Public Works
Capital Projects Update
October 7, 2025
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Creston Road Corridor
Phase 1
Traffic signal, paving/striping
Trigo to Orchard
Traffic control from Orchard
to Trigo
February 2026
Sherwood Park Pickleball
Court Complex
Parking lot, court lighting, and
curbs
Sidewalk closed along Via
Ramona
End of May 2026
Flamson School Pedestrian
Enhancements
Sign installation Sidewalk closure north of
24th Street from Spring
Street to Oak Street
October 2025
Downtown Parking Lot
Improvements
PG&E onsite, curbs 12th and Railroad closed to
the public
January/February
2026
Annual Sidewalk
Replacements
Construction to begin
September 29.

Sidewalk closures during
construction with detours in
place.

February 2026
3 4
Creston Road Corridor Phase 1
• Remaining paving/striping
from Trigo to Orchard
• Traffic signals at
Walnut/Bolen/Creston
activated late October.

The pad for the pre-fabricated restroom has been poured, and the curbs have been installed for the parking lot at the Pickleball Courts.
5 6
Flamson Pedestrian
Improvements
The flashing
pedestrian push
button lights have
been installed, as well
as median curbs and
curb ramps
• Flamson
Pedestrian
Improvements • The striping
on Spring
Street is
currently in
progress
7 • 12th &
Railroad
Parking Lot
Repairs •
Removal of
the old
asphalt has
been
completed
8 12th & Railroad
Parking Lot Repairs
Completion of the
retaining wall is at 90%
9 PG&E’s installation of the
bases for the streetlight
poles
10 Upcoming
Projects
Upcoming Project Name Description Status Est. Start Date Crestline and Fairview
Neighborhood Road
Repairs
Dig-out repairs replace AC berm
with concrete at park perimeter,
and dig-out repairs asphalt
overlay
Contract awarded November /
December 2025
West Side Fiberized Slurry
Seal
Install concrete cross gutters,
dig-out repairs, and place
fiberized slurry seal
Contract awarded November /
December 2025
Riverside / Capitol Hill /
Almond Court Pipeline
Repairs
Repair old pipelines in
preparation of repairing road
surface
Contract awarded October /
November 2025
Creston Road Phase 2 Roundabout at Rolling Hills curb
ramps, sidewalks, decorative
lights, landscaping, signal
modification, and road
resurfacing
100% PS&E in progress 1st Quarter 2026
11 12
Creston Road
Corridor Phase 2
• Continuation of
sidewalk construction
• Numerous pipelines
installations at the
proposed
roundabout at
Creston and Rolling
Hills Existing and New (Black)
Pipeline @ Rolling Hills
13 Measure I-24 Minor Road Repair
Project
• Clubhouse Drive Pavement Repair Project
14 • Clubhouse Drive Pavement Repair Project
15 16
Stormwater Program Project
• Satellite Drainage Rehabilitation Project
17 • Satellite Drainage Rehabilitation Project
18 • Satellite Drainage Rehabilitation Project
19 20
Scott Street Construction
Impacts
21 Scott Street Closure
• Phase 1: Full Road Closure
• Daytime Only: M-F, 7am-5pm
• Est. Dates: Oct.14th-Nov.21st
22 Scott Street Closure
• Phase 2: Temp. Lane Closure
• One-Way Traffic Control
(Expect Delays)
• Daytime Only: M-F, 7am-5pm
• Est. Dates: Nov.21st-Dec.26th
#Pasolights & NYE
Sponsorship Program
Launched
23 www.prcity.com/pasolights
24 • Please visit the City’s website for a full list of city projects and current status: prcity.com/363