Public Works
Capital Improvement Projects
Under Construction

CITY COUNCIL UPDATE
February 4, 2025
City of Paso
Robles –
DPW 12-12H2

CRESTON ROAD
PHASE 1
City of Paso
Robles –
DPW 12-12H2

CRESTON ROAD
PHASE 1
• City of Paso Robles –
• DPW 12-12H2
• CRESTON ROAD PHASE 1
Push button pedestrian
flashing signs installed at
Ivy/Orchard/Trigo
City of Paso Robles – DPW 12-12H3

CRESTON ROAD CORRIDOR
City of Paso Robles – DPW 12-12H3

CRESTON ROAD CORRIDOR
City of Paso Robles – DPW 12-12H3

CRESTON ROAD CORRIDOR
City of Paso Robles – DPW 12-12H3

CRESTON ROAD CORRIDOR
PHASE 2: SOUTH OF ORCHARD TO NIBLICK
• Roundabout at Rolling Hills
• Note: Development Application is in progress for the City to receive the right-of-way needed for the roundabout.
• Road Surface repair and rehabilitation
• Upgrade curb ramps to ADA Standards
• Will use $3M funds from AB 178 and any remainder of the budget from Phase 1
City of Paso Robles – DPW 22-14A

SHERWOOD NEIGHBORHOOD WATERLINE REPAIRS
City of Paso Robles – DPW 22-14A

SHERWOOD NEIGHBORHOOD WATERLINE REPAIRS
City of Paso Robles – DPW 22-14A

SHERWOOD NEIGHBORHOOD WATERLINE REPAIRS
City of Paso Robles – DPW 22-14A

SHERWOOD NEIGHBORHOOD WATERLINE REPAIRS
City of Paso Robles – DPW 23-23
GOLDEN HILL– CRESTON ROAD TO ROLLING HILLS
City of Paso Robles – DPW 23-23
GOLDEN HILL– CRESTON ROAD TO ROLLING HILLS
Pavement striping in progress.

City of Paso Robles – DPW 23-23
GOLDEN HILL– CRESTON ROAD TO ROLLING HILLS
Pavement striping in progress.

City of Paso Robles – DPW 23-26
VETERAN’S/SENIOR CENTER SHADE STRUCTURE
The shade structure at the
Veteran’s & Senior Center
has been installed.

Public Works
Capital Improvement Projects
Upcoming Construction

CITY COUNCIL UPDATE
February 4, 2025
City of Paso
Robles – DPW
13-01

SOUTH VINE

BRIDGE REPAIRS
City of Paso
Robles – DPW
13-01

SOUTH VINE

BRIDGE REPAIRS
City of Paso
Robles – DPW
13-01

SOUTH VINE

BRIDGE REPAIRS
City of Paso
Robles – DPW
13-01

SOUTH VINE

BRIDGE REPAIRS
City of Paso
Robles – DPW
13-01

SOUTH VINE

BRIDGE REPAIRS
City of Paso
Robles – DPW
16-24
13TH & NIBLICK

BRIDGE DECK

REPAIRS
City of Paso
Robles – DPW
21-19A

PICKLEBALL
COURT

CONSTRUCTION
City of Paso
Robles – DPW
23-40
MERRY HILL, 15TH
& TERRACE HILL
City of Paso
Robles – DPW
23-41

SERENADE &
BRAHMA

NEIGHBORHOOD

STREET REPAIRS
City of Paso
Robles – DPW
24-23

MUNICIPAL

AIRPORT RAMP

PAVING REPAIRS
City of Paso
Robles – DPW
24-26

PUBLIC SAFETY

TRAINING

FACILITY
City of Paso
Robles – DPW
24-26

PUBLIC SAFETY

TRAINING

FACILITY