Public Works
Capital Projects Update
March 3, 2026
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Sherwood Park Pickleball
Court Complex
Parking lot, court lighting, and
curbs, and site furnishings
Sidewalk closed along Via
Ramona
End of May 2026
Downtown Parking Lot
Improvements
PG&E onsite, curbs, and
irrigation system
12th and Railroad closed to
the public. Partial closure at
Marv’s Pizza.
January/February
2026
Riverside / Capitol Hill /
Almond Court Pipeline
Repairs
Upgrade of mains None currently. Work to
resume mid January 2026.
May 2026
Sierra Bonita Neighborhood
Road Repairs
Finishing award phase ready for
Pre-construction meeting
None currently. July/August 2026
West Side Fiberized Slurry Seal Leveling course Traffic detours and no parking April 2026 3 4
Pickleball Court
• Court lighting poles
and posts for
interior fences have
been installed
5 12th & Railroad Lot
Improvement • Benches, trash
receptacles, bike
racks, ornamental
fencing, and the
handrail at the
block wall have
been installed
6 Sierra Bonita
Neighborhood
• Road repairs
7 Fiberized Slurry
Seal Project
• 12th St.-Merry Hill to Bailey
• 10th St. – Vine to Olive
• Olive St. – 12th to Pacific
• Pacific St. – Olive to Merry Hill
• 13th St. – Spring to Vine
8 Black Oak
Drive Minor
Repair
9 Upcoming
Projects
Upcoming Project Name Description Status Est. Start Date Creston Road Phase 2 Roundabout at Rolling Hills curb ramps, sidewalks, decorative lights, landscaping,
signal modification, and road resurfacing
100% PS&E in progress 1st Quarter 2026
Downtown Streets Road repairs Preliminary Engineering December 2025 Orchard Bungalow
Neighborhood Road Repairs
Road repairs Preliminary Engineering December 2025
Sherwood Neighborhood Road repairs Preliminary Engineering December 2025 Commerce Way Road repairs Preliminary Engineering
18th Street Alley Sewer upgrades Contract awarded April / May 2026 Riverside Avenue 17th to 21st
Street
Road repairs On going sewer & water
main upgrades
April 2026
10 11
Creston Road
Corridor Phase 2
• Roundabout at
Rolling Hills curb
ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and
road resurfacing
12 Downtown Streets
• Road repairs
13 Orchard Bungalow
• Road repairs
14 Sherwood
Neighborhood
• Road repairs
15 Commerce Way
• Road repairs
16 Riverside-17th to
21st Street
17 • Please visit the City’s website for a full list of city projects and current status: prcity.com/363