Public Works
Capital Projects Update
January 14, 2026
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Sherwood Park Pickleball
Court Complex
Parking lot, court lighting, and
curbs, and site furnishings
Sidewalk closed along Via
Ramona
End of May 2026
Downtown Parking Lot
Improvements
PG&E onsite, curbs, and
irrigation system
12th and Railroad closed to
the public. Partial closure at
Marv’s Pizza.
January/February
2026
Crestline and Fairview
Neighborhood Road
Repairs
Dig-out repairs, and dig-out
repairs asphalt overlay
Project is 95% completed February 2026
Sewer & Water Upgrades Upgrade of mains on Capitol
Hill, Almond Dr, and Riverside
Ave.
None currently. Work to
resume mid January 2026.
May 2026
City Hall Renovation Reconfigured office space,
including new front counter,
conference room, security
enhancements, etc.
Temporary relocation of
counter services & City
Council chambers.
January 2026
3 4
Pickleball Court • Fencing of the south
court is completed,
and the benches
and shade structure
poles have been
placed.
5 Pickleball Court
• Finishing the
pervious concrete
parking lot.
6 Marv’s Pizza Parking
Lot Repairs • Stage 2: alleyways
are in progress,
adjacent to Grapes
and Grain
7 Marv’s Pizza Parking
Lot Repairs
• Stage 1: completed
the alleyway behind
Grapes and Grain
8 12th & Railroad Lot
Improvement
• Streetlight pole
installation & wheel
stops and striping in
progress
9 Upcoming
Projects
Upcoming Project Name Description Status Est. Start Date West Side Fiberized Slurry Seal Install concrete cross gutters, dig-out repairs, and place fiberized slurry seal
Contract awarded January 2026
Riverside / Capitol Hill /
Almond Court Pipeline Repairs
Repair old pipelines in preparation of
repairing road surface
Contract awarded October /
November 2025
Creston Road Phase 2 Roundabout at Rolling Hills curb ramps, sidewalks, decorative lights, landscaping,
signal modification, and road resurfacing
100% PS&E in progress 1st Quarter 2026
Orchard Bungalow
Neighborhood Road Repairs
Road repairs Preliminary Engineering December 2025
Downtown Streets Road repairs Preliminary Engineering December 2025 Sherwood Neighborhood Road repairs Preliminary Engineering December 2025 Sierra Bonita Neighborhood Road repairs Award contract at City Council meeting 1/14/26
March / April 2026
18th Street Alley Sewer upgrades Out to bid; bids due 2/19 April / May 2026 10 11
Fiberized Slurry
Seal Project
• 12th St.-Merry Hill to Bailey
• 10th St. – Vine to Olive
• Olive St. – 12th to Pacific
• Pacific St. – Olive to Merry Hill
• 13th St. – Spring to Vine
12 Creston Road
Corridor Phase 2
• Roundabout at
Rolling Hills curb
ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and
road resurfacing
13 Downtown Streets
• Road repairs
14 Sherwood
Neighborhood
• Road repairs
15 Sierra Bonita
Neighborhood
• Road repairs
16 • Please visit the City’s website for a full list of city projects and current status: prcity.com/363