Public Works
Capital Projects Update
April 7, 2026
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Sherwood Park Pickleball
Court Complex
Parking lot, court lighting, and
curbs, and site furnishings
Sidewalk closed along Via
Ramona
Substantially
completed
Capitol Hill Sewer Upgrade of mains None currently. Work to resume mid April 2026.

June 2026
Sierra Bonita Neighborhood
Road Repairs
Road repairs are in progress No parking at certain
locations
July/August 2026
West Side Fiberized Slurry Seal Fiberized slurry Traffic detours and no parking April 2026 3 4
Pickleball Court
• Pedestrian light
bollards, benches,
shade structures,
fencing and lighting
have been installed
5 Pickleball Court
Pedestrian light bollards and bench shade structures have been installed 6 7
Capitol Hill
Sewer Project
8 MEASURE 1-24 UPDATES
9 Sierra Bonita
Neighborhood
• To date the streets
east of Airport
Road are
completed: Poppy
Lane, Turtle Creek,
and Parkview Lane
10 Fiberized Slurry
Seal Project
• 12th St.-Merry Hill to Bailey
• 10th St. – Vine to Olive
• Olive St. – 12th to Pacific
• Pacific St. – Olive to Merry Hill
• 13th St. – Spring to Vine
11 Upcoming
Projects
Upcoming Project Name Description Status Est. Start Date Creston Road Phase 2 Roundabout at Rolling Hills curb ramps, sidewalks, decorative lights, landscaping,
signal modification, and road resurfacing
100% PS&E in progress 1st Quarter 2026
Downtown Streets Road repairs Preliminary Engineering December 2025 Orchard Bungalow
Neighborhood Road Repairs
Road repairs Preliminary Engineering December 2025
Sherwood Neighborhood Road repairs Preliminary Engineering December 2025 Commerce Way Road repairs Out to bid July 2026
18th Street Alley Sewer upgrades Contract awarded April / May 2026 Riverside Avenue 17th to 21st
Street
Curbs and sidewalks Out to bid June 2026
12 13
Creston Road
Corridor Phase 2
• Roundabout at
Rolling Hills curb
ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and
road resurfacing
14 Downtown
Streets
• Road repairs
• Average PCI of 17,
with 100 being best.
15 Orchard Bungalow
• Road repairs
• Average PCI of 41, with
100 being best.
16 Sherwood
Neighborhood
• Road repairs
• Average PCI of 27, with
100 being best.
17 Commerce Way
• Road repairs
• PCI = 18 (Creston to Santa Bella)
• PCI = 55 (Santa Bella to Scott)
18 Riverside-17th to
21st Street
19 • Please visit the City’s website for a full list of city projects and current status: prcity.com/363