Public Works
Capital Projects Update
June 2, 2026
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Sherwood Park Pickleball
Court Complex
Parking lot, court lighting, and
curbs, and site furnishings
Sidewalk closed along Via
Ramona
Soft Opening
July 13, 2026
Capitol Hill Sewer Upgrade of mains None currently July 2026 Sierra Bonita Neighborhood
Road Repairs
Road repairs are in progress No parking at certain
locations
July/August 2026
3 In-Progress Project Name Current Activity Public Impact Est. Completion Creston Road Phase 2 Roundabout at Rolling Hills
curb ramps, sidewalks,
decorative lights, landscaping,
signal modification, and road
resurfacing
Contract awarded Phase A: roundabout
July/August 2028
Phase B: Melody to
Niblick June/July 2027
Commerce Way Road repairs Out to bid December 2026
Riverside Avenue 17th
to 21st Street
Curbs and sidewalks Out to bid July 13, 2026
4 5
Pickleball
Courts
6 Pickleball
Courts
7 Capitol Hill
Sewer Project
8 MEASURE 1-24
UPDATES
9 Creston Road
Corridor Phase 2
• Roundabout at
Rolling Hills curb
ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and
road resurfacing
10 Commerce Way
• Road repairs
• PCI = 18 (Creston to Santa Bella)
• PCI = 55 (Santa Bella to Scott)
11 Riverside-17th to
21st Street
12 Upcoming
Projects
Upcoming Project Name Description Status
Downtown Streets Road repairs Final Engineering Design in progress
Orchard Bungalow
Neighborhood Road Repairs –
Phase 1
Road repairs Final Engineering Design in
progress
Sherwood Neighborhood Road repairs Final Engineering Design in progress
16th/18th/30th/32nd/36th Street
repairs
Road repairs Out to Bid
13 14
Downtown Streets
• Road repairs
15 Orchard Bungalow
• Road repairs
16 Sherwood
Neighborhood
• Road repairs
17 16th/18th/30th/
32nd/36th
• Road repairs
18 • Please visit the City’s website for a full list of city projects and current status: bit.ly/PRcityCIP
Scan the QR code to
sign up for capital
project updates.