Public Works
Capital Projects Update
September 1, 2026
2 Projects in Progress
In-Progress Project Name Current Activity Public Impact Est. Completion Sierra Bonita Neighborhood
Road Repairs
Road repairs are in progress No parking at certain
locations
August/Sept 2026
Creston Road Phase 2 Roundabout at Rolling Hills
curb ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and road
resurfacing
Contract awarded Phase A:
roundabout
Fall 2028
Phase B: Melody
to Niblick
Fall 2027
Commerce Way Road repairs Begin work August 10th December 2026 Riverside Avenue 17th to
21st Street
Curbs and sidewalks Begin work August 3rd November 2026 3 In-Progress Project Name Current Activity Public Impact Est. Completion West Side Road Repairs
16th, 18th, 30th, & 36th
west of Spring Street
Contract are being routed for
approval
Work begins Sept/Oct 2026 December 2026 /
January 2027
4 5
MEASURE 1-24

UPDATES
6 Creston Road
Corridor Phase 2
• Roundabout at
Rolling Hills curb
ramps, sidewalks,
decorative lights,
landscaping, signal
modification, and
road resurfacing
7 Creston Road Phase 2
• Fiber conduit lines have
started and the curb ramps
at Oak Meadows have been
completed
8 Creston Road Phase 2
• Waterline work is currently
in progress
9 Commerce Way
• Road repairs
• PCI = 18 (Sherwood  Santa Bella)
• PCI = 55 (Santa Bella  Scott St)
10 Commerce Way
• Paving is completed and
the contractor to start
raising water valves,
manhole covers, and
them pavement striping
11 Riverside from
17th - 21st Street
12 Riverside from
17th - 21st Street
• Concrete placed &
sidewalk construction
in progress
13 West Side Road Repairs
16th/18th/30th/32nd/36th
• Full depth reclamation
14 Upcoming
Projects
24th Street Bridge
24th Street Bridge
17 Veterans Bridge:

MIA / POW Flags
VFW Flag Installation: VFW will display flags on
bridge pilasters for 9/11 Remembrance Day and
9/18 National POW/MIA Recognition Day.

Hardware Preparation: City staff will install flag
holders on all four bridge pilasters before
September 11.

Lighting Evaluation: Staff will evaluate existing
lighting on the evening of September 11.

If adequate, flags will remain in place through
September 18; otherwise, they will be removed
and reinstalled for each observance.

Future Permanent Installation: Staff is
evaluating lighting needs to support permanent
flag placement.
18 • Please visit the City’s website for a full list of city projects and current status: bit.ly/PRcityCIP