Cities Index.
agenda-report Accept all bids for the WQCF Admin Phase 3A Wastewater Treatment Expansion Project, award construction to Auburn Constructors, LLC., authorize Staff to execute the Contract and authorize the Finance Department to allocate additional funds.

Patterson City Council
April 15, 2025

Document
agenda-report Accept all bids for the WQCF Admin Phase 3A Wastewater Treatment Expansion Project, award construction to Auburn Constructors, LLC., authorize Staff to execute the Contract and authorize the Finance Department to allocate additional funds.
Meeting
April 15, 2025
Body
Patterson City Council
Original file
102 KB
Text extracted from the city's file for reading and search. Open the original on pattersonca.iqm2.com. That file is the official record.

City Council Agenda Report
TO: Mayor Clauzel and Members of the City Council
FROM: Fernando Ulloa, City Manager
BY: Tiffany Rodriguez, Capital Projects Manager
MEETING DATE: April 15, 2025
ITEM NO: 7.1
SUBJECT: Accept all bids for the WQCF Admin Phase 3A Wastewater Treatment Expansion Project, award construction to Auburn Constructors, LLC., authorize Staff to execute the Contract and authorize the Finance Department to allocate additional funds.

RECOMMENDATION
Motion to Accept all bids for the WQCF Admin Phase 3A Wastewater Treatment Expansion Project, award construction to Auburn Constructors, LLC., authorize Staff to execute the Contract and authorize the Finance Department to allocate additional funds.

BACKGROUND
The City’s existing Wastewater Quality Control Facility (WQCF) is located at the easterly end of Walnut Avenue, approximately 1.5 miles east of city limits. The WQCF consists of three separate processes: The North Activated Sludge Treatment System (NASTS), the Advanced Integrated Pond System (AIPS), and the South Activated Sludge Treatment System (SASTS).

The key objective of the planned improvements for the WQCF is to elevate the treatment capacity of all three treatment systems.

The Patterson WQCF Phase 3A Expansion increases the overall treated design flow capacity and maintains the effluent quality. To meet the future increased flow requirements and higher quality effluent, upgrades are being made to both the primary, secondary filtration and disinfection treatment processes of the existing WQCF. The WQCF Phase 3A expansion will be a Membrane Bioreactor (MBR) treatment system. The MBR treatment system shall include all necessary appurtenances associated for its implementation to the City’s existing WQCF treatment system.

In addition to the MBR treatment system, Phase 3A expansion will include improving the screens at the influent pump station to accommodate the MBR treatment process, new oxidation ditch aeration diffusers, the addition of a screw press for sludge dewatering and an additional pump within the effluent pump station.

ANALYSIS
The WQCF Admin Phase 3A Wastewater Treatment Expansion Project was advertised on the Valley Builder Exchange, the City’s website, and the Patterson Irrigator Newspaper. Bid opening was held on February 19, 2025 at 2:00 P.M. The City received three (3) bids for this project. The three bids received are listed below from lowest to highest:

BIDS
Auburn Constructors, LLC. $28,488,300.00
Clark Bros $32,688,583.45
Steve P. Rados $35,373,500.00
The Engineer’s Estimate for construction was expected to be around $17,088,835. When the bids were opened, the construction costs were substantially higher than expected. City Staff worked with the design team to verify and update the Engineer’s Estimate to better reflect the current construction market. During this update, it was also found some items were erroneously excluded from the estimate. The estimate was found to be $26,348,704, which is in keeping with the construction bids received.

Unfortunately, the cost for construction was higher than anticipated. Therefore, staff is recommending that City Council adjust the budget as shown below.

FISCAL IMPACT
After reviewing the bid documents, Auburn Constructors, LLC., was deemed the lowest responsible bidder.

Funding for this project is as follows:
$ 28,488,300.00 Base Bid
$ 2,848,830.00 10% Contingency
$ 31,337,130.00 Total
Funding for this Project is as follows:

Current Funds on Hand
Residential (Villages of Patterson) CFD 2018-1 (Fund 180) = $7,130,048.76 (Bond Proceeds) West Patterson Business Park CFD 2005-1 (Fund 191) = $5,395,129.76 (Bond Proceeds) Self Help CFD Pre-Payment (Fund 180) = $1,052,839.00
Direct Funding of Facilities from Assessments (Fund 180) = $961,384.11 Sewer Impact Fees (Fund 416) = $252,074.26
Total Funding on Hand = $14,791,475.89
Future Bond Issuance - The City expects these bonds to be issued in late 2025 or early 2026 Residential (Baldwin Ranch) CFD 2022-2 (Fund xxx) = $5,713,413 (Estimated Bonding Capacity as of 10/31/2024)
West Patterson Business Park CFD 2005-1 (Fund 191) = $8,570,119 (Estimated Bonding Capacity as of 11/13/2024)
Future Bond Issuance - The City expects these bonds to be issued closer to the completion of the project if needed to cover contingency
Residential (Villages of Patterson) CFD 2018-1 (Fund 180) = $2,262,122.11 (Estimated Bonding Capacity as of 10/31/2024)
Total Future Bond Issues = $16,545,654.11
Total Funding for the Project = $31,337,130.00