SPERRY AVE/I-5
INTERCHANGE PROJECT
JULY 5, 2022
PROJECT DESCRIPTION
The Sperry Ave interchange at Interstate-5 is located at the west outer limits of Patterson, between the Westly and Crows Landing interchanges. This project proposes to upgrade the Sperry Ave/I-5 Interchange with the following improvements:
• Widen Sperry Avenue from 2-lanes to 4-lanes
• Widen and reconstruct the existing on- and off-ramps
• Install complete Traffic Signalization and Lighting for the interchange • Install Retaining Walls of both sides of Sperry Avenue under I-5 • Widen the bridge over the California Aqueduct to accommodate 4-lanes • Culvert extension and modifications to the Black Gulch Creek SPERRY AVE/I-5 INTERCHANGE
PROJECT SITE PLAN LAYOUT
SPERRY AVE/I-5 INTERCHANGE
KEY ITEMS
• Project Approval & Environmental Document (PA&ED) Phase • Project Specifications & Estimates (PS&E) Phase
• Project Construction Phase
• Project Completion
SPERRY AVE/I-5 INTERCHANGE
PROJECT PHASING:
PROJECT AGENCIES:
• City of Patterson
• Stanislaus County
• California Department of Transportation (Caltrans)
PROJECT APPROVAL & ENVIRONMENTAL DOCUMENT
(PA&ED) PHASE
• The Project Approval & Environmental Document (PA&ED) phase was completed in early part of 2020
• The Final Project Report for Project Approval of the Sperry Avenue/I-5 Interchange was approved on September 22, 2020
SPERRY AVE/I-5 INTERCHANGE
PROJECT SPECIFICATIONS & ESTIMATE (PS&E) PHASE
• The City received proposals for the PS&E phase from two consulting firms in April 2022
• NCM Engineering Corporation
• MNS Engineers, Inc.
SPERRY AVE/I-5 INTERCHANGE
PROJECT SPECIFICATIONS & ESTIMATE (PS&E) PHASE
CONTINUED…..
• NCM Engineering was determined to be the most qualified firm for the design services of the Sperry Ave/I-5 Interchange project.
• NCM Engineering PS&E Proposal
• Project Design Task Items
• Tasks 1-4: Preliminary Design to Final Design Phase
• Task 5: Project Bidding Phase
• Task 6: Construction & Post-Construction Phase
• Project Design Schedule – 18 months
SPERRY AVE/I-5 INTERCHANGE
PROJECT CONSTRUCTION PHASE
• The City will anticipate to Bid the Sperry Ave/I-5 Interchange project for Construction in Spring 2024
SPERRY AVE/I-5 INTERCHANGE
STAFF RECOMMENDATION
• Staff recommends approval of NCM Engineering’s proposal for the Sperry Ave/I-5 Interchange project and authorize Staff to enter into a negotiated Consultant Agreement with NCM Engineering for the Phase 1 Design not to exceed $976,327.55. • Phase 2 Design in the amount of $1,593,652.45 will be presented to City Council for approval at a future date.