Agenda Report
TO:

FROM:

SUBJECT:

July 20, 2026
hlonorable Mayor and City Council
Depari:ment of Water and Power

AUTHORIZE THE CITY MANAGER TO ENTER INTO A CONTRACT
WITH OPCONNECT, INC. FOR THE FURNISHING AND DELIVERY OF

DIRECT CURRENT FAST CHARGING EQUIPMENT FOR THE

MAINTENANCE YARDS ELECTRIC VEHICLE CHARGER EXPANSION
PROJECT FOR AN AMOUNT NOT TO EXCEED $282,744
RECOMMENDATION:

It is recommended that the City Council:

1. Find that the project is categorically exempt from the California Environmental Quality Act ("CEQA") pursuant to State CEQA Guidelines Article 19, Class 1, Section 15301, Existing Facilities, and that there are no features that distinguish the project from others in the exempt class and, therefore, there are no unusual circumstances; and

2. Award a contract to the lowest and best bid dated April 23, 2026, submitted by OpConnect, Inc. ("OpConnect") in response to the specifications for the Direct Current Fast Charging ("DCFC") Equipment, and authorize the City Manager to enter into a one-year contract for an amount not-to-exceed $282,744, which includes the base contract amount of $257,040 and a contingency of $25,704 to provide for any necessary change orders.

BACKGROUND:

Pasadena Water and Power ("PWP") owns and operates a wide range electric vehicle ("EV") charging network as part of the City's commitment to environmental sustainability, clean transportation, and improved air quality. Serving the public, municipal fleet, and emergency responders alike, this infrastructure is being expanded to meet increasing demand for City owned fleet. To facilitate this expansion, PWP requires a qualified vendor to supply DCFC equipment for the EV Charger Expansion Project at the PWP Maintenance Yards.

MEETING OF.07/20/2026AGENDA ITEM NO..3
Contract Award to OpConnect for DCFC Equipment at City Yards July 20, 2026

Page 2 of 4 ends

The EV Charger Expansion Project is intended to help future-proofthe charging needs at the City Yards for PWP including expected medium and heavy-duty utility vehicles scheduled to replace aging equipment. The entire project is broken down into equipment up to the meter, EV charging equipment, and construction. A contract with OpConnect will provide the DCFC equipment needed for the EV Charger Expansion Project. The project was approved by City Council for the Fiscal Year 2026 Capital Improvement Program process.

This specific procurement is for equipment only. The vendor's scope of supply includes the furnishing and delivery of one 600-kilowatt ("kW") DCFC power cabinet and two dual-port satellite dispensers. All installation, construction, civil, and electrical work will be performed under separate contracts.

This project is included in a broader group ofzero-emission vehicle and EV charging infrastructure projects supported by the Environmental Protection Agency Clean Heavy- Duty Vehicles grant program. The City has been awarded $4,615,000 in grant funding, of which $2,275,000 is allocated to PWP-supported zero-emission vehicle and charging infrastructure efforts. Grant funds are anticipated to offset eligible project costs within the applicable Capital Improvement Program ("CIP") budgets, while the required recipient cost-share will be funded from existing approved CIP appropriations, including CIP #03225. The project budgets will remain unchanged.

On February 27, 2026, a Notice Inviting Bids for EV Chargers, Electrical Switchgear, Transformers, and Communications Equipment (Project ID: 2026-IFB-MS-0106) was published on the City's electronic procurement platform, OpenGov. The notice was automatically distributed to all vendors registered under the applicable commodity codes. A total of eight (8) responsive and responsible bids were received via the City's eProcurement portal by the due date of April 23, 2026, with no bids received from a local firm. The bid results are summarized below in Table I.

Table I: Bid Results
Bidder NameOffice LocationBid Amount
OpConnect, Inc.Portland, OR$257,039.47
PowerFlex Systems LLCLos Angeles, CA$257,303.79
Motive Energy Systems LLCTustin, CA$263,503.89
Real City Charging SolutionsSan Diego, CA$280,835.75
National Car Charging LLCDenver, CO$297,672.64
Camber Operating Company LLC | Miami, FL$366,621.31
Pelican Coast ElectricNewport Beach, CA$437,581.11
Graviti Energy - EV ChargersMissouri City, TX$596,700.00 OpConnect was the lowest responsive and responsible bidder meeting the technical specifications and delivery instructions. Staff recommends that the City Council Contract Award to OpConnect for DCFC Equipment at City Yards July 20, 2026

Page 3 of 4 ends

authorize the City Manager to enter into a contract with OpConnect for an amount not- to-exceed $282,744, which includes the base contract amount of $257,040 and a contingency of $25,704 to provide for any necessary change orders.

The proposed contract complies with the Competitive Bidding and Purchasing Ordinance pursuant to Pasadena Municipal Code Chapter 4.08. No prior contracts with OpConnect have been awarded.

COUNCIL POLICY CONSIDERATION:

The proposed contract is consistent with the City Council's goals to maintain fiscal responsibility and stability, and PWP's strategic initiatives to enhance customer satisfaction and confidence, improve efficiency and business continuity, and maintain PWP's fiscal health and stability.

ENVIRONMENTAL ANALYSIS:

This project is categorically exempt from CEQA pursuant to State CEQA Guideline Article 19, Class 1, Section 15301, Existing Facilities. The Class 1 categorical exemption consists of "the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of existing or former use". The proposed contract allows for the continued maintenance, repair, and operation of existing EV charging infrastructure. This action does not involve substantial physical construction activities or an expansion of the existing use. There are no features that distinguish the project from others in the exempt class and, therefore, there are no unusual circumstances.

Contract Award to OpConnect for DCFC Equipment at City Yards July 20, 2026

Page 4 of 4 ends

FISCAL IMPACT:

The total cost of this contract including contingency is $282,744. Funding for this action will be addressed through the utilization of existing appropriations in the EV Charging Infrastructure (03225) CIP budget. It is anticipated that all costs will be expended in Fiscal Year 2027. There is no impact to the General Fund.

The contract summary is shown below in Table II.

Table II: Contract Summary
Base Contract$257,0401
Contingency (10%)$25,704]
Total Contract Not-to-Exceed Amount$282,7441
Respectfully submitted,
DAVID M. REYES
General Manager
Water and Power Department
Prepared by:

Vafc^jan Avedian
Assistant General Manager
Water and Power Department