other op Ɵons from further considera Ɵon. Two variants of Alterna Ɵve A were advanced:
A1 (signalized crossing of Alma Street at El Dorado Avenue ) and A2 (tunnel under both Alma Street and the Caltrain tracks). The Council passed a moƟon to focus evaluaƟons on AlternaƟves A1 and A2, with a preference for A2.
Parking District ImplementaƟon (PL-15003)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $62 $193,000 O ffice of TransportaƟon N/A Recurring
Project Status: This project implements the Bicycle and Pedestrian Transporta Ɵon Plan Update e ffort, which kicked off in fall 2023 and is scheduled to share a dra Ō plan by the end of 2025. This project also includes the implementaƟon of various individual bicycle and pedestrian projects, such as the design and construc Ɵon of bicycle boulevards, enhanced bikeways, shared-paths, bicycle parking, pedestrian improvements, and quick-build implementaƟon of the City’s exis Ɵng 2012 Bicycle and Pedestrian Transporta Ɵon Plan. This proj ect also funds the Embarcadero Road Improvements between Alma and Emerson.
Safe Routes to School (PL-00026)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $144,451 $991,000 O ffice of TransportaƟon N/A Recurring
Project Status: This project enables the City’s Safe Routes to School program, including school commute planning, encouragement ac ƟviƟes, and capital improvements along local and collector streets that may be impacted by school commute ac ƟviƟes. The capital improvements include tra ffic calming devices, enhanced crosswalks, and improved signage along suggested safe routes to school. This project will also support the local match and pre-grant TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 7 of 8
acƟviƟes of the federal “Safe Streets for All”-funded South Palo Alto Bikeways Demonstra Ɵon Project in FY 2026 once sta ff resources are available for project management. The quick-built project will implement bu ffered or protected bike lanes on East Meadow Drive from Alma Street to Fabian Way and on Fabian Way from East Meadow Drive to East Charleston Road.
Traffic Signal and Intelligent TransportaƟon Systems (PL-05030) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $274,768 $672,700 O ffice of TransportaƟon N/A Recurring
Project Status : This project includes design and construc Ɵon of tra ffic signals, tra ffic signal communica Ɵons networks, detecƟon, and data projects for transporta Ɵon use, and maintenance of the City’s tra ffic signal central management system. The project includes the replacement of traffic signal controllers and cabinets, video detecƟon systems, accessible pedestrian bu Ʃons, and related field equipment. Design for tra ffic signal safety and opera Ɵonal improvements at the intersec Ɵon of San Antonio Road and Charle ston Road is nearing 100% comple Ɵon. Sta ff is finalizing the plans and will be preparing bid documents for construc Ɵon to be released in fall 2024, with construcƟon anƟcipated to begin in spring 2025. In 2025, sta ff updated the Centralized Traffic Management system servers to improve opera Ɵonal func Ɵons and system security. The Quarry Road Tra ffic Signal and Intelligent TransportaƟon System upgrade project is currently under construc Ɵon. Sta ff con Ɵnually provide tra ffic signal modificaƟons, installaƟons, provide opera Ɵonal upgrades throughout the City and are developing new tasks on an on-going basis.
TransportaƟon and Parking Improvements (PL-12000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $681,840 $664,100 O ffice of TransportaƟon N/A Recurring
Project Status: This project implements miscellaneous parking and transporta Ɵon related improvements including neighborhood tra ffic calming, neighborhood tra ffic studies, minor striping and signs installa Ɵon, and parking improvements. This project also funds the development of grant proposals used to procure funding for future projects. For the tra ffic calming project in the Crescent Park neighborhood, City Council approved proceeding with the design of permanent improvements in November 2023. Sta ff have procured the services of the consultant to design improvements and conduct community outreach. In addiƟon, staff iniƟated an Engineering and Traffic Survey to select roadway segments to study prevailing speeds and review tra ffic condi Ɵons in order to establish and/or cerƟfy posted speed limits. Staff is also working on the quiet zone project for all railroad crossings along the Caltrain corridor. A quiet zone study was performed for the Palo Alto Avenue and Alma Street crossing in collabora Ɵon with City of Menlo Park in 2022. The design of the required improvements for Quiet Zone at Palo Alto Avenue was completed. The project is currently under construc Ɵon. A Ōer the comple Ɵon of the project, sta ff will send the NoƟce of Intent to implement Quiet Zone to Federal Railroad Administra Ɵo n . I n a d d iƟon, sta ff procured the services of the consultant to conduct a study for evalua Ɵon of quiet zones at the other three crossings of Churchill Avenue, Meadow Drive, and Charleston Road. A Ōer review of the alterna Ɵves, the Rail Commi Ʃee and City Councilselected Four Quadrant Gate Systems for Quiet Zone implementa Ɵon at these crossings in November 2025.
TransportaƟon Projects
Status as of December 2025
TransportaƟon Projects Page 8 of 8
Staff will develop a separate Capitall Improvement Project for the implementa Ɵon phase and seek appropriate funding for design and construc Ɵon of required improvements. The $200K Safe Streets for All (SS4A) Safety Ac Ɵon Plan is funded via this project but will be reimbursed up to $160K by a federal grant. The plan will target elimina Ɵng traffic deaths and life-changing injuries on local streets.
Airport Projects
Status as of December 2025
Airport Projects Page 1 of 2
PROJECT STATS
FY 26 Project Status Pre-Design Design Construction Complete Total One Time Projects 0 5 1 0 6
Recurring Projects 0
ONE-TIME PROJECTS
Airfield Electrical Improvements (AP-19001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $0 $ 532,391 Public Works Design Summer 2031
Project Status: This project is for the design and construction of electrical improvements and installation of LED lighting at the airport runway and taxiway. This project has not received FAA funding and is currently on hold.
Airport Access Road Reconstruction (AP-24000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $0 $4,394,207 Public Works Design Summer 2031
Project Status: This project is for the design and reconstruction of the pavement on Embarcadero Way, which is the main access road for airport businesses and the Air Traffic Control Tower at the Airport. The Airport did not receive FAA funding for this project, and the project is currently on hold.
Airport Layout Plan (AP-21000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,306,851 $ 967,100 Public Works Construction Summer 2027 Project Status: This project provides updates to the Airport Layout Plan, also known as the Long-Range Facilities and Sustainability Plan, including a narrative report and environmental study. The Airport received funding for a Phase I portion of this project in fall 2020. The airport conducted five public meetings for the project, and additional meetings are currently being planned for this project. Phase I is approximately 100% complete and grant has been closed out, and Phase II is approximately 75% complete. This project is currently on hold for CY 2025 to allow airport staff to focus on noise and lead fuel issues. The project will be recommended in CY 2026 with an expected completion date in summer 2027. The FAA granted an extension on this project to accommodate the additional timeline.
Airport Parking Lot Electric Vehicle Charger Installation (AP-24001) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Airport Projects
Status as of December 2025
Airport Projects Page 2 of 2
$0 $28,993 Public Works Design Summer 2031
Project Status: This project will install electric vehicle charging stations in the Airport customer parking lot. The Airport is currently unable to offer electric vehicle charging to its customers, but there is increasing demand for vehicle charging capability from Airport tenants. This project has been delayed as the Airport explores further funding options.
Airport Temporary Office Buildings (AP-22001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $947 $431,005 Public Works Design Summer 2026
Project Status: This project provides funding for the installation and Furniture, Fixtures, & Equipment (FF&E) of existing temporary modular buildings at the Airport to provide adequate office space for airport staff as well as terminal space for the public. The modular buildings were placed on the foundation in fall 2025.
Automated Weather Observation System AWOS (AP-19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $87,309 $2,683,280 Public Works Design Summer 2026
Project Status: This project provides a new weather information system to be installed at the Palo Alto Airport. The Airport has applied for FAA funding and is waiting for the grant agreement to start design. The Airport received a bid for the project and is submitting a grant application to the FAA. The Airport has received funding from the FAA and it is anticipated the project will start in spring 2026.
Electric Fund Projects
Status as of December 2025
Electric Fund Projects Page 1 of 6
PROJECT STATS
FY 26 Project Status Pre-Design Design Construction Complete Total One Time Projects 2 3 6 0 11
Recurring Projects 9
ONE-TIME PROJECTS
115 kV Electric Intertie (EL-06001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $864,219 $1,193,854 Utilities Pre-Design Summer 2027
Project Status: This project provides technical feasibility study to determine the general project requirements to establish a 115 kV electric intertie line and construct a 115/60 kV substation to connect the City's electric system directly to the 115 kV transmission line at an additional receiving station . Initially, staff did not receive California Independent System Operator’s (CAISO) commitment to support this interconnection. Staff have retained the services of a consultant to evaluate the options available to the City. Staff submitted CPAU electric load forecast and proposal for an additional 115 kV transmission line in October 2024 to CAISO for review and acceptance. In May 2025, CAISO approved CPAU’s application for a third transmission line t o the City’s existing receiving station .
Upgrading an existing 4- mile transmission line extension between Palo Alto and Ames in Mountain View will leverage existing right-of-way and vacant tower positions. The estimated cost of the transmission line project ranges between $42M-$84M, will be funded by PG&E , and has an expected in -service date of June 2034. Through PG&E’s pre-construction and design phase, CPAU staff will continue to engage the designated consultant for support with PG&E requests.
Colorado Distribution Feeder Outlet Replacement (EL-22002) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $10,576 $399,998 Utilities Construction Fall 2026
Project Status: T h is p r oje ct is f or t h e ins t alla tion of a n e w electric underground duct bank and cable at Colorado Substation. The installation will improve reliability for all Colorado circuits and increase circuit capacity. The design was completed in spring 2024 and construction will begin spring 2026. C onstruction was delayed due to the procurement of 12 kV pad-mount switches . Council approved the contract in April 2024 and an order for the material was issued and received in July 2025. Other delays were related to the need to coordinate the installation with the fiber hut construction at Colorado station. December 2026 is the expected construction completion date.
Colorado Power Station Equipment Upgrades (EL-19001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Electric Fund Projects
Status as of December 2025
Electric Fund Projects Page 2 of 6
$4,468,548 $10,884,811 Utilities Design Summer 2031
Project Status: This project upgrades equipment at the Colorado Power Substation. In FY 2022 staff completed the evaluation of existing equipment and will proceed with replacing the COP -3 115 kV/60 kV transformer bank and the 115 kV breaker. Engineering is continuing to work on the design for the RFP and construction IFB for contract services to complete the substation projects. The station’s service voltage transformers (SSVT1) were purchased and installed. The 60 kV Bus 1 & 2 Potential Transformers (PT) have been purchased for their eventu al replacement. Due to long lead time of the replacement transformer, completion of this project is not anticipated until FY 2031.
Colorado Substation Site Improvements (EL-19002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $286,233 $1,416,909 Utilities Design May 2028
Project Status: This project will improve the substation driveways and security fence to provide adequate ingress and egress for large utility vehicles and large equipment deliveries . Staff is finalizing a master plan for Colorado Substation to include all proposed improvements. Detailed designs for lighting, driveway, fences, walls, and upgraded oil containment have been prepared. The Planning Department approved the general site plan and fence in May 2024. The solicitation for a construction IFB has been paused to complete the master plan and finish completion of the fiber hut.
Foothills Rebuild (Fire Mitigation) (EL-21001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $11,432,250 $15,102,325 Utilities Construction Spring 2026 Project Status: This project will rebuild approximately 11 miles of overhead line in the Foothills, as necessary to mitigate the risk of utility-caused wildfires. This project converts overhead lines to underground by rerouting to avoid vegetation and improve access for inspections maintenance. Utility Substructure for Phases 1, 2, 3, and 5 are completed. Phase 4 construction has been approved and is currently under construction. The project is expected to be completed by June 2026.
Grid Modernization for Electrification (EL-24000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $14,047,521 $228,689,832 Utilities Construction TBD
Project Status: This project is in s upport of the City’s goal of an 80% carbon emissions reduction by the year 2030.
To meet the 80x30 goal , the electric system must be updated to meet the demands of electrification with older distribution components being replaced to increase system capacity. The Grid -Modernization project includes replacement of distribution and substation transformers, primary/secondary cables and conductors, and upgra ding Palo Alto’s 60kV sub -transmission. In 2025 a pilot area was completed and upgraded electric systems serving just over 900 homes . This project will incorporate and consolidate the scope of work from the following projects into one CIP: Coleridge Cowper Tennyson 4/12kV Conversion (EL -14000), Hopkins Substation 4/12 kV Conversion (EL- Electric Fund Projects
Status as of December 2025
Electric Fund Projects Page 3 of 6
20000), Rebuild Underground District 15 (EL -11003) and Rebuild Underground District 16 (EL -13003). The engineering design for additional distribution grid-modernization, substation upgrades, and transmission reconductors is underway.
Inter-Substation Line Protection Relay (EL-17005)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $371,146 $1,692,895 Utilities Construction Summer 2027
Project Status: This project replaces the existing electromechanical pilot wire relays with new microprocessor line differential protective relay to improve protection for the City’s 60 kV sub-transmission line sections and equipment.
This project is being done in phases, with design and construction happening concurrently on the different phases.
Construction of these improvements relies on work completed by other projects to install fiber optic connections.
Engineering design for segments between the Colorado substation to Adobe Creek substation, Colorado and Hopkins, Park Boulevard substation to Quarry substation, and Maybell substation to Park Boulevard substation are in progress. Staff have completed the testing and verification of a fiber optic transfer switch proof of concept project and are proceeding with replacement of electromechanical relays at COP .
Rebuild Underground District 24 (EL-10006)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,949,767 $2,240,451 Utilities Design Spring 2027
Project Status: This project rebuilds and replaces the underground electric system in Underground District 24, the area bounded by Lytton Avenue; Bryant Street; Forest Avenue; and Alma Street. The engineering design work has been delayed to June 2026, with the expectation that construction will be completed by spring 2027.
Smart Grid Technology Installation (EL-11014)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $ 17,420,618 $18,879,913 Utilities Construction Spring 2026 Project Status: Council approved the Advanced Metering Infrastructure (AMI) with Sensus on October 18, 2021.
The project includes replacement of 30,000 electric meters and retrofitting of 20,800 water and 24,200 gas meters with radio endpoints to transmit meter data to the AMI network. The proof -of-concept phase including AMI network installation, meter testing, and system integration will occur between January 2022 and August 2023. Full deployment is anticipated to run from September 2023 through April 2026.
Colorado Substation Breaker Replacement (EL-17002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,581,171 $7,046,167 Utilities Pre-Design Fall 2033
Project Status: This project will reconstruct the 60kV bus structure and replace high voltage circuit breakers at Colorado Substation. This project is being done in phases, with design and construction happening concurrently and Electric Fund Projects
Status as of December 2025
Electric Fund Projects Page 4 of 6
in conjunction with other planned improvements at the Colorado Substation . Staff are finalizing a master plan for Colorado Substation and then will issue an RFP for the development of construction docu ments. Lead times for materials in related projects (Colorado transformer replacements) will delay this work. Construction is expected to start in FY 2032 and be completed in FY 2033.
Substation Physical Security (EL-16003)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $3,308,562 $7,278,239 Utilities Construction Spring 2028 Project Status: This project installs facilities providing physical protection for nine electric substations from vandalism and intrusion. The installation for the first phase was completed for seven of the nine substations in December 2024. The design and bid package for the second phase and final two substations are in progress. The IFB preparation/solicitation is being paused to coordinate with EL -19002 and will be included in the master plan for Colorado substation. Construction is to be completed by May 2028.
RECURRING PROJECTS
Communications System Improvements (EL-89031)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $11,267 $87,040 Utilities N/A Recurring
Project Status: This project installs high frequency coaxial cable, fiber optic cable, and related equipment to provide communications services for traffic signal coordination, telephone links, computer data transmission, and the Electric Supervisory Control and Data Acquisition (SCADA) system. This project is funding a portion of the design phase of an expanded Utilities fiber optic network. The contract for design of this network was approved by Council in June 2020. Staff installed 48F -FO Cable between Maybell Street and Park Boulevard substations in Existing Aerial Innerduct for pilot wire relay protection.
Electric Customer Connections (EL-89028)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $3,899,318 $2,350,100 Utilities N/A Recurring
Project Status: This project installs electric equipment and substructures in support of new or upgraded electric services, temporary service connections , and overhead and underground line extensions. Projects are in many stages of design and construction to provide temporary and permanent power to residential and commercial Electric Fund Projects
Status as of December 2025
Electric Fund Projects Page 5 of 6
customers in Palo Alto.
Electric System Improvements (EL-98003)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $ 2,057,064 $3,630,860 Utilities N/A Recurring
Project Status: This project consists of various projects that replace deteriorated facilities or install protective devices that improve the Electric Distribution System. Projects are in many stages of development to replace transformers, replace overhead wires and install protective devices to improve service reliability. Due to the focus on Grid-Mod and advancing increased system capacity, limited replacement work has been done under this CIP.
Electric Utility Geographic Information System (EL-02011) Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $46,800 $165,000 Utilities N/A Recurring
Project Status: This project enhances the citywide Geographical Information System (GIS). The project scope includes on-going maintenance/technical support of the existing GIS system and implementation of the new GIS platform, ESRI.
SCADA System Upgrades (EL-02010)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $70,117 $161,030 Utilities N/A Recurring
Project Status: This is an annual recurring project that focuses on upgrades to the Supervisory Control and Data Acquisition (SCADA) system hardware. Staff is working on a replacement project for the Quarry Lane Substation Remote Terminal Unit (RTU) which is at end-of -life. The new RTU f or the Quarry R oad Subst ation is on order and expected to be in service by June 30, 2026. Additionally, staff completed a Disaster Recovery (DR) solution to mirror Master Station at the Utilities Control Center.
Substation Facility Improvements (EL-89044)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $589,249 $993,766 Utilities N/A Recurring
Project Status: This project makes improvements to facilities at CPAU electric substations. Staff has completed the refurbishment of capacitor cans and fuses at Adobe Creek, the procurement and replacement of 12kV Allis- Chalmers circuit breakers at Hansen Way and Hanover Street as well as completed the installation of new Nexus meters at Hansen Way (FY 2023) and Colorado (FY 2021). The design of new Nexus meters at Hansen Way (FY 2021) is in progress. Future projects will include rebuilding the Adobe Creek load tap changer , replacement of 12kV breakers at Maybell, and other miscellaneous preventative replacement of substation equipment.
Electric Fund Projects
Status as of December 2025
Electric Fund Projects Page 6 of 6
Substation Protection Improvements (EL-89038)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $147,751 $261,120 Utilities N/A Recurring
Project Status: This project makes improvements to equipment used at electric substations to protect the substation equipment and circuits. Staff executed a professional service agreement with Soudi Consultants to review and revise protection settings and assist in commissioning updated relay schemes.
Underground System Rebuild (EL-16001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $0 $304,640 Utilities N/A Recurring
Project Status: This project replaces underground electric equipment in areas that were originally installed underground, that are not part of an Underground District. Staff is working to identify areas where the age of the existing cables is a high priority for cable replacement. To date, this includes areas in the Stanford Research Park, Arastradero Road, and along East Bayshore Road. New areas have been identified, and progress has been made on the development of the project. Projects are in many stages of development to replace underground transformers, cables, vaults, and to install protective devices to improve service reliability.
Wood Pole Replacement (EL-19004)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $126,308 $981,760 Utilities N/A Recurring
Project Status: This project funds annual replacement of deteriorated wood utility poles. CPAU staff and contract consultants continuously work to complete pole replacement designs to remove rotted or deteriorated poles from CPAU electric system. Replacement of poles in conjunction with Grid Modernization is the top priority. Early in the current fiscal year, engineering staff identified 30 wood utility poles for replacement. These poles are now in construction and expected to be completed before the end of FY 2026.
Fiber OpƟcs Projects
Status as of December 2025
Fiber OpƟcs Projects Page 1 of 2
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 0 2 0 0 2
Recurring Projects 2
ONE-TIME PROJECTS
Fiber OpƟc Network System Rebuild (FO-16000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $3,733,768 $30,159,107 U ƟliƟes Design December 2030
Project Status: This project is for the System Capacity Improvement that rebuilds por Ɵons of the "dark" fiber opƟc network around Palo Alto. In September 2022, Council approved the City’s fiber expansion plan including construcƟon of a new fiber backbone and a phased buildout of a fiber-to-the-premises network. Sta ff will be designing and construc Ɵng the new fiber backbone in phases based on areas of conges Ɵon, dark fiber customer interest, and strategic opportuni Ɵes for fiber-to-the-premises, with a tenta Ɵve comple Ɵon of the new fiber backbone by December 2030.
Fiber to the Premises (FTTP) (FO-24000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $2,995,192 $ 16,999,998 U ƟliƟes Design Winter 2030
Project Status: This project will build Fiber-to-the-Premises (FTTP) to deliver broadband (high-speed internet) for homes and businesses in the City of Palo Alto under a phased approach without debt financing. One of the primary goals of FTTP is to provide a compe ƟƟvely priced, local, high-speed internet op Ɵon which may reduce prices and enhance customer experience from other available internet service providers. A pilot for the FTTP project was developed in collaboraƟon with the grid mod pilot. Comple Ɵon of fiber construcƟon in the pilot area and ac ƟvaƟon of the fiber hut at the Colorado substa Ɵon is scheduled to be completed by Q1 2026. Palo Alto Fiber internet service should be available to residents in the pilot area by March 2026. Sta ff will return to the U ƟliƟes Advisory Commission and Council with data points, financials, and customer metrics once available from the pilot.
Fiber OpƟcs Projects
Status as of December 2025
Fiber OpƟcs Projects Page 2 of 2
RECURRING PROJECTS
Fiber OpƟcs Customer ConnecƟons (FO-10000)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $123,690 $401,050 U ƟliƟes N/A Recurring
Project Status: This project enables the installaƟon of fiber opƟc infrastructure for new service connecƟons. Projects are developed as needed to meet customer requests for leasing fibers on the Dark Fiber system. There were eighteen new external and internal connec Ɵon inquiries in FY 2025. Sta ff are working on mul Ɵple ac ƟviƟes to promote and add new dark fiber connecƟons such as rate studies, markeƟng, reducing delivery Ɵme, and increasing capacity.
Fiber OpƟcs Network System Improvements (FO-10001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 41,226 $738,705 U ƟliƟes N/A Recurring
Project Status: The original fiber backbone was constructed in mid-1990s. The backbone is reaching the end of its expected life of 30 – 40 years. This project provides maintenance and repair of the exis Ɵng backbone. It also improves reliability and increases capacity within the fiber opƟc network system unƟl a new fiber backbone is built under project FO-16000 Fiber OpƟc Network System Rebuild.
Gas Fund Projects
Status as of December 2025
Gas Fund Projects Page 1 of 3
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 0 2 1 0 3
Recurring Projects 4
ONE-TIME PROJECTS
Gas Line Repair at Arastradero Creek (GS-25001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $442 $1,000,000 U ƟliƟes Design Fall 2032
Project Status: This project is for the design of the Arastradero Creek to address a creek bed erosion project that exposed an 8” natural gas pipeline and threatened the integrity of an 18” potable water pipeline and 10” sanitary sewer pipeline. The project will address requirements outlined by the Water Board in the City emergency work permit to re-bury the exposed 8” gas pipeline. The design and permi ƫng is expected to finish by fall 2026, with gas uƟlity relocaƟon and creek restora Ɵon construcƟon anƟcipated to start in spring 2027, with water and wastewater uƟlity relocaƟon work an Ɵcipated to finish in fall 2029. Creek restora Ɵon monitoring will also be included in this project for a 5-year period following the creek restoraƟon construcƟon.
Gas Main Replacement Project 25 (GS-15000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $170,459 $16,743,848 U ƟliƟes Construc Ɵon Spring 2027
Project Status : This Gas Main Replacement (GMR) project repl aces approximately 26,000 linear feet (which represents 2.3% of the City’s Gas Distribu Ɵon System) of leaking, inadequate sized, and structurally de ficient gas mains and services located on various streets in the neighborhoods of Community Center, Leland Manor, Midtown, and Palo Verde neighborhoods. Staff idenƟfied problemaƟc mains and services by researching maintenance and leak histories, analyzing performance of the en Ɵre Gas Distribu Ɵon System, and considering risk ra Ɵngs of the DistribuƟon Integrity Management Plan. A federal grant applicaƟon was submiƩed in August 2023, and the City was awarded $16.5 million in grant funding for this project. Sta ff completed the Tier 2 Environmental documentaƟon to meet federal grant requirements, and the project has been released to Purchasing for solicita Ɵon. The project is on track for construcƟon to begin in winter 2026.
Gas Main Replacement Project 26 (GS-16000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon Gas Fund Projects
Status as of December 2025
Gas Fund Projects Page 2 of 3
$0 $10,521,691 Public Works Design Summer 2028
Project Status : This project replaces approximately 25,000 linear fe et (which represents 2.0% of the City's Gas DistribuƟon System) of leaking, inadequately sized, and structurally de ficient gas mains and services located on various streets in the Midtown, Palo Verde, Greenmeadow, and Evergreen Park neighborhoods. Sta ff iden Ɵfies problemaƟc mains/services by researching maintenance and leak histories, analyzing performance of the en Ɵre Gas DistribuƟon System and considering risk raƟngs of the DistribuƟon Integrity Management Plan.
RECURRING PROJECTS
Gas DistribuƟon System Improvements (GS-11002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $219,339 $227,950 U ƟliƟes N/A Recurring
Project Status : This project enables Gas Distribu Ɵon System improvements that include increasing distribu Ɵon system capacity for load growth, replacing deteriorated capital facili Ɵes, recon figuring and adding and improving service reliability, and conduc Ɵng research related to performance of the gas distribu Ɵon system or its various components making general improvements to the system. The City must con Ɵnuously evaluate service reliability needs and make improvements to the system to maintain top level service to City customers and to minimize potenƟal economic losses due to service interrup Ɵons. In the first half of FY 2026, City crews completed the replacement of various gas services and valve replacements throughout the system. Addi Ɵonally, two gas pressure monitoring locaƟons were upgraded to fiber.
Gas Equipment and Tools (GS-13002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $52,876 $100,000 U ƟliƟes N/A Recurring
Project Status : This project purchases polyethylene (PE) fusion equipment and tools, direc Ɵonal boring/loca Ɵng equipment and tools, and general shop equipment and tools. The equipment needs to be upgraded on an annual basis to safely operate and maintain a natural gas distribu Ɵon system and to ensure operators’ safety and producƟvity. In the first half of FY 2026, one new push camera reel and monitor were purchased for OperaƟons staff to inspect approximately 980 sewer laterals, prior to releasing to a contractor.
Gas Meters and Regulators (GS-80019)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $218,340 $743,950 U ƟliƟes N/A Recurring
Project Status : This project provides replacement of the exis Ɵng gas meters and regulators annually. The coordinaƟon of gas meters and regulator replacements with gas meters are iden Ɵfied to be replaced under the AMI Gas Fund Projects
Status as of December 2025
Gas Fund Projects Page 3 of 3
contract, which is generally gas meters that are twenty- five years or older. The gas meter replacement program ensures the accuracy of gas consump Ɵon measurement, reduces possible revenue loss due to under-registered gas, and provides customers with accurate monthly bills. Replacement of aged gas meters and regulators is on-going.
The next major replacement of meters and regulators will be coordinated with Gas Main Replacement Project 25 (GS-15000) and the Advanced Metering Infrastructure project.
Gas System, Customer ConnecƟons (GS-80017)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $689,561 $319,130 U ƟliƟes N/A Recurring
Project Status : This project enables the Gas Distribu Ɵo n S y s t e m t o b e e x t e n d e d t o p r o v i d e g a s s e r v i c e s t o n e w customers and augment service to customers with increased natural gas demands. Improvements include new mains, services, valves, regulators, meters, and accessories to meet changes in exis Ɵng customer service demands and respond to changes in gas service requirements due to new development or redevelopment. This project is funded par Ɵally from reimbursements by customers. City cr ews completed thirty-three gas service installa Ɵons, eleven gas service repair/relocaƟons and seventy-four gas service demoliƟons in the first half of FY 2026.
Stormwater Management Fund Projects
Status as of December 2025
Stormwater Management Fund Projects Page 1 of 3
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 1 0 4 0 5
Recurring Projects 2
ONE-TIME PROJECTS
Center Drive Capacity Upgrades (SD-26001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $2,415,000 Public Works Pre-Design Fall 2027
Project Status: This project will remove and replace approximately 1,710 linear feet of the exisƟng storm drainpipes of various sizes (12 and 15 inches) with new 36-inch high-density polyethylene storm drainpipes, and add approximately 330 linear feet of new pipe from Hamilton Avenue to Channing Drive to increase the storm drain capacity. The pipes will conƟnue to drain to Channing Drive, but this project will provide over flow to the Hamilton Avenue system. The project also includes replacing concrete inlets, manholes, and storm drain laterals, and reloca Ɵng other u Ɵlity laterals due to the pipe size changes. The survey data required was obtained in fall 2025. The project design will be done in 2026.
CorporaƟon Way System Upgrades and Pump StaƟon (SD-21000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $414,051 $4,146,554 Public Works Construc Ɵon Summer 2026 Project Status: This project incorporates a design of a new small pump staƟon with a 25 cubic feet per second capacity and upgrades 700 linear feet of pipe to 30-inch diameter High Density Polyethylene pipe. The exisƟng system does not have the force needed to discharge storm flows into the Adobe Creek. Adding a pump sta Ɵon in advance of the ou ƞall and upsizing the storm pipe will eliminate the rou Ɵne flooding along East Bayshore Road and convey runoff from a 10- year storm event. Sta ff secured an easement for the pump sta Ɵon from adjacent property owners. The consultant completed the design of the project in June 2024. The construc Ɵon contract was awarded in spring 2025 and construcƟon started in June 2025. Work is on track to be completed by the end of fall 2026.
Hamilton Avenue System Upgrades (SD-25000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 235,132 $7,714,973 Public Works Construc Ɵon Fall 2026 Stormwater Management Fund Projects
Status as of December 2025
Stormwater Management Fund Projects Page 2 of 3
Project Status: This project adds approximately 3,700 linear feet of new 48-inch high-density polyethylene (HDPE) pipe and manholes on Hamilton Avenue to increase the capacity of the storm drain system. This project upsizes the storm drainpipes on Hamilton Avenue between Center Drive and Rhodes Drive and discharges runo ff into the 96-inch line located at the intersec Ɵon of Hamilton Avenue and Rhodes Drive. In addi Ɵon, the project will add new infrastructure on the 1500 block Hamilton Avenue to capture runo ff that would have other drained into the storm drain system under Channing Avenue. The IFB documents were completed duri ng the second half of FY 2025. The project went out to bid in August 2025, and a construc Ɵon contract was awarded in October 2025. Construc Ɵon starts January 2026 and is scheduled to be completed by November 2026.
West Bayshore Road Pump StaƟon (SD-20000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $474,138 $4,177,865 Public Works Construc Ɵon Summer 2026 Project Status: This project incorporates the design and construc Ɵon of a new small pump sta Ɵon with 15 cubic feet per second capacity. Installing a new pump sta Ɵon will allow storm flows to be pumped into the Adobe Barron Creek confluence while adding a pump sta Ɵon in advance of the ou ƞall would eliminate the rou Ɵne flooding along West Bayshore Road and allow the system to convey runo ff from a 10-year storm event. Sta ff secured an easement for the pump staƟon from adjacent property owners. The consultant co mpleted the design of the project in June 2024. The construcƟon contract was awarded in spring 2025 and construc Ɵon started in June 2025. Work is on track to be completed by the end of fall 2026.
West Bayshore Road Trunk Line Improvements (SD-23000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $75,930 $4,924,529 Public Works Construc Ɵon Summer 2026 Project Status: This project replaces approx imately 1,400 linear feet of exis Ɵng 15-inch diameter pipe with 36-inch High Density Polyethylene pipe. These improvements along with the new West Bayshore Road Pump Sta Ɵon (SD- 20000) will eliminate the rouƟne flooding along West Bayshore Road and allow the system to convey runoff from a 10- year storm event. Sta ff secured an easement for the pump sta Ɵon from adjacent property owners. The consultant completed the design of the project in June 2024. The construc Ɵon contract was awarded in spring 2025 and construcƟon started in June 2025. Work is on track to be completed by the end of fall 2026.
RECURRING PROJECTS
Green Stormwater Infrastructure (SD-22001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $63,722 $1,239,330 Public Works N/A Recurring
Project Status: This project implements Green Stormwater Infrastructure (GSI) and the integraƟon of GSI features in Stormwater Management Fund Projects
Status as of December 2025
Stormwater Management Fund Projects Page 3 of 3
the design and implementa Ɵon of planned CIP projects supported by other funds. GSI mimics the natural environment to slow, spread, in filtrate, and filter pollutants from stormwater runo ff through na Ɵve or engineered soils or other pervious material rather than discharging it directly into the storm drain system, creeks, and the SF Bay. Types of GSI include bioreten Ɵon areas, flow-through planters, tree wells, and pervious pavement to manage stormwater runoff. The City released a request for proposals in Ju ne 2025 to develop a GSI design for the proposed locaƟon at Juana Briones Park. The City anƟcipates entering a contract in January 2026.
Storm Drainage System Replacement and RehabilitaƟon (SD-06101) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $351,102 $1,783,015 Public Works N/A Recurring
Project Status: This project provides for annual replacement and rehabilitaƟon to maintain the integrity of the storm drain system, including deteriorated storm drain piping, manholes, and storm drain inlets. The rehabilita Ɵon includes replacement of broken corrugated metal pipe with High Density Polyethylene pipe. As a result of the December 31, 2022, flood event, the exis Ɵng 12-inch line on Alester Avenue is proposed to be upsized to 36-inch pipe for addiƟonal storage capacity as part of CIP SD-25000. In 202 5, this work was part of Hamilton Avenue System Upgrades project (SD-25000) bid solicita Ɵon. The lowest bidder’s fee for the Alester Avenue improvements was significantly higher than the engineer’s esƟmate and several of the other bids received. As a result, staff decided not to advance the project with the Hamilton Avenue Capacity Upgrade project. Construc Ɵon bids will be solicited for this separately in second half of FY 2026.
Wastewater CollecƟon Projects
Status as of December 2025
Wastewater CollecƟon Projects Page 1 of 2
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 0 1 1 0 2
Recurring Projects 4
ONE-TIME PROJECTS
Closed Circuit Television (CCTV) Sewer Main InspecƟon (WC-26001) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $1,856,506 U ƟliƟes Design Fall 2030
Project Status: This project provides for the Closed-Circuit Television (CCTV) Sewer Main Inspec Ɵon to idenƟfy pipe stretches in need of rehabilita Ɵon/replacement. The project, together with results of the 2025 Sewer Master Plan, will help priori Ɵze capital improvement projects and pipe stretch spot repairs to cost-e ffecƟvely op Ɵmize sewer rehabilitaƟon to renew sewer main assets and mi Ɵgate the poten Ɵal for sanitary sewer over flows. Project is anƟcipated to go out to bid February 2026.
Wastewater CollecƟon System RehabilitaƟon AugmentaƟon Project 32 (WC-20000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $13,797,052 U ƟliƟes Construc Ɵon Summer 2028
Project Status : This project designs and constructs high priori ty main and lateral replacements, which reduces inflow of rainfall and in filtraƟon of groundwater into the collec Ɵon system. The project will replace approximately 26,400 linear feet (which represents 2 percent of the City’s Wastewater Collec Ɵon System) The project will be comprised of laterals idenƟfied in video inspecƟon work or through maintenance records as deficient and in need of replacement. Priority will be given to areas iden Ɵfied by Public Works as targeted work zones ensuring coordinaƟon between departments. WGW is in the process of priori Ɵzing CIP projects and will update the exact loca Ɵons on the June 2026 CIP update report.
RECURRING PROJECTS
Sewer Lateral/Manhole RehabilitaƟon and Replacement (WC-99013) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $218,890 $340,540 U ƟliƟes N/A Recurring
Wastewater CollecƟon Projects
Status as of December 2025
Wastewater CollecƟon Projects Page 2 of 2
Project Status: This project replaces defec Ɵve sewer laterals and cleanouts, to support improved maintenance of the Wastewater Collec Ɵon System. Informa Ɵon collected during rou Ɵne annual maintenance ac ƟviƟes is used to prioriƟze sewer lateral replacement work. The results of this work will reduce maintenance Ɵme, decrease sewage lateral blockages and reduce in flow and in filtraƟon into the collec Ɵon and treatment system. In addi Ɵon to third party construc Ɵon, the City also replaces sewer laterals. In the first half of FY 2026, twelve sewer lateral replacements were completed by City staff.
Sewer System, Customer ConnecƟons (WC-80020)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $494,236 $120,270 U ƟliƟes N/A Recurring
Project Status: This project installs sewer lateral connec Ɵons and addi Ɵons or extensions of exis Ɵng mains to serve new customers and to respond to changes in sewer requi rements due to redevelopment or new development. Old exisƟng non-plas Ɵc sewer laterals with condi Ɵon de ficiencies per U ƟliƟes Opera Ɵons’ criteria are required to be replaced in accordance with the latest 2024 WGW Standards. In the first half of FY 2026, six new lateral connecƟons were installed.
Wastewater General Equipment and Tools (WC-13002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $25,672 $13,360 U ƟliƟes N/A Recurring
Project Status: This project will procure new general equipment and new tools. In the first half of FY 2026, Lodge Foothills LiŌ StaƟon No. 1 pump #2 was replaced and the portable generator was purchased. In the first half of FY 2026, one cross bore inspecƟon camera and two monitors were procured.
Wastewater System Improvements (WC-15002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $329,607 $53,450 U ƟliƟes N/A Recurring
Project Status: This project implements improvements to the Wastewater Collec Ɵon System by increasing system capacity for growth, flow monitoring, hydraulic modeling and system analysis, load simula Ɵons, asset management analysis and assessment, system in filtraƟon analysis and sanitary sewer over flow monitoring and reduc Ɵon. Part of this project funds the Sewer Master Plan Study, which is evaluaƟng the City’s exisƟng wastewater collecƟon system, flows, and flow pa Ʃerns to determine system capacity to meet current and future flows and recommend and prioriƟze capital improvement projects where needed. The consultant contract was approved in November 2023 and work began in December 2023. The project completed calibraƟng the collecƟon system model in fall 2024 and is beginning to run the model to quan Ɵfy exis Ɵng system flows and buildout system flows. Project comple Ɵon is anƟcipated in January 2026.
Wastewater Treatment Fund Projects
Status as of December 2025
Wastewater Treatment Fund Projects Page 1 of 4
PROJECT STATS
FY 26 Project Status Pre-Design Design Construction Complete Total One Time Projects 1 2 4 0 7
Recurring Projects 2
ONE-TIME PROJECTS
Local Advanced Water PurificaƟon System (WQ-19003)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $2,737,035 $67,138,041 Public Works Construc Ɵon Winter 2027 Project Status: This project enables the design and construcƟon of an Advanced Water PurificaƟon Facility to further improve the quality of the ter Ɵary-treated recycled water by ultra filtraƟon followed by reverse osmosis to reduce the level of total dissolved solids. The water reuse part nership agreement with Valley Water and Mountain View provides $16 million in funding from Valley Water grant funding for a por Ɵon of the project costs and a state low- interest loan for the design and construc Ɵon phases. Mountain View pays the remainder of the capital costs associated with this project. Staff executed construcƟon contracts and financial agreements with funding agencies in spring 2025. Construc Ɵon began in summer of 2025. Two major milestones were completed in 2025: a new sewer line on Embarcadero Road and a new odor control system were installed to demolish a former soil bed filter and sewer line. With both items completed, the team plans to finish grading and start installa Ɵon of piles for the main system structure in spring 2026.
Headworks Facility Replacement (WQ-16002)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,210,336 $104,779,656 Public Works Pre-Design Fall 2033 Project Status: This project replaces the exis Ɵng two outdated in fluent pump sta Ɵons and their associated equipment and ancillary systems, including the suc Ɵon and discharge piping manifolds, valves, electrical and controls system, screening equipment, grit handling equipment, pumps, electrical load center and generators, flow meters and yard piping. The consultant is currently performing the advanced planning, anƟcipated to be complete in spring 2026,to finalize the design criteria. At the advanced planning conclusion, either the same or a di fferent consultant will be selected to perform detailed design.
Horizontal Levee Pilot (WQ-22001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $231,263 $887,445 Public Works Construc Ɵon Winter 2026 Wastewater Treatment Fund Projects
Status as of December 2025
Wastewater Treatment Fund Projects Page 2 of 4
Project Status: This project consists of the design, permi ƫng, and construc Ɵon of a horizontal levee pilot system.
The system will u Ɵlize treated wastewater to create a transi Ɵonal brackish habitat on the Bayside of a future flood control levee located in the Palo Alto Baylands, adjacent to the Regional Water Quality Control Plant (RWQCP).
InformaƟon and data collected by this pilot system could support broader implementa Ɵon of horizontal levees as green infrastructure components in larger flood control levee improvement projects within Palo Alto and beyond.
The project completed design, CEQA review, Commission and stakeholder outreach events, created a project webpage, obtained all construcƟon permits from resource agencies, received a recommendaƟon from the Parks and RecreaƟon Commission, and obtained Council approval of the Park Improvement Ordinance as well as a CooperaƟve Agreement between project partners. The project started construc Ɵon in September 2025 and is currently working on installing the pipeline and in-plant connec Ɵons. The project team con Ɵnues to prepare for required monitoring and coordinate future community engagement acƟviƟes including BioBlitz and King Tide Walks.
Joint IntercepƟng Sewer RehabilitaƟon (WQ-24000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $4,116,738 $13,290,181 Public Works Construc Ɵon Winter 2026 Project Status: This project will rehabilitate 2,364 line ar feet of the 72-inch Joint Intercep Ɵng Sewer (JIS) trunk line leading to the Regional Water Quality Control Plant (RWQCP). The en Ɵre trunk sewer line, constructed in 1972, is approximately 9,000 feet long consis Ɵng of thirteen manholes and three junc Ɵon structures. The JIS conveys raw wastewater mainly from the City of Mountain View, City of Los Altos, Los Altos Hills, and a por Ɵon of Palo Alto, which accounts for more than half of the RWQCP’s in fluent flows. A construc Ɵon contract was awarded, and work began in winter 2024 but faced delays due to unforeseen condi Ɵons and contractor challenges. Construc Ɵon resumed in the 2025 dry season. While the ma jor trunk lining work is complete, addi Ɵonal efforts were needed to isolate, assess, and repair a cri Ɵcal junc Ɵon box structure, requiring addi Ɵonal temporary bypass rerou Ɵng.
ConstrucƟon is anƟcipated to be complete by early 2026.
New Laboratory and Environmental Services Building (WQ-14002) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $484,611 $ 16,913,439 Public Works Design Fall 2031
Project Status: The original plan to construct a new laboratory and o ffice building at the Regional Water Quality Control Plant (RWQCP) has been replaced with a lease-based solu Ɵon. This change reflects a broader shiŌ toward a campus-wide faciliƟes strategy, which emphasizes flexibility by leasing and poten Ɵally acquiring nearby proper Ɵes to meet evolving space needs at the RWQCP . The reloca Ɵon will also free up cri Ɵcal space on-site for construc Ɵon staging and future capital projects. In 2025, Ci ty Council approved a 20-year lease for a 13,946 sq. Ō. building at 2470 Embarcadero Way, located directly across from the RWQCP . This building will house the Laboratory and Engineering Groups and includes $6.0 million in tenant improvements funded by this capital project. Sta ff are currently working with an architect to complete the design of the tenant improvements by spring 2026.
ConstrucƟon of the tenant improvements is an Ɵcipated to be completed by end of 2026. Sta ff conƟnue to evaluate opƟons for potenƟally acquiring nearby properƟes to meet long-term workspace planning needs.
Wastewater Treatment Fund Projects
Status as of December 2025
Wastewater Treatment Fund Projects Page 3 of 4
Ouƞall Line ConstrucƟon (WQ-19000)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $17,850,665 Public Works Design Summer 2027
Project Status: This project consists of the construc Ɵon of a new parallel ou ƞall pipe to convey final plant effluent to San Francisco Bay. A re-design of the pipeline is needed to accommodate a poten Ɵally future runway shiŌ at Palo Alto Airport. Sta ff is currently working with the Airport sta ff and Federal Avia Ɵon AdministraƟon (F AA) to gain F AA concurrence for the pipeline construc Ɵon and permanent easements on Airport property. The re-design is anƟcipated to begin in 2026, moving immediately to construcƟon upon design compleƟon.
Secondary Treatment Upgrades (WQ-19001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $120,079,017 $193,322,308 Public Works Construc Ɵon Summer 2028 Project Status: This project upgrades the Secondary Treatment process at the RWQCP . The exis Ɵng Secondary Treatment process has two main components, the Fixed Film Reactors (FFR) and the Ac Ɵvated Sludge (AS) Process.
This project includes the reconstruc Ɵon of the AS process, rehabilita Ɵon and recon figuraƟon of the AS Aera Ɵon Basins, the eliminaƟon of the FFRs, addiƟon of denitrificaƟon capabiliƟes, and replacement of equipment beyond its useful life. ConstrucƟon began in winter 2023 with the comple Ɵon of the new nitri ficaƟon/denitrificaƟon treatment process, and reƟrement of the FFR’s is expected in summer 2028. Construc Ɵon is s Ɵll in progress with much of the underground support infrastructure in place. ReconfiguraƟon of AeraƟon Basin #4 was completed and is in service.
AeraƟon Basin #3 construcƟon was completed in fall 2025 and placed into service in winter 2026.
RECURRING PROJECTS
Plant Master Plan (WQ-10001)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $441,487 $440,000 Public Works N/A Recurring
Project Status: This project enables the ongoing program management support for major capital projects. Current tasks include developing scopes of work, evalua Ɵng consultant proposals, coordina Ɵng project management acƟviƟes, pursuing State low-interest loans for mul Ɵple projects, and upda Ɵng partner agreements. The consultant provides support for the projects associated with the Long-Range FaciliƟes Plan (LRFP) update.
Plant Repair, Retrofit and Equipment Replacement (WQ-19002) Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $2,450,678 $7,949,200 Public Works N/A Recurring
Wastewater Treatment Fund Projects
Status as of December 2025
Wastewater Treatment Fund Projects Page 4 of 4
Project Status : This project enables the assessment, repair, and retro fit of the RWQCP’s concrete and metal structures; the replacement of necessary equipment and ancillary facili Ɵes, including electrical equipment/systems, to maintain treatment reliability and exisƟng infrastructure; and the replacement of large diameter flow meters built into the wastewater treatment system on sewers, pipes, and water lines. A construc Ɵon contract for Phase 1 of the 12-KV Electrical Loop Upgrade Project was executed in winter 2023 and completed in spring 2025. A construc Ɵon contract for Phase 2 of the 12-kV Electrical Loop Upgrade Project was executed in fall 2024 and is scheduled to be completed by fall 2026. The project also supports the Long-Range Facili Ɵes Plan Update, including upda Ɵng the Biosolids Facility Plan and evaluaƟng cost of service allocaƟon methodologies.
Water Fund Projects
Status as of December 2025
Water Fund Projects Page 1 of 4
PROJECT STATS
FY 26 Project Status Pre-Design Design Construc Ɵon Complete Total One Time Projects 0 2 1 0 3
Recurring Projects 7
ONE-TIME PROJECTS
Water Main Replacement Project 30 (WS-16001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $5,371 $4,470,560 U ƟliƟes Design Summer 2027
Project Status: This project replaces structurally deficient water mains and appurtenances in Fiscal Year 2027. Mains are selected by researching the maintenance history of the system and iden Ɵfying those that are undersized, corroded, and subject to breaks. The project scope includes approximately 2,589 linear feet (which represents 0.2 percent of the City’s Water DistribuƟon System) of mains and services on va rious streets within the City, including areas in Duveneck/St. Francis and Evergreen Park neighborhoods.
Water Main Replacement Project 31 (WS-19001)
Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $6,641,796 U ƟliƟes Design Spring 2028
Project Status: This project replaces structurally deficient water mains and appurtenances in Fiscal Year 2028. Mains are selected by researching the maintenance history of the system and iden Ɵfying those that are undersized, corroded, and subject to breaks. The project scope includes approximately 8,000 linear feet (which represents 0.6 percent of the City's Water DistribuƟon System) of mains and services on various streets within the City.
Water Tank Seismic Upgrade and RehabilitaƟon (WS-09000) Prior Years Actuals Total Project Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $9,952,452 $29,099,691 U ƟliƟes Construc Ɵon Fall 2031
Project Status: This project is for Seismic Water System Upgrades and RehabilitaƟon of drinking water storage tanks.
The project includes rehabilitaƟon and seismic upgrades at the Montebello, May field, Corte Madera, Park, Boronda, and Dahl Reservoirs. Mayfield Reservoir was seismically retrofiƩed in 2011, and rehabilita Ɵon and seismic upgrades of Boronda and Montebello Reservoirs were completed in 2016 and 2018, respec Ɵvely. The new concrete Corte Water Fund Projects
Status as of December 2025
Water Fund Projects Page 2 of 4
Madera Reservoir was completed in April 2022. The Park Re servoir and Dahl Reservoir Tanks are scheduled next for retrofit or replacement. An Engineering condi Ɵon assessment of Park Reservoir was completed in spring 2023, and Dahl Reservoir will be assessed in 2026.
RECURRING PROJECTS
Water DistribuƟon System Improvements (WS-11003)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $154,920 $288,120 U ƟliƟes N/A Recurring
Project Status: This project enables improvements to water distribu Ɵon system deliverability and reliability. Typical acƟviƟes include installing restraining joints at cri Ɵcal pipelines and bridge crossings, increasing the size of inadequate facili Ɵes, system leakage surveys, network modeling, and fire flow studies or other system improvements as required. ConƟnuous evaluaƟon of system needs and making required improvements is necessary to maintain adequate quanƟƟes of quality water, meeƟng local, state, and federal safe drinking water standards. The Pump Sta Ɵon Pain Ɵng project to paint the five foothill pump sta Ɵons was completed in May 2024. A three-year services contract for an annual full system leakage survey of the water distribuƟon system was solicited in 2025, and the first year of full system leak survey is expected to be completed by 2026.
Water, Gas, Wastewater UƟlity GIS Data (WS-02014)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $ 519,095 $499,160 U ƟliƟes N/A Recurring
Project Status: This project enables contracts related to U ƟliƟes GIS (Geographic Informa Ɵon System) needs. AME database is heavily u Ɵlized by U ƟliƟes Engineering sta ff to update the u Ɵlity informa Ɵon in GIS. The updated informaƟo n i s u s e d b y v a r i o u s C i t y s t aff, such as marking/loca Ɵng underground u ƟliƟe s t o c o m p l y w i t h U S A (Underground Service Alert) requirements; developing design drawings for pipeline replacement projects; verifying exisƟng underground u ƟliƟes during construc Ɵon ac ƟviƟes; crea Ɵng customized u Ɵlity map books for field crews and on-call personnel to meet their speci fic needs. Annual surveying contracts collect GPS points of exis Ɵng above- ground uƟlity features within CIP project areas. The data being collected con Ɵnues to be used to correct the GIS database. Accurate uƟlity data helps the design to select new pipe alignment to minimize construc Ɵon conflicts and provides data for addi Ɵonal road feature linework to be corrected in the older GIS/AVEC database via ESRI. A migraƟon from AME to ArcGIS is planned as the primary pla ƞorm for maintaining and upda Ɵng GIS data, with work scheduled to begin in February 2026 and conƟnue through December 2026.
Water Fund Projects
Status as of December 2025
Water Fund Projects Page 3 of 4
Water General Equipment Tools (WS-13002)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $0 $46,300 U ƟliƟes N/A Recurring
Project Status: This project acquires new equipment and tools, the replacement of exis Ɵng fusion equipment, and other associated tools. The fusion equipment is used to fuse together pipe joints in the City's water distribu Ɵon system. Equipment and tools are required to be upgraded on an annual basis to maintain high quality standards for the installaƟon of the City's water distribu Ɵon mains, along with the associated service standards and worker safety and produc Ɵvity measures. New equipment purchases made in the 1 st half of FY 2026 include a new clamp-on ultrasonic flow meter, portable transient pressure monitoring device, and a water service tapping machine.
Water Meters (WS-80015)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $220,617 $314,090 U ƟliƟes N/A Recurring
Project Status: This project enables the purchasing of meters for new customers, upgrading meters for current customers, installing meter bypasses, and replacing obsolete meters that are no longer repairable. This funding also allows for annual tes Ɵng and calibra Ɵon of selected meters to maintain meter accuracy and reliability. During the AMI implementaƟon process, approximately 90% of the meters will be replaced with a focus on meters more than twenty years old. Staff conƟnue to test addiƟonal larger diameter meters.
Water Service and Hydrant Replacement (WS-80014)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $207,973 $389,050 U ƟliƟes N/A Recurring
Project Status: This project replaces system control valves, deteriorated galvanized service lines, lead goosenecks, and fire hydrant valves and assemblies per the Fire Department’s flow tesƟng, upgrades fire hydrants in main line replacement project areas, replaces damaged fire hydrants, and replaces exisƟng undersized or deteriorated copper water services on an as needed basis.
Water System Customer ConnecƟons (WS-80013)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $1,373,706. $907,480 U ƟliƟes N/A Recurring
Project Status: This project allows for improvements that include new main extensions, valves, domes Ɵc services, meters on upgraded services, back flow devices, fire services, and fire hydrants. System extensions are required to provide service to new large developments and to serve exis Ɵng customers reques Ɵng expanded service on Development Services projects. A total of 66 water services were installed in the second half of FY 2025.
Water Fund Projects
Status as of December 2025
Water Fund Projects Page 4 of 4
Water System Supply Improvements (WS-11004)
Prior Year Actuals Current Year Budget Implemen Ɵng Department Project Phase Project Comple Ɵon $743,603 $3,643,622 U ƟliƟes N/A Recurring
Project Status: This project evaluates and improves the City’s water distribuƟon system on an as-needed basis. This project includes piping modi ficaƟons, equipment replacements associated with water delivery, supervisory control soŌware upgrades, system modi ficaƟons for water system quality compliance, condi Ɵonal assessment of the reliability of transmission mains, and security system installa Ɵons. The water system includes the connec Ɵon faciliƟes between the City’s and the San Francisco Public UƟlity Commission’s pipelines, water wells within the City’s pumping staƟons, water reservoirs, and pipelines.