NA 19801 Agenda Report
JUNE
September 19, 2022
TO: Honorable Mayor and City Council
FROM: City Manager's Office
SUBJECT: PLANNING PROCESS FOR THE RELINQUISHED 710 PROPERTY RECOMMENDATION:
This is for information only. No action is requested at this time.
BACKGROUND:
This report supplements the report provided for the City Council's information on August 15, 2022 (Attachment A) and provides additional information regarding the planning process for the land that was relinquished by the California Transportation Commission on June 29 of this year.
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION
IN THE CITY OF PASADENA
FROM COLUMBIA STREET TO UNION STREET
PASADENA
KTE 110: FAY
PASADENA
PROPOSED RELINGUISHMENT
09/19/2022 17
MEETING OF AGENDA ITEM NO.
Planning Process for the Former 710
September 19, 2022
As indicated in the previous report, the process will involve a robust outreach process and is anticipated to span 3 years to develop the City's vision for the area and several more before any development would occur. The process will be led by the City Manager's Office and will involve input from the public, Council Task Force(s), Commissions and a variety of City Departments.
PHASED APPROACH TO PROJECT DEVELOPMENT
The planning process will require a phased approach to achieve the goal of a new Specific Plan or Master Plan document to guide any future development of the area.
The RFP may be developed to include each of the phases collectively or individually to provide maximum flexibility in securing the best team of consultants for the City.
Phase 1: Technical Feasibility Study
Key Considerations
• Can the ditch be filled in?
• How can the cost of infrastructure be funded?
• Can the project generate revenue to enhance City services such as providing dedicated funding for affordable housing?
Phase 2: Vision Plan
Develop Goals and Polices
• Establish a new network of streets, blocks, and green space to reconnect the disconnected sides of the city;
• Ensure that future development is sensitive to the surrounding context (scale, mass, form)
• Ensure that future development results in benefits for the greater Pasadena Community
Phase 3: Specific Plan and EIFD/Infrastructure Plan
Create New Development Standards and Financing Plan
• Development of a Form-Based Specific Plan to implement the Vision plan • Development of Enhanced Infrastructure Financing District Multi-Phase, Multi-Year. As indicated below, we are at the infancy of a process that will involve a multi-year planning effort. Subsequent to the planning and visioning exercises, it will likely take several years to complete required infrastructure for the area, followed securing the necessary planning entitlements and construction permits.
This would then be followed by several more years to actually construct a project. It would not be unreasonable to assume that we will not see any development in this area in the next 10 years. The below illustrates the steps and timing for each phase.
Planning Process for the Former 710
September 19, 2022
PHASE 1 -
FEASIBILITY ANALYSIS Start: Spring 2023
Duration: Approximately 9-12 months
PHASE 2- Start: Spring 2024
VISION PLAN Duration: Approximately 9-12 months
• PHASE 3 - Start: Spring 2025
SPECIFIC Duration: Approximately 12-18 months
PLAN/INFRASTRUCTURE
*Future development may be 8-10 years away
NEXT STEPS:
CITY COUNCIL TASK FORCE: Staff will bring forward a separate report providing options that the Council may wish to consider to establish a Task Force(s). Given the unique opportunities that this project presents, it may be desirable to establish separate task forces to address: infrastructure/feasibility; land use/planning; and the work related to the displaced communities.
FISCAL IMPACT:
This item is for information purposes only. There is no fiscal impact associated with this report.