Department of Public Works

CENTRAL LIBRARY SEISMIC RETROFIT & RENOVATIONS

PROJECT UPDATE

MUNICIPAL SERVICES COMMITTEE
March 25, 2025
Item #3
Department of Public Works
Presentation Overview
• Project Background
• Construction Manager at-Risk (CMAR) Alternative
Project Delivery Method
• Request for Proposals (RFP) for CMAR
> Phase 1 – Preconstruction/Constructability Services
> Guaranteed Maximum Price
• Next Steps and Overall Schedule
2 Department of Public Works
Project Background
3 • November 2024 – Pasadena voters
approved $195M bond measure
(Measure PL) to fund the construction
phase
• February 3, 2025 – City Council
authorized use of Construction
Manager at- Risk project delivery
method
• March 12, 2025 – Met with outside
council and the project architect
• March 13, 2025 – Met with the
Technical Oversight Committee

Department of Public Works
Construction Manager at-Risk (CMAR)
Alternative Project Delivery Method
4 • CMAR involves the award of multiple contracts
> Architectural and engineering design services
> Construction manager / Licensed general contractor (CM/GC) • Two-phase CM/GC contract
> Qualifications-based selection
> Phase 1 – Constructability and value engineering services throughout the design and pre-construction phases. Includes scope for necessary demo and storage of historical finishes > Phase 2 – Guaranteed Maximum Price (GMP) and construction.

Department of Public Works
CMAR Phase 1
5 Phase 1 – Preconstruction/
Constructability Services
• Collaboration with City representatives,
architects/engineers, and consultants;
• Creation of the construction schedule;
• Site and building condition investigation;
• Constructability
reviews and recommendations;
• Identify risks and propose mitigation
measures;
• Value engineering and budget
recommendations;
• Work plan development – GMP contract
terms;
• Subcontractor procurement strategies;
• Develop a procurement schedule;
• Verification of required permits
and entitlements

Department of Public Works
CMAR Phase 1
6 Phase 1 – Preconstruction/
Constructability Services
(continued)
• Hazardous materials abatement;
• Demolition of existing mechanical,
electrical, and plumbing systems;
• Completion of a Historic American
Buildings Survey (HABS);
• Removal, cataloging, and storing of
historic finishes such as millwork that will be
reinstalled during Phase 2; and
• Preparation of GMP package for Phase 2.

Department of Public Works
CMAR Phase 2
7 City options after receipt of
GMP
• Accept the GMP and amend the
CM/GC contract to authorize Phase 2;
• Continue negotiating the terms and
price of the GMP;
• Have the Architect or Engineer and
CM/GC adjust the design or schedule to
reduce the GMP;
• Terminate the agreement and begin
negotiation with the next highest-ranked
proposer; or
• Terminate the agreement and proceed
with a traditional design-bid-build
project delivery method.

Department of Public Works
Next Steps
8 • Tentative schedule for solicitation and contracting of CM/GC entity
> RFP Advertisement Date: April 9, 2025
> Mandatory Pre-Proposal Meeting: April 23, 2025
> Proposal Deadline: May 29, 2025
> Interviews with Top Proposers: June 16 – 20, 2025
> Contract Award: July 14, 2025
Department of Public Works
Overall Project Schedule
9 Department of Public Works
10 For more information about the
Central Library Seismic Retrofit and Renovations Project refer to:
https://www.cityofpasadena.net/library/