Public Works
Capital Projects Update
August 4, 2026
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Sierra Bonita Neighborhood
Road Repairs
Road repairs are in progress No parking at certain
locations
August/Sept 2026
Creston Road Phase 2 Roundabout at Rolling Hills
curb ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and road
resurfacing
Contract awarded Phase A:
roundabout
Fall 2028
Phase B: Melody
to Niblick
Fall 2027
Commerce Way Road repairs Begin work August 10th December 2026 Riverside Avenue 17th to
21st Street
Curbs and sidewalks Begin work August 3rd November 2026 3 4
MEASURE 1-24
UPDATES
5 Creston Road
Corridor Phase 2
• Roundabout at
Rolling Hills curb
ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and
road resurfacing
6 Nighttime waterline work
7 Curb ramps & sidewalk upgrades
8 Commerce Way
• Road repairs
• PCI = 18 (Creston to Santa Bella)
• PCI = 55 (Santa Bella to Scott)
9 Riverside-17th to
21st Street
10 Upcoming
Projects
Upcoming Project Name Description Status
Downtown Streets Road repairs Final Engineering Design in progress
Orchard Bungalow
Neighborhood Road Repairs –
Phase 1
Road repairs Final Engineering Design in
progress
Sherwood Neighborhood Road repairs Final Engineering Design in progress
16th/18th/30th/32nd/36th Street
repairs
Road repairs Award Contract
11 12
Downtown Streets
• Road repairs
13 Orchard Bungalow
• Road repairs
14 Sherwood
Neighborhood
• Road repairs
15 16th/18th/30th/
32nd/36th
• Road repairs
16 • Please visit the City’s website for a full list of city projects and current status: bit.ly/PRcityCIP