January 31, 2023 NBS produces and provides the Levy Schedule to City Staff.
February 7, 2023 NBS produces and provides draft Cost Estimates to City Staff.
February 21, 2023 City Staff returns Cost Estimates for Engineer’s Report.
March 24, 2023 NBS produces and provides the draft Engineer’s Report to City Staff.
April 7, 2023 City Staff provides comments regarding the draft Engineer’s Report.
April 28, 2023 NBS prepares and delivers the Engineer’s Report and Resolutions of Intention and Approving the Engineer’s
Report. Public Hearing date is confirmed.
May 16, 2023 Council Meeting – Intent Meeting
Council considers Engineer’s Report and
Resolution Approving the Engineer’s Report;
Council considers Resolution of Intention and
sets date for Public Hearing.
May 27, 2023 NBS prepares and delivers the Resolution Ordering the Levy and Collection of Assessments.
June 1, 2023 City Clerk arranges for publication and posting of Resolution of Intention once in a local newspaper not
less than ten days before Public Hearing date.
June 20, 2023 Council Meeting – Public Hearing
Property owners may ask questions and voice
protest or present written protest;
Council considers all oral statements and written
protests and may order any changes to the
Engineer’s Report or proposed assessments;
Council considers the Resolution Amending the
Engineer’s Report (only if amendments are
desired) and the Resolution Ordering the Levy
and Collection of Assessments.
June 25, 2023 City Clerk provides certified Resolutions to NBS for inclusion with levy submittal to County.
August 10, 2023(1) NBS transmits Resolutions and assessment roll to County and follows up regarding any rejected parcels.