Public Works
Capital Improvement Projects
Under Construction
CITY COUNCIL UPDATE
May 6, 2025
• City of Paso Robles –
• DPW 12-12H2
• CRESTON ROAD PHASE 1
City of Paso
Robles – DPW
12-12H3
CRESTON ROAD
CORRIDOR
City of Paso Robles – DPW 12-12H3
CRESTON ROAD CORRIDOR
City of Paso Robles – DPW 12-12H3
CRESTON ROAD CORRIDOR
PHASE 2: SOUTH OF ORCHARD TO NIBLICK
• Roundabout at Rolling Hills
• Note: Development Application is in progress for the City to receive the right-of-way needed for the roundabout.
• Road Surface repair and rehabilitation
• Upgrade curb ramps to ADA Standards
• Will use $3M funds from AB 178 and any remainder of the budget from Phase 1
DPW 16-01A
East/West 24TH Street
Bridge Pedestrian
Improvements – 24th and
Park Street intersection is
completed and now open.
• DPW 16-01A
• East/West 24TH Street
Bridge Pedestrian
Improvements – 24th and
Park Street intersection is
completed and now open.
City of Paso
Robles – DPW
21-19A
PICKLEBALL
COURT
CONSTRUCTION
DPW 21-19A
New Pickleball Court Construction
• Top picture: excavation of the
detention basin is ongoing for Sherwood
Park.
• Bottom picture: the streetlight poles
for the pickleball courts have been
installed.
DPW 21-19A
New Pickleball Court Construction
• Top picture: Upper pickleball court grading and
base placement.
• Bottom picture: Lower pickleball court grading
and base placement.
City of Paso Robles – DPW 22-14A
SHERWOOD NEIGHBORHOOD WATERLINE REPAIRS
SoCalGas performing repairs of their water mains prior to City’s plan to resurface roads within the Sierra Bonita Neighborhood.
City of Paso
Robles – DPW
23-40
MERRY HILL, 15TH
& TERRACE HILL
DPW 23-40
• 15th Street
Final Paving.
DPW 23-40
• Merry Hill Final
Paving.
City of Paso
Robles – DPW
23-41
SERENADE &
BRAHMA
NEIGHBORHOOD
STREET REPAIRS
DPW 23-41
SERENADE &
BRAHMA
NEIGHBORHOOD
STREET REPAIRS
Public Works
Capital Improvement Projects
Upcoming Construction
CITY COUNCIL UPDATE
May 6, 2025
City of Paso
Robles – DPW
20-25A
Flamson School
Pedestrian
Enhancements
City of Paso
Robles – DPW
20-25A
Flamson School
Pedestrian
Enhancements
City of Paso
Robles – DPW
20-25A
Flamson School
Pedestrian
Enhancements
City of Paso
Robles – DPW
22-08
DOWNTOWN
PARKING LOT
IMPROVEMENTS
City of Paso
Robles – DPW
24-20
ANNUAL
PAVEMENT
REFRESHMENT
OF STRIPING
City of Paso
Robles – DPW
24-23
MUNICIPAL
AIRPORT RAMP
PAVING REPAIRS
City of Paso
Robles – DPW
24-26
PUBLIC SAFETY
TRAINING
FACILITY
City of Paso
Robles – DPW
24-26
PUBLIC SAFETY
TRAINING
FACILITY
For Council Consideration
CITY COUNCIL UPDATE
May 6, 2025
Niblick Bridge Veterans Memorial Bridge