Title Projects Description-From Description-To Type Description Est Useful Life Min Est Useful Life Max Est Start Est Completion 9th Street Improvements 9th Street Las Palmas Ave Sperry Ave Construction: Complete
reconstruction of roadway section
Full Depth Reconstruction of
Road, new road section:
estimated 2" HMA/9" AB 15 20 1-Apr-2024 1-Sep-2024
Sunset Court Improvements Sunset Court Ward Ave Sunset Court Construction: Complete
reconstruction of roadway section
Full Depth Reconstruction of
Road, new road section:
estimated 2" HMA/9" AB 15 20 1-Apr-2024 1-Sep-2024
CITY OF PATTERSON
SB1 Plan Project List (FY 2023/24)
EXHIBIT "A" NEW PROJECTS
Title Projects - Street Description-From Description-To Type Description Est Useful Life Min Est Useful Life Max Est Start Est Completion Ward Avenue Overlay Ward Avenue Las Palmas Ave N. 9th Street 2.5" AC Overlay 2.5" AC Overlay 10 15 1-Jun-2024 30-Sep-2024 City Slurry Seal and Crack Seal
ABELIA LN: MARIGOLD DR to
AZALEA DR, CALVINSON
PKWY: WARD AVE TO Baldwin
Rd, American eagle: ward to
End, heartland Ranch: Ward
to Pipit, Shearwater Drive:
Baldwin Rd to Red Robin, Cliff
Swallow: Baldwin Rd to end,
Lemon Blossom: Garden
Patch to Imperial Lily, Park
Center Drive: Sperry to
Keystone Pacific Parkway,
Miraggio: Ward to End,
Keystone Pacific Parkway:
Rogers Rd to Baldwin Rd, *All
locations subject to change,
and will be selected based on
priority, need and resources
throughout the year.
ABELIA LN: MARIGOLD DR to
AZALEA DR, CALVINSON
PKWY: WARD AVE TO Baldwin
Rd, American eagle: ward to
End, heartland Ranch: Ward
to Pipit, Shearwater Drive:
Baldwin Rd to Red Robin, Cliff
Swallow: Baldwin Rd to end,
Lemon Blossom: Garden
Patch to Imperial Lily, Park
Center Drive: Sperry to
Keystone Pacific Parkway,
Miraggio: Ward to End,
Keystone Pacific Parkway:
Rogers Rd to Baldwin Rd, *All
locations subject to change,
and will be selected based on
priority, need and resources
throughout the year.
ABELIA LN: MARIGOLD DR to
AZALEA DR, CALVINSON
PKWY: WARD AVE TO Baldwin
Rd, American eagle: ward to
End, heartland Ranch: Ward
to Pipit, Shearwater Drive:
Baldwin Rd to Red Robin, Cliff
Swallow: Baldwin Rd to end,
Lemon Blossom: Garden
Patch to Imperial Lily, Park
Center Drive: Sperry to
Keystone Pacific Parkway,
Miraggio: Ward to End,
Keystone Pacific Parkway:
Rogers Rd to Baldwin Rd, *All
locations subject to change,
and will be selected based on
priority, need and resources
throughout the year.
Slurry Seal and Crack Seal Slurry Seal and Crack Seal 5 7 1-Aug-2023 31-Oct-2023
CITY OF PATTERSON
SB1 Plan Project List (FY 2023/24)
EXHIBIT "B" CARRYOVER PROJECTS